CN103866977B - A kind of impervious method for blocking of shear wall screw hole through walls and structure - Google Patents

A kind of impervious method for blocking of shear wall screw hole through walls and structure Download PDF

Info

Publication number
CN103866977B
CN103866977B CN201210528785.0A CN201210528785A CN103866977B CN 103866977 B CN103866977 B CN 103866977B CN 201210528785 A CN201210528785 A CN 201210528785A CN 103866977 B CN103866977 B CN 103866977B
Authority
CN
China
Prior art keywords
walls
screw hole
shear wall
cement mortar
plug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210528785.0A
Other languages
Chinese (zh)
Other versions
CN103866977A (en
Inventor
刘亮
杨淑琼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Third Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority to CN201210528785.0A priority Critical patent/CN103866977B/en
Publication of CN103866977A publication Critical patent/CN103866977A/en
Application granted granted Critical
Publication of CN103866977B publication Critical patent/CN103866977B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

<b> the invention discloses the impervious method for blocking of a kind of shear wall screw hole through walls and structure.Its method with impact electric hammer, plastic bushing in screw hole through walls is smashed and cleaned out, then silicone weather resistant structure glue is injected as plug with glue rifle, plain-water slurry is sprayed again in screw hole through walls, and fill expansive cement mortar and prevent seepage, finally with the sealing of 1:2 dry cement mortar, fill in closely knit.The present invention can reserve in screw hole plugging construction process through walls in shear wall structure and make up current national codes not to the blank of its Uniform provisions, its processing method of specification and acceptance criteria, guarantee that exterior wall leakproof provides powerful guarantee, improves effect, remove a hidden danger, economic environmental protection.Meanwhile, also reference value can be provided for similar engineering construction.</b>

Description

A kind of impervious method for blocking of shear wall screw hole through walls and structure
Technical field
the present invention relates to the impervious method for blocking of a kind of shear wall screw hole through walls and structure, belong to architectural engineering construction technique field.
Background technology
shear wall, in work progress, needs to fix by the template of screw rod through walls by shear wall both sides, after building, is conveniently convenient to screw rod through walls releases from body of wall, and on screw rod through walls, cover has plastic pipe.When after the form removable of building shear wall, shear wall can leave the hole that cover has plastic pipe.In order to anti-hole seepage here, cause hidden dangers in project, need this screw hole through walls to carry out shutoff.Shutoff in the past directly cement mortar is daubed into from wall-through hole two ends in the process of plastering, effect low and in hole fill leakiness; Plastic bushing is not removed, and defines one separation layer in hole, makes wall-through hole be present in the hidden danger that seriously seeps water.
Summary of the invention
the object of the invention is to, the impervious method for blocking of a kind of shear wall screw hole through walls and structure are provided.In shear wall screw hole shutoff through walls process, current national codes can be made up not to the blank of its Uniform provisions, its processing method of specification and acceptance criteria, guarantee that exterior wall leakproof provides effective measure guarantee, improve effect, remove a hidden danger, economic environmental protection.
technical scheme of the present invention:
the impervious method for blocking of a kind of shear wall screw hole through walls, the method operates according to the following steps:
a, employing are impacted electric hammer and are smashed by plastic bushing in screw hole through walls;
b, round steel is utilized to remove clean by plastic residues in screw hole through walls;
c, utilize air compressor air gun by screw hole through walls dust blow down;
d, water pistol is utilized to clean up in screw hole through walls;
in E, shear wall apertura lateralis after the drying, plug is set;
f, utilize water pistol will spray plain-water slurry in screw hole through walls together;
g, inside shear wall, utilize air compressor by the expansive cement mortar injection hole for preparing;
h, to receive after water until cement mortar, two ends adopt the sealing of 1:2 dry cement mortar, fill in closely knit;
i, finally to sprinkle water maintenance, enter next process.
in preceding method, in described steps A, the length of the bit is greater than shear wall's thickness 100mm and is advisable, and drill bit specification is identical with plastic bushing external diameter.
in preceding method, in described step B, the diameter of round steel is identical with screw diameter through walls.
in preceding method, in described step e, plug is positioned at exit orifice 20mm position, and plug is the silicone weather resistant structure glue of thickness 20mm.
in preceding method, described plug adopts glue rifle to inject.
in preceding method, in described step G, inside shear wall, 20mm shutoff space is reserved in aperture.
according to the impervious plugging structure of shear wall screw hole through walls that preceding method is formed, the outer aperture Nei Chu of described shear wall screw hole through walls is provided with plug, be provided with expansive cement mortar in shear wall screw hole through walls, the inner orifice of shear wall screw hole through walls and outer aperture are provided with cement mortar sealing.
in aforementioned structure, described plug is positioned at exit orifice 20mm position, and plug is the silicone weather resistant structure glue of thickness 20mm.
in aforementioned structure, the thickness of described cement mortar sealing is 20mm.
compared with prior art, the present invention can reserve in screw hole plugging construction process through walls in shear wall structure and make up current national codes not to the blank of its Uniform provisions, its processing method of specification and acceptance criteria, guarantee that exterior wall leakproof provides powerful guarantee, improve effect, remove a hidden danger, economic environmental protection.Meanwhile, also reference value can be provided for similar engineering construction.
Accompanying drawing explanation
fig. 1 is structural representation of the present invention.
being labeled as of accompanying drawing: 1-shear wall screw hole through walls, 2-plug, 3-expansive cement mortar, 4-cement mortar are sealed.
Detailed description of the invention
below in conjunction with accompanying drawing, the present invention is described in further detail, but not as any limitation of the invention.
the impervious method for blocking of a kind of shear wall screw hole through walls, as shown in Figure 1.The method operates according to the following steps:
a, employing are impacted electric hammer and are smashed by plastic bushing in screw hole through walls; The length of the bit is greater than shear wall's thickness 100mm and is advisable, and drill bit specification is identical with plastic bushing external diameter.
b, round steel is utilized to remove clean by plastic residues in screw hole through walls; The diameter of round steel is identical with screw diameter through walls.
c, utilize air compressor air gun by screw hole through walls dust blow down;
d, water pistol is utilized to clean up in screw hole through walls;
in E, shear wall apertura lateralis after the drying, plug is set; Plug is positioned at exit orifice 20mm position, and plug is the silicone weather resistant structure glue of thickness 20mm; Plug adopts glue rifle to inject;
f, utilize water pistol will spray plain-water slurry in screw hole through walls together;
g, inside shear wall, utilize air compressor by the expansive cement mortar injection hole for preparing; Inside shear wall, 20mm shutoff space is reserved in aperture;
h, to receive after water until cement mortar slurry, two ends adopt the sealing of 1:2 dry cement mortar, fill in closely knit;
i, finally to sprinkle water maintenance, enter next process.
according to the impervious plugging structure of shear wall screw hole through walls that preceding method is formed, as shown in Figure 1.The outer aperture Nei Chu of described shear wall screw hole through walls 1 is provided with plug 2, is provided with expansive cement mortar 3 in shear wall screw hole 1 through walls, and the inner orifice of shear wall screw hole through walls 1 and outer aperture are provided with cement mortar sealing 4.Plug 2 is positioned at exit orifice 20mm position, and plug is the silicone weather resistant structure glue of thickness 20mm.The thickness of cement mortar sealing 4 is 20mm.

Claims (5)

1. the impervious method for blocking of shear wall screw hole through walls, is characterized in that: the method operates according to the following steps:
A, employing are impacted electric hammer and are smashed by plastic bushing in screw hole through walls; Impact electric hammer drill length is greater than shear wall's thickness 100mm and is advisable, and drill bit specification is identical with plastic bushing external diameter;
B, round steel is utilized to remove clean by plastic residues in screw hole through walls; The diameter of round steel is identical with screw diameter through walls;
C, utilize air compressor air gun by screw hole through walls dust blow down;
D, water pistol is utilized to clean up in screw hole through walls;
In E, shear wall apertura lateralis after the drying, plug is set; Plug is positioned at exit orifice 20mm position, and plug is the silicone weather resistant structure glue of thickness 20mm;
F, utilize water pistol will spray plain-water slurry in screw hole through walls together;
Inside G, shear wall, 20mm shutoff space is reserved in aperture; Inside shear wall, utilize air compressor by the expansive cement mortar injection hole for preparing;
H, to receive after water until cement mortar, two ends adopt the sealing of 1:2 dry cement mortar, fill in closely knit;
I, finally to sprinkle water maintenance, enter next process.
2. method according to claim 1, is characterized in that: described plug adopts glue rifle to inject.
3. the impervious plugging structure of shear wall screw hole through walls that method is formed according to the arbitrary claim of claim 1-2, it is characterized in that: the outer aperture Nei Chu of described shear wall screw hole through walls (1) is provided with plug (2), be provided with expansive cement mortar (3) in shear wall screw hole through walls (1), the inner orifice of shear wall screw hole through walls (1) and outer aperture are provided with cement mortar sealing (4).
4. structure according to claim 3, it is characterized in that: described plug (2) is positioned at exit orifice 20mm position, plug is the silicone weather resistant structure glue of thickness 20mm.
5. structure according to claim 3, is characterized in that: the thickness of described cement mortar sealing (4) is 20mm.
CN201210528785.0A 2012-12-11 2012-12-11 A kind of impervious method for blocking of shear wall screw hole through walls and structure Active CN103866977B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210528785.0A CN103866977B (en) 2012-12-11 2012-12-11 A kind of impervious method for blocking of shear wall screw hole through walls and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210528785.0A CN103866977B (en) 2012-12-11 2012-12-11 A kind of impervious method for blocking of shear wall screw hole through walls and structure

Publications (2)

Publication Number Publication Date
CN103866977A CN103866977A (en) 2014-06-18
CN103866977B true CN103866977B (en) 2016-04-27

Family

ID=50905956

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210528785.0A Active CN103866977B (en) 2012-12-11 2012-12-11 A kind of impervious method for blocking of shear wall screw hole through walls and structure

Country Status (1)

Country Link
CN (1) CN103866977B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612289A (en) * 2015-02-13 2015-05-13 中冶建工集团有限公司 Method for constructing external walls
CN104831925B (en) * 2015-04-09 2017-01-18 江苏建筑职业技术学院 Passive house wall bushing waterproof air tightness structure construction method
CN107237511B (en) * 2017-08-02 2019-04-16 大同泰瑞集团建设有限公司 A kind of efficient shear wall through-wall bolt holes blocking method
CN107461036A (en) * 2017-09-22 2017-12-12 中建四局第六建筑工程有限公司 A kind of homogeneity precast facade holes blocking method
CN114439121A (en) * 2022-02-28 2022-05-06 中冶南方城市建设工程技术有限公司 Method for plugging outer wall through-wall screw hole

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279265A (en) * 1994-04-06 1995-10-24 Hayakawa Rubber Co Ltd Water stop structure for form separator
JP2004052256A (en) * 2002-07-17 2004-02-19 Railway Technical Res Inst Cutoff separator
CN2628646Y (en) * 2003-06-11 2004-07-28 许道满 Concrete wall shuttering mounting positioning fastening assembly
CN102787718A (en) * 2011-05-18 2012-11-21 锦宸集团有限公司 External connection type waterproof wall-penetrating double-headed screw

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07279265A (en) * 1994-04-06 1995-10-24 Hayakawa Rubber Co Ltd Water stop structure for form separator
JP2004052256A (en) * 2002-07-17 2004-02-19 Railway Technical Res Inst Cutoff separator
CN2628646Y (en) * 2003-06-11 2004-07-28 许道满 Concrete wall shuttering mounting positioning fastening assembly
CN102787718A (en) * 2011-05-18 2012-11-21 锦宸集团有限公司 External connection type waterproof wall-penetrating double-headed screw

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《*****工程螺杆洞封堵专项施工方案》;zhizhuo621;《百度文库》;20120611;第1-4页 *

Also Published As

Publication number Publication date
CN103866977A (en) 2014-06-18

Similar Documents

Publication Publication Date Title
CN103866977B (en) A kind of impervious method for blocking of shear wall screw hole through walls and structure
CN104060704B (en) The mechanical type restorative procedure of heat preservation mortar for outer wall hollowing and structure
CN202559540U (en) Waterproof plugging structure for outer wall split bolt hole
CN103132690B (en) Basement exterior wall unilateral template and method for supporting template thereof
CN204728495U (en) Outer wall of basement Screw arbor with nut at both-ends hole plugging structure
CN204703312U (en) A kind of outer shear wall bolt hole plugging structure
CN105604593A (en) Three-stage anchoring combined type hollow grouting anchor rod
CN104775530A (en) Interface treatment method for horizontal construction seam of concrete
CN203296026U (en) Air exhausting device for locked and plugged diversion tunnel
CN207959289U (en) Structure is repaired in a kind of leak for basement post-pouring zone position
CN104100278A (en) Construction method for demolishing original arch frames and primarily supporting windings of transition sections of tunnels
CN104179205A (en) Anticorrosion reinforcing method of transmission line tower foundation
CN103670439A (en) Tunnel lining construction method
CN106116201A (en) A kind of concrete anticracking adulterating agent
CN209163465U (en) A kind of hydrous fluids outer wall of basement Screw arbor with nut at both-ends node waterproof structure
CN204252367U (en) Air-conditioning duct wears the lightweight precast concrete component of building block exterior wall
CN203034617U (en) Impervious and plugging structure for shear wall through-wall screw hole
CN204163744U (en) Net spray leveling layer self waterproof structure between a kind of subway station stake
CN103590508A (en) Composite thermal insulating wall structure and construction method thereof
CN203625902U (en) Expansion shell type anchorage head and anchor rod with same
CN203160693U (en) Detachable water stopping screw
CN102477798A (en) Method for repairing crack of outer wall
CN204552450U (en) A kind of integral prefabricated thermal-insulating waterproof wafts window
CN208534084U (en) A kind of tile decorative surface point face reinforcing repairerment engineering method anchor studs
CN210857547U (en) Be used for outer wall screw rod entrance to a cave plugging device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 57, Beijing Road, Honghuagang District, Zunyi City, Guizhou Province

Patentee after: The Third Construction Co.,Ltd. of China Construction Fourth Engineering Bureau

Address before: Beijing road 563003 in Guizhou province Zunyi city Honghuagang District No. 57

Patentee before: THE THIRD CONSTRUCTION & ENGINEERING Co. OF CCFED