CN107237511B - A kind of efficient shear wall through-wall bolt holes blocking method - Google Patents

A kind of efficient shear wall through-wall bolt holes blocking method Download PDF

Info

Publication number
CN107237511B
CN107237511B CN201710649515.8A CN201710649515A CN107237511B CN 107237511 B CN107237511 B CN 107237511B CN 201710649515 A CN201710649515 A CN 201710649515A CN 107237511 B CN107237511 B CN 107237511B
Authority
CN
China
Prior art keywords
bolt hole
wall
drill
impact
impact drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710649515.8A
Other languages
Chinese (zh)
Other versions
CN107237511A (en
Inventor
任旭红
刘广
刘鑫
李飚
张宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DATONG TAIRUI GROUP CONSTRUCTION Co Ltd
Original Assignee
DATONG TAIRUI GROUP CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DATONG TAIRUI GROUP CONSTRUCTION Co Ltd filed Critical DATONG TAIRUI GROUP CONSTRUCTION Co Ltd
Priority to CN201710649515.8A priority Critical patent/CN107237511B/en
Publication of CN107237511A publication Critical patent/CN107237511A/en
Application granted granted Critical
Publication of CN107237511B publication Critical patent/CN107237511B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions

Abstract

The present invention is specially a kind of efficient shear wall through-wall bolt holes blocking method, and solving the problems, such as existing shear wall through-wall bolt holes blocking, there are time-consuming and laborious, mortar waste is serious, it is difficult to reprocess and hidden leakage defect and heat bridge phenomenon easily occurs.A, after shear wall concreting, bolt hole is formed;B, selection timber wedge drilling rod is mounted on to bore on impact drill I and move, and pvc pipe is taken out;C, it chooses pyramidal alloy bit to be mounted on impact drill I, forms horn mouth in bolt hole outer end;D, spreading glue, and prefabricated mortar block is fixed on bolt hole outer end;E, when slip casting, first by the inner wall of interfacial agents centrifugal atomization to bolt hole, expansive cement mortar is then injected in the surface of interfacial agents, and squeeze to the center of bolt hole front end;F, last artificial filling exterior wall inner end is to closely knit.The present invention effectively increases construction efficiency, while thoroughly having prevented the generation of hidden leakage defect and heat bridge phenomenon.

Description

A kind of efficient shear wall through-wall bolt holes blocking method
Technical field
The present invention relates to architectural engineering method for blocking, specially a kind of efficient shear wall through-wall bolt holes blocking side Method.
Background technique
During shear wall construction, it is reinforcing template when wall form installs, is provided with split bolt (in wood in template two sides During formwork erection, take out and reuse for convenience of split bolt, PVC casing is provided with outside split bolt), concrete pours It builds completion, after form removal, Screw arbor with nut at both-ends is taken out, therefore form on shear wall multiple holes (split bolt on shear wall Quincuncial arrangement is spaced about 450-550mm, general to determine by calculating).
Currently, usually mortar is little by little inserted hole with small ash bucket by worker when holes blocking operation, smash with reinforcing rod In fact, closure process expends a large amount of artificial, and mortar waste is seriously, and more serious is closure leakiness, blocks process also not Pvc pipe is taken, does not take out pvc pipe when if blocking, the mortar of closure is also less prone to bond, especially the hole on exterior wall, it is easy to Cause hidden leakage defect and heat bridge phenomenon, when repairing also needs to reject exterior-wall heat insulation and exterior decoration layer, reprocesses difficulty, and need high-altitude Operation.
Summary of the invention
There are time-consuming and laborious, mortar waste is serious, returns in order to solve existing shear wall through-wall bolt holes blocking by the present invention Difficult and easy the problem of hidden leakage defect and heat bridge phenomenon occurs is repaired, a kind of efficient shear wall through-wall bolt holes blocking side is provided Method.
The present invention is achieved by the following technical scheme: a kind of efficient shear wall through-wall bolt holes blocking method, is adopted With following steps: a, shear wall concreting finish after reaching strength of mould stripping, and form removal simultaneously takes out through-wall bolt, form band The bolt hole of pvc pipe;B, it chooses timber wedge drilling rod to be mounted on impact drill I, starts impact drill I, timber wedge drilling rod is gradually to bolt It bores and moves in hole, after finding that pvc pipe loosens, close impact drill I switch, pvc pipe is taken out from bolt hole;C, to coagulation After soil reaches some strength, chooses pyramidal alloy bit and be mounted on impact drill I, and on the conical surface of pyramidal alloy bit It is fixed with barricade snap ring, later on impact drill I carries out drilling through work against bolt hole in exterior wall outer end, when barricade snap ring It when being blocked by exterior wall end face, stops working, forms horn mouth in bolt hole outer end at this time;D, at the horn mouth of bolt hole Spreading glue, and blocked bolt hole outer end is fixed on the prefabricated mortar block that horn mouth cooperates;E, note is then chosen Sizing device carries out slip casting, and grouting device includes impact drill II, and the front end of impact drill II is clamped with hollow drill, the side of hollow drill Be provided with several mouth sprays on wall, the front end of hollow drill is provided with extruding slurry mouth, the tail end of hollow drill be provided with communicate therewith and The galvanized pipe connected by rotary joint, the upper end of galvanized pipe are provided with the funnel being threadedly coupled with it, and funnel top is provided with Strip aluminium sheet is installed with the cored screw being threadedly coupled with it on strip aluminium sheet, and cored screw lower end is provided with and funnel bottom is pasted The annular disc of conjunction, cored screw upper end is provided with rotating handles, and cored screw upper end is provided with the air pump communicated therewith;Note When slurry, rotation rotating handles and cored screw open annular disc first, and interfacial agents are poured into funnel, and opening impact bores II, interfacial agents enter hollow drill through galvanized pipe, and bolt hole is arrived in interfacial agents centrifugal atomization under the action of impact drill II Inner wall is then switched off impact drill II, and after the interfacial agents final set of bolt hole inner wall, expansive cement mortar is poured into funnel, It is again turned on impact drill II and opens air pump, expansive cement mortar is injected in bolt under the centrifugal force effect that hollow drill rotates The surface of hole inner wall interfacial agents, and under the action of air pump, expansive cement mortar is starched mouth by hollow drill forward ends thereof and is squeezed It is depressed at the center of bolt hole front end, blocks situation then according to mortar and exit hollow drill, at the same time, spray and squeeze Expansive mortar completes slip casting;F, at last artificial filling exterior wall inner end bolt hole to closely knit, bolt hole closure is finished.
Mortar in the shear wall through-wall bolt holes blocking method in funnel can realize oneself of funnel by control handle It is dynamic to open and close function;Horn mouth is drilled out on shear wall using pyramidal alloy bit, is blocked with prefabricated mortar block, is extended Water route, prevents rain leakage;It is dynamic using the brill at full speed of core drilling, the cohesive force of interfacial agents and shear wall is enhanced, simultaneously The cohesive force of mortar and interfacial agents is enhanced, mortar is squeezed using air pump, fills and reserved when hollow drill exits in bolt hole Hole, the mortar so blocked is firmly bonded with shear wall, blocks closely knit, overcomes existing shear wall through-wall bolt hole envelope It is stifled to there are problems that time-consuming and laborious, mortar waste is serious, reprocess difficult and hidden leakage defect and heat bridge phenomenon easily occurs.
Shear wall through-wall bolt holes blocking method of the present invention can be conveniently by bolt sealing hole, effectively Construction efficiency is improved, and is effectively controlled the dosage of mortar, while having the effect of that closure is closely knit, ensure that hole Quality is blocked, the generation of hidden leakage defect and heat bridge phenomenon has thoroughly been prevented, there is simple process, save the cost, prevent to do over again Repair phenomenon, easy to operate and low to worker operation skill requirement advantage.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of grouting device in the present invention;
Fig. 2 is that timber wedge drilling rod is mounted on the structural schematic diagram on impact drill I in the present invention;
Fig. 3 is that pyramidal alloy bit is mounted on the structural schematic diagram on impact drill I in the present invention;
Fig. 4 is the enlarged diagram in Fig. 1 at hollow drill.
In figure: 1- bolt hole, 2- timber wedge drilling rod, the pyramidal alloy bit of 3- impact drill I, 4-, 5- barricade snap ring, 6- are pre- Mortar block processed, 7- impact drill II, 8- hollow drill, 9- galvanized pipe, 10- funnel, 11- strip aluminium sheet, 12- cored screw, 13- ring Shape disk, 14- rotating handles, 15- air pump, 16- mouth spray, 17- squeeze slurry mouth.
Specific embodiment
A kind of efficient shear wall through-wall bolt holes blocking method, using following steps: a, shear wall concreting are complete Finish after reaching strength of mould stripping, form removal simultaneously takes out through-wall bolt, forms the bolt hole 1 with pvc pipe;B, timber wedge drilling rod is chosen 2 are mounted on impact drill I3, start impact drill I3, and timber wedge drilling rod 2 is gradually bored into bolt hole 1 and moved, when discovery pvc pipe loosens Afterwards, impact drill I3 switch is closed, pvc pipe is taken out from bolt hole 1;C, after concrete reaches some strength, cone is chosen Mesa-shaped alloy bit 4 is mounted on impact drill I3, and is fixed with barricade snap ring 5 on the conical surface of pyramidal alloy bit 4, then Opening impact bores I3, carries out drilling through work against bolt hole 1 in exterior wall outer end, when barricade snap ring 5 is blocked by exterior wall end face, It stops working, forms horn mouth in 1 outer end of bolt hole at this time;D, the spreading glue at the horn mouth of bolt hole 1, and will be with The prefabricated mortar block 6 of horn mouth cooperation is fixed on 1 outer end of bolt hole and is blocked;E, grouting device is then chosen to be infused Slurry, grouting device includes impact drill II7, and the front end of impact drill II7 is clamped with hollow drill 8, is provided on the side wall of hollow drill 8 Several mouth sprays 16, the front end of hollow drill 8 are provided with extruding slurry mouth 17, and the tail end of hollow drill 8, which is provided with, to be communicated therewith and lead to The galvanized pipe 9 of rotary joint connection is crossed, the upper end of galvanized pipe 9 is provided with the funnel 10 being threadedly coupled with it, and 10 top of funnel is set It is equipped with strip aluminium sheet 11, the cored screw 12 being threadedly coupled with it is installed on strip aluminium sheet 11,12 lower end of cored screw is provided with The annular disc 13 being bonded with 10 bottom of funnel, 12 upper end of cored screw are provided with rotating handles 14, and 12 upper end of cored screw It is provided with the air pump 15 communicated therewith;When slip casting, rotation rotating handles 14 and cored screw 12 open annular disc 13 first, Interfacial agents are poured into funnel 10, opening impact bores II7, and interfacial agents enter hollow drill 8 through galvanized pipe 9, impact drill II7's By interfacial agents centrifugal atomization to the inner wall of bolt hole 1 under effect, it is then switched off impact drill II7, the boundary to 1 inner wall of bolt hole After the agent final set of face, expansive cement mortar is poured into funnel 10, be again turned on impact drill II7 and opens air pump 15, expanding cement Mortar is injected in the surface of 1 inner wall interfacial agents of bolt hole under the centrifugal force effect that hollow drill 8 rotates, and in air pump 15 Under effect, expansive cement mortar is starched mouth 17 by the extruding of 8 front end of hollow drill and is squeezed to the center of 1 front end of bolt hole, Situation is blocked then according to mortar and exits hollow drill 8, at the same time, is sprayed simultaneously extrusion expansion mortar, is completed slip casting;F, last To closely knit at artificial filling exterior wall inner end bolt hole, the closure of bolt hole 1 is finished.

Claims (1)

1. a kind of efficient shear wall through-wall bolt holes blocking method, it is characterised in that: use following steps: a, shear wall coagulation Soil pours finish and reach strength of mould stripping after, form removal simultaneously takes out through-wall bolt, forms the bolt hole (1) with pvc pipe;B, it selects Timber wedge drilling rod (2) is taken to be mounted on impact drill I(3) on, start impact drill I(3), timber wedge drilling rod (2) is gradually into bolt hole (1) Bore and move, after finding that pvc pipe loosens, close impact drill I(3) switch, pvc pipe is taken out from bolt hole (1) is middle;C, to coagulation After soil reaches some strength, choose pyramidal alloy bit (4) and be mounted on impact drill I(3) on, and in pyramidal alloy bit (4) barricade snap ring (5), later on impact drill I(3 are fixed on the conical surface), it is carried out in exterior wall outer end against bolt hole (1) Work is drilled through, when barricade snap ring (5) is blocked by exterior wall end face, is stopped working, forms loudspeaker in bolt hole (1) outer end at this time Mouthful;D, the spreading glue at the horn mouth of bolt hole (1), and spiral shell will be fixed on the prefabricated mortar block (6) that horn mouth cooperates Keyhole hole (1) outer end is blocked;E, then choose grouting device and carry out slip casting, grouting device includes impact drill II(7), impact Bore II(7) front end be clamped with hollow drill (8), several mouth sprays (16), hollow drill are provided on the side wall of hollow drill (8) (8) front end is provided with extruding slurry mouth (17), and the tail end of hollow drill (8), which is provided with, to be communicated therewith and by rotary joint connection Galvanized pipe (9), the upper end of galvanized pipe (9) are provided with the funnel (10) being threadedly coupled with it, and funnel (10) top is provided with strip Aluminium sheet (11) is installed with the cored screw (12) being threadedly coupled with it on strip aluminium sheet (11), and cored screw (12) lower end is provided with The annular disc (13) being bonded with funnel (10) bottom, cored screw (12) upper end is provided with rotating handles (14), and hollow spiral shell Bar (12) upper end is provided with the air pump (15) communicated therewith;When slip casting, rotating handles (14) and cored screw (12) are rotated first Open annular disc (13), interfacial agents poured into the funnel (10), opening impact bores II(7), interfacial agents through galvanized pipe (9) into Enter hollow drill (8) then to close by the inner wall of interfacial agents centrifugal atomization to bolt hole (1) under the action of impact drill II(7) Close impact drill II(7), after the interfacial agents final set of bolt hole (1) inner wall, expansive cement mortar is poured into funnel (10), then Secondary opening impact bores II(7) and open air pump (15), expansive cement mortar sprays under the centrifugal force effect that hollow drill (8) rotates The surface in bolt hole (1) inner wall interfacial agents is penetrated, and under the action of air pump (15), expansive cement mortar passes through hollow drill (8) extruding slurry mouth (17) of front end is squeezed to the center of bolt hole (1) front end, blocks feelings then according to expansive cement mortar Condition exits hollow drill (8), at the same time, sprays simultaneously extrusion expansion cement mortar, completes slip casting;F, last artificial filling exterior wall To closely knit at the bolt hole of inner end, bolt hole (1) closure is finished.
CN201710649515.8A 2017-08-02 2017-08-02 A kind of efficient shear wall through-wall bolt holes blocking method Active CN107237511B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710649515.8A CN107237511B (en) 2017-08-02 2017-08-02 A kind of efficient shear wall through-wall bolt holes blocking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710649515.8A CN107237511B (en) 2017-08-02 2017-08-02 A kind of efficient shear wall through-wall bolt holes blocking method

Publications (2)

Publication Number Publication Date
CN107237511A CN107237511A (en) 2017-10-10
CN107237511B true CN107237511B (en) 2019-04-16

Family

ID=59989150

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710649515.8A Active CN107237511B (en) 2017-08-02 2017-08-02 A kind of efficient shear wall through-wall bolt holes blocking method

Country Status (1)

Country Link
CN (1) CN107237511B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643050B (en) * 2018-05-22 2020-02-11 宁夏路桥工程股份有限公司 Plugging method for through-wall pull rod hole
CN108979186A (en) * 2018-06-29 2018-12-11 上海全筑建筑装饰集团股份有限公司 Filling-up hole tool and method
CN109057341A (en) * 2018-11-01 2018-12-21 上海宝冶集团有限公司 A kind of method for blocking in Screw arbor with nut at both-ends hole
CN111155780B (en) * 2019-09-02 2021-05-07 广东博智林机器人有限公司 Screw hole plugging robot and building system with same
CN110863667A (en) * 2019-10-31 2020-03-06 上海建工七建集团有限公司 Anti-seepage plugging structure and method for concrete shear wall screw hole
CN113445772B (en) * 2020-03-27 2022-09-20 广东博鼎建筑科技有限公司 Mechanical arm, hole plugging device and hole plugging robot
CN113445771B (en) * 2020-03-27 2022-07-08 广东博鼎建筑科技有限公司 Hole plugging device and hole plugging robot
CN113737969A (en) * 2021-09-02 2021-12-03 三维建设工程咨询有限公司 Wall split bolt hole plugging method
CN114427264B (en) * 2022-01-18 2024-01-26 中国建筑第五工程局有限公司 Single-person-operated external wall screw hole plugging equipment for building construction and operation method thereof
CN115683708B (en) * 2022-11-01 2023-03-31 山东钰涛消防科技有限公司 Automatic sampling detection plugging device for wall thermal insulation material

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03233075A (en) * 1990-02-06 1991-10-17 Shimizu Corp Cut-off method of concrete construction and injection device of grout such as sealing compound, etc.
JPH0886096A (en) * 1994-09-19 1996-04-02 Batsusaa:Kk Injection method of cut-off agent in concrete structure
KR100586395B1 (en) * 2003-12-09 2006-06-09 김천만 A cement injector and method for mending a crack using it
CN202559540U (en) * 2012-05-08 2012-11-28 中建六局建设发展有限公司 Waterproof plugging structure for outer wall split bolt hole
CN103866977B (en) * 2012-12-11 2016-04-27 中建四局第三建筑工程有限公司 A kind of impervious method for blocking of shear wall screw hole through walls and structure
CN103790382A (en) * 2014-01-28 2014-05-14 中建四局第三建筑工程有限公司 Rapid blocking method and structure of external wall screw hole of concrete structure
CN204850463U (en) * 2015-07-23 2015-12-09 山西八建集团有限公司 Shear force wall split bolt hole plugging device
CN206279789U (en) * 2016-12-09 2017-06-27 中国建筑第四工程局有限公司 A kind of plugging structure of exterior wall Screw arbor with nut at both-ends hole

Also Published As

Publication number Publication date
CN107237511A (en) 2017-10-10

Similar Documents

Publication Publication Date Title
CN107237511B (en) A kind of efficient shear wall through-wall bolt holes blocking method
CN207079930U (en) A kind of efficiently centrifugal grouting device of shear wall through-wall bolt hole
CN100513745C (en) Construction method for mechanical hole reaming of anchor rod
CN108999421A (en) A kind of wall body structure seepage treatment method
CN103806840B (en) One-way spiral half soil compaction drill bit and one-way spiral half Squeezing Soil Pile construction technology
CN204959746U (en) Expand integral type stock soon
CN101260669A (en) Drilling, spraying, injection integral enlarging anchor rod construction method
CN210216402U (en) Drilling machine for extruding, spraying, reaming and pressure-grouting concrete pile
CN103291222B (en) Reamer bit for building long-screw pile machine
CN103669337A (en) Head-expansion long spiral drilling pressure irrigation pile and construction method and construction device thereof
CN105464396A (en) Reinforcing method for external wall of protective historical building
CN104895581A (en) Tunnel lining rapid repair structure based on carbon fiber woven mesh and repair method thereof
CN106192996B (en) A kind of T shape drilling tools of construction method and T shapes the cast pile driving construction of T shapes stake
CN112726590A (en) Method for processing quality defects of cast-in-situ bored pile
CN107975651A (en) A kind of method of floor pipeline quick blocking
CN201050303Y (en) Self-dumping cone type spiral anchor drill bit
CN213061989U (en) High-pressure rotary spraying device
CN107806096B (en) Expanding compound pile construction method compacted again is cut in whirl spraying
CN206015668U (en) A kind of T-shaped pours into a mould the T-shaped drilling tool of pile driving construction
CN210621680U (en) Extrusion-spraying reaming pressure-grouting concrete pile
CN206571424U (en) High pressure base expanding and base expanding screw rod drilling equipment and its stake end enlarged footing
CN205421258U (en) High water spray mud is pressed and is irritated concrete composite set
CN207660284U (en) A kind of efficient shear wall through-wall bolt hole mortar controllable type grouting device
CN203559413U (en) End-expanded type long spiral drilling hole pressure pouring pile and construction device thereof
CN110607881A (en) Whitewash mortar hollowing bonding regeneration technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant