CN112726590A - Method for processing quality defects of cast-in-situ bored pile - Google Patents

Method for processing quality defects of cast-in-situ bored pile Download PDF

Info

Publication number
CN112726590A
CN112726590A CN202011619520.2A CN202011619520A CN112726590A CN 112726590 A CN112726590 A CN 112726590A CN 202011619520 A CN202011619520 A CN 202011619520A CN 112726590 A CN112726590 A CN 112726590A
Authority
CN
China
Prior art keywords
processing
pressure
hole
treatment
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011619520.2A
Other languages
Chinese (zh)
Inventor
王轶
项子儒
王跃华
朱晨辉
俞隽
顾镇媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong University
Original Assignee
Nantong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong University filed Critical Nantong University
Priority to CN202011619520.2A priority Critical patent/CN112726590A/en
Publication of CN112726590A publication Critical patent/CN112726590A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/64Repairing piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes

Abstract

The invention discloses a method for processing quality defects of cast-in-situ bored piles, which comprises the following steps: step S1, detecting the integrity of the pile body; step S2, drilling, core pulling and sampling; step S3, determining the setting of the processing hole, and drilling the processing hole; step S4, consolidation treatment is carried out on soil outside the pile at the defective part of the defective I-shaped pile; step S5, performing high-pressure rotary jet cutting and clearing treatment on the defective part until all the treatment holes are communicated; step S6, carrying out gas lift slag removal treatment on each treatment hole; step S7, high-pressure cement slurry is injected; step S8, installing an orifice pipe; step S9, secondary high-pressure cement slurry injection; the invention adopts the high-pressure jet cutting grouting treatment process to remove mud inclusion and segregation loose concrete at the defect part, then combines with gas lift to remove sediment sundries, then carries out high-pressure grouting, and finally carries out secondary high-pressure grouting, and the strength and the bearing capacity of the defect pile foundation treated by the process are greatly improved, and the invention also has the advantages of short construction period and low cost.

Description

Method for processing quality defects of cast-in-situ bored pile
Technical Field
The invention relates to the technical field of bridge construction, in particular to a method for processing quality defects of cast-in-situ bored piles.
Background
Cast-in-situ bored piles are one of the main foundation forms of bridge engineering nowadays, and in actual construction and production, various defects of a pile body are often caused by site hydrogeology problems and problems of construction organization, equipment, materials and process technology control. Such as: pile breaking, mud clamping, reducing, concrete segregation and the like. When the above problems occur, the pile body integrity is judged to be the type III pile or below in the pile body integrity detection. That is, the pile body has obvious or serious defects, which affect the bearing capacity of the pile body structure and can not meet the requirements of the structure function and quality.
For this purpose, the pile is generally treated by: 1. the original pile is impacted, crushed, the hole is formed again, the reinforcement cage is arranged, concrete is poured again, namely, the defective pile is removed, and the pile is made again; 2. pile repairing, namely repairing two piles at two sides of the original pile position, then arranging a cross beam, and manufacturing an upright column above the original pile position on the cross beam; 3. and excavating to the defect position for treatment after certain safety measures are taken for the shallow defect depth.
In recent years, a process for treating the defects of the pile body by high-pressure grouting in the pile appears, and related articles are occasionally published in related magazines. However, most of the treatment effects are not good, and the integrity level of the pile body cannot be improved generally. The key points are that the defect part cannot be effectively cleaned, and the parameters of construction and materials cannot be well mastered.
The high-pressure jet cutting mud jacking treatment process adopted by the invention is a novel cast-in-situ bored pile treatment process, and practice proves that the high-pressure jet cutting mud jacking treatment process has the characteristics of obvious effect, short construction period and low cost, and is one of effective methods for improving the integrity of a pile body.
Disclosure of Invention
In view of the above defects in the prior art, the technical problem to be solved by the invention is to provide a method for processing the quality defect of a bored pile, the method adopts a high-pressure jet cutting grouting processing technology to remove mud inclusion and segregation loose concrete at the defect part, and then the method is combined with air lift to remove sediment impurities, compared with the prior art that grouting is directly performed or grouting is performed after the defect is removed, the method has better processing effect, and can greatly improve the bearing capacity of the defective pile foundation.
The invention provides a method for processing quality defects of a cast-in-situ bored pile, which comprises the following steps:
step S1, detecting the integrity of the cast-in-situ bored pile body;
step S2, drilling, core-pulling and sampling the bored pile body;
step S3, determining the type, position, area and thickness of the defect according to the step S1 and the step S2, further determining the hole position, number and depth of the processing hole according to the type, position, area and thickness of the defect, and drilling the processing hole;
step S4, judging whether the cast-in-situ bored pile belongs to a defective I-shaped pile or not according to the type, position, area and thickness of the defect, and if the cast-in-situ bored pile belongs to the defective I-shaped pile, performing consolidation treatment on a soil body outside the cast-in-situ bored pile;
step S5, performing high-pressure rotary jet cutting and clearing treatment on the defective part until all the treatment holes are communicated;
step S6, carrying out gas lift slag removal treatment on each processing hole until each processing hole is cleaned;
step S7, performing high-pressure cement slurry pressure injection treatment on the treatment holes;
step S8, arranging an orifice pipe at the orifice position of each processing hole, selecting one processing hole as a grouting hole from the plurality of processing holes, and taking the rest processing holes as slurry outlet holes;
and step S9, performing secondary high-pressure cement slurry pressure injection treatment on the grouting holes.
Further, in step S1, during the construction of the cast-in-situ bored pile, three to four acoustic pipes are embedded into the pile body of the cast-in-situ bored pile, and after the construction is completed and reaches a certain age, the defects of the pile are detected by using an acoustic transmission instrument;
in the step S2, a pile body of the cast-in-situ bored pile is drilled and sampled by a drill, the formed hole is a cored hole, and then it is determined by a pile body sample: type, location, area and thickness of the defect.
Further, in the step S3, drilling a processing hole in the pile body of the cast-in-situ bored pile by using a drilling machine, wherein the diameter of the processing hole is 11 cm; selecting the core-pulling holes as the processing holes, and increasing the number of the missing processing holes when the number of the processing holes to be arranged is higher than the actual number of the core-pulling holes;
the number of the processing holes is at least two, and the bottoms of the processing holes are at least 50cm below the positions where the defects are located.
Further, in the step S4, the cement is consolidated by compaction grouting, and the amount of cement is 144kg/m3The water-cement ratio is controlled to be 0.5-0.6, and the grouting pressure is controlled to be 0.4-0.5 MPa; and if the slurry does not sink, stopping grouting, increasing the grouting pressure to 0.6MPa, continuing grouting, and if the slurry does not sink within 10-15 min after the continuous grouting, finishing the consolidation treatment operation.
Further, in step S5, the high-pressure jet cutting and removing process specifically includes:
inserting a high-pressure rotary spraying pipe into the processing hole, wherein the length of the high-pressure rotary spraying pipe is 6cm, four holes with the aperture of 1.8mm are uniformly distributed at the periphery of the bottom of the high-pressure rotary spraying pipe, the high-pressure rotary spraying pipe rotates at a high speed at the defective part of the pile body to form a cutting water disc, and the cutting water disc performs rotary spraying, cutting and cleaning treatment on the defective part of the pile body; the high-pressure rotary spraying pipe is used for repeatedly carrying out rotary spraying, cutting and cleaning treatment on the defective part from bottom to top and from top to bottom; the area treated by the high-pressure rotary spraying pipe needs to cover the defect part, and the upper part and the lower part of the area exceed the defect part by more than 50 cm;
the spraying pressure value of the high-pressure rotary spraying pipe is 28-30 MPa; the rotating speed is 15-18r/min, the lifting speed is 15cm/min, and the discharge capacity is 60-70L/min.
Further, the step S6 is specifically: and arranging an air hose in the treatment hole, carrying out combined deslagging treatment in the hole by adopting an air lift method in combination with the operation of pressing water downwards, pumping out larger particles in the treatment hole by adopting a sand pump, and repeating the steps until clear water returns from each treatment hole.
When the gas lift method is used for slag removal treatment in the hole, the air quantity is set to be 9m3More than min, and the pressure is set to be more than 0.7 MPa.
Further, in step S7, the high-pressure cement slurry pressure injection processing specifically includes:
firstly, selecting a processing hole, inserting a high-pressure rotary jet pipe into the processing hole, then performing cement paste pressure injection by adopting high-pressure cement paste equipment, and finally completing the operation of pressure cement paste pressure injection processing when the specific gravity of cement paste returned from the other processing holes is the same as that of the injected cement paste and all the processing holes are filled with cement paste;
when the cement paste is injected, the pressure is controlled to be 1.0MPa, and the specific gravity of the cement paste is detected in a field detection mode.
Further, in the step S8, the orifice pipe includes a flange plate, an expansion screw is disposed on the flange plate, and the orifice pipe is fixedly connected to the concrete on the top of the bored pile through the expansion screw; the lower end of the orifice pipe is sealed by epoxy resin cement mortar and is tightly cemented with the pile body.
Further, in the step S9, the secondary high-pressure cement slurry is continuously injected until the gap generated when the step S7 is performed is filled up, with the injection pressure of the secondary high-pressure cement slurry being 2.0 MPa.
Further, in the step S7 and the step S9, the cement strength of the cement paste is one grade higher than that of the cement used for the bored pile, the water cement ratio of the cement paste is less than 0.45, 0.6% of an expanding agent, 3% of a water reducing agent and a retarder are added, and the specific gravity of the cement paste is more than 1.9g/cm3
The invention has the beneficial effects that:
1. compared with the prior art, the high-pressure jet cutting and grouting treatment process has the advantages that high-pressure water jet is adopted to remove mud inclusion and segregation loose concrete at the defect part, then sediment impurities are removed by combining a gas lift method, after the removal is finished, the jet grouting pipe is sunk to the bottom of the hole for high-pressure grouting, and finally secondary high-pressure grouting is carried out, so that the strength and the bearing capacity of the defect pile foundation treated by the process are greatly improved, and the process has the advantages of short construction period and low cost.
2. The invention consolidates the soil outside the pile by a compaction grouting method, thereby not only effectively preventing the problem that the soil outside the pile collapses when hydraulic high-pressure jet cutting is carried out inside the pile, but also greatly reducing the cost.
3. The invention adopts the combination of high-pressure rotary jet cutting and removing slag with a gas lift method, and solves the problem of poor treatment effect caused by the fact that the common rotary jet cutting cannot effectively clean the defect part.
4. The invention solves the problems of easy shrinkage, gaps and the like of cement paste caused by large water cement ratio by a secondary grouting measure, and greatly improves the grouting reinforcement effect.
5. According to the invention, through a large number of experiments, the optimal injection pressure value of the high-pressure rotary spray pipe is mastered; rotational speed, lift speed and displacement; and the technical parameters such as the proportion of cement paste and the like well guide the construction.
Drawings
Figure 1 is a schematic view of a defective type i pile.
Figure 2 is a schematic view of a defect type ii pile.
Fig. 3 is a schematic diagram of soil consolidation outside a defective I-shaped pile.
FIG. 4 is a process flow diagram of the present invention.
In the figure: 1-sounding pipe; 2-core-pulling holes; 3-treating the pores; 4-intact part of pile body; 5-defective part of pile body; 6-consolidation of soil outside the pile.
Detailed Description
In order that the invention may be better understood, the invention will now be further illustrated by the following examples, which are intended to be illustrative only and are not to be construed as limiting the invention in any way: the invention is not described in detail, but is well known to those skilled in the art.
Example 1
Referring to fig. 2 and 4, the defective part 5 of the pile body is located in the pile body, the defective part 5 of the pile body is wrapped by the intact part 4 of the pile body, and the outer wall of the pile body is not damaged greatly.
Step S1, detecting the integrity of the cast-in-situ bored pile body
Specifically, in the embodiment, the integrity of the pile body is detected by using a sound wave transmission method, that is, a plurality of sound detection tubes 1 are embedded during pile construction, specifically, several sound detection tubes are arranged according to different pile diameters, in the embodiment, four sound detection tubes 1 are embedded, and after the pile construction is completed and reaches a certain age, a sound wave transmission instrument is used for detecting the defects of the pile.
Step S2, drilling the bored pile body and performing core-pulling sampling;
specifically, the hole left after the drilling treatment is a cored hole 2, and the aperture of the cored hole 2 is 11 cm; the acoustic transmission method can detect the general type, position, area and thickness of the pile body defect, but all are not very accurate. For this purpose, the type, location, area and thickness of the defect must be further defined by core-pulling drilling.
Step S3, determining the type, position, area and thickness of the defect according to the step S1 and the step S2, further determining the hole position, number and depth of the processing hole 3 according to the type, position, area and thickness of the defect, and drilling the processing hole 3;
specifically, the number of the processing holes 3 is determined according to the area of the defect, the number of the processing holes 3 is not less than 2, and the depth of the hole drill is not less than 50cm below the pile defect part. The number of the processing holes 3 is not less than 2 in order to ensure that a passage can be formed in a defective portion, the aperture of the processing hole 3 is 11cm, the core hole 2 is selected as the processing hole 3, and when the number of the processing holes 3 to be arranged is higher than the number of the actual core holes 2, the number of the missing processing holes 3 is increased.
Step S5, performing high-pressure rotary jet cutting and clearing treatment on the defective part until all the treatment holes 3 are communicated;
specifically, the high-pressure jet cutting and removing treatment comprises the following steps: arranging a high-pressure rotary spraying pipe in the processing hole 3, wherein the length of the high-pressure rotary spraying pipe is 6cm, four holes with the aperture of 1.8mm are uniformly distributed at the periphery of the bottom of the high-pressure rotary spraying pipe, the high-pressure rotary spraying pipe rotates at a high speed at the defective part of the pile body to form a cutting water disc, and the cutting water disc performs rotary spraying, cutting and cleaning treatment on the defective part of the pile body; the high-pressure rotary spraying pipe is used for repeatedly carrying out rotary spraying, cutting and cleaning treatment on the defective part from bottom to top and from top to bottom; the defect part is required to be covered in the area treated by the high-pressure rotary spraying pipe, and the upper part and the lower part of the area exceed the defect part by more than 50cm so as to ensure that no blind area is left; the defect parts of the processing holes 3 are cut and cleaned respectively, so that the defect problem is thoroughly eliminated and the processing holes 3 are communicated with each other;
the jet pressure value, the rotating speed, the lifting speed and the discharge capacity of the high-pressure rotary jet pipe are determined according to the type, the position, the area and the thickness of the pile body defect.
The effect is better, in the embodiment, the injection pressure value of the high-pressure rotary spray pipe is 28 MPa; the rotating speed is 15r/min, the lifting speed is 15cm/min, and the discharge capacity is 60L/min.
Step S6, carrying out gas lift slag removal treatment on each processing hole 3 until each processing hole 3 is completely treated;
specifically, a ventilating hose is arranged in the processing hole 3, the gas lift method is adopted to carry out slag removal processing in the hole in combination with the operation of pressing water downwards, larger particles in the processing hole 3 are pumped out by a sand pump, and the operation is repeatedly carried out in the hole mode until clear water returns from each processing hole 3; when the gas lift method is used for slag removal treatment in the hole, the air quantity needs to be set to be 9m3More than min, and the pressure is set to be more than 0.7 MPa.
In this embodiment, to achieve a more excellent effect, the air volume is set to 15m3And/min, the pressure is set to be 0.9MPa, more cement gravel and broken stone are sprayed out from the treatment hole 3 at the initial stage of slag removal, and then water gradually becomes clear, which shows that the cleaning effect is good.
Step S7, grouting the grouting holes by using high-pressure cement slurry equipment; until the injected cement paste and the water returned from the grout outletThe specific gravity of the mud is consistent and each treatment hole 3 is filled with the cement slurry. The cement grade adopted by the cement paste is higher than that adopted by the bored pile body, the cement-water-cement ratio adopted by the cement paste is less than 0.45, and the specific gravity is more than 1.9g/cm3In addition, 0.6% of expanding agent, 3% of water reducing agent and a proper amount of retarder are added, in the embodiment, in order to achieve better effect, the cement water cement ratio adopted by the cement paste is 0.41, and the specific gravity is 2.0g/cm3
Step S8, an orifice pipe is provided at the orifice position of each processing orifice 3, one processing orifice 3 is selected as a grouting orifice from the plurality of processing orifices 3, and the remaining processing orifices 3 are outlet orifices. The hole pipe is fixedly connected with pile top concrete through an expansion screw by utilizing a flange plate on the pipe, and the lower end of the hole pipe is sealed by epoxy resin cement mortar and is tightly cemented with a pile body.
After step S8 is completed, a second injection of cement slurry is performed, the pressure applied to the injection cement slurry is 2.0MPa, and the injection cement slurry is stabilized for 30 minutes to fill up the pores that may appear during shrinkage and the first pressing.
Example 2
Referring to fig. 1 and 4, a defective pile body portion 5 includes an outer wall of a pile body, and for this defect, the present embodiment provides another method for processing a quality defect of a cast-in-situ bored pile, where the method for processing a quality defect of a cast-in-situ bored pile provided by the present embodiment is different from the method in embodiment 1 in that:
after the step S3 is completed, before the step S5 is performed, that is, in the step S4, when it is determined that the type of the defect is the defect type reflected in fig. 1, a compaction grouting process is required to perform grouting consolidation on the soil outside the pile at the defective part 5 of the pile body, that is, the soil consolidating part 6 outside the pile, so as to prevent the soil outside the pile from being collapsed when hydraulic high-pressure jet cutting is performed inside the pile; in some practical engineering situations, under the condition that the injection pressure value, the rotation speed, the lifting speed and the discharge capacity of the high-pressure rotary jet pipe cannot be accurately determined, a compaction grouting process can be adopted to perform grouting consolidation on the soil outside the pile at the defective position so as to prevent the soil outside the pile from collapsing when hydraulic high-pressure rotary jet cutting is performed inside the pile, and the operation can reduce the risk of engineering construction.
In this embodiment, in step S4, the compaction grouting method is performed by using a vibrating plate for steel pipes to be pressed into the soil layer to a designed depth, and using a construction sequence of jumping holes from bottom to top and grouting at intervals. The specific parameters are as follows: the cement amount is 144kg/m3, the water cement ratio is 0.5, the grouting pressure is 0.5MPa, and the grouting is stopped when the slurry does not sink within 15 min. The effective diameter of the grouting is 1.0 m.
In the present embodiment, in step S5, the injection pressure value of the high-pressure rotary nozzle is 30 Mpa; the rotating speed is 18r/min, the lifting speed is 15cm/min, and the discharge capacity is 70L/min.
In this embodiment, in step S6, when the in-hole slag removal treatment is performed by the gas lift method, the air flow rate is set to 9m3Min, the pressure was set at 0.7 MPa.
In this example, in step S7, the cement paste used has a cement-water-cement ratio of 0.40 and a specific gravity of 2.1g/cm3
Example 3
And (3) carrying out cast-in-situ bored pile defect treatment on the new Ji salt highway bridge, wherein the new Ji salt highway bridge consists of a salina sea-crossing bridge section and A, B line approaches on two banks, and the overall length of the project is 3.899 km. Wherein the length of the saltern sea-crossing bridge section is 1298.362m, and the width is 23.5 m; the length of the approach A line is 469.783m, and the width is 24.5 m; the length of the guide way B is 2130.913m, and the width of the guide way B is 24.5 m. The sea-crossing bridge adopts a prefabricated 22 multiplied by 30mT beam to hoist and drill a cast-in-place pile foundation. The total investment of the project is 19997.26 ten thousand yuan, and the construction period is 30 months.
The detection result of the integrity of the pile foundation of the bridge 23 piles (all of which are underwater concrete with the pile diameter of 1600mm, the pile length of 47m and C30) by a detection unit by using a sound wave transmission method shows that the integrity of the pile body of 21 piles is good, and the piles can be determined as I-type piles. And if one pile body (19-3) has defects, evaluation is not carried out for the moment, and core drilling sampling is recommended to verify the integrity of the pile body. For this purpose, two holes drilled in the pile were sampled, and the results show: the pile body of the 19-3 pile has a honeycomb phenomenon in the first hole with the diameter of 2.2-3.7 m, the sediment at the bottom of the pile is too thick, and the mud sand and concrete are seriously separated. The second hole has serious concrete segregation honeycombs within 0-2 m downward of the pile head, serious sand inclusion at the position of 19 m and 20CM thickness.
And aiming at the core sampling detection result, determining to adopt the method for processing. The problems of mud-included sand and concrete segregation are solved by high-pressure rotary jet cutting treatment on the defect, the pile body is reinforced by high-pressure cement slurry compaction grouting, and the integrity of the pile body is good through secondary sound wave transmission method pile foundation integrity detection, so that the standard requirement of the type I pile is met.
The foregoing detailed description of the preferred embodiments of the invention has been presented. It should be understood that numerous modifications and variations could be devised by those skilled in the art in light of the present teachings without departing from the inventive concepts. Therefore, the technical solutions available to those skilled in the art through logic analysis, reasoning and limited experiments based on the prior art according to the concept of the present invention should be within the scope of protection defined by the claims.

Claims (10)

1. A method for processing quality defects of cast-in-situ bored piles is characterized by comprising the following steps:
step S1, detecting the integrity of the cast-in-situ bored pile body;
step S2, drilling, core-pulling and sampling the bored pile body;
step S3, determining the type, position, area and thickness of the defect according to the step S1 and the step S2, further determining the hole position, number and depth of the processing hole according to the type, position, area and thickness of the defect, and drilling the processing hole;
step S4, judging whether the cast-in-situ bored pile belongs to a defective I-shaped pile or not according to the type, position, area and thickness of the defect, and if the cast-in-situ bored pile belongs to the defective I-shaped pile, performing consolidation treatment on a soil body outside the cast-in-situ bored pile;
step S5, performing high-pressure rotary jet cutting and clearing treatment on the defective part until all the treatment holes are communicated;
step S6, carrying out gas lift slag removal treatment on each processing hole until each processing hole is cleaned;
step S7, performing high-pressure cement slurry pressure injection treatment on the treatment holes;
step S8, arranging an orifice pipe at the orifice position of each processing hole, selecting one processing hole as a grouting hole from the plurality of processing holes, and taking the rest processing holes as slurry outlet holes;
and step S9, performing secondary high-pressure cement slurry pressure injection treatment on the grouting holes.
2. The method for processing quality defects of a cast-in-situ bored pile according to claim 1, wherein in step S1, during construction of the cast-in-situ bored pile, three to four acoustic pipes are embedded in the pile body of the cast-in-situ bored pile, and after a certain period of time after construction is completed, defects of the pile are detected by using an acoustic transilluminator;
in the step S2, a pile body of the cast-in-situ bored pile is drilled and sampled by a drill, the formed hole is a cored hole, and then it is determined by a pile body sample: type, location, area and thickness of the defect.
3. The method for processing the quality defect of the cast-in-situ bored pile according to claim 2, wherein in step S3, a processing hole is drilled in the pile body of the cast-in-situ bored pile by a drilling machine, and the diameter of the processing hole is 11 cm; selecting the core-pulling holes as the processing holes, and increasing the number of the missing processing holes when the number of the processing holes to be arranged is higher than the actual number of the core-pulling holes;
the number of the processing holes is at least two, and the bottoms of the processing holes are at least 50cm below the positions where the defects are located.
4. The method for processing quality defects of cast-in-situ bored pile according to claim 3, wherein the consolidation process is performed by a compaction grouting method in step S4, and the amount of cement is selected to be 144kg/m3The water-cement ratio is controlled to be 0.5-0.6, and the grouting pressure is controlled to be 0.4-0.5 MPa; and if the slurry does not sink, stopping grouting, increasing the grouting pressure to 0.6MPa, continuing grouting, and if the slurry does not sink within 10-15 min after the continuous grouting, finishing the consolidation treatment operation.
5. The method for processing the quality defect of the cast-in-situ bored pile according to claim 4, wherein in step S5, the high-pressure jet cutting and removing process specifically comprises:
inserting a high-pressure rotary spraying pipe into the processing hole, wherein the length of the high-pressure rotary spraying pipe is 6cm, four holes with the aperture of 1.8mm are uniformly distributed at the periphery of the bottom of the high-pressure rotary spraying pipe, the high-pressure rotary spraying pipe rotates at a high speed at the defective part of the pile body to form a cutting water disc, and the cutting water disc performs rotary spraying, cutting and cleaning treatment on the defective part of the pile body; the high-pressure rotary spraying pipe is used for repeatedly carrying out rotary spraying, cutting and cleaning treatment on the defective part from bottom to top and from top to bottom; the area treated by the high-pressure rotary spraying pipe needs to cover the defect part, and the upper part and the lower part of the area exceed the defect part by more than 50 cm;
the spraying pressure value of the high-pressure rotary spraying pipe is 28-30 MPa; the rotating speed is 15-18r/min, the lifting speed is 15cm/min, and the discharge capacity is 60-70L/min.
6. The method for processing the quality defect of the cast-in-situ bored pile according to claim 5, wherein the step S6 specifically includes: arranging an air hose in the treatment hole, performing combined deslagging treatment in the hole by adopting an air lift method in combination with the operation of pressing water downwards, pumping out larger particles in the treatment hole by adopting a sand pump, and repeating the steps until clear water returns from each treatment hole;
when the gas lift method is used for slag removal treatment in the hole, the air quantity is set to be 9m3More than min, and the pressure is set to be more than 0.7 MPa.
7. The method for processing the quality defect of the cast-in-situ bored pile according to claim 6, wherein in step S7, the high-pressure cement slurry injection processing is specifically:
firstly, selecting a processing hole, inserting a high-pressure rotary jet pipe into the processing hole, then performing cement paste pressure injection by adopting high-pressure cement paste equipment, and finally completing the operation of pressure cement paste pressure injection processing when the specific gravity of cement paste returned from the other processing holes is the same as that of the injected cement paste and all the processing holes are filled with cement paste;
when the cement paste is injected, the pressure is controlled to be 1.0MPa, and the specific gravity of the cement paste is detected in a field detection mode.
8. The method according to claim 7, wherein in step S8, the orifice tube includes a flange plate, the flange plate is provided with an expansion screw, and the orifice tube is fixedly connected to the concrete on the top of the bored pile through the expansion screw; the lower end of the orifice pipe is sealed by epoxy resin cement mortar and is tightly cemented with the pile body.
9. The method for processing quality defects of a bored pile according to claim 8, wherein in step S9, the secondary high-pressure cement slurry pressure is 2.0MPa, and the cement slurry is continuously injected until the gaps generated when step S7 is performed are filled.
10. The method for processing the quality defect of the bored pile according to claim 9, wherein in the steps S7 and S9, the cement strength of the cement paste is higher than the cement strength of the bored pile by one grade, the water cement ratio of the cement paste is less than 0.45, 0.6% of an expansion agent, 3% of a water reducing agent and a retarder are added, and the specific gravity of the cement paste is greater than 1.9g/cm3
CN202011619520.2A 2020-12-31 2020-12-31 Method for processing quality defects of cast-in-situ bored pile Pending CN112726590A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011619520.2A CN112726590A (en) 2020-12-31 2020-12-31 Method for processing quality defects of cast-in-situ bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011619520.2A CN112726590A (en) 2020-12-31 2020-12-31 Method for processing quality defects of cast-in-situ bored pile

Publications (1)

Publication Number Publication Date
CN112726590A true CN112726590A (en) 2021-04-30

Family

ID=75609579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011619520.2A Pending CN112726590A (en) 2020-12-31 2020-12-31 Method for processing quality defects of cast-in-situ bored pile

Country Status (1)

Country Link
CN (1) CN112726590A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529829A (en) * 2021-07-02 2021-10-22 中铁十九局集团华东工程有限公司 Method for treating excessive thickness of pile bottom sediment of long and large pile foundation and pile body concrete interlayer or loose
CN113774970A (en) * 2021-08-05 2021-12-10 深圳宏业基岩土科技股份有限公司 Cast-in-place pile socketed section defect repairing construction method
CN113897962A (en) * 2021-10-27 2022-01-07 福建建中岩土工程有限责任公司 Novel underground continuous wall sediment treatment method
CN114622553A (en) * 2022-03-22 2022-06-14 陈倩 Defect bored concrete pile maintenance processing method
CN115467325A (en) * 2022-09-12 2022-12-13 厦门捷航工程检测技术有限公司 Disease repairing treatment process for inclined long pile

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001049661A (en) * 1999-08-05 2001-02-20 Nippon Hume Corp Earthquake-resisting reinforcing method for existing concrete pile
CN101413266A (en) * 2008-11-28 2009-04-22 广东省长大公路工程有限公司 Processing method of interlayer defect injection concrete of drill filling pile
CN103541359A (en) * 2013-09-18 2014-01-29 浙江省岩土基础公司 Method for repairing and treating quality defect of cast-in-place pile
CN106836214A (en) * 2017-02-06 2017-06-13 姬凤玲 Rotary digging bored concrete pile pile body collapse hole or the construction method of pile bottom sediment mass defect treatment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001049661A (en) * 1999-08-05 2001-02-20 Nippon Hume Corp Earthquake-resisting reinforcing method for existing concrete pile
CN101413266A (en) * 2008-11-28 2009-04-22 广东省长大公路工程有限公司 Processing method of interlayer defect injection concrete of drill filling pile
CN103541359A (en) * 2013-09-18 2014-01-29 浙江省岩土基础公司 Method for repairing and treating quality defect of cast-in-place pile
CN106836214A (en) * 2017-02-06 2017-06-13 姬凤玲 Rotary digging bored concrete pile pile body collapse hole or the construction method of pile bottom sediment mass defect treatment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
饶天赞,曹喜仁: "《高层建筑基础工程施工》", 31 October 1995 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113529829A (en) * 2021-07-02 2021-10-22 中铁十九局集团华东工程有限公司 Method for treating excessive thickness of pile bottom sediment of long and large pile foundation and pile body concrete interlayer or loose
CN113774970A (en) * 2021-08-05 2021-12-10 深圳宏业基岩土科技股份有限公司 Cast-in-place pile socketed section defect repairing construction method
CN113897962A (en) * 2021-10-27 2022-01-07 福建建中岩土工程有限责任公司 Novel underground continuous wall sediment treatment method
CN114622553A (en) * 2022-03-22 2022-06-14 陈倩 Defect bored concrete pile maintenance processing method
CN115467325A (en) * 2022-09-12 2022-12-13 厦门捷航工程检测技术有限公司 Disease repairing treatment process for inclined long pile

Similar Documents

Publication Publication Date Title
CN112726590A (en) Method for processing quality defects of cast-in-situ bored pile
CN102322058B (en) Construction process and equipment for downhole impacting high-pressure jet grouting pile
CN111119940B (en) Grouting construction treatment method
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN107747312B (en) Method for drilling and grouting construction of gravel stratum
CN104929114A (en) High pressure jet grouting pile waterproof curtain construction device and method
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN107513995A (en) A kind of bridge struction pile post grouting construction method
CN110952953B (en) Pressure-maintaining plugging device for horizontal directional drill hole and water gushing treatment method using same
CN107338789B (en) A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake
CN110409433B (en) Construction system and method for performing foundation treatment by using cast-in-place pile with steel sleeve
CN110747847A (en) Double-pipe high-pressure jet grouting construction method for building impervious wall in soft foundation
CN1986974A (en) Pressure reducing horizontal reinforcing process for soft soil layer
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN214460276U (en) Be applied to mud jacking steel-pipe pile device of soft foundation
CN113089655A (en) Construction method in three-pipe rotary spraying pile pit in flowing water environment
CN106677190A (en) Grouting construction method for underwater pebble bed foundation pit curtain
CN110984137A (en) Bridge cast-in-situ bored pile construction method
CN113774970B (en) Cast-in-place pile socketed section defect repairing construction method
CN211773602U (en) Defect bored concrete pile slip casting reinforced structure
CN106592514A (en) Construction method of old city riverway piling wall integrated vertical type retaining wall
CN115233664B (en) Reinforcing and repairing method for deep pile breaking defect of cast-in-place pile
CN107975034B (en) The floating stake ground processing method of hollow preformed pile
CN111980674A (en) Tunnel advanced curtain grouting process and comprehensive inspection and evaluation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210430

RJ01 Rejection of invention patent application after publication