CN106592514A - Construction method of old city riverway piling wall integrated vertical type retaining wall - Google Patents

Construction method of old city riverway piling wall integrated vertical type retaining wall Download PDF

Info

Publication number
CN106592514A
CN106592514A CN201611127991.5A CN201611127991A CN106592514A CN 106592514 A CN106592514 A CN 106592514A CN 201611127991 A CN201611127991 A CN 201611127991A CN 106592514 A CN106592514 A CN 106592514A
Authority
CN
China
Prior art keywords
construction
pile
reinforced concrete
concrete pile
deposited reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611127991.5A
Other languages
Chinese (zh)
Inventor
李敏哲
周亚军
续晶晶
要会科
李少华
娄国伟
周文博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Municipal Engineering Co Ltd Of Jinan City
Original Assignee
Municipal Engineering Co Ltd Of Jinan City
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Municipal Engineering Co Ltd Of Jinan City filed Critical Municipal Engineering Co Ltd Of Jinan City
Priority to CN201611127991.5A priority Critical patent/CN106592514A/en
Publication of CN106592514A publication Critical patent/CN106592514A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to the field of municipal engineering construction, in particular to a construction method of an old city riverway piling wall integrated vertical type retaining wall. The construction method comprises the following steps: (1) performing reinforced concrete grouting pile construction; (2) performing high-pressure jet grouting pile construction; (3) performing crown beam construction; and (4) performing net-hanging spraying and protecting construction. According to the construction method, the occupied working surface is small, the deconstruction quantity of buildings on the two sides of a riverway is reduced, and the cross section of passage of the riverway can be guaranteed in the construction period. Settlement and cracks of the buildings on the two sides of the riverway caused by rainfall and foundation pit excavation can be avoided, and surrounding building safety and traffic safety are guaranteed.

Description

A kind of old town river course mixture of piles and concrete wall vertical type retaining wall construction method
Technical field
The present invention relates to Municipal Engineering Construction field, more particularly to a kind of old town river course mixture of piles and concrete wall vertical type retaining wall Construction method.
Background technology
Economy is developed rapidly in recent years, and urbanization process is accelerated, and road mostly is asphalt concrete pavement or cement concrete Road surface, earth's surface water percolating capacity are reduced, and surface water majority is arranged into the river courses for flood discharge for passing through old town, and urban rives are due to older mistake Repair, the alluvial such as mud, debris is serious in river course, has a strong impact on the normal flood discharge in river course, river training works gradually increases, to alleviate River course flood pressure.
Due to historical reasons, old town river course both sides building is nearer apart from river course, is such as constructed using traditional handicraft, removes Larger, long construction period is invested, the life, traffic order on nearby residents affects larger.
The content of the invention
The present invention is in order to make up the defect of prior art, there is provided it is a kind of be not required to remove can be carried out the old of dredging waterway Urban rives mixture of piles and concrete wall vertical type retaining wall construction method.
The present invention is achieved through the following technical solutions:
A kind of old town river course mixture of piles and concrete wall vertical type retaining wall construction method, is characterized in that:Comprise the steps:
(1)Deposited reinforced concrete pile is constructed:Spacing between two neighboring deposited reinforced concrete pile is equal, advanced before construction The prospecting of row underground utilities, makes visible marking there is underground utilities position, it is to avoid other pipelines are damaged in pile foundation construction, then Line setting is carried out according to design, then carries out embedded casing, deposited reinforced concrete pile construction;
(2)Carry out Construction of High Pressure Jet Grouting Pile between two neighboring deposited reinforced concrete pile, high-pressure rotary jet grouting pile with diameter greater than The spacing of two neighboring deposited reinforced concrete pile so that deposited reinforced concrete pile is mutually twisted one with high-pressure rotary jet grouting pile Rise;
(3)Guan Liang is constructed:Guan Liang construction is carried out in reinforced concrete body bored concrete pile and high-pressure rotary jet grouting pile upper end;
(4)Linked network spray shield construction:First remove river course in the earthwork and carry out between stake clear up, make deposited reinforced concrete pile and high pressure rotation Spray stake is exposed out, and rejecting the armored concrete on deposited reinforced concrete pile with machinery makes its cage bar come out, Ran Hou The facade of deposited reinforced concrete pile and high-pressure rotary jet grouting pile hangs reinforced mesh, and will be cage bar and reinforced mesh welded together; Then construction of shotcrete is carried out, the larger position of thickness between first spray stake, other positions of fill-before-fire, after the completion of injection, manually It is locally levelling, finally carry out metope modification.
In step(4)In, carry out bar planting on each deposited reinforced concrete pile and high-pressure rotary jet grouting pile, and by bar-mat reinforcement Piece and bar planting weld together.
In step(4)During middle gunite concrete, first supporting module.
The invention has the beneficial effects as follows:
1st, take work surface little, reduce river course both sides building removal amount, while being able to ensure that the river course excessively stream of construction period is broken Face.
2nd, river course both sides building settlement because precipitation, excavation of foundation pit cause, crack can be avoided, it is ensured that neighboring buildings are pacified Entirely, and traffic safety.
3rd, reliable construction quality, economical rationality, duration are shorter.
Description of the drawings
The present invention is further illustrated below in conjunction with the accompanying drawings:
Fig. 1 is the position relationship schematic diagram of deposited reinforced concrete pile and high-pressure rotary jet grouting pile;
In figure:1 deposited reinforced concrete pile, 2 high-pressure rotary jet grouting piles.
Specific embodiment
As shown in figure 1, this kind of old town river course mixture of piles and concrete wall vertical type retaining wall construction method, comprises the following steps:
(1)Deposited reinforced concrete pile is constructed:Spacing between two neighboring deposited reinforced concrete pile 1 is equal, before construction first The prospecting of underground utilities is carried out, and visible marking is made there is underground utilities position, it is to avoid other pipelines are damaged in pile foundation construction, so Line setting is carried out according to design afterwards, then carries out embedded casing, deposited reinforced concrete pile construction;
(2)High-pressure rotary jet grouting pile 2 is carried out between two neighboring deposited reinforced concrete pile 1 to construct, as shown in figure 1, high-pressure rotary-spray The spacing with diameter greater than two neighboring deposited reinforced concrete pile 1 of stake 2 so that deposited reinforced concrete pile 1 and high-pressure rotary-spray Stake 2 is mutually twisted together;The jet pipe inner high voltage jet cutting soil body under high-pressure rotary jet grouting pile utilization in depth, using compressed air Protection jet will not disperse too early, and fine particle is taken back outside hole, form passage, after the cement mortar injection soil body, with undisturbed soil Fully mix, forms compound induration.Several compound indurations and the tight interconnection of deposited reinforced concrete pile, have formed Whole continuous diaphram wall body, reaches the purpose of antiseepage supporting.
Jet grouting pile driving machine carries out rotary-spraying construction using double pipe or triple tube, adopts different pressures according to different soil properties Power.When rotary churning pile machine is in place, support is steady, and vertical shaft or rotating disk are aligned with hole position, and inclination angle cannot be greater than 0.5 ° with design error.
High pressure equipment and pipe-line system to be checked before jet groutinl, the pressure and discharge capacity of equipment must are fulfilled for requiring, pipeline The sealing ring of system must be good, must not have debris in each passage and nozzle.
Grouting pump is started, is treated after about 5 seconds that the forward of cement mortar has flowed out shower nozzle, is started hoisting grouting pipe, from lower Upper jet groutinl.
(3)Guan Liang is constructed:Guan Liang construction, including spoil are carried out in reinforced concrete body bored concrete pile and high-pressure rotary jet grouting pile upper end Side, broken pile head and flatten, straightening stake top reinforcing bar, surveying setting-out, reinforcing bar colligation, supporting module, concrete perfusion, maintenance, form removal;
(4)Linked network spray shield construction:First remove river course in the earthwork and carry out between stake clear up, in order to ensure spray mask not by river rush Brush, when removing the earthwork in river course, should dig a deep part near barricade position(About 20cm), according still further to design river after the completion of shield to be painted Bottom elevation is recovered.Then scaffold is set up in river course, carry out clearing up between stake, will loosen the soil to wait and remove clean, and make reinforcing bar mixed Solidifying soil bored concrete pile and high-pressure rotary jet grouting pile are exposed out, and rejecting the armored concrete on deposited reinforced concrete pile with machinery leads which Muscle comes out, and then the facade in deposited reinforced concrete pile and high-pressure rotary jet grouting pile hangs reinforced mesh, and by cage bar and steel Muscle mesh sheet is welded together;Then carry out construction of shotcrete, be improve jetting cement and concrete filling pile, high-pressure rotary jet grouting pile it is whole Body, on each bored concrete pile and rotary churning pile carries out bar planting, the reinforced mesh for hanging and bar planting is welded together.Sprayed When penetrating concrete construction, first spray stake between the larger position of thickness, if necessary can supporting module, finally spray surface layer when, need people Work is levelling to locally carrying out, and finally carries out metope modification construction again.
In addition to technical characteristic described in description, remaining technical characteristic is technology known to those skilled in the art.

Claims (3)

1. a kind of old town river course mixture of piles and concrete wall vertical type retaining wall construction method, is characterized in that:Comprise the steps:
(1)Deposited reinforced concrete pile is constructed:Spacing between two neighboring deposited reinforced concrete pile is equal, advanced before construction The prospecting of row underground utilities, makes visible marking there is underground utilities position, it is to avoid other pipelines are damaged in pile foundation construction, then Line setting is carried out according to design, then carries out embedded casing, deposited reinforced concrete pile construction;
(2)Carry out Construction of High Pressure Jet Grouting Pile between two neighboring deposited reinforced concrete pile, high-pressure rotary jet grouting pile with diameter greater than The spacing of two neighboring deposited reinforced concrete pile so that deposited reinforced concrete pile is mutually twisted one with high-pressure rotary jet grouting pile Rise;
(3)Guan Liang is constructed:Guan Liang construction is carried out in reinforced concrete body bored concrete pile and high-pressure rotary jet grouting pile upper end;
(4)Linked network spray shield construction:First remove river course in the earthwork and carry out between stake clear up, make deposited reinforced concrete pile and high pressure rotation Spray stake is exposed out, and rejecting the armored concrete on deposited reinforced concrete pile with machinery makes its cage bar come out, Ran Hou The facade of deposited reinforced concrete pile and high-pressure rotary jet grouting pile hangs reinforced mesh, and will be cage bar and reinforced mesh welded together; Then construction of shotcrete is carried out, the larger position of thickness between first spray stake, other positions of fill-before-fire, after the completion of injection, manually It is locally levelling, finally carry out metope modification.
2. mixture of piles and concrete wall vertical type retaining wall construction method in old town river course according to claim 1, is characterized in that:In step Suddenly(4)In, bar planting is carried out on each deposited reinforced concrete pile and high-pressure rotary jet grouting pile, and reinforced mesh and bar planting are welded Together.
3. mixture of piles and concrete wall vertical type retaining wall construction method in old town river course according to claim 1, is characterized in that, in step Suddenly(4)During middle gunite concrete, first supporting module.
CN201611127991.5A 2016-12-09 2016-12-09 Construction method of old city riverway piling wall integrated vertical type retaining wall Pending CN106592514A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611127991.5A CN106592514A (en) 2016-12-09 2016-12-09 Construction method of old city riverway piling wall integrated vertical type retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611127991.5A CN106592514A (en) 2016-12-09 2016-12-09 Construction method of old city riverway piling wall integrated vertical type retaining wall

Publications (1)

Publication Number Publication Date
CN106592514A true CN106592514A (en) 2017-04-26

Family

ID=58598261

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611127991.5A Pending CN106592514A (en) 2016-12-09 2016-12-09 Construction method of old city riverway piling wall integrated vertical type retaining wall

Country Status (1)

Country Link
CN (1) CN106592514A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110629778A (en) * 2018-06-21 2019-12-31 北京东地岩土工程有限公司 Construction method for stopping leakage of waterproof curtain
CN110939101A (en) * 2019-12-26 2020-03-31 长江勘测规划设计研究有限责任公司 Vertical dike structure and construction method thereof
CN114293566A (en) * 2021-12-21 2022-04-08 中交二航局成都城市建设工程有限公司 Enclosure construction method suitable for subway station auxiliary structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286984A (en) * 2011-05-25 2011-12-21 深圳市鸿荣轩建设工程有限公司 Water-stop curtain and construction method thereof
CN103711136A (en) * 2013-08-28 2014-04-09 中交二公局第一工程有限公司 Deeply buried bearing platform curtain structure of bridge and process for constructing deeply buried bearing platform curtain structure
CN203960880U (en) * 2014-07-22 2014-11-26 北京城建建设工程有限公司 Campshed and water-seal pile system of deep foundation pit support
CN104631470A (en) * 2014-12-26 2015-05-20 合肥建工集团有限公司 Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN204959767U (en) * 2015-09-10 2016-01-13 沈阳铁道勘察设计院有限公司 Novel suspended net shotcrete structure between stake

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286984A (en) * 2011-05-25 2011-12-21 深圳市鸿荣轩建设工程有限公司 Water-stop curtain and construction method thereof
CN103711136A (en) * 2013-08-28 2014-04-09 中交二公局第一工程有限公司 Deeply buried bearing platform curtain structure of bridge and process for constructing deeply buried bearing platform curtain structure
CN203960880U (en) * 2014-07-22 2014-11-26 北京城建建设工程有限公司 Campshed and water-seal pile system of deep foundation pit support
CN104631470A (en) * 2014-12-26 2015-05-20 合肥建工集团有限公司 Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN204959767U (en) * 2015-09-10 2016-01-13 沈阳铁道勘察设计院有限公司 Novel suspended net shotcrete structure between stake

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110629778A (en) * 2018-06-21 2019-12-31 北京东地岩土工程有限公司 Construction method for stopping leakage of waterproof curtain
CN110939101A (en) * 2019-12-26 2020-03-31 长江勘测规划设计研究有限责任公司 Vertical dike structure and construction method thereof
CN114293566A (en) * 2021-12-21 2022-04-08 中交二航局成都城市建设工程有限公司 Enclosure construction method suitable for subway station auxiliary structure
CN114293566B (en) * 2021-12-21 2023-08-22 中交二航局成都城市建设工程有限公司 Building envelope construction method suitable for subway station auxiliary structure

Similar Documents

Publication Publication Date Title
CN102322058B (en) Construction process and equipment for downhole impacting high-pressure jet grouting pile
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN101736760B (en) Construction method of prestressed anti-floating anchor rod
CN103343544B (en) Construction method for large-scale open caisson
CN110359467A (en) A kind of construction method that base pit engineering high-pressure rotary jet grouting pile is reinforced
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN109881696B (en) HPPG (high Performance Poly propylene glycol) bottom sealing construction method
CN107338789B (en) A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake
CN203924137U (en) Serious seepage block structure of underground continuous wall
CN108080409A (en) A kind of triple churning device and method thereof of soil remediation
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN108193606A (en) A kind of means of defence of local scour near pier
CN106592514A (en) Construction method of old city riverway piling wall integrated vertical type retaining wall
CN114575355B (en) Soil protection construction method
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN108894247A (en) A kind of Metro Connection Passage periphery soil body subsidence pressure circle spray reinforcement structure and construction method
CN111456021A (en) Construction method for reversely making enclosure structure by utilizing RJP piles
CN112176954A (en) Construction method for newly excavated channel
CN115198790A (en) Reinforcing and supporting method for existing embankment upright retaining wall
CN213953596U (en) Reinforcing system for water-rich stratum underground tunnel crossing sensitive pipeline section
CN113202110A (en) Construction method for supporting and protecting finite space railway bridge and culvert prefabricated foundation pit
CN112176953A (en) Construction method for newly-built channel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426