CN107956484B - The ruggedized construction and construction method of existing shield tunnel Deformation control - Google Patents

The ruggedized construction and construction method of existing shield tunnel Deformation control Download PDF

Info

Publication number
CN107956484B
CN107956484B CN201711193765.1A CN201711193765A CN107956484B CN 107956484 B CN107956484 B CN 107956484B CN 201711193765 A CN201711193765 A CN 201711193765A CN 107956484 B CN107956484 B CN 107956484B
Authority
CN
China
Prior art keywords
drilling
shield tunnel
drilling machine
engineering method
existing shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201711193765.1A
Other languages
Chinese (zh)
Other versions
CN107956484A (en
Inventor
蔡昕宸
刘阳
唐新军
王亚明
申浩
吴先勇
郭新平
田军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Urban Rail Transit Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN201711193765.1A priority Critical patent/CN107956484B/en
Publication of CN107956484A publication Critical patent/CN107956484A/en
Application granted granted Critical
Publication of CN107956484B publication Critical patent/CN107956484B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses the ruggedized construction of existing shield tunnel Deformation control and construction methods, this method comprises: label need to establish the drilling position of engineering method stake;It is drilled using drilling machine to the first drilling position;After first drilling position reaches predetermined depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;After the completion of first engineering method stake, drilled using drilling machine to the second drilling position, wherein the second drilling position is located at the opposite side of the first drilling position;After second drilling position reaches predetermined depth, slip casting is carried out to the second drilling position, to form the second engineering method stake being cross-linked with the first engineering method stake;And so on, until the foundation of all engineering method stakes is completed, to constitute the reinforcement system of existing shield tunnel.The present invention effectively avoids the deformation of existing shield tunnel, while the influence to ground is smaller.

Description

The ruggedized construction and construction method of existing shield tunnel Deformation control
Technical field
The present invention relates to existing shield tunnel reinforcement construction technology field, more specifically a kind of existing shield tunnel becomes The ruggedized construction and construction method of shape control.
Background technique
In recent years, a large amount of subway network has been built in many cities in China, due to the long-term settlement of subway itself and neighbouring Tunnel subsidence caused by field construction or floating influence the safe operation of subway, so reinforcement measure must be taken to reduce Influence of the excavation of foundation pit to existing tunnel.
Currently, domestic some subway work units propose the method for some control existing shield tunnel deformations, such as soil Body grouting strengthening method.Not only boundary of works area is wider for this reinforcement means, and enforcement difficulty is larger, and consolidation effect is difficult to ensure, and The influence of adjacent piles is difficult to control when construction.Therefore it is required to invention and finds out a kind of more cost-effective reinforcement means Control the deformation of existing shield tunnel.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide the ruggedized constructions of existing shield tunnel Deformation control And construction method.
To achieve the above object, the invention adopts the following technical scheme: existing shield tunnel Deformation control ruggedized construction Construction method, which comprises
Label need to establish the drilling position of engineering method stake;
It is drilled using drilling machine to the first drilling position;
After first drilling position reaches predetermined depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;
After the completion of first engineering method stake, drilled using drilling machine to the second drilling position, wherein the second drilling position is located at first The opposite side of drilling position;
After second drilling position reaches predetermined depth, slip casting is carried out to the second drilling position, is interlocked with being formed with the first engineering method stake Second engineering method stake of connection;
And so on, until the foundation of all engineering method stakes is completed, to constitute the reinforcement system of existing shield tunnel.
Its further technical solution are as follows: it is described using drilling machine to first drilling position drill the step of, specifically include with Lower step:
Start drilling machine;
Drill bit of drilling machine is pressed into the soil body at an oblique angle;
It is pressed into during the soil body, certain interval of time is needed to promote drilling machine drilling pipe;
Cutting soil, until stopping when drill bit of drilling machine reaches predetermined depth.
Its further technical solution are as follows: the tilt angle and the angle on ground of the favourable turn drill bit are 30 °~60 °.
Its further technical solution are as follows: the step cutting soil, until when drill bit of drilling machine reaches predetermined depth in stopping, When the soil property of cutting soil is harder, the pump of water pipe and drilling machine is connected.
Its further technical solution are as follows: after first drilling position reaches predetermined depth, slip casting is carried out to the first drilling position, With the step of forming the first engineering method stake, specifically includes the following steps:
Open the reflux stomata and reflux high-pressure pump of drilling machine;
Open the mud valve of drilling machine;
Open high pressure water dredge pump and air compressor machine;
The downward 180 ° of high pressure jet groutings of gunniting hole.
Its further technical solution are as follows: it is described open drilling machine reflux stomata and reflux high-pressure pump the step of and the opening It is further comprised the steps of: between the step of mud valve of drilling machine
Confirm whether plasma discharge is normal, if normal, then opens the mud valve of drilling machine, if abnormal, then until plasma discharge is normal When, open the mud valve of drilling machine.
Its further technical solution are as follows: the drilling machine is MJS drilling machine.
Its further technical solution are as follows: the engineering method stake is semicylinder shape.
Its further technical solution are as follows: the diameter of the engineering method stake is 0.8~1.1 meter.
The ruggedized construction of existing shield tunnel Deformation control, it is described to add including the ruggedized construction being set to below shield tunnel Fixing structure includes the semi-cylindrical engineering method stake of interconnection;The angle on the engineering method stake and ground is 30 °~60 °;The engineering method The diameter of stake is 0.8~1.1 meter.
Compared with the prior art, the invention has the advantages that: existing shield tunnel Deformation control ruggedized construction of the present invention Construction method performs a reinforcing area below to existing shield tunnel, reinforcing area by two rows of certain angles diagonally downward Engineering method stake is intersected with each other to be formed by overlapping, and engineering method stake is first punched by MJS drilling machine, grouting behind shaft or drift lining and formed, sound construction, effectively The deformation of existing shield tunnel is avoided, while the influence to ground is smaller.
The above description is only an overview of the technical scheme of the present invention, can in order to better understand technical measure It is implemented in accordance with the contents of the specification, and in order to make above and other objects of the present invention, feature and advantage brighter Show understandable, special below to lift preferred embodiment, detailed description are as follows.
Detailed description of the invention
Fig. 1 is the flow chart of the construction method specific embodiment of existing shield tunnel Deformation control ruggedized construction of the present invention;
Fig. 2 is the stream that drills in the construction method specific embodiment of existing shield tunnel Deformation control ruggedized construction of the present invention Cheng Tu;
Fig. 3 is the stream of slip casting in the construction method specific embodiment of existing shield tunnel Deformation control ruggedized construction of the present invention Cheng Tu;
Fig. 4 is the perspective view of the ruggedized construction specific embodiment of existing shield tunnel Deformation control of the present invention;
Fig. 5 is the structural schematic diagram of the ruggedized construction specific embodiment of existing shield tunnel Deformation control of the present invention;
Fig. 6 is the structural representation of engineering method stake in the ruggedized construction specific embodiment of existing shield tunnel Deformation control of the present invention Figure.
Appended drawing reference
1, ground;2, Grouting Pipe;3, engineering method stake;4, existing shield tunnel;5, the soil body.
Specific embodiment
In order to more fully understand technology contents of the invention, combined with specific embodiments below to technical solution of the present invention into One step introduction and explanation, but not limited to this.
Specific embodiment shown in Fig. 1-3 is please referred to, a kind of existing shield tunnel Deformation control is present embodiments provided and adds The construction method of fixing structure, method include:
S10, label need to establish the drilling position of engineering method stake;
S20, it is drilled using drilling machine to the first drilling position;
After S30, the first drilling position reach predetermined depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;
After the completion of S40, the first engineering method stake, drilled using drilling machine to the second drilling position, wherein the second drilling position is located at The opposite side of first drilling position;
After S50, the second drilling position reach predetermined depth, slip casting is carried out to the second drilling position, to be formed and the first engineering method stake The second engineering method stake being cross-linked;
S60, and so on, until the foundation of all engineering method stakes is completed, to constitute the reinforcement system of existing shield tunnel.
For above-mentioned step S10, the mode of label can mark the position of drilling using infrared ray, or use stone Ash sketches the contours of the general profile of a bore position.
For above-mentioned step S20, before drilling machine is drilled, drilling machine need to be transported into hole site, connect power supply And data line, open oil pump.Drill bit of drilling machine is connected with pressure monitor display in ground, condition of the confirmation drill bit of drilling machine in no-load Lower clearing.Again to stacks and drill bit of drilling machine, it is ensured that the leakproofness of sealing ring when docking, while checking whether pressure shows in ground Show normal.
The first engineering method stake is needed to reach hardness requirement before second drilling position is drilled above-mentioned step S40 And then carry out the drilling of the second drilling position.
For above-mentioned step S60, after the second engineering method stake is completed, slip casting, third drilling are carried out to third drilling position Positioned at first drilling position the same side, the 4th drilling position is located at the opposite side that third bores vacancy.Upper drilling position slip casting completes it Afterwards, it is formed after engineering method stake, just next drilling position is operated.
Further, for above-mentioned step S20, in certain embodiments, specifically includes the following steps:
S201, starting drilling machine;
S202, drill bit of drilling machine are pressed into the soil body at an oblique angle;
During S203, the indentation soil body, certain interval of time is needed to promote drilling machine drilling pipe;
S204, cutting soil, until stopping when drill bit of drilling machine reaches predetermined depth.
For above-mentioned steps S201, the case where when starting need to observe surrounding, if there are security risks, and it is hidden that safety need to be discharged After trouble, drilling machine could be started.
For above-mentioned step S202, drill bit of drilling machine is pressed into the soil body with 45 ° of angle, in order to protect the peace of surrounding people Entirely, surrounding staff needs the security settings such as safe wearing cap.
For step S203, soil block blocks drill bit of drilling machine in order to prevent, needs certain interval of time that will promote drilling pipe.
Specifically, in step S204, encounter cutting soil soil property it is harder when, need to connect the pump of water pipe and drilling machine It connects, to drench the soil body, smoothly works convenient for drilling machine.
Further, for above-mentioned step S30, in certain embodiments, specifically includes the following steps:
S301, the reflux stomata for opening drilling machine and reflux high-pressure pump;
S302, the mud valve for opening drilling machine;
S303, high pressure water dredge pump and air compressor machine are opened;
The downward 180 ° of high pressure jet groutings of S304, gunniting hole.
Specifically, also needing confirm whether plasma discharge is normal between step S301 and step S302, if normal, then brill is opened The mud valve of machine, if abnormal, then until opening the mud valve of drilling machine when plasma discharge is normal.
Preferably, drilling machine uses MJS drilling machine.Engineering method stake is semicylinder shape.The diameter of engineering method stake is 1 meter.
In summary: the construction method of existing shield tunnel Deformation control ruggedized construction of the present invention is to existing shield tunnel Lower section performs a reinforcing area, and reinforcing area is formed by overlapping by the engineering method stake of two rows of certain angles diagonally downward is intersected with each other, Engineering method stake is first punched by MJS drilling machine, grouting behind shaft or drift lining and formed, sound construction, effectively avoid the change of existing shield tunnel Shape, while the influence to ground is smaller.
Specific embodiment described in Fig. 4-6 is please referred to, the present embodiment additionally provides a kind of using existing shield tunnel deformation Control ruggedized construction used by the construction method of ruggedized construction comprising the semi-cylindrical engineering method stake of interconnection;Engineering method stake Angle with ground is 30 °~60 °;The diameter of engineering method stake is 0.8~1.1 meter.
Specifically, the forming process of engineering method stake is first to use drilling machine from the drilling position on ground 1 to 5 internal drilling of the soil body, then lead to The slip casting into drilling position of Grouting Pipe 2 is crossed, is waited for a period of time, the slurry solidification to drill in position, to form engineering method stake 3.Engineering method stake 3 Interconnection setting, stability is preferable, and the stability of existing shield tunnel 4 has been effectively ensured, and avoids deforming.
In summary: existing shield tunnel Deformation control ruggedized construction of the present invention performs one below to existing shield tunnel A reinforcing area, reinforcing area are formed by overlapping by the engineering method stake of two rows of certain angles diagonally downward is intersected with each other, and engineering method stake passes through MJS drilling machine is first punched, grouting behind shaft or drift lining and formed, sound construction, effectively avoid the deformation of existing shield tunnel, while over the ground The influence in face is smaller.
It is above-mentioned that technology contents of the invention are only further illustrated with embodiment, in order to which reader is easier to understand, but not It represents embodiments of the present invention and is only limitted to this, any technology done according to the present invention extends or recreation, by of the invention Protection.Protection scope of the present invention is subject to claims.

Claims (9)

1. the construction method of existing shield tunnel Deformation control ruggedized construction, which is characterized in that the existing shield tunnel deformation The ruggedized construction of control includes the ruggedized construction below shield tunnel, and the ruggedized construction includes the semicolumn of interconnection Shape engineering method stake;The angle on the engineering method stake and ground is 30 °~60 °;The described method includes:
Label need to establish the drilling position of engineering method stake;
It is drilled using drilling machine to the first drilling position;
After first drilling position reaches predetermined depth, slip casting is carried out to the first drilling position, to form the first engineering method stake;
After the completion of first engineering method stake, drilled using drilling machine to the second drilling position, wherein the second drilling position is located at the first drilling The opposite side of position;
After second drilling position reaches predetermined depth, slip casting is carried out to the second drilling position, is cross-linked with being formed with the first engineering method stake The second engineering method stake;
And so on, until the foundation of all engineering method stakes is completed, to constitute the reinforcement system of existing shield tunnel.
2. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, which is characterized in that institute The step of drilling using drilling machine to the first drilling position is stated, specifically includes the following steps:
Start drilling machine;
Drill bit of drilling machine is pressed into the soil body at an oblique angle;
It is pressed into during the soil body, certain interval of time is needed to promote drilling machine drilling pipe;
Cutting soil, until stopping when drill bit of drilling machine reaches predetermined depth.
3. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 2, which is characterized in that institute The angle of the tilt angle and ground of stating drill bit of drilling machine is 30 °~60 °.
4. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 2, which is characterized in that institute Step cutting soil is stated, until stopping when drill bit of drilling machine reaches predetermined depth, when the soil property of cutting soil is harder, by water pipe and is bored The pump of machine connects.
5. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, which is characterized in that institute It states after the first drilling position reaches predetermined depth, slip casting is carried out to the first drilling position, it is specific to wrap the step of to form the first engineering method stake Include following steps:
Open the reflux stomata and reflux high-pressure pump of drilling machine;
Open the mud valve of drilling machine;
Open high pressure water dredge pump and air compressor machine;
The downward 180 ° of high pressure jet groutings of gunniting hole.
6. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 5, which is characterized in that institute It is also wrapped between the step of the step of stating the reflux stomata for opening drilling machine and reflux high-pressure pump and the mud valve for opening drilling machine Include step:
Confirm whether plasma discharge is normal, if normal, then opens the mud valve of drilling machine, if abnormal, then until beating when plasma discharge is normal It spuds in the mud valve of machine.
7. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, which is characterized in that institute Stating drilling machine is MJS drilling machine.
8. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, which is characterized in that institute Stating engineering method stake is semicylinder shape.
9. the construction method of existing shield tunnel Deformation control ruggedized construction according to claim 1, which is characterized in that institute The diameter for stating engineering method stake is 0.8~1.1 meter.
CN201711193765.1A 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control Expired - Fee Related CN107956484B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711193765.1A CN107956484B (en) 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711193765.1A CN107956484B (en) 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control

Publications (2)

Publication Number Publication Date
CN107956484A CN107956484A (en) 2018-04-24
CN107956484B true CN107956484B (en) 2019-08-27

Family

ID=61961717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711193765.1A Expired - Fee Related CN107956484B (en) 2017-11-24 2017-11-24 The ruggedized construction and construction method of existing shield tunnel Deformation control

Country Status (1)

Country Link
CN (1) CN107956484B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685205A (en) * 2021-09-22 2021-11-23 中铁隧道股份有限公司 Rotary spraying lifting structure and construction method
CN116044455B (en) * 2023-04-03 2023-06-23 湖南大学 Grouting system for directional reinforcement of tunnel

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202215256U (en) * 2011-09-23 2012-05-09 中铁十二局集团第三工程有限公司 Reinforcing structure for fine sand layer of tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed through advanced processing of weathered ball by percussion drill within shield tunneling range
CN103924987A (en) * 2014-04-24 2014-07-16 中铁十一局集团城市轨道工程有限公司 SMW pile shielding portal waterproof structure and construction method thereof
CN204676562U (en) * 2015-05-28 2015-09-30 中国二十冶集团有限公司 One encloses purlin and SMW engineering method stake connection reinforcing structure
CN105297797A (en) * 2015-11-30 2016-02-03 浙江华展工程研究设计院有限公司 Hoop support form for in-situ protection of existing building in underground space development
CN105298517A (en) * 2015-11-21 2016-02-03 中铁二十局集团第二工程有限公司 Soft and weak wall rock tunnel advance reinforced support construction method
CN205242388U (en) * 2015-12-23 2016-05-18 中铁十二局集团有限公司 Enhancement mode SMW worker method pilework
CN205778878U (en) * 2016-05-13 2016-12-07 中铁二十三局集团第一工程有限公司 A kind of supporting construction being applicable to large-section box culvert jacking crossing construction
CN107091095A (en) * 2017-06-19 2017-08-25 中建隧道建设有限公司 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield
CN107366282A (en) * 2017-07-11 2017-11-21 北京市政建设集团有限责任公司 A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202215256U (en) * 2011-09-23 2012-05-09 中铁十二局集团第三工程有限公司 Reinforcing structure for fine sand layer of tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed through advanced processing of weathered ball by percussion drill within shield tunneling range
CN103924987A (en) * 2014-04-24 2014-07-16 中铁十一局集团城市轨道工程有限公司 SMW pile shielding portal waterproof structure and construction method thereof
CN204676562U (en) * 2015-05-28 2015-09-30 中国二十冶集团有限公司 One encloses purlin and SMW engineering method stake connection reinforcing structure
CN105298517A (en) * 2015-11-21 2016-02-03 中铁二十局集团第二工程有限公司 Soft and weak wall rock tunnel advance reinforced support construction method
CN105297797A (en) * 2015-11-30 2016-02-03 浙江华展工程研究设计院有限公司 Hoop support form for in-situ protection of existing building in underground space development
CN205242388U (en) * 2015-12-23 2016-05-18 中铁十二局集团有限公司 Enhancement mode SMW worker method pilework
CN205778878U (en) * 2016-05-13 2016-12-07 中铁二十三局集团第一工程有限公司 A kind of supporting construction being applicable to large-section box culvert jacking crossing construction
CN107091095A (en) * 2017-06-19 2017-08-25 中建隧道建设有限公司 Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield
CN107366282A (en) * 2017-07-11 2017-11-21 北京市政建设集团有限责任公司 A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique

Also Published As

Publication number Publication date
CN107956484A (en) 2018-04-24

Similar Documents

Publication Publication Date Title
CA3084096C (en) Fracturing relief method for stress concentration of remaining ore pillars in overlying goaf
CN101737060B (en) Beneath-soil through-tunnel superlarge diameter pipe curtain construction method
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN102182472B (en) Backfill repairing method for tunnel collapse cavity
CN103510957B (en) A kind of combined type coal uncovering method
CN101514637B (en) Execution system of gas tunnel outburst prevention comprehensive measures
CN104453913A (en) Vertical shaft working face ahead pre-grouting method
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN111734420B (en) Water-rich stratum shield underwater receiving method provided with tunnel portal mortar retaining wall
CN108661650A (en) A kind of rich water magmatic body area depth pozo shaft construction method
CN104594919A (en) Soft rock roadway buffering tapered double strong shell support system and construction method thereof
CN106401645A (en) Pressure-relief support coordination control method for deep high-stress tunnel based on borehole pressure relief
CN103835651A (en) Single-hole directional drilling local grouting raise boring technology
CN106545007A (en) The method of pile in stratum of the bottom for hard rock stratum
CN107956484B (en) The ruggedized construction and construction method of existing shield tunnel Deformation control
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN107420104A (en) The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter
CN101979835B (en) Method for preventing coal and gas burst by drill communicated coal mining exhaust
CN109989756B (en) Method for preventing water inrush and sand collapse of thick-surface-soil thin-bedrock drilling shaft
CN110454164A (en) Impulsion pressure tunnel buffering energy-absorbing band waterpower pre-setting method
CN102220764A (en) Deep foundation pit bracing system and construction method thereof
KR100835597B1 (en) filling method by blasting and groutting
CN102758443B (en) Novel enclosing structure applicable to connection change between new pipes and old pipes and construction method thereof
CN104929564A (en) High-pressure water hole grouting and feeding device
CN1013132B (en) Post grouting process for water bearing sand strata behind the wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190827

Termination date: 20211124

CF01 Termination of patent right due to non-payment of annual fee