CN107956484A - The ruggedized construction and construction method of existing shield tunnel Deformation control - Google Patents

The ruggedized construction and construction method of existing shield tunnel Deformation control Download PDF

Info

Publication number
CN107956484A
CN107956484A CN201711193765.1A CN201711193765A CN107956484A CN 107956484 A CN107956484 A CN 107956484A CN 201711193765 A CN201711193765 A CN 201711193765A CN 107956484 A CN107956484 A CN 107956484A
Authority
CN
China
Prior art keywords
drilling
shield tunnel
drilling machine
engineering method
existing shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711193765.1A
Other languages
Chinese (zh)
Other versions
CN107956484B (en
Inventor
蔡昕宸
刘阳
唐新军
王亚明
申浩
吴先勇
郭新平
田军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN201711193765.1A priority Critical patent/CN107956484B/en
Publication of CN107956484A publication Critical patent/CN107956484A/en
Application granted granted Critical
Publication of CN107956484B publication Critical patent/CN107956484B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses the ruggedized construction and construction method of existing shield tunnel Deformation control, this method includes:Mark need to establish the drilling position of engineering method stake;Drilled using drilling machine to the first drilling position;After first drilling position reaches desired depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;After the completion of first engineering method stake, drilled using drilling machine to the second drilling position, wherein, opposite side of the second drilling position positioned at the first drilling position;After second drilling position reaches desired depth, slip casting is carried out to the second drilling position, to form the second engineering method stake being cross-linked with the first engineering method stake;And so on, until the foundation of all engineering method stakes is completed, to form the reinforcement system of existing shield tunnel.The effective deformation for avoiding existing shield tunnel of the invention, while the influence to ground is smaller.

Description

The ruggedized construction and construction method of existing shield tunnel Deformation control
Technical field
The present invention relates to existing shield tunnel reinforcement construction technology field, more specifically a kind of existing shield tunnel becomes The ruggedized construction and construction method of shape control.
Background technology
In recent years, substantial amounts of subway network has been built in many cities in China, due to the long-term settlement of subway itself and neighbouring Tunnel subsidence caused by field construction or floating, influence the safe operation of subway, so reinforcement measure must be taken to reduce Influence of the excavation of foundation pit to existing tunnel.
At present, the method that some domestic subway work units propose some control existing shield tunnel deformations, such as soil Body grouting strengthening method.Not only boundary of works area is wider for this reinforcement means, and enforcement difficulty is larger, and consolidation effect is difficult to ensure that, and Influence during construction to adjacent piles is difficult to control.Therefore it is required to invention and finds out a kind of more cost-effective reinforcement means Control the deformation of existing shield tunnel.
The content of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide the ruggedized construction of existing shield tunnel Deformation control And construction method.
To achieve the above object, the present invention uses following technical scheme:Existing shield tunnel Deformation control ruggedized construction Construction method, the described method includes:
Mark need to establish the drilling position of engineering method stake;
Drilled using drilling machine to the first drilling position;
After first drilling position reaches desired depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;
After the completion of first engineering method stake, drilled using drilling machine to the second drilling position, wherein, the second drilling position is located at first The opposite side of drilling position;
After second drilling position reaches desired depth, slip casting is carried out to the second drilling position, is interlocked with being formed with the first engineering method stake Second engineering method stake of connection;
And so on, until the foundation of all engineering method stakes is completed, to form the reinforcement system of existing shield tunnel.
Its further technical solution is:It is described using drilling machine to first drilling position drill the step of, specifically include with Lower step:
Start drilling machine;
Drill bit of drilling machine is pressed into the soil body at an oblique angle;
It is pressed into during the soil body, needs certain interval of time to lift drilling machine drilling pipe;
Cutting soil, until drill bit of drilling machine stops when reaching desired depth.
Its further technical solution is:The angle of inclination of the favourable turn drill bit and the angle on ground are 30 °~60 °.
Its further technical solution is:The step cutting soil, until during drill bit of drilling machine stops when reaching desired depth, When the soil property of cutting soil is harder, the pump of water pipe and drilling machine is connected.
Its further technical solution is:After the first drilling position reaches desired depth, slip casting is carried out to the first drilling position, The step of to form the first engineering method stake, specifically include following steps:
Open the reflux stomata and reflux high-pressure pump of drilling machine;
Open the mud valve of drilling machine;
Open high pressure water dredge pump and air compressor machine;
The downward 180 ° of high pressure jet groutings of gunniting hole.
Its further technical solution is:The step of reflux stomata for opening drilling machine and reflux high-pressure pump and the opening Step is further included between the step of mud valve of drilling machine:
Confirm whether plasma discharge is normal, if normally, opening the mud valve of drilling machine, if abnormal, until plasma discharge is normal When, opening opens the mud valve of drilling machine.
Its further technical solution is:The drilling machine is MJS drilling machines.
Its further technical solution is:The engineering method stake is semicylinder shape.
Its further technical solution is:A diameter of 0.8~1.1 meter of the engineering method stake.
The ruggedized construction of existing shield tunnel Deformation control, including the ruggedized construction below shield tunnel, it is described to add Fixing structure includes the semi-cylindrical engineering method stake of interconnection;The angle on the engineering method stake and ground is 30 °~60 °;The engineering method A diameter of 0.8~1.1 meter of stake.
Compared with the prior art, the invention has the advantages that:Existing shield tunnel Deformation control ruggedized construction of the present invention Construction method performing a reinforcing area below existing shield tunnel, reinforcing area by two rows of certain angles diagonally downward Engineering method stake it is intersected with each other overlap joint form, engineering method stake by MJS drilling machines through first punching, grouting behind shaft or drift lining and formed, sound construction, effectively The deformation of existing shield tunnel is avoided, while the influence to ground is smaller.
Described above is only the general introduction of technical solution of the present invention, can in order to better understand technical measure Content according to specification is practiced, and in order to make above and other objects of the present invention, feature and advantage brighter It is aobvious understandable, below especially exemplified by preferred embodiment, describe in detail as follows.
Brief description of the drawings
Fig. 1 is the flow chart of the construction method specific embodiment of existing shield tunnel Deformation control ruggedized construction of the present invention;
Fig. 2 is the stream to drill in the construction method specific embodiment of existing shield tunnel Deformation control ruggedized construction of the present invention Cheng Tu;
Fig. 3 be existing shield tunnel Deformation control ruggedized construction of the present invention construction method specific embodiment in slip casting stream Cheng Tu;
Fig. 4 is the stereogram of the ruggedized construction specific embodiment of existing shield tunnel Deformation control of the present invention;
Fig. 5 is the structure diagram of the ruggedized construction specific embodiment of existing shield tunnel Deformation control of the present invention;
Fig. 6 be existing shield tunnel Deformation control of the present invention ruggedized construction specific embodiment in engineering method stake structural representation Figure.
Reference numeral
1st, ground;2nd, Grouting Pipe;3rd, engineering method stake;4th, existing shield tunnel;5th, the soil body.
Embodiment
In order to more fully understand the present invention technology contents, with reference to specific embodiment to technical scheme into One step introduction and explanation, but not limited to this.
The specific embodiment shown in -3 is please referred to Fig.1, a kind of existing shield tunnel Deformation control is present embodiments provided and adds The construction method of fixing structure, method include:
S10, mark need to establish the drilling position of engineering method stake;
S20, using drilling machine to first drilling position drill;
After S30, the first drilling position reach desired depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;
After the completion of S40, the first engineering method stake, drilled using drilling machine to the second drilling position, wherein, the second drilling position is located at The opposite side of first drilling position;
After S50, the second drilling position reach desired depth, slip casting is carried out to the second drilling position, to be formed and the first engineering method stake The second engineering method stake being cross-linked;
S60, and so on, until the foundation of all engineering method stakes is completed, to form the reinforcement system of existing shield tunnel.
For above-mentioned step S10, the mode of mark can mark the position of drilling using infrared ray, or using stone Ash sketches the contours of the general profile of a bore position.
For above-mentioned step S20, before drilling machine is drilled, drilling machine need to be transported into hole site, connect power supply And data cable, open oil pump.Drill bit of drilling machine is connected with pressure monitor display in ground, confirms condition of the drill bit of drilling machine in no-load Lower clearing.Again to stacks and drill bit of drilling machine, it is ensured that the leakproofness of sealing ring during docking, while check whether pressure shows in ground Show normal.
For above-mentioned step S40, the second drilling position drilled before, it is necessary to which the first engineering method stake reaches hardness requirement And then carry out the drilling of the second drilling position.
For above-mentioned step S60, after the second engineering method stake is completed, slip casting, the 3rd drilling are carried out to the 3rd drilling position Positioned at first drilling position the same side, the 4th drilling position is positioned at the 3rd opposite side for boring room.Upper drilling position slip casting completes it Afterwards, formed after engineering method stake, just next drilling position is operated.
Further, for above-mentioned step S20, in certain embodiments, following steps are specifically included:
S201, start drilling machine;
S202, drill bit of drilling machine are pressed into the soil body at an oblique angle;
During S203, the press-in soil body, certain interval of time is needed to lift drilling machine drilling pipe;
S204, cutting soil, until drill bit of drilling machine stops when reaching desired depth.
For above-mentioned steps S201, when startup, need to observe the situation of surrounding, if there are security risk, and it is hidden need to discharge safety After trouble, drilling machine could be started.
For above-mentioned step S202, drill bit of drilling machine is pressed into the soil body with 45 ° of angle, in order to protect the peace of surrounding people Entirely, surrounding staff needs the security settings such as safe wearing cap.
For step S203, soil block is blocked drill bit of drilling machine, it is necessary to which certain interval of time will lift drilling pipe in order to prevent.
Specifically, in step S204, run into cutting soil soil property it is harder when, it is necessary to which the pump of water pipe and drilling machine is connected Connect, to drench the soil body, smoothly work easy to drilling machine.
Further, for above-mentioned step S30, in certain embodiments, following steps are specifically included:
S301, the reflux stomata for opening drilling machine and reflux high-pressure pump;
S302, the mud valve for opening drilling machine;
S303, open high pressure water dredge pump and air compressor machine;
The downward 180 ° of high pressure jet groutings of S304, gunniting hole.
Specifically, also need to confirm whether plasma discharge is normal between step S301 and step S302, if normally, opening and boring The mud valve of machine, if abnormal, until when plasma discharge is normal, opens the mud valve of drilling machine.
Preferably, drilling machine uses MJS drilling machines.Engineering method stake is semicylinder shape.A diameter of 1 meter of engineering method stake.
Summary:The construction method of existing shield tunnel Deformation control ruggedized construction of the present invention is to existing shield tunnel Lower section performs a reinforcing area, and engineering method stake of the reinforcing area by two rows of certain angles diagonally downward overlap joint intersected with each other forms, Engineering method stake by MJS drilling machines through first punching, grouting behind shaft or drift lining and formed, sound construction, effectively avoid the change of existing shield tunnel Shape, while the influence to ground is smaller.
The specific embodiment described in Fig. 4-6 is referred to, the present embodiment additionally provides a kind of using existing shield tunnel deformation Ruggedized construction used by the construction method of control ruggedized construction, it includes the semi-cylindrical engineering method stake of interconnection;Engineering method stake Angle with ground is 30 °~60 °;A diameter of 0.8~1.1 meter of engineering method stake.
Specifically, the forming process of engineering method stake is first using drilling machine from the drilling position on ground 1 to 5 internal drilling of the soil body, then lead to The slip casting into drilling position of Grouting Pipe 2 is crossed, is waited for a period of time, the slurry solidification to drill in position, so as to form engineering method stake 3.Engineering method stake 3 Interconnection is set, and stability is preferable, and the stability of existing shield tunnel 4 has been effectively ensured, and avoids deforming.
Summary:Existing shield tunnel Deformation control ruggedized construction of the present invention is performing one below existing shield tunnel A reinforcing area, engineering method stake of the reinforcing area by two rows of certain angles diagonally downward overlap joint intersected with each other form, and engineering method stake passes through MJS drilling machines through first punching, grouting behind shaft or drift lining and formed, sound construction, effectively avoid the deformation of existing shield tunnel, while over the ground The influence in face is smaller.
The above-mentioned technology contents that the present invention is only further illustrated with embodiment, in order to which reader is easier to understand, but not Represent embodiments of the present invention and be only limitted to this, any technology done according to the present invention extends or recreation, by the present invention's Protection.Protection scope of the present invention is subject to claims.

Claims (10)

1. the construction method of existing shield tunnel Deformation control ruggedized construction, it is characterised in that the described method includes:
Mark need to establish the drilling position of engineering method stake;
Drilled using drilling machine to the first drilling position;
After first drilling position reaches desired depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;
After the completion of first engineering method stake, drilled using drilling machine to the second drilling position, wherein, the second drilling position is positioned at the first drilling The opposite side of position;
After second drilling position reaches desired depth, slip casting is carried out to the second drilling position, is cross-linked with being formed with the first engineering method stake The second engineering method stake;
And so on, until the foundation of all engineering method stakes is completed, to form the reinforcement system of existing shield tunnel.
2. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, it is characterised in that institute The step of drilling using drilling machine to the first drilling position is stated, specifically includes following steps:
Start drilling machine;
Drill bit of drilling machine is pressed into the soil body at an oblique angle;
It is pressed into during the soil body, needs certain interval of time to lift drilling machine drilling pipe;
Cutting soil, until drill bit of drilling machine stops when reaching desired depth.
3. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 2, it is characterised in that institute It is 30 °~60 ° to state the angle of inclination of favourable turn drill bit and the angle on ground.
4. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 2, it is characterised in that institute State step cutting soil, until in stopping when drill bit of drilling machine reaches desired depth, when the soil property of cutting soil is harder, by water pipe with The pump connection of drilling machine.
5. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, it is characterised in that institute State after the first drilling position reaches desired depth, slip casting is carried out to the first drilling position, the step of to form the first engineering method stake, specific bag Include following steps:
Open the reflux stomata and reflux high-pressure pump of drilling machine;
Open the mud valve of drilling machine;
Open high pressure water dredge pump and air compressor machine;
The downward 180 ° of high pressure jet groutings of gunniting hole.
6. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 5, it is characterised in that institute Also wrapped between the step of mud valve of the step of stating the reflux stomata for opening drilling machine and reflux high-pressure pump and the opening drilling machine Include step:
Confirm whether plasma discharge is normal, if normally, opening the mud valve of drilling machine, if abnormal, until when plasma discharge is normal, beat Perform fighting the mud valve of the machine of spudding in.
7. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, it is characterised in that institute It is MJS drilling machines to state drilling machine.
8. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, it is characterised in that institute It is semicylinder shape to state engineering method stake.
9. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 9, it is characterised in that institute State engineering method stake a diameter of 0.8~1.1 meter.
10. the ruggedized construction of existing shield tunnel Deformation control, it is characterised in that including the reinforcing knot below shield tunnel Structure, the ruggedized construction include the semi-cylindrical engineering method stake of interconnection;The angle on the engineering method stake and ground is 30 °~60 °; A diameter of 0.8~1.1 meter of the engineering method stake.
CN201711193765.1A 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control Expired - Fee Related CN107956484B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711193765.1A CN107956484B (en) 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711193765.1A CN107956484B (en) 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control

Publications (2)

Publication Number Publication Date
CN107956484A true CN107956484A (en) 2018-04-24
CN107956484B CN107956484B (en) 2019-08-27

Family

ID=61961717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711193765.1A Expired - Fee Related CN107956484B (en) 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control

Country Status (1)

Country Link
CN (1) CN107956484B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685205A (en) * 2021-09-22 2021-11-23 中铁隧道股份有限公司 Rotary spraying lifting structure and construction method
CN116044455A (en) * 2023-04-03 2023-05-02 湖南大学 Grouting system for directional reinforcement of tunnel

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202215256U (en) * 2011-09-23 2012-05-09 中铁十二局集团第三工程有限公司 Reinforcing structure for fine sand layer of tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed by advanced treatment of weathering ball of impact drill in tunneling range of shield tunneling machine
CN103924987A (en) * 2014-04-24 2014-07-16 中铁十一局集团城市轨道工程有限公司 SMW pile shielding portal waterproof structure and construction method thereof
CN204676562U (en) * 2015-05-28 2015-09-30 中国二十冶集团有限公司 One encloses purlin and SMW engineering method stake connection reinforcing structure
CN105297797A (en) * 2015-11-30 2016-02-03 浙江华展工程研究设计院有限公司 Hoop support form for in-situ protection of existing building in underground space development
CN105298517A (en) * 2015-11-21 2016-02-03 中铁二十局集团第二工程有限公司 Soft and weak wall rock tunnel advance reinforced support construction method
CN205242388U (en) * 2015-12-23 2016-05-18 中铁十二局集团有限公司 Enhancement mode SMW worker method pilework
CN205778878U (en) * 2016-05-13 2016-12-07 中铁二十三局集团第一工程有限公司 A kind of supporting construction being applicable to large-section box culvert jacking crossing construction
CN107091095A (en) * 2017-06-19 2017-08-25 中建隧道建设有限公司 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield
CN107366282A (en) * 2017-07-11 2017-11-21 北京市政建设集团有限责任公司 A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202215256U (en) * 2011-09-23 2012-05-09 中铁十二局集团第三工程有限公司 Reinforcing structure for fine sand layer of tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed by advanced treatment of weathering ball of impact drill in tunneling range of shield tunneling machine
CN103924987A (en) * 2014-04-24 2014-07-16 中铁十一局集团城市轨道工程有限公司 SMW pile shielding portal waterproof structure and construction method thereof
CN204676562U (en) * 2015-05-28 2015-09-30 中国二十冶集团有限公司 One encloses purlin and SMW engineering method stake connection reinforcing structure
CN105298517A (en) * 2015-11-21 2016-02-03 中铁二十局集团第二工程有限公司 Soft and weak wall rock tunnel advance reinforced support construction method
CN105297797A (en) * 2015-11-30 2016-02-03 浙江华展工程研究设计院有限公司 Hoop support form for in-situ protection of existing building in underground space development
CN205242388U (en) * 2015-12-23 2016-05-18 中铁十二局集团有限公司 Enhancement mode SMW worker method pilework
CN205778878U (en) * 2016-05-13 2016-12-07 中铁二十三局集团第一工程有限公司 A kind of supporting construction being applicable to large-section box culvert jacking crossing construction
CN107091095A (en) * 2017-06-19 2017-08-25 中建隧道建设有限公司 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield
CN107366282A (en) * 2017-07-11 2017-11-21 北京市政建设集团有限责任公司 A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685205A (en) * 2021-09-22 2021-11-23 中铁隧道股份有限公司 Rotary spraying lifting structure and construction method
CN116044455A (en) * 2023-04-03 2023-05-02 湖南大学 Grouting system for directional reinforcement of tunnel
CN116044455B (en) * 2023-04-03 2023-06-23 湖南大学 Grouting system for directional reinforcement of tunnel

Also Published As

Publication number Publication date
CN107956484B (en) 2019-08-27

Similar Documents

Publication Publication Date Title
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN101737060B (en) Beneath-soil through-tunnel superlarge diameter pipe curtain construction method
CN102182472B (en) Backfill repairing method for tunnel collapse cavity
CN103510957B (en) A kind of combined type coal uncovering method
CN104453913A (en) Vertical shaft working face ahead pre-grouting method
CN110617072B (en) Tunnel excavation construction method for obliquely passing existing operation tunnel at minimum clear distance
CN108661650A (en) A kind of rich water magmatic body area depth pozo shaft construction method
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN106401645A (en) Pressure-relief support coordination control method for deep high-stress tunnel based on borehole pressure relief
CN103835651A (en) Single-hole directional drilling local grouting raise boring technology
CN107035376B (en) One kind common law in huge thick bedrock aquifer digs shaft construction method
CN107339122A (en) A kind of steel pipe column handles goaf engineering method
CN110905536A (en) Construction method for receiving complex stratum earth pressure shield in underground excavation tunnel
CN107956484B (en) The ruggedized construction and construction method of existing shield tunnel Deformation control
CN206616565U (en) Door font double-row pile and double high-pressed spin-spewing water-stopping curtain combined retaining structure
CN112942441B (en) Pre-grouting water-stopping construction method for water-rich powder sand stratum
CN110454164A (en) Impulsion pressure tunnel buffering energy-absorbing band waterpower pre-setting method
CN105909262A (en) Subsurface tunnel driving method
JP2009068213A (en) Construction method for underground structure using caisson, and caisson with cut-off device
JP2007332559A (en) Removal method for existing underground pile
CN102220764A (en) Deep foundation pit bracing system and construction method thereof
CN112012746A (en) Construction method of railway tunnel deep and large vertical shaft under condition of thick-layer water-rich broken zone
CN111877344A (en) Old pipe pile breaking method
CN201078234Y (en) Integral hydraulic pressure steel sheet piling curtain of vertical shaft construction overflowing sand bed
CN114856688B (en) Method for controlling deformation of coal seam floor rock stratum by underground grouting slurry filling casing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190827

Termination date: 20211124