CN107169620A CN201710212902.5A CN201710212902A CN107169620A CN 107169620 A CN107169620 A CN 107169620A CN 201710212902 A CN201710212902 A CN 201710212902A CN 107169620 A CN107169620 A CN 107169620A
Authority
CN
China
Prior art keywords
model
flow
workflow
model version
superior
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710212902.5A
Other languages
Chinese (zh)
Inventor
杨启京
徐春雷
陈鹏
季学纯
钱玉妹
翟毅
畅广辉
尹寿垚
李�昊
季惠英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
State Grid Henan Electric Power Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Nanjing NARI Group Corp
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
State Grid Henan Electric Power Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Nanjing NARI Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, State Grid Henan Electric Power Co Ltd, Nari Technology Co Ltd, NARI Nanjing Control System Co Ltd, Nanjing NARI Group Corp filed Critical State Grid Corp of China SGCC
Priority to CN201710212902.5A priority Critical patent/CN107169620A/en
Publication of CN107169620A publication Critical patent/CN107169620A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of model version circulation method between power network the superior and the subordinate scheduling system based on workflow, comprise the following steps:Step S1, specifies the status information of each involved flow nodes of model version interaction between the superior and the subordinate's power network dispatching system and each flow nodes needed for model version circulation;Step S2, definition is described with E formatted files by each node status information in interaction flow and forms workflow template file, model version file circulates with workflow template file in each procedure links;Step S3, according to the workflow template file received, obtains the file of model version.The inventive method passes through the workflow template file based on E formatted files, it is ensured that model version circulate information between different system information flow it is general and efficient.

Description

Model version circulation method between power network the superior and the subordinate scheduling system based on workflow
Technical field
The present invention relates to model sharing technical field between power network dispatching system, and in particular to a kind of power network based on workflow Model version circulation method between the superior and the subordinate's scheduling system.
Background technology
Electric network model is that a kind of digitized description electricity grid network models of objective electric power grid structure are power system software The basis of analysis;Intelligent scheduling requires that complete, consistent, accurate, timely, reliable grid model data is supported.With alternating current-direct current The continuous expansion of interconnected power grid scale, objectively requires scheduling integration operations at different levels, and complete, consistent electric network model is to protect Demonstrate,prove the basic condition of multi-stage scheduling business integrative operation.Power network large-sized model is typically formed by the model splicing of multi-stage scheduling, existing There is model splicing to need more artificial operation and intervention, model splicing interval is longer between the superior and the subordinate's scheduling, partial model is safeguarded Exchange not in time, model can not reflect the quick change of electric network composition in time.
At present, intelligent grid Dispatching Control System (referred to as " D5000 " system) have application to national grid it is provincial and more than All regulation and control center and multiple regional regulation and control centers, to realize that the intelligent dispatch of power network provides good support, are achieved Significant economic and social benefit.But as alternating current-direct current interconnected power grid scale constantly expands continuous with the construction of big operation architecture In-depth, the power dispatch system operation and management of power network is faced with more, more complicated challenge, to the electricity as power network safety operation basis Pessimistic concurrency control and figure propose higher requirement.The accuracy and convenience of scheduling system artwork maintenance need to be further lifted, is carried Efficiency, security and the automatization level of model splicing between rising tune degree system.
Model version is carried out in the circulation of control centre of the superior and the subordinate also by the way of manual intervention at this stage, model from Control centre of subordinate is distributed to behind higher level control centre, it is necessary to which manual notifications higher level dispatches, and higher level is dispatched after the completion of split-join model, It is also required to manually inform that subordinate dispatches.Lack the information that means obtain whole splicing flow state between the superior and the subordinate's scheduling, lack spelling Connect the closed-loop control of flow.
With the construction of network system, power network characteristic is increasingly complicated, it is more next that the related application of system is dispatched to intelligent grid More, the pressure of the model maintenance thus brought to control centre is also increasing, if model maintenance is improper, it is possible to power network Safe operation cause significant impact.Therefore it is urgent that offer means must be provided, the closed loop management of on-time model splicing is realized, is improved In the automatization level of splicing, it is ensured that the safe and stable operation of dispatch automated system.
The content of the invention
It is an object of the invention to overcome deficiency of the prior art, there is provided a kind of power network the superior and the subordinate based on workflow Model version circulation method between scheduling system, model version circulation needs are more artificial between solving traditional the superior and the subordinate's scheduling system Intervene, circulation information is opaque, lack automation means, it is impossible to realize the closed loop management problem of splicing flow.
In order to solve the above technical problems, the invention provides mould between a kind of power network the superior and the subordinate scheduling system based on workflow Stencilling this circulation method, it is characterized in that, comprise the following steps:
Step S1, specifies each involved flow nodes of model version interaction and mould between the superior and the subordinate's power network dispatching system The status information of each flow nodes needed for this circulation of stencilling;
Step S2, is described definition with E formatted files by each node status information in interaction flow and forms workflow mould Plate file, model version associated documents circulate with workflow template file in each procedure links;
Step S3, the information according to described in workflow template file obtains the information of model version associated documents.
Further, flow includes model issue, model examination & verification, model splicing, the reception of point table and online, result verification inspection Look into, model retracts and result feedback.
Further, the status information of each flow nodes includes mark, process name, node type name, safeguards people Member, sponsor unit, recruiting unit, node state, safeguard information, model version name, node time, types of models, annex name and Plant stand;Wherein node state specific object value is represented successfully including 1 and 0,1, and 0 represents failure;.
Further, workflow template file with<MODEL_MERGE_FLOW>Beginning, the row of@symbols beginning is to define Each status information of process recording, the row of " // " beginning is to represent Chinese annotation, and the row of # symbols beginning is to describe flow The specific object of record, finally with</MODEL_MERGE_FLOW>Ending.
Further, the entitled process name .wf of workflow template file, process name name form be:Flow initiated area name _ Markers _ serial number.
Further, when being circulated between flow nodes, if this flow operations success, this flow will form new workflow Template file and model version associated documents are sent to downstream node, if this flow operations fails, and this flow will be formed Comprising node state a upper flow nodes are back to for 0 workflow template file.
Further, model version associated documents include:* .CIME is model file, and * .g are graphic files, and * .log are Journal file, * .error are error message files.
Compared with prior art, the beneficial effect that is reached of the present invention is:By defining between the superior and the subordinate's power network dispatching system Each involved flow nodes of model version interaction specify that the specific letter of each flow nodes needed for model version circulation Breath, passes through the workflow template file based on E formatted files, it is ensured that model version circulation information information flow between different system What is turned is general and efficient.
Brief description of the drawings
Fig. 1 is the involved flow of model version interaction between the superior and the subordinate's power network dispatching system in the prior art.
Embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following examples are only used for clearly illustrating the present invention Technical scheme, and can not be limited the scope of the invention with this.
Model version circulation method between power network the superior and the subordinate scheduling system based on workflow of the present invention, including following step Suddenly:
Step S1, specifies each involved flow nodes of model version interaction and mould between the superior and the subordinate's power network dispatching system The status information of each flow nodes needed for this circulation of stencilling.
Longitudinal maintenance process of model version is divided between power network dispatching system:Model issue, model examination & verification, model splicing, Point table is received and online, result verification inspection, model retract, and result feedback totally 7 nodes, referring specifically to Fig. 1.Flow section Point serial number be respectively successively:1,2,3,4,5,6,7.
Information involved during each flow interaction in the prior art is introduced separately below:
Model is issued:Subordinate's regulation and control center carries out model issue, and detailed process is subordinate's scheduled maintenance personnel selection model File, graphic file safeguards that information etc. is sent to higher level control centre by mail service.
Model is audited:Higher level's regulation and control center is received after model file, and higher level's scheduled maintenance personnel select to need by interface The model and figure to be audited, fills in auditing result information.
Model splicing:Model splicing, safeguards newly-increased picture, and lower loading amount surveys concordance list, fills in splicing result information.
Point table is received and lower dress:Receive the measurement concordance list of higher level (or other) scheduled feedback and be put in storage.
Result verification is checked:Check data correctness, state estimation convergence situation.If the result mistake, enters Model rollback flow, if the result is correct, into result process of feedback.
Model retracts:If result inspection result is mistake, the state for returning to model before model splicing is needed.Pass through Splice the state that a correct model version can retract to this splicing.
As a result feed back:Higher level, which regulates and controls center, will verify that result correctly or incorrectly is sent to subordinate's regulation and control center, flow knot Beam.
The status information of each flow nodes needed for model version circulation includes:Mark, process name, node type name Title, attendant, sponsor unit, recruiting unit, node state, safeguard information, model version name, node time, types of models, Annex name and plant stand.There is the detailed description to each field definition content in step below.
Step S2, is described definition with E formatted files by each node status information in interaction flow and forms workflow mould Plate file, model version associated documents (such as model file, graphic file, journal file etc.) exist with workflow template file Each procedure links circulation.
Between each flow nodes during circulation model version file, by each node status information E forms in interaction flow File be described definition formed between workflow template file, the superior and the subordinate can efficient Share Model circulation information, it is convenient not The high efficiency interactive of procedure information between homologous ray.While the autgmentability based on E formatted files, in the flow defined in E formatted files Nodal information can carry out nodal information extension according to demand.
Workflow template file defined in the present embodiment is as follows:
1) the workflow template file name defined based on E formatted files
Workflow template file name is process name .wf, and flow name format is:Flow initiated area name _ markers (days Day) _ serial number.
Example:Jiangsu _ 20170104_001.wf, is represented by Jiangsu start flow, the initiation time is on January 4th, 2017, Order is the 001st flow.
2) the workflow template file format defined based on E formatted files
The specific form of workflow template file is as follows:
<MODEL_MERGE_FLOW>
@ID NAME TYPE_NAME WORKER SEND_UNIT RECV_UNIT NODE_STATUS COMMENT VERSION_NAME NODE_DATE MODEL_TYPE ENCLOSURE SUBSTAION
Recruiting unit of // mark process name node type name attendant sponsor unit node state safeguards information mould Stencilling real name node time types of models annex name plant stand name
#
</MODEL_MERGE_FLOW>
Workflow template file with<MODEL_MERGE_FLOW>Beginning, with</MODEL_MERGE_FLOW>Ending ,@symbols Number beginning row be used to definitim flow record each attribute, " // " beginning row to represent Chinese annotation.The beginning of # symbols The specific object gone to describe process recording.In one wf file, the information of a flow nodes is defined.
Each field attribute is described in detail to more than below:
ID, the unique identification of process recording, the database purchase for process recording is retrieved;
NAME, (process name form is process name:Flow initiated area name _ markers (date) _ serial number);
TYPE_NAME, node type name, particular content is defined according to model version interaction flow between power network dispatching system Flow nodes name, be model issue in the present embodiment, model examination & verification, model splicing, point table are received and online, result verification Check, model retracts, result feeds back one of seven node type names.
WORKER, flow operations personal information;
SEND_UNIT, flow nodes sponsor unit;
RECV_UNIT, flow nodes recruiting unit;
NODE_STATUS, node state, specific object value include 1 and 0, wherein 1, successfully, 0, failure;
COMMENT, Operation and Maintenance information, for safeguarding information to flow operations personnel record's associative operation;
VERSION_NAME, the related model version title of flow;
NODE_DATE, the time of node maintenance operation;
MODEL_TYPE, the type of model file, 1, single station model, 0, full model;
ENCLOSURE, the file name information of model version associated documents (can also referred to as " annex ");Definition side Method:* .CIME endings is model file, and * .g endings are graphic files, and * .log endings are journal file, * .error knots Tail is error message file;
SUBSTAION, if model file type is single station model, fills in specific plant stand title herein;
The workflow template file example of model issue is provided in the present embodiment:
<MODEL_MERGE_FLOW>
@ID NAME TYPE_NAME WORKER SEND_UNIT RECV_UNIT NODE_STATUS COMMENT VERSION_NAME NODE_DATE MODEL_TYPE ENCLOSURE SUBSTATION
Recruiting unit of // mark process name node type name attendant sponsor unit node state safeguards information mould Stencilling real name node time types of models annex name plant stand
Adjust Mianyang 1 in # Mianyang _ 20160914_153301_6 Mianyang _ 20160914_153301 models issue Zhang Yuan Sichuan Province Model issue splicing uses Sichuan _ 0 Mianyang of 20160914_03320160914_154445 _ 20160914_001.CIME NULL
</MODEL_MERGE_FLOW>
Step S3, the information according to described in workflow template file obtains the information of model version associated documents.
Flow nodes recipient is received after workflow template file, according to the fileinfo of ENCLOSURE field definitions, Obtain the information of corresponding model version associated documents.As obtained in above example:This file is by model issue flow hair Rise, the entitled Mianyang _ 20160914_153301 of flow, model version name is Sichuan _ 20160914_033, model file name is continuous Sun _ 20160914_001.CIME etc..
The detailed process that the inventive method is applied between power network the superior and the subordinate scheduling system, issues flow with model and is examined to model Exemplified by being circulated between core flow, model issue flow generates corresponding workflow template file, send workflow template file and Model version associated documents are to model auditing flow, and model auditing flow obtains model version associated documents and workflow template text Part, workflow template file interior joint state now is 1, (can regard workflow template file warehousing as model version text The circulation record of part), the related nodal information of parsing workflow template file acquisition, model auditing flow is according to set flow Content is audited to model version associated documents;If auditing successfully, model auditing flow will form new workflow template File and model version associated documents are sent to model splicing flow, if examination & verification failure, model auditing flow will be formed newly Workflow template file is back to model issue flow, and this new workflow template file interior joint state NODE_STATUS will For 0, the failure of this flow operations is represented, model issue flow, which is received, obtains the mistake of model auditing flow after this workflow template file Lose, subordinate's regulation and control center then re-starts model issue.
Each node letter in model version interaction flow between workflow template document definition power network dispatching system in the present invention Breath, model version file needs to follow workflow template file to be circulated.By respectively being saved defined in workflow template file Point circulation information, realizes that the closed loop management and model file of whole splicing flow, by automatic flow in setting process, are reduced The maintenance workload manually just circulated to model, so as to improve model circulation efficiency.For example avoid artificial transmission's model version This, and needs the situation of phone or mail notification other side, it is to avoid model version mistake, and the model caused retracts not in time Situation.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, some improvement and modification can also be made, these improvement and modification Also it should be regarded as protection scope of the present invention.

Claims (7)

1. model version circulation method between power network the superior and the subordinate scheduling system based on workflow, it is characterized in that, comprise the following steps:
Step S1, model version interacts involved each flow nodes and model version between specifying the superior and the subordinate's power network dispatching system The status information of each flow nodes needed for this circulation;
Step S2, definition is described with E formatted files by each node status information in interaction flow and forms workflow template text Part, model version associated documents circulate with workflow template file in each procedure links;
Step S3, the information according to described in workflow template file obtains the information of model version associated documents.
2. model version circulation method between power network the superior and the subordinate scheduling system according to claim 1 based on workflow, its It is characterized in that flow includes model issue, model examination & verification, model splicing, the reception of point table and online, result verification inspection, model and returned Move back and result feedback.
3. model version circulation method between power network the superior and the subordinate scheduling system according to claim 1 based on workflow, its It is characterized in that the status information of each flow nodes includes mark, process name, node type name, attendant, initiation list Position, recruiting unit, node state, safeguard information, model version name, node time, types of models, annex name and plant stand;Wherein Node state specific object value is represented successfully including 1 and 0,1, and 0 represents failure;.
4. model version circulation method between power network the superior and the subordinate scheduling system according to claim 3 based on workflow, its Be characterized in, workflow template file with<MODEL_MERGE_FLOW>Beginning, the row of@symbols beginning is to definitim flow record Each status information, the row of " // " beginning is to represent Chinese annotation, and the row of # symbols beginning is to describe the specific of process recording Attribute, finally with</MODEL_MERGE_FLOW>Ending.
5. model version circulation method between power network the superior and the subordinate scheduling system according to claim 1 based on workflow, its It is characterized in, workflow template file entitled process name .wf that process name name form is:Flow initiated area name _ markers _ order Number.
6. model version circulation method between power network the superior and the subordinate scheduling system according to claim 4 based on workflow, its Be characterized in, when being circulated between flow nodes, if the success of this flow operations, this flow will be formed new workflow template file and Model version associated documents are sent to downstream node, if this flow operations fails, and this flow will form and include node shape State is back to a flow nodes for 0 workflow template file.
7. model version circulation method between power network the superior and the subordinate scheduling system according to claim 1 based on workflow, its It is characterized in that model version associated documents include:* .CIME is model file, and * .g are graphic files, and * .log are journal file, * .error it is error message file.
CN201710212902.5A 2017-04-01 2017-04-01 Model version circulation method between power network the superior and the subordinate scheduling system based on workflow Pending CN107169620A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710212902.5A CN107169620A (en) 2017-04-01 2017-04-01 Model version circulation method between power network the superior and the subordinate scheduling system based on workflow

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710212902.5A CN107169620A (en) 2017-04-01 2017-04-01 Model version circulation method between power network the superior and the subordinate scheduling system based on workflow

Publications (1)

Publication Number Publication Date
CN107169620A true CN107169620A (en) 2017-09-15

Family

ID=59849677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710212902.5A Pending CN107169620A (en) 2017-04-01 2017-04-01 Model version circulation method between power network the superior and the subordinate scheduling system based on workflow

Country Status (1)

Country Link
CN (1) CN107169620A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110717739A (en) * 2019-10-15 2020-01-21 深圳前海微众银行股份有限公司 Workflow issuing method, device, equipment and computer readable storage medium
CN112488485A (en) * 2020-11-25 2021-03-12 华南中外运供应链管理有限公司 Business process management system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101699454A (en) * 2009-11-02 2010-04-28 国电南瑞科技股份有限公司 Method for exchanging and merging electric network models between control center of electric power system and substation
KR101557261B1 (en) * 2015-03-31 2015-10-02 ㈜지엔피시스템 An Auto-Generating System of Text-Based Operational Sequence Diagram for Computerized Procedure System Built in the Training Simulator of Power Plant
CN105046408A (en) * 2015-06-25 2015-11-11 国网山东省电力公司 Configurable workflow realization method and system
CN105678447A (en) * 2015-12-31 2016-06-15 中国南方电网有限责任公司 CIM model verification servitization method between power grid upper-level and lower-level scheduling
CN105719078A (en) * 2016-01-20 2016-06-29 广东电网有限责任公司电力调度控制中心 Holographic flow management method based on business flow butt joint and state monitoring

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101699454A (en) * 2009-11-02 2010-04-28 国电南瑞科技股份有限公司 Method for exchanging and merging electric network models between control center of electric power system and substation
KR101557261B1 (en) * 2015-03-31 2015-10-02 ㈜지엔피시스템 An Auto-Generating System of Text-Based Operational Sequence Diagram for Computerized Procedure System Built in the Training Simulator of Power Plant
CN105046408A (en) * 2015-06-25 2015-11-11 国网山东省电力公司 Configurable workflow realization method and system
CN105678447A (en) * 2015-12-31 2016-06-15 中国南方电网有限责任公司 CIM model verification servitization method between power grid upper-level and lower-level scheduling
CN105719078A (en) * 2016-01-20 2016-06-29 广东电网有限责任公司电力调度控制中心 Holographic flow management method based on business flow butt joint and state monitoring

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宁剑 等: "外网模型不全下的网络分析优化方案研究与应用", 《电力科学与工程》 *
王宁 等: "一体化配电网调控信息管理系统研究", 《中国科技信息》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110717739A (en) * 2019-10-15 2020-01-21 深圳前海微众银行股份有限公司 Workflow issuing method, device, equipment and computer readable storage medium
CN110717739B (en) * 2019-10-15 2024-03-22 深圳前海微众银行股份有限公司 Workflow publishing method, device, equipment and computer readable storage medium
CN112488485A (en) * 2020-11-25 2021-03-12 华南中外运供应链管理有限公司 Business process management system

Similar Documents

Publication Publication Date Title
CN109492876A (en) A kind of assembled architecture production and construction management module information system
CN107862450A (en) Performance appraisal system and method
TW201714122A (en) Production scheduling method and automatically scheduling system
CN113258669B (en) Networked intelligent scheduling method and terminal based on distribution network maintenance
CN108736465A (en) A kind of future-state electric network model construction method and device
CN110349049B (en) Automatic work permission system and method for distribution network overhaul
CN109271602A (en) Deep learning model dissemination method and device
CN102709894A (en) On-line checking method and system for relay protection setting value
CN101364284A (en) Production management system for electrical power system
CN101976240A (en) Form number generating method and system
CN103065217A (en) Digital model splicing method of electric power setting calculating system
CN108228726A (en) The increment unusual fluctuation content acquisition method and storage medium of power distribution network red and black figure
CN110555609A (en) Hydropower station field standardized operation management and control system and method
CN109615088A (en) A kind of processing operation/maintenance work orders based on power information acquisition label
CN107169620A (en) Model version circulation method between power network the superior and the subordinate scheduling system based on workflow
CN107169180A (en) A kind of power grid regulation model center system of two-stage deployment
CN110826926A (en) Intelligent manufacturing execution system for surface assembly production line
CN104915523B (en) A kind of regulation full-service unified modeling method based on time series
CN106649684B (en) A kind of electric system figure multi version dynamic memory and dissemination method
CN109377412A (en) A kind of intensive artwork maintenance system of auxiliary tone and its maintaining method
CN112288394B (en) Controller scheduling test verification system
CN109167354B (en) Power grid expected fault parallel analysis and calculation method based on file exchange
CN107679736A (en) Definite value check method based on Mobile solution
CN113256074A (en) Automatic process operation system and method for electric robot
CN109102255B (en) Full-process cooperative management method for electric energy transaction and defect

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915