CN107339122A - A kind of steel pipe column handles goaf engineering method - Google Patents

A kind of steel pipe column handles goaf engineering method Download PDF

Info

Publication number
CN107339122A
CN107339122A CN201710773329.5A CN201710773329A CN107339122A CN 107339122 A CN107339122 A CN 107339122A CN 201710773329 A CN201710773329 A CN 201710773329A CN 107339122 A CN107339122 A CN 107339122A
Authority
CN
China
Prior art keywords
steel pipe
goaf
pipe column
hole
engineering method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710773329.5A
Other languages
Chinese (zh)
Other versions
CN107339122B (en
Inventor
高盛翔
丁陈建
陈益民
杨栋梁
李志永
陈书平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Zhongkuang geotechnical Technology Co.,Ltd.
Original Assignee
Cumt Geotechnical Engineering & New Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cumt Geotechnical Engineering & New Technology Development Co ltd filed Critical Cumt Geotechnical Engineering & New Technology Development Co ltd
Priority to CN201710773329.5A priority Critical patent/CN107339122B/en
Publication of CN107339122A publication Critical patent/CN107339122A/en
Application granted granted Critical
Publication of CN107339122B publication Critical patent/CN107339122B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Abstract

The present invention proposes a kind of steel pipe column processing goaf engineering method, by using by under steel pipe column to mined out region, casting concrete makes it turn into a male cone body with surrounding rock body in steel pipe column, so as to form carrying short column in goaf, reach prevention, the purpose that deformation meets top-out composition deformation is continued in reduction goaf.When being directed to water head site Mined-out Area control, using in steel pipe casting concrete do not change original hydrologic condition, disturbance to underground water and pollution are minimized, the steel pipe column male cone body being supported between the roof and floor of goaf solves steel-pipe pile and passes through the length stake buckling stability that goaf is run into and the negative frictional resistance for acting on a side, steel pipe column male cone body stress is more reasonable, and stability is higher;More conventional grouting treatment, the improvement area in goaf is substantially reduced, reduce material usage, saved cost, efficiency of construction greatly improves.

Description

A kind of steel pipe column handles goaf engineering method
Technical field
The invention belongs to goaf harnessing technical field, and in particular to a kind of steel pipe column handles goaf engineering method.
Background technology
Goaf refers to the exploitation space that underground is formed after subterranean resource is produced, after subterranean resource produces, cavity week Enclose original original stress equilibrium state to be destroyed, cause stresses re-distribution, overlying strata are known from experience gradual unstability and produced thereon in goaf Displacement, cracking, destruction are caving, according to its top covering rockmass deformation and failure degree be roughly divided into " caving zone ", " fracture belt ", " curved bel ", with the upward development of deformation of subterranean body, when involving to earth's surface, earth's surface produces mobile and deformation, base area The speed of table movement and deformation is classified as " initial period ", " active period ", " decline phase ", " residual deformation phase ".When on goaf When carrying out construction activity, the construction of structures thereon will necessarily be deformed by goaf to be influenceed, must before engineering construction is carried out Goaf must be evaluated, the complexity in the significance level built according to construction and construction place is determined at control measures Reason.
The processing method for reducing mined out ground deformation is directed to, mainly there is down-hole treatment at present(Below ground)Locate with well Reason(It is more than ground).Restricted by cost of winning, domestic mining area exploitation is exploited using sunken method entirely mostly, i.e., goaf is not entered Row filling treatment, carry out generally requiring during construction activity thereon carrying out processing mode on well, at present to the ground in goaf at Reason method mainly have slip casting method, digging up and filling in method, heavy-tamping method, across method, pass through method etc..Digging up and filling in method, heavy-tamping method, pass through method It is primarily adapted for use in the shallower goaf of buried depth;It is mainly used for handling the less regions of scope such as tunnel, pit shaft across method;Slip casting Method application is wider, most goafs is can be suitably used for by adjusting grout coordinate ratio and grouting process, in processing procedure All mined out scopes for influenceing its top construction and building construction need to be filled, charging quantity is big;When cavity is larger in goaf, The unsuitable coagulation forming of slurries;When rich water in goaf, slurries should not solidify when for circumstance of flowing water when, slurries diffusion area increase Construction cost and slip casting effect can be substantially increased;When goaf is located near water head site, injecting paste material can be with underground water Flowing affects greatly to groundwater quality.
It is directed to during injecting treatment goaf, construction work amount is big, long in time limit, slurries setting percentage is low, to underground ring There is certain influence in border.Also steel-pipe pile is taken to pass through goaf, in the administering method of steel casing pack concrete, it is controlled Thought is managed equivalent to the goaf that mini pile passes through to bottom plate certain depth, by upper load by pile body reach pile body side wall and Stake end is to reach the purpose for reducing goaf and influenceing, but with the increase of goaf depth, and Rock And Soil adds to steel around steel-pipe pile The downdrag of pile tube can greatly increase, and the stability and bearing capacity of pile body can substantially reduce, and can increase construction cost and Difficulty.
The content of the invention
In order to solve defect present in above-mentioned prior art, the present invention proposes a kind of steel pipe column processing goaf work Method, by using by, to mined out region, casting concrete makes it turn into one with surrounding rock body in steel pipe column under steel pipe column Male cone body, so as to form carrying short column in goaf, reach prevention, reduction goaf continues deformation and meets that upper building becomes The purpose of shape.
The technical solution adopted by the present invention:A kind of steel pipe column handles goaf engineering method, and the engineering method comprises the steps of:
Step 1:With reference to proposed place goaf distribution characteristics, surrounding enviroment condition and building characteristic, the plane of drilling is designed Arrangement and depth;
Step 2:Hole structure is designed by 1 ~ 2 reducing from aperture to bottom hole according to drilling depth and Rock And Soil intensity, i.e., certainly Upper and lower boring aperture is gradually reduced 1 ~ 2 grade;
Step 3:Tripping in protection pipe after bedrock surface certain depth below is drilled into using large aperture in soil layer, decomposed rock, prevents hole Wall caves in;
Step 4:Reduce bore diameter and continue to drill through goaf to 1 ~ 2 meter of gob floor;
Step 5:According to goaf data and the integrated degree of hole wall, tripping in seamless steel pipe to bottom hole, described seamless steel pipe Length exceedes goaf top plate and is no less than 2 meters;
Step 6:To after bottom hole under seamless steel pipe, mixed microlith is irrigated into hole to seamless steel pipe bottom under concreting conduit Solidifying soil fills out at the top of perfusion to seamless steel pipe 3 ~ 5 meters, forms male cone body;
Step 7:After seamless steel pipe inner concrete initial set, into hole, perfusion mortar carries out sealing of hole.
Preferably, tripping in drilling well Image-forming instrument peephole inwall integrated degree is also included in described step 4.
Preferably, the method for observation hole wall integrated degree is in described step 4:Tripping in ultrasonic probe, to hole wall week Enclose 360 degree of spatial dimension transmittings and receive ultrasonic signal, scan the geological condition of country rock in the range of 0.5 meter around whole drilling, The integrity degree of borehole wall is analyzed by speed, amplitude, the frequency of analyzing ultrasonic wave.
Preferably, described seamless steel pipe upper inner is provided with screw thread, is connected by joint with drilling rod, i.e. one end of joint It is connected with seamless steel pipe, one end is connected with drilling rod, and the hand of spiral at joint both ends is on the contrary, i.e.:The screw thread being connected with seamless steel pipe For " anti-silk ", the screw thread being connected with drilling rod is " positive silk ".
Seamless steel pipe, joint, drilling rod are connected on ground, in tripping in hole, treat that seamless steel pipe is passed through under goaf to bottom hole Afterwards, pressurizeed downwards by rig while rotate drilling rod, now, " screw thread " that drilling rod is connected with joint gradually becomes tight, and seamless steel Manage " screw thread " being connected with joint gradually to fluff until threading off, now, joint disengages with seamless steel pipe, and seamless steel pipe is that tripping in is pre- Positioning is put, and the process of the concrete perfusion into seamless steel pipe can be entered by above carrying drilling tool.
Preferably, in described step 5, before tripping in seamless steel pipe, nitrolite is put into 3 ~ 5 meters of goaf top plate, led to Cross explosion and expand aperture, so as to increase the volume of male cone body in step 6.
Beneficial effects of the present invention:When the 1st, being directed to water head site Mined-out Area control, using in steel pipe, casting concrete is not Change original hydrologic condition, the disturbance to underground water and pollution are minimized.
2nd, the steel pipe column male cone body being supported between the roof and floor of goaf solves steel-pipe pile and passes through the length that goaf is run into Stake buckling stability and the negative frictional resistance for acting on a side, steel pipe column male cone body stress is more reasonable, and stability is higher.
3rd, more conventional grouting treatment, substantially reduce the improvement area in goaf, reduce material usage, saved into This, efficiency of construction greatly improves.
4th, when gob floor gradient is larger, the empty highly larger, goaf in goaf is satisfied water, goaf are in dynamic water When in environment, can there are grouting amount increase, the low shortcoming of slurries calculus rate using the grouting treatment of routine, using steel pipe column engineering method Because there is the constraint of steel pipe in outside when being administered, construction work amount will not be increased, while can guarantee that preferable regulation effect, should The accommodation of engineering method is wider.
5th, steel pipe top insertion goaf top plate, the slurry overflowed during slip casting can improve goaf top plate with filled opening Geological environment.
Brief description of the drawings
Fig. 1 is the embodiment of the present invention 1, the steel pipe column schematic diagram for completion of constructing;
Fig. 2 is the steel pipe column schematic diagram that the present invention administers water head site goaf;
Fig. 3 is the steel pipe column schematic diagram that the present invention administers Inclined Mined;
Fig. 4 is drilling plane layout drawing partial schematic diagram in embodiment 1;
In figure, 1, soil layer, 2, decomposed rock, 3, rock stratum, 4, goaf top plate, 5, goaf, 6, gob floor, 7, soil layer set Pipe, 8, concreting conduit, 9, seamless steel pipe, 10, crack, 11, concrete, 12, mortar, 13, waterline.
Embodiment
In order to further illustrate the ins and outs of the present invention, illustrated in conjunction with accompanying drawing and Specific construction case.
Step 1, with reference to proposed place goaf distribution characteristics, surrounding enviroment condition and building characteristic, drilling is designed Horizontal layout and depth;
According to《Coal mine gob is built(Structure)Build thing foundation treatment technology specification》、《Goaf(Cavity)Prospective design and construction are controlled Manage handbook》Deng the relevant requirement of specification, with reference to goaf cavity size, the fractured situation and plan of overlying Rock And Soil The factors such as construction of structures facade plane arrangement form, load, base form are built, it is comprehensive to determine drilling plane arrangement, hole depth Coal seam depth according to disclosed by the data such as data collection early stage, survey Evaluation determines.The step is the conventional judgement before construction Means, to those skilled in the art, implementation can be determined how according to specification requirement.
Step 2,3:Hole structure is designed by 1 ~ 2 change from aperture to bottom hole according to drilling depth and Rock And Soil intensity Footpath, i.e., boring aperture is gradually reduced 1 ~ 2 grade from top to bottom, and below bedrock surface is drilled into using large aperture in soil layer 1, decomposed rock 2 Tripping in protection pipe afterwards(Soil layer sleeve pipe 7), prevent hole wall collapse.Boring aperture size mainly according to hole depth, rock-soil layer degree of crushing, The factors such as steel pipe column diameter, are designed for actual conditions.Reducing is set generally between soil layer 1 and rock stratum 3, Tripping in protection pipe simultaneously(Soil layer sleeve pipe 7).The main reason for this layer of position drilling reducing is soil layer 1 and the physico-mechanical properties of rock stratum 3 Difference is larger, and Weathering Zones of Igneous Rock is serious, rock crushing, and underground water is generally stranded between soil layer 1 and rock stratum 3, increases the boundary The unstability in face, chip off-falling collapse hole easily occurs for collision disturbance of the drilling tool to hole wall, the region in hole in addition, and therefore, drilling is deep After degree passes through rock-soil layer interface and reaches stable rock stratum, tripping in and boring aperture protection pipe of a size(Soil layer sleeve pipe 7) To intact rock, boring aperture diminution one-level is continued to creep into downwards.In drilling process, if running into rock stratum smashed to pieces (Such as wear the mined out region of multilayer), during pore-forming difficulty, can meet on the basis of design requirement can as stated above, then one layer of guarantor of tripping in Pillar(Soil layer sleeve pipe 7), reduced bore, to reach the purpose by broken rock.Aperture specification presses DCDMA standards, φ 108, φ 127, φ 146, φ 168 etc., or the standard geology tubing that in the market is general.
Step 4:Reduce bore diameter to continue after drilling through goaf to 1 ~ 2 meter of bottom plate, the complete journey of peephole inner hole wall Degree;Specifically engineering method is:Tripping in ultrasonic probe, to hole wall around the transmitting of 360 degree of spatial dimensions and receive ultrasonic signal, scanning is whole Around individual drilling in the range of 0.5 meter country rock geological condition, by analyzing the speed of ultrasonic wave, amplitude, frequency to borehole wall Integrity degree analyzed.The purpose of peephole inwall integrated degree has two:
(1)By observing mined out zone position and its surrounding cranny development degree, control is carried out with guiding construction and to construction quality (Concrete is filled in the length of tripping in seamless steel pipe and hole exceed steel pipe column top to obtain by observing goaf cavity size The parameter informations such as the height in face).
(2), can tripping in imager observation hole wall cranny development when creeping into difficult if occurring hole wall collapse in boring procedure Situation, to find out drilling well difficult reason, while according to information such as crack size, length, allotment mortar, concrete, it is injected into In hole, after its solidification, continue drilling in foramen primum position to gob floor 6(Hole wall is after mortar, concrete strengthening, beneficial to applying The continuation of work, while be advantageous to the tripping in of seamless steel pipe 9 to design level position).
Step 5,6:According to goaf data and the integrated degree of hole wall, tripping in seamless steel pipe 9 to bottom hole, described nothing Stitch the length of steel pipe 9 and exceed goaf top plate no less than 2 meters;To after bottom hole under seamless steel pipe 9, by under concreting conduit 8 extremely The bottom of seamless steel pipe 9 irrigates pea gravel concreten into hole and fills out perfusion to 3 ~ 5 meters of the top of seamless steel pipe 9, forms male cone body.
Before tripping in seamless steel pipe, nitrolite can be put into 3 ~ 5 meters of goaf top plate, pass through explosion expanded hole Footpath, increase steel pipe column(The penetration concrete 11 of seamless steel pipe 9 forms steel pipe column)The volume of the male cone body on top, so as to play increase The effect of steel pipe column support force.Influenceed by downhole explosion, hole wall collapse, seamless steel pipe can not tripping in original drilling depth, need to carry out Subsequent step can be carried out after cleaning bottom of hole, the specific method of cleaning bottom of hole is:In foramen primum position tripping in drilling tool, it is drilled into former depth and takes out in hole Fragmented rock body(1 ~ 2 meter of gob floor is drilled into again), subsequent step can be carried out.
Step 7:After the initial set of 9 inner concrete of seamless steel pipe 11, into hole, perfusion mortar 12 carries out sealing of hole.
Embodiment 1, Xuzhou Huai-Hai art work show center east is successfully applied to steel pipe column processing goaf engineering method Exemplified by the building yard of southern side, the ins and outs of this engineering method are introduced.
45 meters or so of the plot underground is 22 coal goafs, and run of mine coal seam working thickness is 1.0 meters or so, and probing discloses mined out Region core crushes, and falls to bore up to 10cm.
As shown in figure 1, the structure of Mined-out Area control stake holes is:The tripping in φ 168mm retaining wall of thin-wall steel tube 1, rock in soil layer 1 Layer segment aperture is φ 146mm, and stake bottom should be crept into 22 coal seam floor 1.0m, and stake holes horizontal layout is that every row transverse direction pilespacing is 2 meters, Line-spacing is 2 meters, and often the stake holes of row stake holes and adjacent lines is staggeredly arranged, as shown in Figure 4.
φ 146mm seamless steel pipe 9, wall thickness 8mm, steel pipe hollow space fill C35 pea gravel concretens 11 under mined out section, Steel pipe column length is according to the situation in goaf, it is ensured that 1.0m is no less than below 22 coal goafs, 22 coal goaf roofs 4 are not Less than 2.0m., to after bottom hole, C35 pea gravel concretens 11 will be irrigated under seamless steel pipe 9 into hole using concreting conduit 8 and filled Fill out at the top of perfusion to steel pipe column above 3.5m.After the initial set of steel pipe inner concrete 11, into hole, perfusion mortar 12 carries out sealing of hole. Under this place after the completion of Mined-out Area control, proposed building is built by laying bricks or stones when foundation trench is excavated before basis, should be backbreak no less than 0.5m, laying Blotter(Thickness is no less than 0.5m), and carry out compacting processing by relevant specification.
The advantage of the present invention is also embodied in when the gradient of gob floor 6 is larger, the empty highly larger, goaf in goaf The processing that full water, goaf are in circumstance of flowing water, several situations of the above all can cause conventional grouting treatment to have slip casting Amount increase, the low shortcoming of slurries calculus rate, and can also be in the presence of the disturbance and dirt to underground water when administering water head site goaf Dye.Because there is the constraint of steel pipe in outside when the present invention is administered using steel pipe column engineering method, as shown in Fig. 2 during grouting, slurry is straight Connect and fill into steel pipe, and form male cone body, supporting effect is good, and will not increase construction work amount, realizes preferable regulation effect.

Claims (6)

1. a kind of steel pipe column handles goaf engineering method, the engineering method comprises the steps of:
Step 1:With reference to proposed place goaf distribution characteristics, surrounding enviroment condition and building characteristic, the plane of drilling is designed Arrangement and depth;
Step 2:Hole structure is designed by 1 ~ 2 reducing from aperture to bottom hole according to drilling depth and Rock And Soil intensity, i.e., certainly Upper and lower boring aperture is gradually reduced 1 ~ 2 grade;
It is characterized in that, further comprising the steps of:
Step 3:The rear tripping in protection pipe of below bedrock surface is drilled into using large aperture in soil layer, decomposed rock, prevents hole wall collapse;
Step 4:Reduce bore diameter and continue to drill through goaf to 1 ~ 2 meter of gob floor;
Step 5:To bottom hole, described seamless steel pipe top exceedes goaf top plate and is no less than 2 meters tripping in seamless steel pipe;
Step 6:To after bottom hole under seamless steel pipe, mixed microlith is irrigated into hole to seamless steel pipe bottom under concreting conduit Solidifying soil fills out at the top of perfusion to seamless steel pipe 3 ~ 5 meters, forms male cone body.
A kind of 2. steel pipe column processing goaf engineering method according to claim 1, it is characterised in that:In described step 4 also Including tripping in drilling well Image-forming instrument peephole inwall integrated degree.
A kind of 3. steel pipe column processing goaf engineering method according to claim 2, it is characterised in that:Seen in described step 4 The method of gaging hole inwall integrated degree is:Tripping in ultrasonic probe, to hole wall around the transmitting of 360 degree of spatial dimensions and receive ultrasound Signal, the geological condition of country rock in the range of 0.5 meter around whole drilling is scanned, by speed, amplitude, the frequency of analyzing ultrasonic wave The integrity degree of borehole wall is analyzed.
A kind of 4. steel pipe column processing goaf engineering method according to claim 1, it is characterised in that:In described seamless steel pipe Side is provided with external screw thread.
A kind of 5. steel pipe column processing goaf engineering method according to claim 1, it is characterised in that:In described step 5, under Before entering seamless steel pipe, nitrolite is put into 3 ~ 5 meters of goaf top plate, aperture is expanded by explosion, so as to increase anchor in step 6 The volume of cock body.
A kind of 6. steel pipe column processing goaf engineering method according to claim 1, it is characterised in that:Described steel pipe column processing Goaf engineering method also includes step 7:After seamless steel pipe inner concrete initial set, into hole, perfusion mortar carries out sealing of hole.
CN201710773329.5A 2017-08-31 2017-08-31 Construction method for treating goaf by steel pipe column Active CN107339122B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710773329.5A CN107339122B (en) 2017-08-31 2017-08-31 Construction method for treating goaf by steel pipe column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710773329.5A CN107339122B (en) 2017-08-31 2017-08-31 Construction method for treating goaf by steel pipe column

Publications (2)

Publication Number Publication Date
CN107339122A true CN107339122A (en) 2017-11-10
CN107339122B CN107339122B (en) 2020-02-11

Family

ID=60214943

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710773329.5A Active CN107339122B (en) 2017-08-31 2017-08-31 Construction method for treating goaf by steel pipe column

Country Status (1)

Country Link
CN (1) CN107339122B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939280A (en) * 2017-11-14 2018-04-20 中国科学院寒区旱区环境与工程研究所 Drilling rig and boring method
CN110425004A (en) * 2019-08-16 2019-11-08 徐州中国矿大岩土工程新技术发展有限公司 The floated guide and construction method in the underwater goaf of paste body filling
CN110672062A (en) * 2019-08-23 2020-01-10 广州市地质调查院(广州市地质环境监测中心) Embedding method of monitoring points for monitoring settlement of bedrock
CN112855029A (en) * 2021-04-26 2021-05-28 中铁九局集团第七工程有限公司 Goaf drilling external pipe expansion construction method
CN114108609A (en) * 2021-09-29 2022-03-01 华北水利水电大学 Goaf multistage subsection precise filling deep pile-forming construction process and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101122131A (en) * 2007-08-14 2008-02-13 蓝冰 Foundation pit supporting pile using pipe casting pile embedding in rock
CN101906991A (en) * 2010-07-19 2010-12-08 刘清洁 Construction method for managing underground mined-out area or cavity
CN102425155A (en) * 2011-08-29 2012-04-25 北京科技大学 Method for reinforcing overlying shallow rockmass in mined-out area
CN102877865A (en) * 2012-09-10 2013-01-16 刘清洁 Construction method for treating underground gob or cavity
CN103147435A (en) * 2013-02-23 2013-06-12 西山煤电建筑工程集团有限公司 Method for treating construction engineering foundation in gob
CN104563147A (en) * 2014-08-29 2015-04-29 上海市政工程设计研究总院(集团)有限公司 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101122131A (en) * 2007-08-14 2008-02-13 蓝冰 Foundation pit supporting pile using pipe casting pile embedding in rock
CN101906991A (en) * 2010-07-19 2010-12-08 刘清洁 Construction method for managing underground mined-out area or cavity
CN102425155A (en) * 2011-08-29 2012-04-25 北京科技大学 Method for reinforcing overlying shallow rockmass in mined-out area
CN102877865A (en) * 2012-09-10 2013-01-16 刘清洁 Construction method for treating underground gob or cavity
CN103147435A (en) * 2013-02-23 2013-06-12 西山煤电建筑工程集团有限公司 Method for treating construction engineering foundation in gob
CN104563147A (en) * 2014-08-29 2015-04-29 上海市政工程设计研究总院(集团)有限公司 Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李永栋: "利用钢套管施工钻孔灌注桩穿越采空区的方法介绍", 《工程勘察》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939280A (en) * 2017-11-14 2018-04-20 中国科学院寒区旱区环境与工程研究所 Drilling rig and boring method
CN110425004A (en) * 2019-08-16 2019-11-08 徐州中国矿大岩土工程新技术发展有限公司 The floated guide and construction method in the underwater goaf of paste body filling
CN110672062A (en) * 2019-08-23 2020-01-10 广州市地质调查院(广州市地质环境监测中心) Embedding method of monitoring points for monitoring settlement of bedrock
CN112855029A (en) * 2021-04-26 2021-05-28 中铁九局集团第七工程有限公司 Goaf drilling external pipe expansion construction method
CN114108609A (en) * 2021-09-29 2022-03-01 华北水利水电大学 Goaf multistage subsection precise filling deep pile-forming construction process and method
CN114108609B (en) * 2021-09-29 2023-03-10 华北水利水电大学 Construction method for multistage segmented precise filling and deep pile forming in goaf

Also Published As

Publication number Publication date
CN107339122B (en) 2020-02-11

Similar Documents

Publication Publication Date Title
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN107339122A (en) A kind of steel pipe column handles goaf engineering method
CN104564128B (en) A kind of shallow-depth-excavation tunnel construction deformation monitoring method
CN111305876A (en) Deep roadway anchoring-splitting grouting-hydraulic fracturing pressure relief cooperative control method
CN106014423B (en) The excavation and method for protecting support of a kind of shallow coal level lane
CN106121661A (en) A kind of tunnel trunk is by loess separating surface water rich strata construction method
CN109899089A (en) Goaf grouting method based on pinniform horizontal branch directional drilling technique
CN110685714B (en) Micro-step reserved core soil construction structure and method for shallow-buried bias tunnel under phyllite geology
CN106245626A (en) A kind of hard formation churning driven enters method
CN110617072B (en) Tunnel excavation construction method for obliquely passing existing operation tunnel at minimum clear distance
CN108194132B (en) A kind of pier formula multi-arch type Mined-out Area control method
CN103899351B (en) A kind of filling reinforcement means of processing complicated cavity
CN108915736A (en) The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN113027462B (en) Reinforcing method for shaft penetrating through weak surrounding rock
CN103628912A (en) Goaf management filling grouting construction method
CN105862721B (en) A kind of high building structure reinforcement and rectification that is applied to has the slip casting composite foundation and its construction method of adjustability embedded steel tube
CN109487804A (en) The low disturbance reinforcement protection system of red soft rock cut slope and construction method
CN106979012A (en) Hidden conduit pipe Comprehensive Treatment method in shaft of vertical well freezing hole
CN105971630B (en) A kind of shallow coal level lane roof collapse prevention and controls
CN108374672B (en) A method of reinforcing Deep Mine soft coal level roadway surrounding rock
CN110173301A (en) Fully mechanized mining goaf grouting method based on cluster type multilateral well directional drilling
CN108487286A (en) A kind of construction method of the continuous supporting course of beading karst region super long pile
CN104695458A (en) Construction method of deep stirring and jet grouting compound pile waterproof curtain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 221000 10th floor, building C6, Xuzhou Software Park, No. 6, Software Park Road, Quanshan District, Xuzhou City, Jiangsu Province

Patentee after: Xuzhou Zhongkuang geotechnical Technology Co.,Ltd.

Address before: Room 101, unit 1, building 1, science and Technology Incubation Center, National University Science and Technology Park, China University of mining and technology, Xuzhou City, Jiangsu Province

Patentee before: CUMT GEOTECHNICAL ENGINEERING & NEW TECHNOLOGY DEVELOPMENT Co.,Ltd.

CP03 Change of name, title or address