CN107091095A - Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield - Google Patents

Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield Download PDF

Info

Publication number
CN107091095A
CN107091095A CN201710464607.9A CN201710464607A CN107091095A CN 107091095 A CN107091095 A CN 107091095A CN 201710464607 A CN201710464607 A CN 201710464607A CN 107091095 A CN107091095 A CN 107091095A
Authority
CN
China
Prior art keywords
tunnel
mjs
construction
engineering methods
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710464607.9A
Other languages
Chinese (zh)
Inventor
钟志全
郑邦友
陈仁朋
吴熠文
刘湛
孙和美
彭继勇
田涌泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
China Construction Tunnel Construction Co Ltd
Original Assignee
Hunan University
China Construction Tunnel Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University, China Construction Tunnel Construction Co Ltd filed Critical Hunan University
Priority to CN201710464607.9A priority Critical patent/CN107091095A/en
Publication of CN107091095A publication Critical patent/CN107091095A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D8/00Shafts not provided for in groups E21D1/00 - E21D7/00
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Abstract

The invention provides existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield in a kind of urban subway tunnel technical field of construction.The main construction procedure of this kind of reinforcement system has:(a) operation tunnel section of jurisdiction security status is investigated, monitoring system layout in (b) tunnel;(c) construction shaft;(d) MJS leveling pegs strengthening construction;(e) consolidation effect is detected;(f) vertical shaft is filled.This kind of method reinforces proposed tunnel and water-rich sand layer between operation tunnel by applying MJS leveling pegs in vertical shaft, and detected after the completion of construction, ensure consolidation effect, so as to reduce the influence in proposed tunneling shield tunneling process to top operation tunnel, tunneling shield is worn under tunneling, everything goes well with your work is carried out.

Description

Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield
Technical field
The present invention relates to Construction of City Tunnel technical field, existing tunnel MJS works are more particularly to worn under water-rich sand layer shield Method stake reinforcement system and its construction method.
Background technology
In recent years, as Chinese Urbanization level is improved constantly, urban track traffic demand is increasingly increased, city rail Construction technology obtains fast development.In existing track construction technology, usually used shield machine progress tunnel piercing, but city Track circuit plans the situation for inevitably wearing existing tunnel down, if construction wrong, will lead to top and has runed tunnel Road additional stress and relative settlement.In existing construction technology, generally use surface grout injection to reinforce and dug with reducing proposed tunneling shield Enter influence of the construction to existing operation tunnel.
, may be due to rich water if continuing to use above-mentioned construction method when the soil body is water-rich sand layer between cross tunnel Layer of sand void ratio is big, and slurries gelling time is long, and diffusion velocity is fast, and range of scatter is big, causes grouting in soil mass not full, it is impossible to effectively Water stopping function is realized, soil strength can not be also improved, when bottom tunneling shield tunneling construction, the soil body easily occurs sedimentation and become Shape, shows as operation tunnel relative settlement and additional stress increases, the problems such as section of jurisdiction is damaged serious, meanwhile, surface grout injection adds Gu construction method construction intensity is big, and routinely tunneling boring reinforcing mode is easily caused compared with large-engineering waste.
The content of the invention
It is an object of the invention to:Tunneling shield tunneling construction is carried out in water-rich sand layer, is existed above construction tunnel Operation tunnel, when being reinforced using surface grout injection, because water-rich sand layer void ratio is big, grouting quality is poor, it is impossible to effective sealing with Soil body own wt is supported, causing top, operation tunnel differential deformation and additional stress are excessive, section of jurisdiction is impaired serious, and ground Grouting and reinforcing construction intensity is big, and there is provided wear existing tunnel MJS engineering methods under a kind of water-rich sand layer shield during the problems such as engineering wastes many Stake reinforcement system and its construction method, this method are carried out by applying the horizontal pile bodies of MJS in vertical shaft the soil body cross tunnel Reinforce, and detected after the completion of construction, it is ensured that consolidation effect, it is to avoid runed tunneling shield tunneling construction process middle and upper part Tunnel settlement after construction is with deforming the problems such as excessive and section of jurisdiction is damaged serious.
In order to realize foregoing invention purpose, the invention provides following technical scheme:
The construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield, is comprised the following steps:
A, the investigation of operation tunnel section of jurisdiction security status;
Monitoring system layout in b, tunnel;
C, construction shaft;
D, MJS leveling peg strengthening construction;
E, detection consolidation effect;
F, vertical shaft landfill.
In above-mentioned construction procedure, by the way that operation tactics section of jurisdiction security status is investigated to top, its tunnel lining is verified Existing deformation and existing crack situation are built, foundation is provided on top operation tunnel influence for subsequent analysis MJS engineering methods pile driving construction, And pass through potential safety hazard during crack repairing elimination part MJS engineering method pile driving constructions.Wherein described deformation investigation is mainly tunnel lining Build circumferential deformation and the change of arch axis shape in tunnel caused by linear deformation and section of jurisdiction form;The investigation of cracks mainly includes to ring Crack etc. detects at seam, longitudinal joint, section of jurisdiction crack and injected hole, bolt hole.
When taking above-mentioned construction procedure, monitoring system layout is tunnel internal strain-ga(u)ge unit, slit gauge and settlement monitoring in tunnel The arrangement of system.Wherein, the strain is calculated as hoop strain meter, and crack is calculated as circumferential weld slit gauge and longitudinal joint slit gauge.By Top arrangement settlement monitoring system, hoop strain meter and ring, longitudinal joint slit gauge in operation tunnel, can in real time monitor and find out MJS engineering method pile driving construction processes are to the affecting laws of top operation tunnel, so that distinguish top operation tunnel deformation present situation, and Guiding construction.
In above-mentioned construction procedure, before construction MJS leveling pegs, on plan-position, apart from top on proposed tunnel axis Empty size 8m × 6m, long side direction and proposed tunnel axis direction in construction shaft at operation tunnel side 5m positions, vertical shaft Vertically;Horizontal support and bottom plate are provided with vertical shaft, bottom plate depth is more than MJS leveling peg reinforcement depths.
Soil stabilization zone cross-sectional is domed between cross tunnel, reinforce section length be from vertical shaft to distal side operation tunnel outside 3m, thickness is essentially soil body thickness between cross tunnel;MJS divergences, stake length direction is proposed tunnel axis direction;Every MJS are lower semi-circular, stake footpath 2m;For make slurries progressively fill extruding cross tunnel between the soil body, MJS pile driving constructions order for a left side Downside pile body (lower right side pile body) --- middle and lower part pile body --- lower right side pile body (lower left side pile body) --- remaining pile body interval Construction.
Above-mentioned form of construction work is taken to when the soil body carries out consolidation process between proposed tunnel and top operation tunnel, MJS Body uses neat slurry, and its ratio of mud is 1:1, maximum spray pressure is 40MPa.
In step d, MJS leveling pegs work progress can be decomposed into following steps in detail:
D1, control point arranged in construction area using total powerstation, pass through control point and carry out stake position setting-out;
D2, drilling rod veer away, i.e., drilling rod level veers away to design attitude drawing in hole, the difficulty if drilling rod veers away, opening cuts hole Water progress is normally cut hole drill and entered;
D3, to stacks and drill bit, during docking, conscientiously check sealing ring situation, see whether lack or damage, pressure is whether in ground Display is normal;
D4, repeat c2 and c3 steps, until drill bit, drilling rod in place;
D5, drill bit are reached behind precalculated position, set each technological parameter, including swing angle, pulling speed, winding number etc., and open Begin to improve;
D6, positioning injection, first open suck-back current and suck-back air, when confirming that plasma discharge is normal, open spoil disposal valve, open high pressure Cement pump and primary air air compressor machine.Sprayed downwards with water first and set 50cm, pressure is 10MPa, water is then switched to cement mortar, bored Bar veers away again starts injection improvement downwards afterwards in place;
D7, open water under high pressure dredge pump when, pressure can not be too high, should progressively be pressurized, until reaching specified pressure, i.e. 40MPa, After reaching specified pressure and confirming that pressure is normal in ground, it can just start back to pull out;
Pressure in ground is monitored closely when d8, construction, when pressure is abnormal, it is necessary to adjust pulp-expelling valve size, control ground internal pressure in time Power is within safe range;
The stake sealing of hole construction of d9, MJS horizontal reinforcing;
D10, when return pull out a drilling rod after, drilling rod is dismantled;
D11, repetition above step, until construction terminates.
When taking the aforesaid way horizontal pile driving construction of carry out, during horizontal drilling construction anti-spouting device should be installed first, Slurries are gushed from aperture and oozed out during preventing whitewashing, cause expanded diameter small, slurries are not full, and reinforcing body infiltration coefficient is big, The problems such as low intensity.
In above-mentioned construction procedure, MJS engineering method pile driving constructions employ the antipriming pipe of uniqueness and device is caused in front end, described porous Pipe by discharge pipeline, water under high pressure mud tube, primary air pipe, suck-back air hose, suck-back water pipe, mud valve sensor control lines road pipe, Cut the composition such as hole sparge pipe, antipriming pipe link bolt hole, spare duct;Cause that pressure sensing is distributed with device in the front end Device, mud discharging mouth, mouth spray etc..
After the completion of the horizontal pile driving constructions of MJS, 10 coring points must be chosen to the stabilization zone soil body and carry out vertical core pulling detection, detection Content includes pile effective pile diameter, core sample uniaxial compressive strength, pile body overlap joint thickness, pile horizontal gradient error etc..MJS leveling pegs Stabilization zone should meet pile effective pile diameter not less than pile body diameter, i.e., not less than 2m;Core sample uniaxial compressive strength is not less than 1.0MPa;Pile body overlap joint thickness is not less than 0.4m, and lap body should be continuous;Pile horizontal gradient error is not more than 1/100.Check and close After lattice, vertical shaft is filled.
Brief description of the drawings
Fig. 1 is the construction method flow chart that existing tunnel MJS engineering methods reinforcement system is worn under water-rich sand layer shield of the present invention.
Fig. 2 is MJS engineering method pile driving construction floor map.
Fig. 3 is MJS engineering method pile driving construction vertical section schematic diagrams.
Fig. 4 is MJS engineering method pile driving construction schematic cross sections.
Fig. 5 is MJS engineering method pile driving construction flow charts.
Marked in figure:1-top operation tunnel;The proposed tunnel in 2-bottom;3-vertical shaft;4-MJS stabilization zones;5-vertical shaft Connect wall;6-MJS;7-vertical shaft horizontal support;8-shaft floor.
Embodiment
With reference to test example and embodiment, the present invention is further elaborated.But it should not be construed as this The scope for inventing above-mentioned theme is only limitted to following embodiment, all to belong to the present invention based on the technology that present invention is realized Category.
The present embodiment is used for a kind of construction that existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield Close.
As shown in figure 1, existing tunnel MJS engineering methods stake reinforcement system and its construction method are worn under water-rich sand layer shield, including Following steps:
A, the investigation of operation tunnel section of jurisdiction security status;
Monitoring system layout in b, tunnel;
C, construction shaft;
D, MJS leveling peg strengthening construction;
E, detection consolidation effect;
F, vertical shaft landfill;
In above-mentioned construction procedure, by the way that row operation tunnel section of jurisdiction security status is investigated to top, its tunnel-liner is verified Existing deformation and existing crack situation, for analyze follow-up MJS engineering methods pile driving construction to top operation tunnel affecting laws provide according to According to, and pass through potential safety hazard during crack repairing elimination part MJS engineering methods stake.(MJS engineering methods, MJS engineering methods (Mixed Jet System) it is also known as comprehensive high-pressure injection engineering method).
When taking above-mentioned construction procedure, monitoring system layout is top operation tunnel internal strain-ga(u)ge unit, slit gauge and sedimentation prison Survey system is arranged.The strain is calculated as hoop strain meter, and slit gauge is mainly circumferential weld slit gauge and longitudinal joint slit gauge.By upper Portion arrangement settlement monitoring system, hoop strain meter and ring, longitudinal joint slit gauge in operation tunnel, can in real time monitor and find out MJS To the affecting laws of top operation tunnel during engineering method pile driving construction, so that distinguish that whether safe operation tunnel is on top, and According to real-time monitoring feedback information guiding construction, construction parameter is adjusted in time, reduces the influence to top operation tunnel.
As shown in Fig. 2 before MJS leveling peg consolidation process is carried out the soil body cross tunnel, for convenience of constructing, from plane Position is seen, must be set on the proposed tunnel axis in bottom at top operation tunnel side 5m positions in vertical shaft, vertical shaft Empty 8m × 6m, long side direction is vertical with proposed tunnel axis direction.
As shown in Fig. 2 MJS divergences, stake length direction is that dotted portion is represented in proposed tunnel axis direction, figure MJS leveling peg reinforcing scopes;Between cross tunnel soil stabilization length be from vertical shaft to distal side operation tunnel outside 3m, reinforce thickness base This is soil body thickness between cross tunnel.
As shown in Figures 3 and 4, vertical shaft is made up of ground-connecting-wall, horizontal support and bottom plate, and ground-connecting-wall thickness 0.8m, bottom plate depth is big In MJS engineering methods stake reinforcement depth;MJS stabilization zones cross section is domed, 13 pile bodies is had in reinforcing area, every MJS For lower semi-circular, stake footpath 2m;MJS pile driving constructions order is lower left side pile body (lower right side pile body) --- lower right side pile body (lower left side Pile body) construction of --- middle and lower part pile body --- remaining pile body interval, top and the bottom can be effectively altered in steps with such a sequence of construction Soil body density between tunnel, reduces stabilization zone soil body permeability, improves stabilization zone soil strength, reduces and is worn under tunneling shield driving Top operation tunnel when soil deformation, and contribute to reduce settlement after construction, so as to protect top operation tunnel.
As shown in figure 5, MJS leveling peg work progress comprises the following steps:
D1, control point arranged in construction area using total powerstation, pass through control point and carry out stake position setting-out;
D2, drilling rod veer away, i.e., drilling rod level veers away to design attitude drawing in hole, the difficulty if drilling rod veers away, opening cuts hole Water progress is normally cut hole drill and entered;
D3, to stacks and drill bit, during docking, conscientiously check sealing ring situation, see whether lack or damage, pressure is whether in ground Display is normal;
D4, repeat c2 and c3 steps, until drill bit, drilling rod in place;
D5, drill bit are reached behind precalculated position, set each technological parameter, including swing angle, pulling speed, winding number etc., and open Begin to improve;
D6, positioning injection, first open suck-back current and suck-back air, when confirming that plasma discharge is normal, open spoil disposal valve, open high pressure Cement pump and primary air air compressor machine.Sprayed downwards with water first and set 50cm, pressure is 10MPa, water is then switched to cement mortar, bored Bar veers away again starts injection improvement downwards afterwards in place;
D7, open water under high pressure dredge pump when, pressure can not be too high, should progressively be pressurized, until reaching specified pressure, i.e. 40MPa, After reaching specified pressure and confirming that pressure is normal in ground, it can just start back to pull out;
Pressure in ground is monitored closely when d8, construction, when pressure is abnormal, it is necessary to adjust pulp-expelling valve size, control ground internal pressure in time Power is within safe range;
The stake sealing of hole construction of d9, MJS horizontal reinforcing;
D10, when return pull out a drilling rod after, drilling rod is dismantled;
D11, repetition above step, until construction terminates.
Above-mentioned form of construction work is taken to when the soil body carries out consolidation process between proposed tunnel and top operation tunnel, MJS water Flat stake pile body uses neat slurry, and the cement mortar ratio of mud is 1:1, maximum spray pressure is 40MPa.
After the completion of the horizontal pile driving constructions of MJS, 10 coring points must be chosen to the stabilization zone soil body and carry out vertical core pulling inspection, checked Content includes pile effective pile diameter, core sample uniaxial compressive strength, pile body overlap joint thickness, pile horizontal gradient error etc..MJS leveling pegs Stabilization zone should meet pile effective pile diameter not less than pile body diameter, i.e., not less than 2m;Core sample uniaxial compressive strength is not less than 1.0MPa;Pile body overlap joint thickness is not less than 0.4m, and lap body should be continuous;Pile horizontal gradient error is not more than 1/100.Check and close After lattice, vertical shaft is filled.
Existing tunnel MJS engineering methods stake reinforcement system is worn under the present embodiment water-rich sand layer shield and its construction method passes through under The proposed tunnel in portion and top apply MJS leveling pegs between operation tunnel and the transposition section soil body are reinforced, and improve between cross tunnel Soil strength, reduces soil body permeability, reduces under the tunneling shield driving of bottom through soil deformation caused by journey and settlement after construction Deformation, protects the top molded tunnel safety of operation tunnel and bottom.
From above-described embodiment, the reinforcement system of this patent, including the top proposed tunnel of operation tunnel and bottom, on Portion sets MJS stabilization zones between the proposed tunnel of operation tunnel and bottom;Axial direction of the MJS stabilization zones along the proposed tunnel in bottom is set Put;MJS stabilization zones include some axially arranged MJS leveling pegs along the proposed tunnel in bottom.The proposed tunnel in bottom is communicated with perpendicular Vertical shaft horizontal support is installed in well, vertical shaft.

Claims (10)

1. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under a kind of water-rich sand layer shield, it is characterised in that including Following construction procedure:
A, the investigation of operation tunnel section of jurisdiction security status;
Monitoring system layout in b, tunnel;
C, construction shaft;
D, MJS leveling peg strengthening construction;
E, detection consolidation effect;
F, vertical shaft landfill.
2. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, in step a, security status investigation in the operation tactics section of jurisdiction includes existing deformation investigation and adjusted with crack Look into;The deformation investigation is mainly tunnel-liner circumferential deformation and the change of tunnel arch axis shape and section of jurisdiction caused by linear deformation Existing form;The investigation of cracks is mainly including crack at circumferential weld, longitudinal joint, section of jurisdiction crack and injected hole, bolt hole;
Investigated by Tunnel Lining Deformation, distinguish existing operation tunnel deformation present situation, be follow-up MJS engineering methods stake reinforcement system construction Caused top operation tunnel deformation analysis provides foundation;Distinguish that existing operation tunnel is existing safely by Tunnel Lining Cracks investigation Shape, and be that follow-up MJS engineering methods stake reinforcement system construction eliminates Partial security hidden danger by crack repairing.
3. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, in stepb, monitoring system layout includes top operation tunnel internal strain-ga(u)ge unit, slit gauge and tunnel in the tunnel The arrangement of settlement monitoring system in road, the strain is calculated as hoop strain meter, and crack is calculated as circumferential weld slit gauge and longitudinal joint slit gauge.
4. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, in step c, the vertical shaft is arranged on proposed tunnel axis, and plan-position is outside top operation tunnel Side 5m;Empty size 8m × 6m in vertical shaft, long side direction is vertical with proposed tunnel axis direction;Horizontal support and bottom are provided with vertical shaft Plate, bottom plate depth is more than MJS leveling peg reinforcement depths.
5. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its Be characterised by, in step d, MJS engineering methods stake strengthening length be from vertical shaft to distal side operation tunnel outside 3m, thickness is reinforced to intersect Soil body thickness between tunnel, its stabilization zone cross section overarches;MJS divergences, stake length direction is proposed tunnel axis direction; Every MJS are lower semi-circular, stake footpath 2m;All MJS lapping constructions;MJS pile driving constructions order is lower left side pile body --- Middle and lower part pile body --- --- construct lower right side pile body or lower right side pile body --- middle and lower part pile body --- is left by remaining pile body interval Construct at downside pile body --- remaining pile body interval.
6. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, in step d, MJS pile bodies are reinforced and use neat slurry, and the ratio of mud is 1:1, maximum spray pressure 40MPa.
7. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, in step d, MJS leveling peg work progress comprises the following steps:
D1, control point arranged in construction area using total powerstation, pass through control point and carry out stake position setting-out;
D2, each stake stake position at by drawing hole, by drilling rod, progressively level veers away to design attitude;
D3, set in each technological parameter, positioning injection pile, monitoring ground pressure and control it in safe range;
The stake sealing of hole construction of d4, MJS horizontal reinforcing.
8. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, MJS engineering methods pile driving construction causes device using antipriming pipe and front end, and the antipriming pipe is by discharge pipeline, water under high pressure mud Pipe, primary air pipe, suck-back air hose, suck-back water pipe, mud valve sensor control lines road are managed, cut hole sparge pipe, antipriming pipe connection Bolt hole and spare duct composition;Cause that pressure sensor, mud discharging mouth, mouth spray are distributed with device in the front end.
9. the construction method of existing tunnel MJS engineering methods stake reinforcement system is worn under water-rich sand layer shield according to claim 1, its It is characterised by, after the completion of the horizontal pile driving constructions of MJS, vertical core pulling inspection is carried out to stabilization zone, the core pulling inspection project includes into Stake effective pile diameter, core sample uniaxial compressive strength, pile body overlap joint thickness, pile horizontal gradient error etc., after passed examination, landfill is perpendicular Well.
10. wear existing tunnel MJS engineering methods stake reinforcement system under a kind of water-rich sand layer shield, including top operation tunnel and bottom Proposed tunnel, it is characterised in that the top sets MJS stabilization zones between the proposed tunnel of operation tunnel and bottom;MJS is reinforced Area is axially arranged along the proposed tunnel in bottom;MJS stabilization zones include some axially arranged MJS levels along the proposed tunnel in bottom Stake.
CN201710464607.9A 2017-06-19 2017-06-19 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield Pending CN107091095A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710464607.9A CN107091095A (en) 2017-06-19 2017-06-19 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710464607.9A CN107091095A (en) 2017-06-19 2017-06-19 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield

Publications (1)

Publication Number Publication Date
CN107091095A true CN107091095A (en) 2017-08-25

Family

ID=59639556

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710464607.9A Pending CN107091095A (en) 2017-06-19 2017-06-19 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield

Country Status (1)

Country Link
CN (1) CN107091095A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956484A (en) * 2017-11-24 2018-04-24 中铁十局集团城市轨道交通工程有限公司 The ruggedized construction and construction method of existing shield tunnel Deformation control
CN108344638A (en) * 2018-01-24 2018-07-31 浙江大学城市学院 A kind of compound mortar reinforces the indoor test method of existing subway tunnel structure effect
CN110185035A (en) * 2019-05-31 2019-08-30 武汉江钻恒立工程钻具股份有限公司 A kind of pile making method of the MJS engineering method suitable for hardpan
CN111593726A (en) * 2020-05-19 2020-08-28 南京林业大学 Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing
CN111733839A (en) * 2020-06-16 2020-10-02 中建三局基础设施建设投资有限公司 Method for reinforcing receiving end of deep-buried shield water-rich sand layer next to excavation foundation pit
CN112160341A (en) * 2020-09-27 2021-01-01 中建三局集团有限公司 Combined reinforcement construction method for underground structure
CN113374496A (en) * 2021-06-23 2021-09-10 上海隧道工程有限公司 Upper-crossing tunnel structure and construction method
CN114293993A (en) * 2021-12-09 2022-04-08 中国建筑第五工程局有限公司 Vertical deformation repairing structure for construction of up-down overlapped tunnel and construction method
CN114293994A (en) * 2021-12-09 2022-04-08 中国建筑第五工程局有限公司 Control structure and construction method for vertical deformation of existing tunnel during construction of vertically-overlapped tunnel
CN114293559A (en) * 2021-12-23 2022-04-08 上海市机械施工集团有限公司 Horizontal MJS construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061778A (en) * 2013-02-05 2013-04-24 北京首尔工程技术有限公司 Tunnel arch foot circumferential high pressure jet strengthening method and construction equipment
CN103790164A (en) * 2014-01-23 2014-05-14 中铁四局集团有限公司上海分公司 Construction method for having control over floating deformation of existing pipeline tunnel in mollisol deep foundation pit excavation
CN104033160A (en) * 2014-06-11 2014-09-10 同济大学 Novel support method applicable to shallow-buried subsurface tunnel of soft soil stratum
CN104712340A (en) * 2015-01-21 2015-06-17 同济大学 Contact passage construction method using combination of MJS method and freezing method
CN104912562A (en) * 2015-06-30 2015-09-16 中铁一局集团有限公司 Construction method for deformation control over existing operation tunnel crossing under shield
CN106677161A (en) * 2016-12-29 2017-05-17 中铁隧道勘测设计院有限公司 Treatment method for soft soil foundation of existing shield rectangular tunnel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103061778A (en) * 2013-02-05 2013-04-24 北京首尔工程技术有限公司 Tunnel arch foot circumferential high pressure jet strengthening method and construction equipment
CN103790164A (en) * 2014-01-23 2014-05-14 中铁四局集团有限公司上海分公司 Construction method for having control over floating deformation of existing pipeline tunnel in mollisol deep foundation pit excavation
CN104033160A (en) * 2014-06-11 2014-09-10 同济大学 Novel support method applicable to shallow-buried subsurface tunnel of soft soil stratum
CN104712340A (en) * 2015-01-21 2015-06-17 同济大学 Contact passage construction method using combination of MJS method and freezing method
CN104912562A (en) * 2015-06-30 2015-09-16 中铁一局集团有限公司 Construction method for deformation control over existing operation tunnel crossing under shield
CN106677161A (en) * 2016-12-29 2017-05-17 中铁隧道勘测设计院有限公司 Treatment method for soft soil foundation of existing shield rectangular tunnel

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李建设等: "深圳地铁11号线车公庙站-红树湾站区间盾构隧道小静距上穿既有线区间隧道施工关键技术", 《隧道建设》 *
李晓光: "MJS工法在紧邻地铁工程中的应用", 《工程建设》 *
王科甫: "盾构隧道下穿客运专线沉降预测及控制研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956484A (en) * 2017-11-24 2018-04-24 中铁十局集团城市轨道交通工程有限公司 The ruggedized construction and construction method of existing shield tunnel Deformation control
CN107956484B (en) * 2017-11-24 2019-08-27 中铁十局集团城市轨道交通工程有限公司 The ruggedized construction and construction method of existing shield tunnel Deformation control
CN108344638A (en) * 2018-01-24 2018-07-31 浙江大学城市学院 A kind of compound mortar reinforces the indoor test method of existing subway tunnel structure effect
CN110185035A (en) * 2019-05-31 2019-08-30 武汉江钻恒立工程钻具股份有限公司 A kind of pile making method of the MJS engineering method suitable for hardpan
CN111593726A (en) * 2020-05-19 2020-08-28 南京林业大学 Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing
CN111733839A (en) * 2020-06-16 2020-10-02 中建三局基础设施建设投资有限公司 Method for reinforcing receiving end of deep-buried shield water-rich sand layer next to excavation foundation pit
CN112160341A (en) * 2020-09-27 2021-01-01 中建三局集团有限公司 Combined reinforcement construction method for underground structure
CN113374496A (en) * 2021-06-23 2021-09-10 上海隧道工程有限公司 Upper-crossing tunnel structure and construction method
CN114293993A (en) * 2021-12-09 2022-04-08 中国建筑第五工程局有限公司 Vertical deformation repairing structure for construction of up-down overlapped tunnel and construction method
CN114293994A (en) * 2021-12-09 2022-04-08 中国建筑第五工程局有限公司 Control structure and construction method for vertical deformation of existing tunnel during construction of vertically-overlapped tunnel
CN114293559A (en) * 2021-12-23 2022-04-08 上海市机械施工集团有限公司 Horizontal MJS construction method

Similar Documents

Publication Publication Date Title
CN107091095A (en) Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield
CN106837352A (en) Fault belt surrounding rock tunnel construction method
CN101737060B (en) Beneath-soil through-tunnel superlarge diameter pipe curtain construction method
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN106837351A (en) Tunnel Karst water detects Treatment Methods
CN109723443B (en) Tunnel construction method
CN112012753B (en) Shield tunneling machine starting method based on special-shaped extension steel ring
CN111878079B (en) Method for treating gas of soft outburst coal seam of underground large mining length working face of coal mine
CN111997624A (en) Shallow-buried large-section underground excavation rectangular tunnel construction method
CN110130901A (en) On across both wired Urban Underground mining sectbn construction methods
CN114233385A (en) Treatment method for mud burst and water burst of inclined shaft
CN113309526B (en) Construction method for excavation and supporting of buckling arch of subway station
AU2021101943A4 (en) A construction control method for a subway shield to penetrate through existing buildings
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
CN105926626A (en) Construction process for super-long vibration jet-grouting pile of pneumatic down-the-hole hammer, and equipment thereof
KR100835597B1 (en) filling method by blasting and groutting
CN114593927B (en) Method for carrying out prototype test of shield tunnel by using middle wind well
CN115681613A (en) Pipe jacking construction method for silt silty clay layer construction
CN113047853B (en) Shield originating construction method for water-rich soft soil geological region
CN110985017B (en) Construction method for shield tunneling of rainwater box culvert under expansive soil stratum
CN106837343A (en) Push pipe goes out the construction method of hole second consolidation
CN208039234U (en) A kind of engineering pile in solution cavity geology
CN113338983A (en) Large-diameter mud-water balance pipe jacking construction method suitable for high-water-level rock geology
CN102191770A (en) Geology improving method for trenchless construction
CN113217036A (en) Post-grouting construction method for tunnel structure at water burst section of fault fracture zone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170825