CN107190900A - 一种过道穿孔板铝板吊顶施工工艺 - Google Patents

一种过道穿孔板铝板吊顶施工工艺 Download PDF

Info

Publication number
CN107190900A
CN107190900A CN201710592995.9A CN201710592995A CN107190900A CN 107190900 A CN107190900 A CN 107190900A CN 201710592995 A CN201710592995 A CN 201710592995A CN 107190900 A CN107190900 A CN 107190900A
Authority
CN
China
Prior art keywords
aluminium sheet
passageway
batches
depth
perforated plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710592995.9A
Other languages
English (en)
Inventor
张小俊
杨佼杰
李斯维
秦晓星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu East Decoration Group Co Ltd
Original Assignee
Jiangsu East Decoration Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu East Decoration Group Co Ltd filed Critical Jiangsu East Decoration Group Co Ltd
Priority to CN201710592995.9A priority Critical patent/CN107190900A/zh
Publication of CN107190900A publication Critical patent/CN107190900A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Floor Finish (AREA)

Abstract

本发明公开了一种过道穿孔板铝板吊顶施工工艺,包括:吊挂方案优化与BIM应用;板型优化与分批下单;板面加固与分批装箱打包;二次深化设计;成品保护与修复;兄弟单位积极配合。本发明的过道穿孔板铝板吊顶施工工艺,针对超长过道、超宽过道进行专门设计,具有施工工艺合理,施工效果好和施工效率高等优点。

Description

一种过道穿孔板铝板吊顶施工工艺
技术领域
本发明涉及一种吊顶施工工艺,具体涉及一种过道穿孔板铝板吊顶施工工艺。
背景技术
本工程公共部位走道设计均为1mm厚穿孔铝板造型顶,走道长度超过40000mm,宽度为2100mm,设计铝板板面较大,多处板面尺寸超过1200mm*1200mm,考虑铝板厚度及铝板板面大小,铝板本身平整度及安装平整度为本工程一大难点。
根据经验,铝板加工周期长是影响工期的一大要素,本工程铝板总使用面积超过2500平方,且造型及规格尺寸较多,下单及加工周期成为工期把控的一大难点。
通过制作样板段,项目部发现,虽然第二家供应商制作的铝板吊顶整体效果满足要求,但实际操作过程中仍存在多个问题:
1、过道较长且过道内风管、管道较多,设计做法现场多处无法满足标高要求且平整度把控较难,需重新考虑铝板吊挂方案。
2、铝板板型复杂,尺寸较多对下单、加工周期影响较大。
3、铝板板厚较薄,板面较大,加工、运输及二次搬运易造成变形。
4、铝板造型多处收口易造成露黑,下单时造型各处收口需着重把控。
5、铝板与边线吊顶阴角,受铝板加工设备影响,易产生豁口,在下单时板型需重新深化。
6、石膏板边线吊顶,在铝板安装过程中易造成损坏,乳胶漆二次修复施工难度较大。
7、喷淋、烟感、风口、检修口等多家单位配合。
发明内容
发明目的:本发明针对现有技术中的不足,提出一种过道穿孔板铝板吊顶施工工艺,针对超长过道、超宽过道进行专门设计,具有施工工艺合理,施工效果好和施工效率高等优点。
技术方案:本发明所述的一种过道穿孔板铝板吊顶施工工艺,包括如下步骤:
(1)吊挂方案优化与BIM应用
通过现场实际勘测、与设计和厂家的多次沟通,确定最终采用铝板勾搭方式进行吊挂;选用壁厚较厚的主龙骨,局部由于风管等影响无法敷设吊筋的,采用角钢焊制反支撑,保证基层的平整度及吊顶标高;面层铝板安装平整度,利用BIM技术及时检查安装平整度;
(2)板型优化与分批下单
根据原设计排版图,重新编排下单,统一大部分尺寸,小部分尺寸微调,一层一下,分批下单;
(3)板面加固与分批装箱打包
考虑铝板超薄,板面较大,易变形,铝板背面覆贴瓦楞面,有效的降低了铝板的变形系数;在深化上,较常规铝板折边多增加一道,形成U型边,一定程度上增加了铝板强度,货流物运采用分批装箱打包,到场后直接电梯上运至相应楼层,减少运输过程中变形;
(4)二次深化设计
细部编号深化,对造型转口、易产生卷折豁口的板型着重编号深化,做到每一处可能露黑的均无遗漏地二次深化;
(5)成品保护与修复
铝板安装前,对铝板安装工进行技术交底,着重强调成品保护,安装过程中每个安装工均佩戴白手套,装一块,擦一块,对不可避免的造成二次损坏的石膏板吊顶,及时修复,修复过程中对铝板粘贴防护膜进行保护;
(6)兄弟单位积极配合
与各兄弟单位沟通,提供各相关顶面图,铝板下单深化时,同时深化铝板顶面综合点位布置图,各配套单位按照顶面布置图布置点位,项目部并派专人对喷淋、烟感、监控、检修孔等点位按图纸进行强制定位;铝板安装时,项目部派专人对每层需开孔的铝板进行确认开孔,保证无错开错拿现象。
进一步的,步骤(1)所述主龙骨的壁厚为100-300mm。
有益效果:本发明的过道穿孔板铝板吊顶施工工艺,针对超长过道、超宽过道进行专门设计,具有施工工艺合理,施工效果好和施工效率高等优点。
具体实施方式
下面结合具体实施例对本发明作进一步说明:
实施例1
一种过道穿孔板铝板吊顶施工工艺,包括如下步骤:
(1)吊挂方案优化与BIM应用
通过现场实际勘测、与设计和厂家的多次沟通,确定最终采用铝板勾搭方式进行吊挂;选用壁厚较厚的主龙骨,主龙骨的壁厚为100-300mm。局部由于风管等影响无法敷设吊筋的,采用角钢焊制反支撑,保证基层的平整度及吊顶标高;面层铝板安装平整度,利用BIM技术及时检查安装平整度;
(2)板型优化与分批下单
根据原设计排版图,重新编排下单,统一大部分尺寸,小部分尺寸微调,一层一下,分批下单;
(3)板面加固与分批装箱打包
考虑铝板超薄,板面较大,易变形,铝板背面覆贴瓦楞面,有效的降低了铝板的变形系数;在深化上,较常规铝板折边多增加一道,形成U型边,一定程度上增加了铝板强度,货流物运采用分批装箱打包,到场后直接电梯上运至相应楼层,减少运输过程中变形;
(4)二次深化设计
细部编号深化,对造型转口、易产生卷折豁口的板型着重编号深化,做到每一处可能露黑的均无遗漏地二次深化;
(5)成品保护与修复
铝板安装前,对铝板安装工进行技术交底,着重强调成品保护,安装过程中每个安装工均佩戴白手套,装一块,擦一块,对不可避免的造成二次损坏的石膏板吊顶,及时修复,修复过程中对铝板粘贴防护膜进行保护;
(6)兄弟单位积极配合
与各兄弟单位沟通,提供各相关顶面图,铝板下单深化时,同时深化铝板顶面综合点位布置图,各配套单位按照顶面布置图布置点位,项目部并派专人对喷淋、烟感、监控、检修孔等点位按图纸进行强制定位;铝板安装时,项目部派专人对每层需开孔的铝板进行确认开孔,保证无错开错拿现象。
本发明的过道穿孔板铝板吊顶施工工艺,针对超长过道、超宽过道进行专门设计,具有施工工艺合理,施工效果好和施工效率高等优点。
以上所述,仅是本发明的较佳实施例而已,并非对本发明作任何形式上的限制,虽然本发明已以较佳实施例揭露如上,然而并非用以限定本发明,任何熟悉本专业的技术人员,在不脱离本发明技术方案范围内,当可利用上述揭示的技术内容作出些许更动或修饰为等同变化的等效实施例,但凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。

Claims (2)

1.一种过道穿孔板铝板吊顶施工工艺,其特征在于:包括如下步骤:
(1)吊挂方案优化与BIM应用
通过现场实际勘测、与设计和厂家的多次沟通,确定最终采用铝板勾搭方式进行吊挂;选用壁厚较厚的主龙骨,局部由于风管等影响无法敷设吊筋的,采用角钢焊制反支撑,保证基层的平整度及吊顶标高;面层铝板安装平整度,利用BIM技术及时检查安装平整度;
(2)板型优化与分批下单
根据原设计排版图,重新编排下单,统一大部分尺寸,小部分尺寸微调,一层一下,分批下单;
(3)板面加固与分批装箱打包
考虑铝板超薄,板面较大,易变形,铝板背面覆贴瓦楞面,有效的降低了铝板的变形系数;在深化上,较常规铝板折边多增加一道,形成U型边,一定程度上增加了铝板强度,货流物运采用分批装箱打包,到场后直接电梯上运至相应楼层,减少运输过程中变形;
(4)二次深化设计
细部编号深化,对造型转口、易产生卷折豁口的板型着重编号深化,做到每一处可能露黑的均无遗漏地二次深化;
(5)成品保护与修复
铝板安装前,对铝板安装工进行技术交底,着重强调成品保护,安装过程中每个安装工均佩戴白手套,装一块,擦一块,对不可避免的造成二次损坏的石膏板吊顶,及时修复,修复过程中对铝板粘贴防护膜进行保护;
(6)兄弟单位积极配合
与各兄弟单位沟通,提供各相关顶面图,铝板下单深化时,同时深化铝板顶面综合点位布置图,各配套单位按照顶面布置图布置点位,项目部并派专人对喷淋、烟感、监控、检修孔等点位按图纸进行强制定位;铝板安装时,项目部派专人对每层需开孔的铝板进行确认开孔,保证无错开错拿现象。
2.根据权利要求1所述的一种过道穿孔板铝板吊顶施工工艺,其特征在于:步骤(1)所述主龙骨的壁厚为100-300mm。
CN201710592995.9A 2017-07-19 2017-07-19 一种过道穿孔板铝板吊顶施工工艺 Pending CN107190900A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710592995.9A CN107190900A (zh) 2017-07-19 2017-07-19 一种过道穿孔板铝板吊顶施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710592995.9A CN107190900A (zh) 2017-07-19 2017-07-19 一种过道穿孔板铝板吊顶施工工艺

Publications (1)

Publication Number Publication Date
CN107190900A true CN107190900A (zh) 2017-09-22

Family

ID=59884020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710592995.9A Pending CN107190900A (zh) 2017-07-19 2017-07-19 一种过道穿孔板铝板吊顶施工工艺

Country Status (1)

Country Link
CN (1) CN107190900A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528767A (zh) * 2019-08-20 2019-12-03 泰源工程集团股份有限公司 一种复杂造型吊顶收口单元体制作安装方法
CN110552510A (zh) * 2019-09-12 2019-12-10 中建八局装饰工程有限公司 装配式曲面吊顶的施工方法
CN111058640A (zh) * 2019-12-24 2020-04-24 中启胶建集团有限公司 钢桁架下异形透空铝单板吊顶施工工艺
CN111236650A (zh) * 2020-03-12 2020-06-05 中铁建设集团有限公司 一种异形穿孔铝板组合吊顶施工工法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266705A (zh) * 2013-05-28 2013-08-28 苏州柯利达装饰股份有限公司 大规格薄壁金属板吊顶结构
CN103993694A (zh) * 2014-05-23 2014-08-20 郑州中茂建材有限公司 无龙骨模压卡扣固定式条形铝板厨卫吊顶系统及安装方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266705A (zh) * 2013-05-28 2013-08-28 苏州柯利达装饰股份有限公司 大规格薄壁金属板吊顶结构
CN103993694A (zh) * 2014-05-23 2014-08-20 郑州中茂建材有限公司 无龙骨模压卡扣固定式条形铝板厨卫吊顶系统及安装方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
丁烈云: "《BIM应用.施工》", 31 March 2015 *
北京土木建筑学会: "《建筑工程质量常见问题防止手册.装饰装修工程》", 31 January 2016 *
王振强: "《钣金展开计算法》", 31 January 2014 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528767A (zh) * 2019-08-20 2019-12-03 泰源工程集团股份有限公司 一种复杂造型吊顶收口单元体制作安装方法
CN110552510A (zh) * 2019-09-12 2019-12-10 中建八局装饰工程有限公司 装配式曲面吊顶的施工方法
CN111058640A (zh) * 2019-12-24 2020-04-24 中启胶建集团有限公司 钢桁架下异形透空铝单板吊顶施工工艺
CN111236650A (zh) * 2020-03-12 2020-06-05 中铁建设集团有限公司 一种异形穿孔铝板组合吊顶施工工法

Similar Documents

Publication Publication Date Title
CN107190900A (zh) 一种过道穿孔板铝板吊顶施工工艺
CN110440429B (zh) 地铁拱形顶通风管道装配施工方法
US10947720B2 (en) Block construction of prefabricated buildings
EP3889374B1 (en) Method for constructing buildings
CN105058055B (zh) 用于建筑施工的内置法兰风管制作安装工法
US20160145859A1 (en) Ecological building and insulation structural body thereof and method for assembling insulation structural body
CN111898255A (zh) 一种基于规范的工程设计文件的智能化检查方法
CN103306414B (zh) 一种单元装配式的暗龙骨吊顶系统及其施工方法
JP3827431B2 (ja) クリーンルーム建物の施工方法
CN113550599B (zh) 一种双曲面锯齿形grg施工方法
CN207346428U (zh) 一种带报警系统集装箱仓库
CN207518099U (zh) 一种带巡检通道的后开门式预制舱
JP5551202B2 (ja) ダクト用cad装置及びプログラム
Abou Ibrahim et al. Role of formwork systems in high-rise construction
CN103967187B (zh) 超大面积不锈钢吊顶防变形结构
CN204728557U (zh) 一种立体平面烤漆龙骨跌级板吊顶系统
CN104295042B (zh) 椭圆外倾建筑异型外挂人造石面板固定结构及施工方法
CN112177330B (zh) 建筑模板摆装方法
Amhoff The electrification of the factory: or the flexible layout of work (s)
ES2714507T3 (es) Un canal multipropósito para paneles de techo o fachada
CN207376833U (zh) 一种适用于被动式低能耗建筑的楼面结构
HAM et al. Prefabricated Modular Housing
Eren The Elimination of Problems That Arise During The Construction Stage of Industrialised Lightweight Steel Residences
JPH0762874A (ja) 建物のプレハブ型シャフトユニット積上げ工法
ENGINEER MARYLAND STADIUM AUTHORITY M&T BANK STADIUM 1101 RUSSELL STREET BALTIMORE, MD 21230 STADIUM OPERATIONS OFFICES RENOVATION

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170922