EP3889374B1 - Method for constructing buildings - Google Patents

Method for constructing buildings Download PDF

Info

Publication number
EP3889374B1
EP3889374B1 EP19888380.3A EP19888380A EP3889374B1 EP 3889374 B1 EP3889374 B1 EP 3889374B1 EP 19888380 A EP19888380 A EP 19888380A EP 3889374 B1 EP3889374 B1 EP 3889374B1
Authority
EP
European Patent Office
Prior art keywords
prefabricated
modules
dimensional
floor
pillars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP19888380.3A
Other languages
German (de)
French (fr)
Other versions
EP3889374A1 (en
EP3889374A4 (en
Inventor
Sergey Alexandrovich AMBARTSUMYAN
Alexandr Sergeyevich MESHCHERYAKOV
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obschestvo S Ogranichennoy Otvetsvennostyu "kontsern Monarkh"
Original Assignee
Obschestvo S Ogranichennoy Otvetsvennostyu "kontsern Monarkh"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obschestvo S Ogranichennoy Otvetsvennostyu "kontsern Monarkh" filed Critical Obschestvo S Ogranichennoy Otvetsvennostyu "kontsern Monarkh"
Publication of EP3889374A1 publication Critical patent/EP3889374A1/en
Publication of EP3889374A4 publication Critical patent/EP3889374A4/en
Application granted granted Critical
Publication of EP3889374B1 publication Critical patent/EP3889374B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/005Modulation co-ordination
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B5/00Producing shaped articles from the material in moulds or on moulding surfaces, carried or formed by, in or on conveyors irrespective of the manner of shaping
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B5/00Producing shaped articles from the material in moulds or on moulding surfaces, carried or formed by, in or on conveyors irrespective of the manner of shaping
    • B28B5/02Producing shaped articles from the material in moulds or on moulding surfaces, carried or formed by, in or on conveyors irrespective of the manner of shaping on conveyors of the endless-belt or chain type
    • B28B5/021Producing shaped articles from the material in moulds or on moulding surfaces, carried or formed by, in or on conveyors irrespective of the manner of shaping on conveyors of the endless-belt or chain type the shaped articles being of definite length
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/02Moulds with adjustable parts specially for modifying at will the dimensions or form of the moulded article
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/22Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • E04B1/34823Elements not integrated in a skeleton the supporting structure consisting of concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • E04B1/34853Elements not integrated in a skeleton the supporting structure being composed of two or more materials
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/02Dwelling houses; Buildings for temporary habitation, e.g. summer houses
    • E04H1/04Apartment houses arranged in two or more levels

Definitions

  • the invention relates to the field of construction, in particular to modular three-dimensional-block construction, and can be used for construction of low-rise and multi-storey residential buildings, public buildings and structures, as well as other buildings of any other purpose.
  • a method of constructing buildings from three-dimensional blocks which consists in installing a three-dimensional block in a vertical position, side walls of which are rigidly connected to side walls of a next block through gaskets.
  • the blocks are installed one by one around the perimeter of the building.
  • the lower part of the connected blocks can serve as a foundation when they are installed below the zero mark of the building.
  • internal walls, floors and openings can be formed in buildings (see patent RU 2076178C1 , convention priority: 09.12.1994 RU 94 94044472 ).
  • the closest approach to the proposed solution is a method of buildings construction, which consists in manufacturing three-dimensional blocks, after which prefabricated three-dimensional blocks are formed using construction components, including engineering communications, by means of installing engineering communications and performing interior finishing, then the prefabricated three-dimensional blocks are transported using vehicles to a construction site, where, by means of lifting devices, prefabricated three-dimensional blocks are installed in an appropriate place and the prefabricated three-dimensional blocks are installed and connected to each other, while the prefabricated three-dimensional blocks are installed on top of one another in a similar position (see, for example, the website on the Internet https://studf ⁇ les.net/preview/5193963/).
  • the disadvantage of the known method is the lack of possibility to quickly change configuration of blocks, their shapes and sizes, when implementing the method, it is possible to manufacture only the same type of blocks, low productivity, small overall dimensions of blocks with a limited area, lack of possibility to change quickly planning solutions of premises and finishing and engineering preparation at the factory is no more than 20-30%.
  • US 3,714,304 A and SU 495208 A1 disclose conveyors used for manufacture of prefabricated three-dimensional modules, installation during manufacture of engineering communications, performing interior and exterior finishing, forming internal partitions installing built-in furniture, etc.
  • the invention is defined in claim 1.
  • the technical problem solved by the invention is an increase in area of buildings constructed and in volume of daily output, an increase in productivity, a reduction in time and labor costs for construction of buildings, an increase in comfort of premises constructed and a significant increase in their quality.
  • the technical result of the invention which provides a solution to the technical problem, is the reduce in complexity and cost of construction, simplicity of three-dimensional modules installation, ensuring building versatility for any three-dimensional planning solutions due to the possibility of rapid changes in size and shape of three-dimensional modules in all coordinates, increase in rigidity, reliability and stability of the building due to the floor-by-floor re-laying of three-dimensional modules during their installation, increase in accuracy of the buildings assembling due to provision of high-precision dimensions of three-dimensional modules, ensuring the possibility of rapid changes in three-dimensional planning solutions.
  • the technical result of the invention is achieved by implementing a method for constructing buildings, wherein on robotic conveyors located in a plant workshop, prefabricated three-dimensional modules are made, moreover, on the first robotic conveyor, a formwork system is formed and a monolithic reinforced-concrete three-dimensional module including a base plate and/ or pillars and/ or walls and/ or beams and/ or crosspieces and/ or ceiling panels is manufactured in said formwork system, said manufactured three-dimensional module is transferred to a second robotic conveyor, where the prefabricated three-dimensional module is formed, using construction components, including engineering communications, by means of installing engineering communications, performing internal and/ or external finishing, and/ or installing built-in furniture, then at the end of the second robotic conveyor the prefabricated three-dimensional module is packaged in a protective material, and other prefabricated three-dimensional modules are manufactured in the same way, the packaged prefabricated three-dimensional modules are transported to a construction site by means of vehicles, where, by means of lifting devices, the packaged prefabricated three-dimensional modules are installed in the appropriate place, unpacked,
  • manufacture of a prefabricated three-dimensional module on robotic conveyors can be carried out with the help of industrial robots.
  • the building can be constructed with the possibility of dismounting and transporting the prefabricated three-dimensional modules to another construction site by means of a vehicle.
  • the three-dimensional module can have internal walls, and after the installation of engineering communications, the execution of internal and/ or external finishing and/ or the installation of built-in furniture, spatial arrangement of the internal walls, as well as engineering communications and/ or built-in furniture can be changed.
  • the formation of the formwork system on the first robotic conveyor can be carried out on a pallet, which is cleaned and covered with a layer of oil-air lubricant before the formation of the formwork system.
  • some of the prefabricated three-dimensional modules have protrusions from the side of the beams, some of the prefabricated three-dimensional modules have recesses from the side of the base, and all the prefabricated three-dimensional modules have through holes in some of the sides, so that while connecting the prefabricated three-dimensional modules of the overlying floors with the prefabricated three-dimensional modules of the underlying floors by inserting the protrusions into the recesses, and connecting the prefabricated three-dimensional modules of one and the same floor by threaded connection through said through holes.
  • the method for constructing buildings of any type and purpose consists in the preliminary manufacture of three-dimensional-block products (three-dimensional modules) and their subsequent installation and connection with each other.
  • Prefabricated three-dimensional modules are made in a warm and bright premise of a modular residential construction technopolis (plant of reinforced-concrete products).
  • Prefabricated three-dimensional modules form prefabricated residential or public premises with 99% finishing with full readiness for their use, including living. Being manufactured in factory conditions, three-dimensional modules, when assembled and connected to each other on a construction site, form a prefabricated building of a residential or public type, or any other purpose.
  • the implementation of the proposed method allows one to construct buildings of any type and purpose (multi-storey or low-rise residential buildings, public buildings and structures, including hospitals, kindergartens, schools, sanatoriums, office buildings, etc.), of any configuration, of any planning solution, of any area, depending on the need, requires and design documentation.
  • prefabricated modules On the robotic conveyors 1 and 2, located in a workshop of a plant (technopolis), prefabricated three-dimensional modules 6, 7, 8, 9, 10 with 100% internal and external finishing are manufactured (hereinafter referred to as "prefabricated modules").
  • prefabricated modules On the robotic conveyors 1 and 2, located in a workshop of a plant (technopolis), prefabricated three-dimensional modules 6, 7, 8, 9, 10 with 100% internal and external finishing are manufactured (hereinafter referred to as "prefabricated modules”).
  • a formwork system form-installation, hereinafter referred to as the formwork
  • modules monolithic reinforced-concrete three-dimensional modules 12
  • the first conveyor 1 can have either one load-bearing body 13, or a larger number of load-bearing bodies 13 (two, three or more), on each of which, with the help of industrial robots and manipulators, the corresponding formwork 11 is formed, wherein the corresponding module 12 is manufactured.
  • a formwork 11 is formed for the manufacture of one module 12 (for example, a one-room apartment), on the second body 13, a formwork 11 is formed for the manufacture of another module 12 of a different size or shape (for example, a two-room apartment), on the third body 13, a formwork 11 is formed for the manufacture of a third module 12 (for example, a pre-apartment hall), on the fourth body 13, a formwork 11 is formed for the manufacture of another module 12 (for example, a stair-lift unit), and so on.
  • each formwork 11 on each load-bearing body 13 of the conveyor 1 has the possibility of operational readjustment, i.e. operational changes in its size and shape in all three coordinates (in plan and height, i.e. changes in length, width, height, configuration), depending on the required nomenclature configuration of the building, as well as taking into account the specified parameters, characteristics, shapes and standard sizes of the modules 12.
  • the corresponding module 12 may include a base plate 14, and/ or pillars 15, and/ or load-bearing walls 16, and/ or ceiling beams 17 (longitudinal and transverse), and/or ceiling crosspieces 18, and/ or ceiling panels 19.
  • a module 12 that forms an apartment
  • such a module includes a base plate 14, and pillars 15 (or solid walls 16 instead of pillars both with window openings, doorways, and without them), and ceiling beams 17 (or ceiling panel 19 instead of beams) and special crosspieces 18.
  • the corresponding module 12 may not have a base plate 14 and a ceiling panel 19, and such a module 12 will include pillars 15 or solid walls 16 and beams 17.
  • the module 12, which forms the apartment hall includes, mainly, both the base plate 14 and the ceiling panel 19.
  • Manufacturing of the corresponding modules 12 on the load-bearing bodies 13 of the conveyor 1 in the formwork 11 is carried out as follows (for example, manufacturing of modules 12 that form an apartment, a pre-apartment hall and an office space).
  • pallets 20 are placed, on which a corresponding formwork 11 is formed for the manufacture of a module 12 of required size and shape (the dimensions of the pallets 20-25 meters by 8 meters (length/ width), or a smaller size, preferably 17 meters by 8 meters (length/ width), depending on the size of the manufactured module 12).
  • Each pallet 20 is made of metal and has a smooth, flat surface. Before forming the formwork 11 on the pallet 20, the surface of the pallet 20 is treated, cleaned and covered with a thin layer of oil-air lubricating.
  • the pallets 20 are mostly of the same size and they transport along the factory floor along the roller conveyor.
  • a plate 14 of the base of the module 12 forming an apartment (6) is manufactured, on another load-bearing body 13, a plate 14 of the base of the module 12 forming an apartment hall (7) is manufactured, and on the third body 13, a plate 14 of the base of the module 12 forming an office space is manufactured.
  • Placement and fixing of the sides 22 to the pallet 20 is carried out by means of magnets 51, by means of which the sides 22 are fixed on the pallet 20 from four sides, forming the formwork dimensions of the lower base plate 14.
  • the sides 22 are located in the so-called "store" of the conveyor line 1.
  • the outer sides 22 are different in length and, depending on the geometric dimensions of the base plate 14, the robot independently determines the set of end sides 22.
  • the height of the sides 22 is mainly 250 mm.
  • reinforcement frames 26 are installed in the places where the pillars 15 are installed to form the pillars 15.
  • the concrete is supplied and the base plate 14 is formed in the corresponding formwork 11 for the base plate 14.
  • fire insulation and sound insulation are installed in the forms, as well as engineering communications are laid with the possibility of replacing them during operation.
  • the base plate 14 (the upper flat part) is treated with special devices (power trowels, not shown) in order to obtain an ideal flat surface.
  • the reinforcement frames 26 are not touched, while the release points of the reinforcement frame 26 may remain untreated in order to better further bond the concrete.
  • the dimensions of the plates 14 in the plan are mainly 15 meters by 6.5 meters (length/ width) or 16 meters by 7 meters (length/ width), which corresponds to a certain area of the manufactured, for example, apartment module (6), but the dimensions of the plates 14 can be different (smaller or larger) depending on the required area.
  • the ribbed plate 14 has both external longitudinal and transverse ribs 21 and internal ribs, with the size of the external ribs 21 being mainly 250 mm in height (the total height of the plate 14) and 180 mm in width, and the internal ribs in cross-section have a constant size (except for the places where the pillars 15 are installed), which is mainly 100 mm in width and 160 mm in height.
  • the thickness of the "field" of the plate 14 has, mainly, a thickness of 50 mm.
  • the specified dimensions may vary, depending on the purpose and type of module 12.
  • a formwork system can be used, having instead of inserts 23 for the formation of cells 24 a certain set of sides, which includes both end sides 22 and inner sides 52 and 53 for the formation of longitudinal and transverse ribs, and the sides 52 and 53 also have magnets 51, with which the sides 52 and 53 are placed and fixed on the pallet 20 ( Fig. 24 ).
  • the sides 52 and 53 are installed using a robot, which, depending on the size of the plate 14, independently determines the necessary set of sides 52 and 53, their size and placement on the pallet 20 by means of software.
  • the sides 27 of the formwork 11 for pillars 15 (or walls 16) and beams 17 have the ability to quickly change their spatial position relative to the base plate 14 with the help of a robot and make pillars 15 of any size and in any position (in any place) on the base plate 14 (including rotates by 90° with different brands of the module 12).
  • Void formers (inserts 28) between the pillars 15 are attached to the moving end sides 27 of the installation form, and they allow one to design any gaps between the pillars 15, as well as to design doorways 29, panoramic windows 30, etc.
  • the dimensions of the pillars 15 in the plan are preferably 180/500 mm, but the pillars 15 may have other dimensions (smaller or larger).
  • the number of pillars 15 in the module 12 is preferably eight, but there may be a different number of pillars 15 (more or less) depending on the size and configuration of the modules 12.
  • a module 12 forming a pre-apartment hall (7) may have dimensions, for example, 3/ 18/ 3 m. Or, if it is necessary to make, for example, a module 12 that forms an office space, then it may have dimensions, for example, 7,2/ 21/ 3,5 m. And so on, depending on the purpose of the corresponding module 12, it should be understood that, if necessary, the corresponding module 12 can also be made smaller, for example, in length, have the same size as in width (for example, 3 meters in length and width, or 4 meters in length and width, or, for example, 3,5 meters in width and 6 meters in length).
  • protrusions 31 and recesses 46 are formed in the modules 12.
  • the protrusions 31 (rod protrusions) are formed on top of the modules 12, and the recesses 46 are formed on the bottom of the modules 12 (from the bottom of the plate 14 in the ribs 21).
  • Protrusions 31 and recesses 46 are formed mainly in the places where the pillars 15 are executed and are directed along the pillars 15.
  • the protrusions 31 and the recesses 46 are designed for high-precision connection and installation of prefabricated modules on top of each other when they are installed on a construction site.
  • Construction products and components include: construction materials for engineering communications; materials for ventilation and roofing, as well as insulation materials; materials for the waterproofing process; materials for connecting any articles; materials for all types of finishing works (both for internal roughing and finishing of the room, and for external finishing); materials for creating built-in furniture; as well as any other materials necessary for the implementation of 99.9% of the premise finishing and the preparation of the prefabricated module 6-10 for its intended use.
  • Engineering communications (engineering support networks) used to form prefabricated modules 6-10 include (but are not limited to): external power supply systems (power transmission lines, transformer and tracking substations, etc.); internal power supply systems (including low-current ones); external heat supply systems; internal heat supply systems (hot water and heating systems); external water supply and sewerage systems (water supply sources, hydraulic structures, water and sewer treatment plants, collectors, pumping stations, etc.); internal water supply and sewage systems; ventilation and air conditioning systems; lighting systems; gas supply systems (gas distribution sites, pressure regulators, filters, safety valves, meters, gas pipelines, etc.); external communication networks; internal communication networks (telephone network, structured cabling system, automated dispatch control system, access control system, visualization system, video surveillance, Internet, smart home system, etc.); sewerage; drainage; fire water supply and security systems; etc.
  • external power supply systems power transmission lines, transformer and tracking substations, etc.
  • internal power supply systems including low-current ones
  • external heat supply systems internal heat supply systems (hot water and heating systems); external water supply and sewer
  • the conveyor 2 has, mainly, two levels 32 and 33 ( Fig. 18 ).
  • the first level 32 (for example, the lower one) includes one or two or more longitudinal parts 34 (lines) that transport the manufactured modules 12 on load-bearing bodies, and on which the prefabricated modules 6-10 are directly formed, both using robots and by manual labor.
  • the number of longitudinal parts 34 and load-bearing bodies of the first level 32 depends on the number of modules 12 that are transported simultaneously on the first level 32.
  • the second level 33 includes several transverse parts 35 (lines), with the help of which prefabricated construction articles and components are transported to the first level 32 in the corresponding zone to form the prefabricated modules 6-10.
  • the second level 33 can also produce construction articles and components necessary for formation of the prefabricated modules 6-10, which are subsequently also transported to the first level 32 for formation of the prefabricated modules 6-10.
  • the second conveyor 2 can have a special lift 36 in each zone, with the help of which the corresponding construction products and components are supplied from the second level 33 to the first level 32.
  • the workshop of the conveyor 2 can be combined with storage spaces where construction products and components are stored, which are subsequently supplied by means of the transverse parts 35 of the second level 33 of the conveyor 2 to the first level 32.
  • the transverse supply can be either on one side or on both sides relative to the first level 32.
  • monitors 45 can be installed, which broadcast to the workers the sequence of formation of the prefabricated modules 6-10 (when using manual labor to form the prefabricated modules 6-10), i.e. the sequence of certain communications installation, room finishing, etc.
  • the broadcast can be carried out, for example, by playing animated video files, or playing special video scenes that demonstrate the complete sequence of actions when forming the prefabricated modules 6-10 in the corresponding zone.
  • modules 12 that form the apartments (prefabricated module 6).
  • modules 12 are also prefabricated, but maybe with the use of other components, or excluding part of the components, depending on the type of module.
  • the load-bearing bodies of the first level 32 of the conveyor 2 transport with the modules 12, mainly continuously (or may have short stops).
  • all the necessary construction articles and components are supplied to the first level 32 from the second level 33, and inside the module 12 they do (both with the help of manual labor and with the help of robots), for example, pour the floor, install, for example, metal crosspieces 18 of the overlap (in the absence of a ceiling panel 19), carry out cladding work, cover the ceiling with drywall, prepare ventilation, insulate the walls and carry out other rough finishing.
  • the corresponding module (6) is transferred to the second zone of the conveyor 2 (second stage), where all necessary materials and components are also supplied from the second level 33 to the first level 32 and, for example, all plumbing work is carried out on the first level 32 inside and outside the modules (6), all plumbing communications are laid, pipelines, wiring, mortgages, sewer pipelines are installed, risers or connectors with risers are installed outside the apartment module (6) (if the risers are installed in the module 7 of the apartment hall), etc. Access points are being prepared for servicing pipe connections or for replacing pipes. Plumbing communication 40 is installed outside the modules 6, including on the side of the base plate 14 in special cells 24.
  • the apartment module 6 (originally module 12) is transferred to the third zone (the third stage), where the necessary materials and components are also supplied from the second level 33, and, for example, all electrical work is carried out, cables are laid, electric shields, weak points, lighting, etc. are installed. Necessary cables are laid, for example, for fire safety, for the "smart home" system, video surveillance, etc. Places of access to service electricians are prepared, special hatches 37 are installed (adjacent to the module 7 of the apartment hall), niches 38 are prepared for terminal blocks, etc. Electrical wiring 39 is performed mainly in the intermodule space, i.e. outside the modules, including from the side of the base plate 14 in special cells 24 (as well as through the inter-storey floors of adjacent apartment modules 7).
  • the module 6 is transferred to the next zone on the first level 32 (the fourth stage), where the necessary materials and components are also supplied from the second level 33 and, for example, complete interior decoration is carried out, for example, wallpaper is pasted, walls are painted, tiles are laid, parquet or linoleum or parquet board is laid, etc.
  • the module 6 is transferred to the next zone (the fifth stage), where the necessary materials and components are also supplied from the second level 33 and, for example, sockets, switches, a smart home system, video cameras, etc. are installed. Also in this area, for example, built-in water filters, sinks, showers, bathtubs, etc. can be installed. That is, at this stage, all the necessary work related to electrical and plumbing communication is completed.
  • the module 6 is transferred to the next zone (the sixth stage), where the necessary materials and components are also supplied from the second level 33 and, for example, the installation of built-in furniture in the appropriate specially prepared places is carried out.
  • the installers change the spatial location of the internal walls, as well as engineering communications and/ or built-in furniture.
  • Changing the spatial location of the internal walls with communications is carried out quickly by moving (transforming) the walls with communications and built-in furniture along special guides (niches in the floor and walls), as well as by using special fasteners, clamps, connections, etc.
  • the consumer can make a change in the spatial location and after the completion of the building construction, when he settled in the apartment (either on his own or with the involvement of specialists).
  • This transporting (transformation) of walls with communications and built-in furniture allows consumers to quickly change the space-planning solutions of their apartments (offices, etc.), depending on their needs, requires and wishes.
  • the prefabricated module 6 After all the finishing work is done, when the prefabricated module 6 is formed and ready to transport to the construction site, it is transported to the next zone, where electricians, plumbers and other persons conduct a control inspection of the prefabricated module 6, conduct crimping and testing, and make a conclusion about the readiness of the module 6.
  • the prefabricated module 6 is transferred to the next zone of the conveyor 2 (the last zone is the end of the second conveyor 2), where the prefabricated module 6 is packed in a protective material that prevents dust, moisture, dirt, etc. from entering the prefabricated module 6, as well as which eliminates any impact on the prefabricated module 6 that can damage it, and generally excludes access to the prefabricated module 6 by anyone.
  • a thick coating or a special cover is used as a protective material.
  • modules 6-10 are made, while in the case, for example, of the modules 8, 9 manufacture, forming a stair-lift unit, then on the second conveyor 2 (in the corresponding zone) inside such a module 7, lift shafts, staircases, etc. are prepared, railings, pipeline and/ or garbage disposal units, electrical communications (lighting, pipes and slats for electrical wiring, terminals, sockets, junction boxes, fuses and plugs, automatic fuses, switches, plug connections, distributors, etc.) are installed, walls are painted or tiled.
  • electrical communications lighting, pipes and slats for electrical wiring, terminals, sockets, junction boxes, fuses and plugs, automatic fuses, switches, plug connections, distributors, etc.
  • the prefabricated modules 10 are made, forming basements (lower modules).
  • all external networks enter and exit the lower modules 10 (for example, sewage and wastewater for heat ("return")).
  • the lower (basement) modules 10 have perfect waterproofing on the outside.
  • Some modules 10 have solid ribbed walls 16 (around the perimeter of the building), and some modules 10 may not have solid walls (internal modules 10 in the basement). Between the adjacent modules 10, passageways are organized along the entire building, there are separate entrances and exits to the basements.
  • Such modules 10 should have floor slabs 19, to which engineering pipes can be fixed.
  • all engineering equipment is mounted on the conveyor 2 (individual heat points, water pumping stations, centralized water and heat meters, etc.), i.e., 99.9% finishing is also carried out.
  • All prefabricated modules 6-10 are fully factory-ready, with the corresponding prefabricated modules 6-10 having the following (but not limited to): glazed window and balcony door blocks; door blocks with architraves and door devices; built-in cabinets and mezzanines; mounted wiring of central heating, cold and hot water supply, sewerage networks with sanitary and technical devices; mounted hidden electrical wiring with fittings for connection; ventilation units with exhaust radiators; floors on balconies (loggias); barrier constructions on the balconies; fully prefabricated facade surface of the exterior walls; interior finishing that meets the requirements of the building project, etc.
  • the second conveyor 2 which has two levels 32 and 33, combined with storage facilities, time is saved for the manufacture of prefabricated modules 6-10, and labor productivity is significantly increased.
  • it eliminates the need for workers of the relevant specialties (electricians, plumbers, finishers, etc.) to transport from one zone to another in order to carry out certain works.
  • Each worker is located in his own zone and only the products, components and tools necessary for his work are supplied to this zone from the second level 32.
  • Monitors 45 in each zone of the conveyor 2 demonstrating the sequence of certain works, also reduce the time for carrying out the corresponding works.
  • prefabricated modules 6-10 are installed (from the second conveyor 2) on the platform of a special vehicle 3 for transporting prefabricated modules 6-10 (one prefabricated module 6-10 per vehicle 3) and transport the prefabricated modules 6-10 to the construction site.
  • Transportation is carried out accompanied by special services and special equipment, mainly at night, as well as on pre-prepared and agreed routes that allow one to transport large-sized heavy cargo.
  • the packed prefabricated modules 6-10 are installed in the appropriate place by means of a lifting device 4.
  • the installation of prefabricated modules 6-10 is carried out on a floor-by-floor basis with the formation of a building by the method of floor-by-floor re-laying, i.e. a part of the prefabricated modules 6 (7) of even floors is installed relative to a part of the prefabricated modules 6 (7) of odd floors with an intersection in the plan of part of the load-bearing walls 16 (part of the prefabricated modules 6 is rotated 90° relative to a part of the lower prefabricated modules 6).
  • the building is constructed as follows.
  • Basement (lower) prefabricated modules 10 are installed, unpacked, mounted and connected to each other. In this case, the connection is carried out without the use of welding due to the places 47, where threaded connections are used.
  • prefabricated apartment modules 6 of the first floor prefabricated apartment modules 7, prefabricated modules of stair-lift units 8 and 9 are installed (by introducing projections 31 into recesses 46), workers unpack them and mount the prefabricated modules 6-9 and connect them to each other and to the prefabricated basement modules 10 (also without the use of welding due to the presence of places 47 for connecting adjacent modules using threaded connections).
  • prefabricated modules 6-9 Due to the presence of specially prepared protrusions 31 and recesses 46 in prefabricated modules 6-9 (10), respectively, in the upper and lower parts, through which the overlying prefabricated modules 6-9 are connected to the underlying ones, high-precision installation of the prefabricated modules 6-10 and their reliable connection to each other is ensured.
  • the prefabricated apartment modules 6, pre-apartment modules 7 and modules 8 and 9 of the stair-lift units of the second floor are installed, while part of the prefabricated modules 6 (7) of the second floor is rotated by 90° relative to part of the prefabricated modules 6 (7) of the first floor.
  • This floor-by-floor layout ensures high rigidity of the entire building, its stability and durability.
  • a bolted connection is mainly used, while ensuring that the modules 6-10 are vertically and horizontally adjacent to each other without a gap.
  • the size of the external joints between the modules is 14 mm (according to the previously conducted thermal engineering calculations (Mosstroy Research Institute), sizes less than this value are not allowed due to changes in the ambient temperature).
  • pallets 20 of the described size the possibility of changing the dimensions of the formwork 11 formed on pallets 20 in all three coordinates, as well as the use of different sizes of sets of inserts 23, 28 and the hydraulic system 48 (hydraulic cylinders that drive the formwork 11) for the formwork 11 allows one to increase the area of the buildings constructed, to ensure the versatility of buildings for any space-planning solutions.
  • robotic conveyors 1 and 2 as well as the presence of the conveyor 2 separate zones wherein certain operations are carried out to form prefabricated modules 6-10, allows one to significantly increase the volume of daily manufacture of prefabricated modules 6-10 and increase productivity.
  • Floor-by-floor re-laying of prefabricated modules 6-10 during the construction of buildings i.e., turning part of the prefabricated modules of even storeys relative to part of the prefabricated modules of odd storeys, mainly by 90° (or at a different angle), ensures high rigidity, durability and stability of buildings even in the absence of welded joints.
  • one of the main principles of the invention is that the architect manages the factory manufacture, and not vice versa.
  • Module-apartments are large in size and have free layout.
  • the workplace the place of labor application
  • materials and components transfer to the performer of the work, and not vice versa, as in existing construction technologies.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Automatic Assembly (AREA)

Description

    FIELD OF THE INVENTION
  • The invention relates to the field of construction, in particular to modular three-dimensional-block construction, and can be used for construction of low-rise and multi-storey residential buildings, public buildings and structures, as well as other buildings of any other purpose.
  • BACKGROUND OF THE INVENTION
  • From the state of the technologic construction, a method of constructing buildings from three-dimensional blocks is known, which consists in installing a three-dimensional block in a vertical position, side walls of which are rigidly connected to side walls of a next block through gaskets. The blocks are installed one by one around the perimeter of the building. The lower part of the connected blocks can serve as a foundation when they are installed below the zero mark of the building. Depending on the intended purpose, internal walls, floors and openings can be formed in buildings (see patent RU 2076178C1 , convention priority: 09.12.1994 RU 94 94044472 ).
  • A disadvantage of the known method is that the blocks used are block rooms at best case, and not module apartments, the blocks do not have interior finishing and are not ready for use for their intended purpose, low productivity, small space-planning characteristics of the block and the lack of quickly changing the configuration possibility of the blocks, there are no free layouts, the lack of possibility for an architect to offer his solutions, since the plant dictates and offers only its manufacturing capabilities.
  • Also known from the state of the technologic construction is a method for buildings constructing using a modular frame, which consists in assembling the lower floor panel - floor beams, installing a pre-assembled metal frame on the floor beams, and installing metal frame racks. On the frame assembled in this way, the upper binding beam of the frame is laid on top, which forms ceiling, then parts of the frame and the metal frame are bolted together. Utilities elements are installed in the assembled frame, according to planning solutions. After casing the frame and laying the insulation, there is a start for the module interior finishing. Doors, windows are installed and walls are being prefabricated, flooring and ceiling are being put in position. The module manufactured at the factory is transported to the construction site, where final assembly of the building is carried out (see patent RU128219U1, published on 20.05.2013 ).
  • The disadvantage of the known method is high mass of the module structure per one meter of square area, low productivity, lack of possibility of rapid changes in the module's configuration, their shapes and sizes, modules' small overall dimensions with a limited area, lack of possibility of rapid changes in the planning solutions of premises.
  • The closest approach to the proposed solution is a method of buildings construction, which consists in manufacturing three-dimensional blocks, after which prefabricated three-dimensional blocks are formed using construction components, including engineering communications, by means of installing engineering communications and performing interior finishing, then the prefabricated three-dimensional blocks are transported using vehicles to a construction site, where, by means of lifting devices, prefabricated three-dimensional blocks are installed in an appropriate place and the prefabricated three-dimensional blocks are installed and connected to each other, while the prefabricated three-dimensional blocks are installed on top of one another in a similar position (see, for example, the website on the Internet https://studfíles.net/preview/5193963/).
  • The disadvantage of the known method is the lack of possibility to quickly change configuration of blocks, their shapes and sizes, when implementing the method, it is possible to manufacture only the same type of blocks, low productivity, small overall dimensions of blocks with a limited area, lack of possibility to change quickly planning solutions of premises and finishing and engineering preparation at the factory is no more than 20-30%.
  • US 3,714,304 A and SU 495208 A1 disclose conveyors used for manufacture of prefabricated three-dimensional modules, installation during manufacture of engineering communications, performing interior and exterior finishing, forming internal partitions installing built-in furniture, etc.
  • US 3,884,613 A and JP 3 236834 B2 constitute further prior art.
  • SUMMARY OF THE INVENTION
  • The invention is defined in claim 1.
  • The technical problem solved by the invention is an increase in area of buildings constructed and in volume of daily output, an increase in productivity, a reduction in time and labor costs for construction of buildings, an increase in comfort of premises constructed and a significant increase in their quality.
  • The technical result of the invention, which provides a solution to the technical problem, is the reduce in complexity and cost of construction, simplicity of three-dimensional modules installation, ensuring building versatility for any three-dimensional planning solutions due to the possibility of rapid changes in size and shape of three-dimensional modules in all coordinates, increase in rigidity, reliability and stability of the building due to the floor-by-floor re-laying of three-dimensional modules during their installation, increase in accuracy of the buildings assembling due to provision of high-precision dimensions of three-dimensional modules, ensuring the possibility of rapid changes in three-dimensional planning solutions.
  • The technical result of the invention is achieved by implementing a method for constructing buildings, wherein on robotic conveyors located in a plant workshop, prefabricated three-dimensional modules are made, moreover, on the first robotic conveyor, a formwork system is formed and a monolithic reinforced-concrete three-dimensional module including a base plate and/ or pillars and/ or walls and/ or beams and/ or crosspieces and/ or ceiling panels is manufactured in said formwork system, said manufactured three-dimensional module is transferred to a second robotic conveyor, where the prefabricated three-dimensional module is formed, using construction components, including engineering communications, by means of installing engineering communications, performing internal and/ or external finishing, and/ or installing built-in furniture, then at the end of the second robotic conveyor the prefabricated three-dimensional module is packaged in a protective material, and other prefabricated three-dimensional modules are manufactured in the same way, the packaged prefabricated three-dimensional modules are transported to a construction site by means of vehicles, where, by means of lifting devices, the packaged prefabricated three-dimensional modules are installed in the appropriate place, unpacked, assembled and connected to one another, moreover, the installation of the prefabricated three-dimensional modules is carried out floor-by-floor resulting in the formation of a building so that a portion of the prefabricated three-dimensional modules of even-numbered floors is installed relative to a portion of the prefabricated three-dimensional modules of odd-numbered floors so that, in plan view, some of the walls intersect.
  • In addition, it is possible to form a formwork system on the first robotic conveyor with the possibility of changing its dimensions in plan and height.
  • In addition, it is possible to manufacture the monolithic reinforced-concrete three-dimensional module, mainly with the width of 3 to 7.2 meters, the length of 8 to 21 meters, and the height of 3 to 3.5 meters.
  • In addition, the manufacture of a prefabricated three-dimensional module on robotic conveyors can be carried out with the help of industrial robots.
  • In addition, as at least one lifting device, a crawler-mounted heavy boom-type crane with a lifting capacity of mainly up to 750 tons can be used.
  • In addition, the second robotic conveyor can be used, which can include two levels, while the first level can include at least one longitudinal part for moving the monolithic reinforced-concrete three-dimensional module, and the second level can include transverse parts for manufacturing construction components and supplying them to the first level.
  • In addition, after the installation and connection of the corresponding prefabricated three-dimensional modules to each other, the building can be constructed with the possibility of dismounting and transporting the prefabricated three-dimensional modules to another construction site by means of a vehicle.
  • In addition, the three-dimensional module can have internal walls, and after the installation of engineering communications, the execution of internal and/ or external finishing and/ or the installation of built-in furniture, spatial arrangement of the internal walls, as well as engineering communications and/ or built-in furniture can be changed.
  • In addition, the formation of the formwork system on the first robotic conveyor can be carried out on a pallet, which is cleaned and covered with a layer of oil-air lubricant before the formation of the formwork system.
  • In addition, some of the prefabricated three-dimensional modules have protrusions from the side of the beams, some of the prefabricated three-dimensional modules have recesses from the side of the base, and all the prefabricated three-dimensional modules have through holes in some of the sides, so that while connecting the prefabricated three-dimensional modules of the overlying floors with the prefabricated three-dimensional modules of the underlying floors by inserting the protrusions into the recesses, and connecting the prefabricated three-dimensional modules of one and the same floor by threaded connection through said through holes.
  • DESCRIPTION OF THE DRAWINGS
  • The invention is illustrated using drawings, where:
    • Fig. 1 shows a general view of one of the embodiments of a monolithic reinforced-concrete three-dimensional module with protrusions on the upper part for connection (during installation) with overlying three-dimensional modules, as well as with places for connection with neighboring modules of the same floor;
    • Fig. 2 shows an example of one of the options for installing three-dimensional modules on top of each other (basement and the first two floors);
    • Fig. 3 schematically shows an example of the floor-by-floor rearrangement of three-dimensional modules during their installation;
    • Fig. 4 schematically shows an example of the three-dimensional modules location in the plan, for example, odd floors;
    • Fig. 5 schematically shows an example of the three-dimensional modules location in the plan, for example, even floors;
    • Fig. 6 schematically shows the location of connected three-dimensional modules, for example, odd floors, a view in axonometry;
    • Fig. 7 schematically shows the location of connected three-dimensional modules, for example, even floors, a view in axonometry;
    • Fig. 8 shows the underside of the base panel of the module forming an apartment or room, or a pre-apartment hall, or an office space, etc.;
    • Fig. 9 shows the section A-A in Fig. 8;
    • Fig. 10 schematically shows a part of one load-bearing body of the first conveyor in plan view with a pallet placed on it and a product (a three-dimensional module);
    • Fig. 11 schematically shows an example of the formwork formation for manufacture of three-dimensional modules in plan view;
    • Fig. 12 shows the same as on Fig. 11 in axonometry;
    • Fig. 13 shows the section B-B in Fig. 11 (in the manufacture of a three-dimensional module);
    • Fig. 14 schematically shows interior space of one of the pre-apartment module variants;
    • Fig. 15 schematically shows an example of coupling of an apartment module with a pre-apartment module at the junction of engineering communications (section C-C in Fig. 14);
    • Fig. 16 schematically shows the location of engineering communications between three-dimensional pre-apartment modules (when installing three-dimensional modules);
    • Fig. 17 schematically shows the conveyors on which the prefabricated three-dimensional modules are formed, and transporting of three-dimensional modules on the conveyors;
    • Fig. 18 schematically shows the second conveyor with movable three-dimensional modules (view D in Fig. 17);
    • Fig. 19 schematically shows an example of construction (installation) of a building from prefabricated three-dimensional modules using a lifting device (floor-by-floor laying of the prefabricated three-dimensional modules);
    • Fig. 20 schematically shows bolted connection (without welding) of adjacent prefabricated three-dimensional modules during their installation;
    • Fig. 21 shows an example of assembling and connecting modules to each other during floor-to-floor laying without welding;
    • Fig. 22 shows the junction of the overlying floors' three-dimensional modules with the underlying ones, the disassembly of E in Fig. 21;
    • Fig. 23 shows the connection point of adjacent three-dimensional modules of one floor, the disassembly ofF in Fig. 21;
    • Fig. 24 shows an example of a formwork for the manufacture of a base plate with longitudinal and transverse ribs.
    EXAMPLES OF EMBODIMENTS OF THE INVENTION
  • The method for constructing buildings of any type and purpose consists in the preliminary manufacture of three-dimensional-block products (three-dimensional modules) and their subsequent installation and connection with each other. Prefabricated three-dimensional modules are made in a warm and bright premise of a modular residential construction technopolis (plant of reinforced-concrete products). Prefabricated three-dimensional modules form prefabricated residential or public premises with 99% finishing with full readiness for their use, including living. Being manufactured in factory conditions, three-dimensional modules, when assembled and connected to each other on a construction site, form a prefabricated building of a residential or public type, or any other purpose.
  • To implement the method, robotic conveyors 1 and 2 (Fig. 17) are used with industrial robots, manipulators and other robotic equipment (using special software and hardware complexes, not shown), which are fully automated, and which are located in a workshop of modular residential construction technopolis (in a warm premise). Moreover, two robotic conveyors 1 and 2 are mainly used, or a larger number of conveyors, depending on the need and the necessity of performing a certain operation with three-dimensional modules, while each of the conveyors 1 and 2 is equipped with industrial robots, both stationary and mobile. Also, for the implementation of the method, in particular for transporting prefabricated three-dimensional modules to the construction site, special vehicles 3 (module-transporters) are used, which have large platforms for placing prefabricated three-dimensional modules on them. Directly on the construction site for the implementation of the method, in particular for lifting prefabricated three-dimensional modules, assembling them and connecting them to each other, a heavy boom-type crane 4 (Fig. 19) is used, mainly on a crawler track, with a load capacity of up to 750 tons (for example, by Liebherr). This crane 4 allows one to lift and install large three-dimensional modules (weighing more than 60 tons) to a height of up to 100 meters (and higher, i.e. to construct a building of up to 30 floors or more). Also, other lifting devices, such as a gantry crane and any other lifting devices, can be used for lifting, installing and mounting three-dimensional modules.
  • The implementation of the proposed method allows one to construct buildings of any type and purpose (multi-storey or low-rise residential buildings, public buildings and structures, including hospitals, kindergartens, schools, sanatoriums, office buildings, etc.), of any configuration, of any planning solution, of any area, depending on the need, requires and design documentation.
  • Further, we will consider the implementation of the proposed method for the construction of a residential building, however, it should be understood that a similar sequence of actions is applicable for the construction of buildings of any other purpose and differs only in size, shape and planning solutions of corresponding three-dimensional modules that form buildings of a particular purpose.
  • The proposed method for constructing buildings is as follows.
  • On the robotic conveyors 1 and 2, located in a workshop of a plant (technopolis), prefabricated three- dimensional modules 6, 7, 8, 9, 10 with 100% internal and external finishing are manufactured (hereinafter referred to as "prefabricated modules"). At the same time, on the first conveyor 1 (located, for example, in the molding workshop of the factory), a formwork system (form-installation, hereinafter referred to as the formwork) is formed first, wherein monolithic reinforced-concrete three-dimensional modules 12 (hereinafter referred to as "modules") are manufactured. The first conveyor 1 can have either one load-bearing body 13, or a larger number of load-bearing bodies 13 (two, three or more), on each of which, with the help of industrial robots and manipulators, the corresponding formwork 11 is formed, wherein the corresponding module 12 is manufactured. For example, on the first body 13, a formwork 11 is formed for the manufacture of one module 12 (for example, a one-room apartment), on the second body 13, a formwork 11 is formed for the manufacture of another module 12 of a different size or shape (for example, a two-room apartment), on the third body 13, a formwork 11 is formed for the manufacture of a third module 12 (for example, a pre-apartment hall), on the fourth body 13, a formwork 11 is formed for the manufacture of another module 12 (for example, a stair-lift unit), and so on. In the variant version, the same formwork can be formed on each load-bearing body 13 And, wherein the same modules 12 are manufactured (for example, only apartments), or on one part of the bodies 13, one formwork 11 is formed (for example, for the manufacture of apartments), on another part of the bodies 13, other formwork 11 is formed (for example, for the manufacture of apartment halls), etc. Moreover, each formwork 11 on each load-bearing body 13 of the conveyor 1 has the possibility of operational readjustment, i.e. operational changes in its size and shape in all three coordinates (in plan and height, i.e. changes in length, width, height, configuration), depending on the required nomenclature configuration of the building, as well as taking into account the specified parameters, characteristics, shapes and standard sizes of the modules 12. The possibility of rapid changeover of the formwork 11 to the required dimensions, configuration and shape of the modules 12 is provided by the use of industrial robots and manipulators on the robotic conveyor 1, which are controlled by an operator using a special software and hardware complex, while special software allows robots to quickly select and form the necessary formwork 11 of a given size and shape.
  • Depending on the type of modules 12 (a module forming a room
    or an apartment (one -, two -, three-room, etc.), or an apartment hall, or a stair-lift unit, or an office space in a residential building, etc.), the corresponding module 12 (Fig. 1) may include a base plate 14, and/ or pillars 15, and/ or load-bearing walls 16, and/ or ceiling beams 17 (longitudinal and transverse), and/or ceiling crosspieces 18, and/ or ceiling panels 19. So, for example, if it is necessary to manufacture a module 12 that forms an apartment, then such a module includes a base plate 14, and pillars 15 (or solid walls 16 instead of pillars both with window openings, doorways, and without them), and ceiling beams 17 (or ceiling panel 19 instead of beams) and special crosspieces 18. If it is necessary to make a stair-lift unit, then the corresponding module 12 may not have a base plate 14 and a ceiling panel 19, and such a module 12 will include pillars 15 or solid walls 16 and beams 17. And so on, depending on the purpose of the corresponding module 12, and the module 12, which forms the apartment hall, includes, mainly, both the base plate 14 and the ceiling panel 19.
  • Manufacturing of the corresponding modules 12 on the load-bearing bodies 13 of the conveyor 1 in the formwork 11 is carried out as follows (for example, manufacturing of modules 12 that form an apartment, a pre-apartment hall and an office space). On the load-bearing bodies 13, pallets 20 are placed, on which a corresponding formwork 11 is formed for the manufacture of a module 12 of required size and shape (the dimensions of the pallets 20-25 meters by 8 meters (length/ width), or a smaller size, preferably 17 meters by 8 meters (length/ width), depending on the size of the manufactured module 12). Each pallet 20 is made of metal and has a smooth, flat surface. Before forming the formwork 11 on the pallet 20, the surface of the pallet 20 is treated, cleaned and covered with a thin layer of oil-air lubricating.
  • The pallets 20 are mostly of the same size and they transport along the factory floor along the roller conveyor. At the same time, at the first stage, on one load-bearing body 13 of the conveyor 1, a plate 14 of the base of the module 12 forming an apartment (6) is manufactured, on another load-bearing body 13, a plate 14 of the base of the module 12 forming an apartment hall (7) is manufactured, and on the third body 13, a plate 14 of the base of the module 12 forming an office space is manufactured.
  • Each pallet 20, after preparation, transported to the position of the line (conveyor 1), where the industrial robot positions the module 12 of a specific brand. The base plates 14 in the lower part have a cellular structure with longitudinal and transverse ribs 21 (see Fig. 8). For the manufacture of base plates 14, the external sides 22 of the formwork 11 are installed on the pallet 20 using a robot according to the specified geometric dimensions, as well as special calibrated inserts 23 for forming square or rectangular cells 24 (recesses) in the lower part of the base plate 14 (inserts 23 for cells 24 have slopes for demoulding). The sides 22 are positioned and promptly placed by the robot under the module 12 of a specific brand in accordance with the documentation available in the computer. Placement and fixing of the sides 22 to the pallet 20 is carried out by means of magnets 51, by means of which the sides 22 are fixed on the pallet 20 from four sides, forming the formwork dimensions of the lower base plate 14. Initially, the sides 22 are located in the so-called "store" of the conveyor line 1. Moreover, the outer sides 22 are different in length and, depending on the geometric dimensions of the base plate 14, the robot independently determines the set of end sides 22. The height of the sides 22 is mainly 250 mm. Next, it is laid the reinforcement 25, the frames in the ribs 21. In the base plate 14 that has not yet been formed, reinforcement frames 26 are installed in the places where the pillars 15 are installed to form the pillars 15. Further, by means of, for example, a concrete paver, the concrete is supplied and the base plate 14 is formed in the corresponding formwork 11 for the base plate 14. In a variant implementation of the invention, before pouring the formwork 11 with concrete, fire insulation and sound insulation are installed in the forms, as well as engineering communications are laid with the possibility of replacing them during operation. After setting the concrete, the base plate 14 (the upper flat part) is treated with special devices (power trowels, not shown) in order to obtain an ideal flat surface. When processing the plate 14 with turntables, the reinforcement frames 26 are not touched, while the release points of the reinforcement frame 26 may remain untreated in order to better further bond the concrete.
  • Each base plate 14 can be changed in overall dimensions depending on the required size of the module 12, for this purpose, on the corresponding pallet 20, unnecessary inserts 23 for cells 24 are removed by a robot (or manually) and the sides 22 of the formwork 11 are narrowed (in case of reducing the overall dimensions of the module 12). Also, the dimensions of the base plates 14 during their manufacture can vary in length and width due to the sets of end sides 22 and inserts 23 to form cells 24, which are stored in a special place near the conveyor 1 (in the "store"). The robot takes the necessary sides 22 and inserts 23 from the "store" at the necessary time to form cells 24 and places them on the pallet 20 in the appropriate places and in the appropriate position. On one pallet 20, one can make both one base plate 14 and two plates 14, if they have small overall dimensions. The dimensions of the plates 14 in the plan are mainly 15 meters by 6.5 meters (length/ width) or 16 meters by 7 meters (length/ width), which corresponds to a certain area of the manufactured, for example, apartment module (6), but the dimensions of the plates 14 can be different (smaller or larger) depending on the required area. The ribbed plate 14 has both external longitudinal and transverse ribs 21 and internal ribs, with the size of the external ribs 21 being mainly 250 mm in height (the total height of the plate 14) and 180 mm in width, and the internal ribs in cross-section have a constant size (except for the places where the pillars 15 are installed), which is mainly 100 mm in width and 160 mm in height. The thickness of the "field" of the plate 14 has, mainly, a thickness of 50 mm. However, the specified dimensions may vary, depending on the purpose and type of module 12. In addition, for the manufacture of base plates 14, a formwork system can be used, having instead of inserts 23 for the formation of cells 24 a certain set of sides, which includes both end sides 22 and inner sides 52 and 53 for the formation of longitudinal and transverse ribs, and the sides 52 and 53 also have magnets 51, with which the sides 52 and 53 are placed and fixed on the pallet 20 (Fig. 24). The sides 52 and 53 are installed using a robot, which, depending on the size of the plate 14, independently determines the necessary set of sides 52 and 53, their size and placement on the pallet 20 by means of software. The sides 52 and 53 are also located in the "store" and, when placed by the robot, have the ability to change their position on the pallet 20 in order to change, if necessary, the dimensions (height and width) of the internal longitudinal and transverse ribs of the base plate 14. When using such a formwork system for the formation of cells 24, special, for example, plywood sheets 54 are used, which are installed on the stops 55, fixed on the sides 52 and 53. The sides 52 and 53 also have slopes to ensure that the base plate 14 is demoulded after it is formed. The replaceable sides 22, 52 and 53 with magnets 51, which are quickly installed by the robot on the pallet 20, depending on the required size of the plate 14, provide an operational change in the spatial location on the pallet 20 and the possibility of manufacturing the plate 14 with ribs (external and internal, longitudinal and transverse) of any required size. The use of such sides 22, 52 and 53 allows one to significantly save time on the formation of the formwork 11 for the base plate 14 and increase labor productivity.
  • After forming and finishing the upper part of the plate 14, the entire surface of the plate 14 can be covered with special decking, and before that can be covered with a coating so that when the cement interacts (reacts) with water in the concrete mass of the plate 14, isothermal processes begin, and the product begins to warm itself 20. It is necessary to ensure that the fresh concrete of the pillars 15 "goes" to the surface of the already not sufficiently hardened concrete of the plate 14. At the same time, certain concrete compositions are selected so that when pouring pillars 15, the concrete does not squeeze the set concrete of the plate 14 out from under the formwork 11.
  • After forming the base plate 14, the pallet 20 (with the base plate 14 formed on it and the outlets of the reinforcement frame 26) on the first conveyor 1 (along the roller) is supplied to the installation post of the vertical formwork 11 (the vertical molding post), i.e. it transports to the installation form for the manufacture of vertical pillars 15 and beams 17 (it drives under the installation form, which forms the formwork 11, Fig. 11 and 12). The number of mold units in the factory is preferably not less than sixteen units, but there can be any other number of such mold units, depending on the required capacity. In advance, the robot puts the inserts 28 (pillar formers 15) on the longitudinal and transverse sides 27. Such inserts 28 are typeset and, depending on the location, are attached to magnets, taking into account the horizontal forces of the robot. Similarly, with the help of the robot, other inserts are installed, which form the geometric dimensions of the pillars 15 and the upper binding beams 17 around the entire perimeter of the module 12. Then a formwork for intermittent floor slabs can be installed (separately) on the closed plate 14 (in the middle and ends of the module 12, and depending on the width of the module 12, the dimensions of such a formwork may change).
  • The longitudinal and transverse sides 27 of the formwork 11 for the manufacture of pillars 15 and beams 17 with inserts 28 already attached to them (in accordance with the drawings) are transported only in the horizontal plane to the desired size. At the same time, these sides 27 with inserts 28 have, mainly, a fan arrangement (and work on the "shutter" principle). Such sides 27 "hover" over the pallet 20 and the end sides 22 of the base plate 14, and they have the possibility to "drive" inside a forming system of the pillar 15 of the vertical reinforcement 26. In addition, the sides 27 of the formwork 11 for pillars 15 (or walls 16) and beams 17 have the ability to quickly change their spatial position relative to the base plate 14 with the help of a robot and make pillars 15 of any size and in any position (in any place) on the base plate 14 (including rotates by 90° with different brands of the module 12). Void formers (inserts 28) between the pillars 15 are attached to the moving end sides 27 of the installation form, and they allow one to design any gaps between the pillars 15, as well as to design doorways 29, panoramic windows 30, etc. Further, after preparing the formwork 11 for pillars 15 and beams 17, fill the formwork 11 with concrete to form pillars 15, made at the same time as the base plate 14, and with the formation of longitudinal and transverse beams 17 for the ceiling (or, if necessary, immediately the ceiling panel 19). Between the pillars 15 (if necessary), a wall 16 of rigidity can be formed, which is solved by the absence of an insert 28. In this case, in some of the pillars 15 (on top of the module 12), for example, located in the corners of the base panel 15, or in all the pillars 15, special loops (catchers, not shown) can be formed to lift the module 12, or special sleeves can be formed with threaded holes for reinforced bolts or studs (not shown), with the help of which the subsequent high-precision installation of the prefabricated modules and their connection to each other on the construction site. If necessary, using the formwork 11 with inserts 28 instead of pillars 15 or along with them, it is possible to form load-bearing walls 16 in the module 12 with window and/ or door openings 30, 29 in any place in accordance with the design documentation and drawings. Due to the manufacture of the modules 12 completely monolithic, i.e. the monolithic connection of the base plate 14 with the pillars 15, and the pillars 15 with the beams 17 in the longitudinal and transverse direction, high rigidity of the modules 12 is ensured. And due to the use of quickly changeable formwork 11 (with the help of industrial robots), the highest precision of manufacturing modules 12 is provided, which is very important during subsequent assembly during installation. The dimensions of the pillars 15 in the plan are preferably 180/500 mm, but the pillars 15 may have other dimensions (smaller or larger). The number of pillars 15 in the module 12 is preferably eight, but there may be a different number of pillars 15 (more or less) depending on the size and configuration of the modules 12.
  • On the first conveyor 1, the modules 12 can be manufactured in any size, while depending on the area of the modules 12 to be manufactured, the purpose and type of modules 12 (apartment, apartment hall, stairlift unit, etc.), the modules 12 can have, mainly, a width of 3 to 7.2 meters, a length of 8 to 21 meters, a height of 3 to 3.5 meters (however, there may be smaller sizes in the corresponding direction). That is, for example, if it is necessary to make a module 12 that forms an apartment (6), then it can have dimensions (depending on the area of the apartment), for example, 6,5/ 15/ 3 m (width/ length/ height, respectively) or 7/ 10/ 3 m, etc. If it is necessary to make, for example, a module 12 forming a pre-apartment hall (7), then such a module 12 may have dimensions, for example, 3/ 18/ 3 m. Or, if it is necessary to make, for example, a module 12 that forms an office space, then it may have dimensions, for example, 7,2/ 21/ 3,5 m. And so on, depending on the purpose of the corresponding module 12, it should be understood that, if necessary, the corresponding module 12 can also be made smaller, for example, in length, have the same size as in width (for example, 3 meters in length and width, or 4 meters in length and width, or, for example, 3,5 meters in width and 6 meters in length).
  • In addition, when manufacturing the modules 12 on the first conveyor 1, it is possible to form protrusions 31 and recesses 46 in the modules 12. Moreover, the protrusions 31 (rod protrusions) are formed on top of the modules 12, and the recesses 46 are formed on the bottom of the modules 12 (from the bottom of the plate 14 in the ribs 21). Protrusions 31 and recesses 46 are formed mainly in the places where the pillars 15 are executed and are directed along the pillars 15. The protrusions 31 and the recesses 46 are designed for high-precision connection and installation of prefabricated modules on top of each other when they are installed on a construction site. When installing the prefabricated modules 6-10 of the overlying floors on the prefabricated modules 6-10 of the underlying floors, the projections 31 enter the recesses 46, as a result of which high-precision positioning of the prefabricated modules 6-10 is provided during construction of the building and, as a result, high-precision installation of prefabricated modules 6-10. Such protrusions 31 and recesses 46 can also be formed on the second conveyor 2 after manufacturing of the prefabricated modules 6-10.
  • Also, when manufacturing the modules 12 on the first conveyor 1 with the help of the formwork 11, it is possible to form special places 47 in the modules 12, made in the form of recesses and through holes 49. The places 47 are formed in pillars 15 (or in solid walls 16, if available) and provide the possibility of connecting the prefabricated modules 6-10 to each other when they are installed on the construction site using threaded connections (without welding). Such places 47 allow to connect prefabricated modules 6-10 of one (own) floor to each other by inserting through the holes 49, for example, reinforced bolts 50 and fixing them, for example, with reinforced locking nuts. The places 47 can also be formed already on the second conveyor 2 after manufacturing of the prefabricated modules 6-10.
  • Thus, due to the use of industrial robots and manipulators on the conveyor 1, which quickly form the formwork 11 of any shape and size, it is possible to quickly change the dimensions and shapes of the formwork 11 in order to manufacture modules 12 of any size, shape and configuration. As a result, productivity increases, time for manufacturing modules 12 of the desired shape, type and size is significantly reduced, need for manual labor for forming the formwork 11 is eliminated, accuracy of the specified dimensions of the modules 12 is increased, as well as quality of the manufactured modules 12.
  • After the first conveyor 1 has produced the corresponding frame-monolithic module 12 (modules forming apartments (6), pre-apartment halls (7), stair-lift units (8, 9), basements (10), etc.), it (they) is transported to the second robotic conveyor 2 (located, for example, in the conveyor workshop, where the temperature corresponds to room temperature), where a prefabricated module (prefabricated modules 6-10) is formed from it (them) using construction products and components. At the same time, the formation of prefabricated modules 6-10 can also be carried out with the help of industrial robots (not shown), as well as through manual labor.
  • Construction products and components include: construction materials for engineering communications; materials for ventilation and roofing, as well as insulation materials; materials for the waterproofing process; materials for connecting any articles; materials for all types of finishing works (both for internal roughing and finishing of the room, and for external finishing); materials for creating built-in furniture; as well as any other materials necessary for the implementation of 99.9% of the premise finishing and the preparation of the prefabricated module 6-10 for its intended use.
  • The corresponding prefabricated modules 6-10 (depending on the purpose) are formed on the conveyor 2 by installing engineering communications, by forming internal partitions (internal walls separating the premises in the corresponding module), by forming external walls, if only pillars 15 were originally made in the formwork 11 instead of load-bearing walls 16, by performing internal finishing (as well as external finishing, if necessary, i.e. if part of the external walls of the corresponding prefabricated modules 6-10 form the facade of the building), by installing built-in furniture. Engineering communications (engineering support networks) used to form prefabricated modules 6-10 include (but are not limited to): external power supply systems (power transmission lines, transformer and tracking substations, etc.); internal power supply systems (including low-current ones); external heat supply systems; internal heat supply systems (hot water and heating systems); external water supply and sewerage systems (water supply sources, hydraulic structures, water and sewer treatment plants, collectors, pumping stations, etc.); internal water supply and sewage systems; ventilation and air conditioning systems; lighting systems; gas supply systems (gas distribution sites, pressure regulators, filters, safety valves, meters, gas pipelines, etc.); external communication networks; internal communication networks (telephone network, structured cabling system, automated dispatch control system, access control system, visualization system, video surveillance, Internet, smart home system, etc.); sewerage; drainage; fire water supply and security systems; etc.
  • Thus, on the second conveyor 2, prefabricated modules 6-10 are formed with 100% finishing, completely ready for use. In this case, the conveyor 2 has, mainly, two levels 32 and 33 (Fig. 18). The first level 32 (for example, the lower one) includes one or two or more longitudinal parts 34 (lines) that transport the manufactured modules 12 on load-bearing bodies, and on which the prefabricated modules 6-10 are directly formed, both using robots and by manual labor. The number of longitudinal parts 34 and load-bearing bodies of the first level 32 depends on the number of modules 12 that are transported simultaneously on the first level 32. The second level 33 includes several transverse parts 35 (lines), with the help of which prefabricated construction articles and components are transported to the first level 32 in the corresponding zone to form the prefabricated modules 6-10. In addition, the second level 33 can also produce construction articles and components necessary for formation of the prefabricated modules 6-10, which are subsequently also transported to the first level 32 for formation of the prefabricated modules 6-10. The second conveyor 2 can have a special lift 36 in each zone, with the help of which the corresponding construction products and components are supplied from the second level 33 to the first level 32. The workshop of the conveyor 2 can be combined with storage spaces where construction products and components are stored, which are subsequently supplied by means of the transverse parts 35 of the second level 33 of the conveyor 2 to the first level 32. In this case, the transverse supply can be either on one side or on both sides relative to the first level 32. In addition, on the first level 32 of the conveyor 2 in the corresponding zone (at each stage of the prefabricated module 6-10 formation), monitors 45 (screens, televisions, projectors, etc.) can be installed, which broadcast to the workers the sequence of formation of the prefabricated modules 6-10 (when using manual labor to form the prefabricated modules 6-10), i.e. the sequence of certain communications installation, room finishing, etc. The broadcast can be carried out, for example, by playing animated video files, or playing special video scenes that demonstrate the complete sequence of actions when forming the prefabricated modules 6-10 in the corresponding zone. Due to the use of such monitors 45, which broadcast to workers the entire sequence of actions for the formation of the prefabricated modules 6-10, it eliminates the need for workers to study in detail the design documentation, to select certain construction products and components, as a result of which workers quickly begin to form prefabricated modules 6-10 by installing certain articles, which significantly reduces the time for formation of the prefabricated modules 6-10 and increases labor productivity.
  • The proposed method is carried out using the conveyor 2 as follows.
  • After manufacturing the corresponding module 12 in the molding workshop on the conveyor 1 and transferring it to the conveyor 2, complete finishing of the modules 12 is carried out on the first level 32.
  • Further, we will consider the option of finishing the modules 12 that form the apartments (prefabricated module 6). However, it should be understood that other modules 12 (apartment halls (7), stair-lift units (8, 9), office premises, basements (10), etc.) are also prefabricated, but maybe with the use of other components, or excluding part of the components, depending on the type of module.
  • The load-bearing bodies of the first level 32 of the conveyor 2 transport with the modules 12, mainly continuously (or may have short stops). At the same time, for example, in the first zone (at the first stage) of the conveyor 2, all the necessary construction articles and components are supplied to the first level 32 from the second level 33, and inside the module 12 they do (both with the help of manual labor and with the help of robots), for example, pour the floor, install, for example, metal crosspieces 18 of the overlap (in the absence of a ceiling panel 19), carry out cladding work, cover the ceiling with drywall, prepare ventilation, insulate the walls and carry out other rough finishing. Prepare internal interior partitions, internal walls, and such partitions and walls have the possibility of transformation, i.e., changing their spatial location by performing special guides, fasteners, latches and connections in the module 12 (for example, in the base plate 14 and/ or in the walls) (not shown). In addition, in this zone, on the second level 33, they can, for example, cut dry wall to the required dimensions, form ventilation products, prepare insulation of the desired size, make material for plaster, etc. Also, in this zone, exterior finishing is carried out, the necessary materials and components are also supplied from the second level 33, and, for example, prepare facades, balconies, etc.
  • Then, after performing all the necessary preparatory work (rough finishing) at the first level 32, the corresponding module (6) is transferred to the second zone of the conveyor 2 (second stage), where all necessary materials and components are also supplied from the second level 33 to the first level 32 and, for example, all plumbing work is carried out on the first level 32 inside and outside the modules (6), all plumbing communications are laid, pipelines, wiring, mortgages, sewer pipelines are installed, risers or connectors with risers are installed outside the apartment module (6) (if the risers are installed in the module 7 of the apartment hall), etc. Access points are being prepared for servicing pipe connections or for replacing pipes. Plumbing communication 40 is installed outside the modules 6, including on the side of the base plate 14 in special cells 24.
  • Then the apartment module 6 (originally module 12) is transferred to the third zone (the third stage), where the necessary materials and components are also supplied from the second level 33, and, for example, all electrical work is carried out, cables are laid, electric shields, weak points, lighting, etc. are installed. Necessary cables are laid, for example, for fire safety, for the "smart home" system, video surveillance, etc. Places of access to service electricians are prepared, special hatches 37 are installed (adjacent to the module 7 of the apartment hall), niches 38 are prepared for terminal blocks, etc. Electrical wiring 39 is performed mainly in the intermodule space, i.e. outside the modules, including from the side of the base plate 14 in special cells 24 (as well as through the inter-storey floors of adjacent apartment modules 7).
  • Then the module 6 is transferred to the next zone on the first level 32 (the fourth stage), where the necessary materials and components are also supplied from the second level 33 and, for example, complete interior decoration is carried out, for example, wallpaper is pasted, walls are painted, tiles are laid, parquet or linoleum or parquet board is laid, etc.
  • Then the module 6 is transferred to the next zone (the fifth stage), where the necessary materials and components are also supplied from the second level 33 and, for example, sockets, switches, a smart home system, video cameras, etc. are installed. Also in this area, for example, built-in water filters, sinks, showers, bathtubs, etc. can be installed. That is, at this stage, all the necessary work related to electrical and plumbing communication is completed.
  • After that, the module 6 is transferred to the next zone (the sixth stage), where the necessary materials and components are also supplied from the second level 33 and, for example, the installation of built-in furniture in the appropriate specially prepared places is carried out.
  • At the same time, if the consumer of the prefabricated module 6 wants,
    for example, to change the spatial location of the internal walls, i.e., for example, to change the area of the rooms (or kitchen, or corridor, etc.), the installers change the spatial location of the internal walls, as well as engineering communications and/ or built-in furniture. Changing the spatial location of the internal walls with communications is carried out quickly by moving (transforming) the walls with communications and built-in furniture along special guides (niches in the floor and walls), as well as by using special fasteners, clamps, connections, etc. In addition, the consumer can make a change in the spatial location and after the completion of the building construction, when he settled in the apartment (either on his own or with the involvement of specialists). This transporting (transformation) of walls with communications and built-in furniture allows consumers to quickly change the space-planning solutions of their apartments (offices, etc.), depending on their needs, requires and wishes.
  • After all the finishing work is done, when the prefabricated module 6 is formed and ready to transport to the construction site, it is transported to the next zone, where electricians, plumbers and other persons conduct a control inspection of the prefabricated module 6, conduct crimping and testing, and make a conclusion about the readiness of the module 6.
  • Then the prefabricated module 6 is transferred to the next zone of the conveyor 2 (the last zone is the end of the second conveyor 2), where the prefabricated module 6 is packed in a protective material that prevents dust, moisture, dirt, etc. from entering the prefabricated module 6, as well as which eliminates any impact on the prefabricated module 6 that can damage it, and generally excludes access to the prefabricated module 6 by anyone. A thick coating or a special cover is used as a protective material.
  • In the same way, all prefabricated modules 6-10 are made, while in the case, for example, of the modules 8, 9 manufacture, forming a stair-lift unit, then on the second conveyor 2 (in the corresponding zone) inside such a module 7, lift shafts, staircases, etc. are prepared, railings, pipeline and/ or garbage disposal units, electrical communications (lighting, pipes and slats for electrical wiring, terminals, sockets, junction boxes, fuses and plugs, automatic fuses, switches, plug connections, distributors, etc.) are installed, walls are painted or tiled.
  • If, for example, a module 7 of an apartment hall is made, then life support systems, engineering boxes with hoods, air exchange shafts, fire valves, transit cabinets 41 with sewer risers, water supply, transit electrical cabinets 42, electrical shields, boxes with terminal blocks (mainly coincide with the niches 38 for terminal blocks of apartment modules 6), distributors, panels for meters together with meters (water, electricity, gas, etc.), form other engineering communications, etc. In the inter-panel space (floor and ceiling of the underlying module 7), all communications 39 and 40 are located, going away from the electrical system and from the risers. Such communications 39, 40 are located between the ribs 21 of plates 14 and 19, and they must enter each apartment through the bottom of the doorway 29 or next to the doorways 29. In such places, special niches 43 are made for servicing and connecting prefabricated modules 6 and 7 for engineering communications (separately for electrics and separately for plumbing), for example, hatches 44 with lower or upper wiring are placed. Painting the walls or laying tiles, preparing lighting, etc. are also performed.
  • Similarly, the prefabricated modules 10 are made, forming basements (lower modules). At the same time, all external networks enter and exit the lower modules 10 (for example, sewage and wastewater for heat ("return")). In addition, the lower (basement) modules 10 have perfect waterproofing on the outside. Some modules 10 have solid ribbed walls 16 (around the perimeter of the building), and some modules 10 may not have solid walls (internal modules 10 in the basement). Between the adjacent modules 10, passageways are organized along the entire building, there are separate entrances and exits to the basements. Such modules 10 should have floor slabs 19, to which engineering pipes can be fixed. In the basement modules 10, all engineering equipment is mounted on the conveyor 2 (individual heat points, water pumping stations, centralized water and heat meters, etc.), i.e., 99.9% finishing is also carried out.
  • All prefabricated modules 6-10 are fully factory-ready, with the corresponding prefabricated modules 6-10 having the following (but not limited to): glazed window and balcony door blocks; door blocks with architraves and door devices; built-in cabinets and mezzanines; mounted wiring of central heating, cold and hot water supply, sewerage networks with sanitary and technical devices; mounted hidden electrical wiring with fittings for connection; ventilation units with exhaust radiators; floors on balconies (loggias); barrier constructions on the balconies; fully prefabricated facade surface of the exterior walls; interior finishing that meets the requirements of the building project, etc.
  • Due to the use of the second conveyor 2, which has two levels 32 and 33, combined with storage facilities, time is saved for the manufacture of prefabricated modules 6-10, and labor productivity is significantly increased. In addition, due to the presence of separate zones (stages) wherein certain finishing works are carried out for prefabricated modules 6-10, it eliminates the need for workers of the relevant specialties (electricians, plumbers, finishers, etc.) to transport from one zone to another in order to carry out certain works. Each worker is located in his own zone and only the products, components and tools necessary for his work are supplied to this zone from the second level 32. As a result, the workers do not need to transport around the entire plant workshop, and the time for carrying out all types of finishing work in each zone on the first level 32 of the conveyor 2 is significantly reduced. Monitors 45 in each zone of the conveyor 2, demonstrating the sequence of certain works, also reduce the time for carrying out the corresponding works.
  • After the corresponding prefabricated modules 6-10 are fully formed and have a full 99% finish, and after they are packed, such prefabricated modules 6-10 are installed (from the second conveyor 2) on the platform of a special vehicle 3 for transporting prefabricated modules 6-10 (one prefabricated module 6-10 per vehicle 3) and transport the prefabricated modules 6-10 to the construction site. Transportation is carried out accompanied by special services and special equipment, mainly at night, as well as on pre-prepared and agreed routes that allow one to transport large-sized heavy cargo.
  • At the construction site, where the foundation 5 has already been prepared, the packed prefabricated modules 6-10 are installed in the appropriate place by means of a lifting device 4. In this case, the installation of prefabricated modules 6-10 is carried out on a floor-by-floor basis with the formation of a building by the method of floor-by-floor re-laying, i.e. a part of the prefabricated modules 6 (7) of even floors is installed relative to a part of the prefabricated modules 6 (7) of odd floors with an intersection in the plan of part of the load-bearing walls 16 (part of the prefabricated modules 6 is rotated 90° relative to a part of the lower prefabricated modules 6).
  • The building is constructed as follows. Basement (lower) prefabricated modules 10 are installed, unpacked, mounted and connected to each other. In this case, the connection is carried out without the use of welding due to the places 47, where threaded connections are used. Then, on the basement prefabricated modules 10, prefabricated apartment modules 6 of the first floor, prefabricated apartment modules 7, prefabricated modules of stair- lift units 8 and 9 are installed (by introducing projections 31 into recesses 46), workers unpack them and mount the prefabricated modules 6-9 and connect them to each other and to the prefabricated basement modules 10 (also without the use of welding due to the presence of places 47 for connecting adjacent modules using threaded connections). Due to the presence of specially prepared protrusions 31 and recesses 46 in prefabricated modules 6-9 (10), respectively, in the upper and lower parts, through which the overlying prefabricated modules 6-9 are connected to the underlying ones, high-precision installation of the prefabricated modules 6-10 and their reliable connection to each other is ensured. The places 47 for the threaded connections of the adjacent modules 6-10, as well as the use of threaded connections, also ensure a reliable and rigid connection of the prefabricated modules 6-10 with each other. Then the prefabricated apartment modules 6, pre-apartment modules 7 and modules 8 and 9 of the stair-lift units of the second floor are installed, while part of the prefabricated modules 6 (7) of the second floor is rotated by 90° relative to part of the prefabricated modules 6 (7) of the first floor. Then the prefabricated apartment modules 6, pre-apartment modules 7 and modules 8 and 9 of the stair-lift units of the third floor are installed, while part of the prefabricated modules 6 (7) of the third floor is also rotated 90° relative to part of the prefabricated modules 6 (7) of the second floor, and the position of the prefabricated modules 6 (7) of the third floor corresponds to the position of the prefabricated modules 6 (7) of the first floor. And so on, to construct a building of the desired number of storeys. Some prefabricated modules (8, 9) of even floors do not transport (do not rotate) relative to the prefabricated modules (8, 9) of odd floors and are installed relative to them in the same way. This refers, for example, to prefabricated modules 8, 9 of stair-lift units, where floor-by-floor re-laying is not allowed. This floor-by-floor layout ensures high rigidity of the entire building, its stability and durability. When connecting the prefabricated modules 6-10, a bolted connection is mainly used, while ensuring that the modules 6-10 are vertically and horizontally adjacent to each other without a gap. The size of the external joints between the modules is 14 mm (according to the previously conducted thermal engineering calculations (Mosstroy Research Institute), sizes less than this value are not allowed due to changes in the ambient temperature).
  • Thus, factory- prefabricated modules 6-10, as well as buildings constructed from such prefabricated modules 6-10, have the necessary durability, rigidity, stability and provide the load-bearing capacity of the building for the entire period of its operation. The maximum degree of factory readiness is ensured, it is possible to preserve the prefabricated modules 6-10 during storage, transportation and installation, as well as to preserve the exterior and interior finishes. The required operational qualities of buildings are insured: the necessary sanitary and hygienic conditions, sound insulation, thermal protection, fire safety. The prefabricated modules 6-10 are manufactured with high dimensional accuracy (±1 mm), ensuring equality of their heights at the extreme points, equality of diagonals, accuracy of compliance with the thickness of the faces and the configuration of the support parts, ensuring the correct transmission of loads. At the same time, the prefabricated modules (for example, 6, 8, 9) have a reduced weight, mainly due to absence of the monolithic slabs 19 floors, as a result of which the weight of the constructed building as a whole is reduced.
  • Due to absence of welded joints, presence of the prefabricated modules 6-10 special docking units (protrusions 31, recesses 46, places 47 of the connection of adjacent modules 6-10), the speed and accuracy of mounting and connecting modules 6-10 to each other significantly increases. Also due to this, the building is made with the possibility of dismantling and transporting (if it is required in exceptional cases) with the help of vehicles 3 prefabricated modules 6-10 to another construction site, where such a building is re-constructed with similar rigidity and stability.
  • The use of pallets 20 of the described size, the possibility of changing the dimensions of the formwork 11 formed on pallets 20 in all three coordinates, as well as the use of different sizes of sets of inserts 23, 28 and the hydraulic system 48 (hydraulic cylinders that drive the formwork 11) for the formwork 11 allows one to increase the area of the buildings constructed, to ensure the versatility of buildings for any space-planning solutions. The use of robotic conveyors 1 and 2, as well as the presence of the conveyor 2 separate zones wherein certain operations are carried out to form prefabricated modules 6-10, allows one to significantly increase the volume of daily manufacture of prefabricated modules 6-10 and increase productivity. In addition, due to the use of formwork 11 with constantly changing sizes and shapes, as well as due to the separation of zones for finishing prefabricated modules 6-10 on the conveyor 2, the time and labor costs for construction of buildings are significantly reduced, the labor intensity and cost of construction of buildings are reduced. 99.9% factory finish of the prefabricated modules 6-10 with the possibility of changing the space-planning solutions (including due to the possibility of rapid changes in the spatial position of the internal walls inside the room) allows one to increase the comfort of the constructed premises. High-precision manufacturing of the prefabricated modules 6-10 with specially prepared connection nodes (protrusions 31, recesses 46, places 47 connections) allows one to simplify installation of three-dimensional modules on the construction site without the use of welded joints and increase the accuracy of the placement of modules relative to each other. Floor-by-floor re-laying of prefabricated modules 6-10 during the construction of buildings, i.e., turning part of the prefabricated modules of even storeys relative to part of the prefabricated modules of odd storeys, mainly by 90° (or at a different angle), ensures high rigidity, durability and stability of buildings even in the absence of welded joints.
  • Due to all of the above mentioned, one of the main principles of the invention is that the architect manages the factory manufacture, and not vice versa. Module-apartments are large in size and have free layout. During conveyor manufacture, the workplace (the place of labor application) of the module, materials and components transfer to the performer of the work, and not vice versa, as in existing construction technologies.

Claims (11)

  1. A method for manufacturing a prefabricated three-dimensional module (6, 7, 8, 9, 10), the method comprising
    placing a pallet (20) on a first robotic conveyor (1), on which, with the help of industrial robots, a formwork system is formed,
    the formwork system including a first and a second formwork for the manufacture of a monolithic reinforced-concrete three-dimensional module (12), including a base plate (14), lateral pieces, namely pillars (15) and/ or walls (16), beams (17), and ceiling pieces, namely crosspieces (18) and/or ceiling panels (19),
    the method further comprising positioning, placing and fixing sides (52, 53) on the pallet (20) using magnets (51) to form the first formwork for the base plate (14) with the help of said industrial robots, such that longitudinal and transverse ribs (21) of the base plate (14) are formed,
    reinforcement (25) is laid, and in the places where the pillars (15) are to be located, reinforcement frames (26) are installed for formation of the pillars (15),
    the base plate (14) is formed by supplying concrete to the first formwork with the formation of longitudinal and transverse ribs (21) with recesses (24) between them, placed at the locations of the pillars (15) and directed along the pillars (15),
    the pallet (20) with the base plate (14) formed on it with reinforcement frames (26) for the formation of pillars (15) is supplied on the first robotic conveyor (1) to a vertical formwork installation post, where industrial robots form the second formwork (11) for the lateral pieces, beams (17), and ceiling pieces from longitudinal and transverse sides (27), as well as a set of inserts (28) fixed with magnets (51) on the longitudinal and transverse sides (27),
    the monolithic reinforced concrete three-dimensional module (12) is made by supplying concrete into the second formwork (11) with the formation of protrusions (31) on the beams (17), placed at the locations of the pillars (15) and directed along the pillars (15),
    the manufactured monolithic reinforced concrete three-dimensional module (12) is transferred to a second robotic conveyor (2), where, with the help of industrial robots, the prefabricated three-dimensional module (6, 7, 8, 9, 10) is manufactured by installing engineering communications, performing interior and exterior finishing, forming internal partitions and/ or installing built-in furniture.
  2. The method according to claim 1, wherein the formation of the formwork system for the manufacture of a monolithic reinforced concrete three-dimensional module is carried out with the possibility of changing its dimensions from 3 to 7.2 meters in width, from 8 to 21 meters in length and from 3 to 3.5 meters in height, in which the production of the monolithic reinforced concrete three-dimensional module is carried out, the width of which is from 3 to 7.2 meters, the length from 8 to 21 meters, the height from 3 to 3.5 meters.
  3. The method according to claim 1, wherein the lateral pieces of the monolithic reinforced concrete three-dimensional module are formed with recesses and through holes for connecting the prefabricated three-dimensional modules.
  4. The method according to claim 1, wherein the first robotic conveyor (1) is used to manufacture a monolithic reinforced concrete three-dimensional module having at least six pillars (15), the dimensions of which in the plan view are 180/500 mm.
  5. The method according to claim 1, wherein, before supplying concrete to the first formwork, fire insulation and sound insulation are installed in the first formwork, as well as engineering communications are laid.
  6. The method according to claim 1, wherein, after the formation of the base plate (14), its upper part is treated with a power trowel to form a smooth, flat surface.
  7. The method according to claim 6, in which, after processing the upper part of the base plate (14), it is covered with decking.
  8. The method according to claim 1, in which, in the manufacture of the monolithic reinforced concrete three-dimensional module, at least some of the pillars form loops in their upper part for lifting the module.
  9. A method for constructing buildings from prefabricated three-dimensional modules manufactured according to any of claims 1-8, consisting in the fact that on the construction site, by means of at least one lifting device, the prefabricated three-dimensional modules are installed in the appropriate place floor-by-floor, while basement prefabricated three-dimensional modules are installed on the foundation, on the basement prefabricated three-dimensional modules, prefabricated three-dimensional modules of the first floor are installed by introducing protrusions of the basement prefabricated three-dimensional modules located in the upper part at the locations of the pillars, in the recesses of the prefabricated three-dimensional modules of the first floor located in the lower part at the pillars, the prefabricated three-dimensional modules of the first floor are assembled and connected with each other by means of threaded connections passing via through holes in the pillars or the walls of adjacent prefabricated three-dimensional modules of the first floor, prefabricated three-dimensional modules of the first floor are installed on prefabricated three-dimensional modules of the second floor by introducing protrusions of prefabricated three-dimensional modules of the first floor, located in the upper part at the pillars, in the recesses of prefabricated three-dimensional modules of the second floor, located in the lower part at the pillars, and a portion of the corresponding prefabricated three-dimensional modules of the second floor is rotated relative to a portion of the corresponding prefabricated three-dimensional modules of the first floor by 90°, the prefabricated three-dimensional modules of the second floor are assembled and connected to each other by means of threaded connections passing via through holes in the pillars or walls of adjacent prefabricated three-dimensional modules of the second floor, prefabricated three-dimensional modules of the following floors are successively installed on the prefabricated three-dimensional modules of the second floor by introducing the protrusions of the prefabricated three-dimensional modules of each previous floor, located in the upper part at the pillars, into the recesses of the prefabricated three-dimensional modules of each next floor, located in the lower part at the pillars, the prefabricated three-dimensional modules of each floor are assembled and connected with each other using threaded connections, passing via through holes in the pillars or walls of adjacent prefabricated three-dimensional modules of the corresponding floor, and a portion of the corresponding prefabricated three-dimensional modules of each subsequent floor are rotated relative to a portion of the corresponding prefabricated three-dimensional modules of the previous floor by 90° and form a building so that a portion of the prefabricated three-dimensional modules of even-numbered floors is installed relative to a portion of the prefabricated three-dimensional modules of odd-numbered floors so that, in plan view, some of the walls intersect.
  10. The method according to claim 9, wherein a crawler-mounted heavy boom-type crane with a lifting capacity of up to 750 tons is used as at least one lifting device.
  11. The method according to claim 9, wherein the installation of prefabricated three-dimensional modules using at least one lifting device is carried out using loops on the pillars (15).
EP19888380.3A 2018-11-30 2019-02-08 Method for constructing buildings Active EP3889374B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
RU2018142384A RU2712845C1 (en) 2018-11-30 2018-11-30 Method of manufacturing large-sized finished three-dimensional module and method of building construction from large-size finished 3d modules
PCT/RU2019/000080 WO2020111966A1 (en) 2018-11-30 2019-02-08 Method for constructing buildings

Publications (3)

Publication Number Publication Date
EP3889374A1 EP3889374A1 (en) 2021-10-06
EP3889374A4 EP3889374A4 (en) 2022-08-31
EP3889374B1 true EP3889374B1 (en) 2023-10-18

Family

ID=69625337

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19888380.3A Active EP3889374B1 (en) 2018-11-30 2019-02-08 Method for constructing buildings

Country Status (7)

Country Link
EP (1) EP3889374B1 (en)
DK (1) DK3889374T3 (en)
ES (1) ES2969483T3 (en)
HU (1) HUE065298T2 (en)
PL (1) PL3889374T3 (en)
RU (1) RU2712845C1 (en)
WO (1) WO2020111966A1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2759467C1 (en) * 2021-04-28 2021-11-15 Публичное акционерное общество "Федеральная гидрогенерирующая компания - РусГидро" Method for automated installation of the power structure of a gravitational energy storage device and a set of devices for its implementation
EP4355678A1 (en) * 2021-06-17 2024-04-24 KONE Corporation Method of monitoring assembly of an elevator and apparatus
RU2761783C1 (en) * 2021-06-21 2021-12-13 Сергей Анатольевич Сибиряков Method for automated construction of structures
CN113550599B (en) * 2021-08-05 2022-10-11 中建八局第二建设有限公司 Hyperboloid sawtooth-shaped GRG construction method
CN117255260B (en) * 2023-11-20 2024-03-01 深圳市云图华祥科技有限公司 Intelligent monitoring system for construction site of building engineering
CN117988601B (en) * 2024-04-07 2024-07-02 成都中品建设工程有限公司 Assembled functional building and construction method thereof

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3884613A (en) * 1968-12-10 1975-05-20 Lely Cornelis V D Apparatus for forming and displacing a prefabricated building section
US3714304A (en) * 1969-12-29 1973-01-30 F Anderson Building construction
SU495208A1 (en) * 1971-10-01 1975-12-15 Проектно-Технологический Институт "Оргпромстрой" Conveyor line for the manufacture of bulk units
SU1689075A1 (en) * 1989-03-31 1991-11-07 Московский научно-исследовательский и проектный институт типового и экспериментального проектирования Production line to manufacture three-dimensional blocks
RU2026479C1 (en) * 1993-12-07 1995-01-09 Салават Ахатович Шакиров Multistory building
RU2076178C1 (en) 1994-12-09 1997-03-27 Валерий Иванович Костин Building from concrete box units
JP3236834B2 (en) * 1998-07-07 2001-12-10 普 山田 Basement structure, its manufacturing method, its transportation method and its construction method
JP5707418B2 (en) * 2010-11-24 2015-04-30 ▲勧▼ 渡辺 Concatenation method for container-type unit construction
DK2617911T3 (en) * 2012-01-23 2016-08-01 Vastint Hospitality B V Method and system for construction of a building
RU128219U1 (en) 2012-12-21 2013-05-20 Владимир Иванович Бондаренко MODULAR BUILDING FRAME
RU2616306C1 (en) * 2016-04-13 2017-04-14 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный архитектурно-строительный университет" (ФГБОУ ВПО "СПбГАСУ") Method for construction of multistore buildings of three-dimensional blocks

Also Published As

Publication number Publication date
RU2712845C1 (en) 2020-01-31
WO2020111966A1 (en) 2020-06-04
EP3889374A1 (en) 2021-10-06
EP3889374A4 (en) 2022-08-31
ES2969483T3 (en) 2024-05-20
HUE065298T2 (en) 2024-05-28
PL3889374T3 (en) 2024-04-02
DK3889374T3 (en) 2024-01-22

Similar Documents

Publication Publication Date Title
EP3889374B1 (en) Method for constructing buildings
EP1971727B1 (en) Construction of buildings
US10947720B2 (en) Block construction of prefabricated buildings
US20160040443A1 (en) Modular Building System
US20130305629A1 (en) Modular Building System
EP2175088B1 (en) Method of installation on site of a prefabricated semi-resistant module for construction
JP2009528464A (en) Prefabricated reinforced concrete single-person house and method for constructing the house
US12091872B2 (en) Hybrid building system, building and method
WO2008004896A2 (en) Building system
WO2018174825A1 (en) Pre-fabricated pre-finished volumetric construction of a building
US20220154448A1 (en) Centralized core and node system for construction projects
RU2766076C1 (en) Prefabricated building module and method of installation thereof
RU2715781C1 (en) Method for production of volume module
JPS6365785B2 (en)
RU2627436C1 (en) Large-panel building
BRPI1103773A2 (en) constructive process of modular units and modular units thus obtained
AU2011201797A1 (en) Prefabricated Room Assembly
WO2023222853A2 (en) Hybrid building system, building and method
JPH11200498A (en) Method for constructing multiple dwelling house and room unit for use therein
CN117813439A (en) Hybrid building system, building and method
WO2024103128A1 (en) Buiding method and panel
EA041217B1 (en) MODULAR BUILDING ASSEMBLY METHOD
RU1796748C (en) Multi-store building
WO2017035622A1 (en) Suspended floor construction method and corresponding components
IE84811B1 (en) Construction of buildings

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20210630

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
A4 Supplementary search report drawn up and despatched

Effective date: 20220802

RIC1 Information provided on ipc code assigned before grant

Ipc: B28B 5/00 20060101ALI20220727BHEP

Ipc: E04B 1/348 20060101ALI20220727BHEP

Ipc: E04H 1/00 20060101AFI20220727BHEP

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

RIC1 Information provided on ipc code assigned before grant

Ipc: E04H 1/04 20060101ALI20230424BHEP

Ipc: B28B 15/00 20060101ALI20230424BHEP

Ipc: B28B 7/22 20060101ALI20230424BHEP

Ipc: B28B 7/02 20060101ALI20230424BHEP

Ipc: B28B 5/02 20060101ALI20230424BHEP

Ipc: E04B 1/348 20060101ALI20230424BHEP

Ipc: B28B 5/00 20060101ALI20230424BHEP

Ipc: E04H 1/00 20060101AFI20230424BHEP

INTG Intention to grant announced

Effective date: 20230510

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602019039835

Country of ref document: DE

REG Reference to a national code

Ref country code: DK

Ref legal event code: T3

Effective date: 20240117

REG Reference to a national code

Ref country code: NL

Ref legal event code: FP

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: LU

Payment date: 20240220

Year of fee payment: 6

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240119

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240218

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20240220

Year of fee payment: 6

Ref country code: ES

Payment date: 20240304

Year of fee payment: 6

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20240301

Year of fee payment: 6

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240218

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240119

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240118

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240219

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: HU

Payment date: 20240325

Year of fee payment: 6

Ref country code: DE

Payment date: 20240228

Year of fee payment: 6

Ref country code: CZ

Payment date: 20240202

Year of fee payment: 6

Ref country code: GB

Payment date: 20240131

Year of fee payment: 6

REG Reference to a national code

Ref country code: ES

Ref legal event code: FG2A

Ref document number: 2969483

Country of ref document: ES

Kind code of ref document: T3

Effective date: 20240520

REG Reference to a national code

Ref country code: HU

Ref legal event code: AG4A

Ref document number: E065298

Country of ref document: HU

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240118

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: TR

Payment date: 20240131

Year of fee payment: 6

Ref country code: PL

Payment date: 20240131

Year of fee payment: 6

Ref country code: IT

Payment date: 20240222

Year of fee payment: 6

Ref country code: FR

Payment date: 20240129

Year of fee payment: 6

Ref country code: DK

Payment date: 20240131

Year of fee payment: 6

Ref country code: BE

Payment date: 20240226

Year of fee payment: 6

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602019039835

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231018

REG Reference to a national code

Ref country code: AT

Ref legal event code: UEP

Ref document number: 1622601

Country of ref document: AT

Kind code of ref document: T

Effective date: 20231018

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT