CN111733839A - A method for strengthening the receiving end of the water-rich sand layer of the shield deep-buried close to the excavation foundation pit - Google Patents
A method for strengthening the receiving end of the water-rich sand layer of the shield deep-buried close to the excavation foundation pit Download PDFInfo
- Publication number
- CN111733839A CN111733839A CN202010547520.XA CN202010547520A CN111733839A CN 111733839 A CN111733839 A CN 111733839A CN 202010547520 A CN202010547520 A CN 202010547520A CN 111733839 A CN111733839 A CN 111733839A
- Authority
- CN
- China
- Prior art keywords
- construction
- reinforcement
- internal
- mjs
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/001—Improving soil or rock, e.g. by freezing; Injections
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Soil Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
技术领域technical field
本发明涉及盾构隧道施工技术领域,具体为一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法。The invention relates to the technical field of shield tunnel construction, in particular to a method for reinforcing a receiving end of a shield tunnel with water-rich sand layers that is deeply buried next to an excavation foundation pit.
背景技术Background technique
随着我国基础设施建设快速发展,盾构法施工以其安全性和高效性在城市地铁和污水隧道施工中得到了广泛的应用。盾构接收是盾构施工过程中最主要的风险点之一,而控制该风险的关键是选择合适的盾构接收端头加固方案。With the rapid development of infrastructure construction in my country, shield construction has been widely used in the construction of urban subways and sewage tunnels due to its safety and efficiency. Shield receiving is one of the most important risk points in the process of shield construction, and the key to controlling this risk is to choose an appropriate reinforcement scheme for the receiving end of the shield.
传统的端头加固方法如高压旋喷桩、CSM搅拌墙、素地连墙及降水井单一或其中两种相互叠加使用,均有自身的局限性,即难以保证基坑同步开挖的安全性,也难以在大深度富水砂层中达到预期加固效果。The traditional end reinforcement methods, such as high-pressure rotary jetting piles, CSM mixing walls, plain connecting walls and dewatering wells used alone or in combination with each other, have their own limitations, that is, it is difficult to ensure the safety of synchronous excavation of foundation pits. It is also difficult to achieve the expected reinforcement effect in the deep water-rich sand layer.
发明内容SUMMARY OF THE INVENTION
为了克服现有技术中传统端头加固方法难以保证基坑同步开挖的安全性,以及难以在大深度富水砂层达到预期加固效果的技术缺陷,本发明提供了一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,可根据场地和竖井情况适时调整,特别适用于超深基坑、超厚砂层、超高承压水等不良地质条件下的端头加固施工,解决了上述技术问题。In order to overcome the technical defects that the traditional end reinforcement method in the prior art is difficult to ensure the safety of synchronous excavation of the foundation pit, and it is difficult to achieve the expected reinforcement effect in the large-depth water-rich sand layer, the present invention provides a method for excavating the foundation pit next to the foundation pit. The reinforcement method of the receiving end of the water-rich sand layer of the deep-buried shield tunnel can be adjusted in time according to the site and shaft conditions, and is especially suitable for the reinforcement of the end under adverse geological conditions such as ultra-deep foundation pits, ultra-thick sand layers, and ultra-high confined water. The construction solves the above technical problems.
本发明通过以下技术方案来实现上述目的,一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,包括以下施工步骤:The present invention achieves the above object through the following technical solutions, a method for reinforcing the receiving end of the water-rich sand layer of a shield deep buried in close proximity to the excavation foundation pit, comprising the following construction steps:
S1:端头加固组合形式及相关参数的设计:S1: Design of the end reinforcement combination form and related parameters:
根据传统加固方法并结合加固区域的情况对端头加固组合形式及相关参数进行设计,设计加固理念为以双层堵水为主,以内外降水为辅,即采用内部MJS工法桩进行内层堵水,采用U型素地连墙作为外层堵水,并在内部MJS工法桩与U型素地连墙的中间位置设置有内部疏干降水井,在U型素地连墙的外围设置有外部降水井;According to the traditional reinforcement method and combined with the situation of the reinforcement area, the end reinforcement combination form and related parameters are designed. The design reinforcement concept is to focus on double-layer water plugging, supplemented by internal and external precipitation, that is, internal MJS construction method piles are used for inner layer plugging. For water, the U-shaped plain-ground connecting wall is used as the outer layer for water blocking, and an internal draining and dewatering well is set in the middle of the internal MJS construction method pile and the U-shaped plain-ground connecting wall, and an external dewatering well is set on the periphery of the U-shaped plain-ground connecting wall. ;
S2:采用工法桩专用设备进行内部MJS工法桩加固体的施工:S2: Use special equipment for construction method piles to carry out the construction of internal MJS construction method pile reinforcement:
采用引孔机、MJS工法主机并配备水泥罐、高压泵、清水泵、挖掘机根据内部MJS工法桩分布情况合理进行工法桩施工,施工步骤主要为:导向钻头下钻成孔→套管放置→工法桩钻头从套管中下钻至底→套管分节回拔及喷浆至桩顶;Adopt hole-guiding machine, MJS construction method host and equipped with cement tank, high pressure pump, clean water pump and excavator to carry out construction method pile construction reasonably according to the internal MJS construction method pile distribution. The construction method pile drill bit is drilled from the casing to the bottom → the casing is pulled back in sections and sprayed to the top of the pile;
S3:采用成槽机进行外围U型素地连墙的施工:S3: Use the slotting machine to construct the peripheral U-shaped plain wall:
采用成槽机配备泥浆系统、锁口管、导管根据素墙分幅情况进行跳幅施工;The slotting machine is equipped with a mud system, a locking pipe and a conduit to perform the amplitude jumping construction according to the framing conditions of the plain wall;
S4:在U型素地连墙薄弱处外围进行素墙接缝处MJS工法桩的加固施工:S4: The reinforcement construction of MJS construction method piles at the joints of the plain wall is carried out on the periphery of the weak part of the U-shaped plain-ground connecting wall:
对U型素地连墙接缝位置外侧的素墙接缝处MJS工法桩进行局部加固处理,施工步骤与内部MJS工法桩一致;The MJS construction method piles at the joints of the plain wall outside the U-shaped plain-ground connecting wall are partially reinforced, and the construction steps are the same as those of the internal MJS construction method piles;
S5:采用反循环钻进行U型素地连墙内外降水井的施工:S5: Reverse circulation drilling is used for the construction of U-shaped plain ground wall and inner and outer dewatering wells:
根据地质情况采用具备入岩能力的反循环钻进行加固区域降水井施工。According to the geological conditions, the reverse circulation drill with rock penetration ability is used to construct the dewatering well in the reinforcement area.
上述的一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,所述内部MJS工法桩的成桩加固原理与传统的加固方式如高压旋喷桩、CSM搅拌墙存在较大的差异,高压旋喷桩、CSM搅拌墙是通过搅拌土体注入水泥浆进行混合加固,而MJS工法桩则是先通引孔至桩底,然后下套管,并将工法桩钻头从套管中下钻至底后分节上提并喷射高压力的水泥浆切割周围土体;实现了孔内强制排浆和地内压力监测,同时通过调整强制排浆量来控制地内压力,使深处排泥和地内压力得到合理控制,也就降低了在施工中出现地表变形的可能性,大幅度减弱对环境的影响。The above-mentioned reinforcement method for the receiving end of the shield buried in the water-rich sand layer close to the excavation foundation pit, the pile-forming reinforcement principle of the internal MJS construction method pile is compared with the traditional reinforcement methods such as high-pressure rotary jet piles and CSM mixing walls. The big difference is that the high-pressure jetting pile and the CSM mixing wall are mixed and reinforced by mixing the soil and injecting cement slurry, while the MJS construction method first passes the lead hole to the bottom of the pile, and then sets the casing, and the construction method pile drill bit from the casing. After drilling down to the bottom in the pipe, it is lifted up in sections and sprayed with high-pressure cement slurry to cut the surrounding soil; the forced slurry discharge in the hole and the monitoring of the pressure in the ground are realized. The reasonable control of sludge discharge and pressure in the ground also reduces the possibility of surface deformation during construction and greatly reduces the impact on the environment.
上述的一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,所述U型素地连墙分幅位置采用锁口管进行接缝处理,管壁密贴槽壁,防止混凝土倒灌和绕流。In the above-mentioned method for strengthening the receiving end of the shield buried in the water-rich sand layer of the shield buried close to the excavation foundation pit, the U-shaped plain ground connecting wall is used for joint treatment with a locking pipe, and the pipe wall is closely attached to the groove wall to prevent it. Concrete pour and flow around.
上述的一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,所述U型素地连墙接缝薄弱处进行二次加固处理,提升加固区外侧素墙的挡水能力,增强外围加固体的加固效果。In the above-mentioned method for strengthening the receiving end of a shield buried in a water-rich sand layer close to the excavation foundation pit, the weak joint of the U-shaped plain connecting wall is subjected to secondary reinforcement treatment to improve the water-retaining capacity of the plain wall outside the reinforcement area. , to enhance the reinforcement effect of the peripheral reinforcement.
上述的一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,所述降水井分布于U型素地连墙的内外侧,在承压水由接缝处进入U型素地连墙内部时,外部降水井通过抽排水,降低接缝处局部水头标高,减少进入U型素地连墙内部的地下水水量;U型素地连墙与MJS加固体之间设置内部疏干降水井,能够将进入U型素地连墙内部的地下水及时汇集抽排,从而提升加固区整体质量。In the above-mentioned method for strengthening the receiving end of a shielded water-rich sand layer that is deeply buried next to the excavation foundation pit, the dewatering wells are distributed on the inner and outer sides of the U-shaped plain ground connecting wall, and the confined water enters the U-shaped plain ground through the joint. When inside the connecting wall, the external dewatering wells are pumped and drained to lower the local water head elevation at the joints and reduce the amount of groundwater entering the interior of the U-shaped plain-ground connecting wall. The groundwater entering the U-shaped plain wall can be collected and drained in time, thereby improving the overall quality of the reinforcement area.
上述的一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法,所述内部MJS工法桩的桩径设计值为1.2m,内部MJS工法桩及U型素地连墙底标高低于盾构隧道底标高3.0m以上,降水井底标高与盾构隧道底标高平齐。In the above-mentioned method for strengthening the receiving end of the shield tunnel with water-rich sand layers that are deeply buried in the excavation foundation pit, the design value of the pile diameter of the internal MJS construction method pile is 1.2 m, and the internal MJS construction method pile and the U-shaped plain ground connecting wall bottom mark. The height is more than 3.0m lower than the bottom elevation of the shield tunnel, and the bottom elevation of the dewatering well is the same as the bottom elevation of the shield tunnel.
总体而言,通过本发明所构思的以上技术方案与现有技术相比,可以达到以下有益效果:In general, compared with the prior art, the following beneficial effects can be achieved by the above technical solutions conceived by the present invention:
1、本发明所述的端头加固方法首次将MJS工艺与隧道端头接收加固结合起来,在传统高压旋喷桩+素地连墙+降水井组合形式上进一步优化,创新性的提出MJS工法桩+U型素地连墙+内外降水井组合端头加固方法,摒弃传统单一止水加固理念,形成了以双层堵水为主、以内外降水为辅新的加固理念;1. The end reinforcement method of the present invention combines the MJS process with the tunnel end receiving reinforcement for the first time, and further optimizes the combination form of the traditional high-pressure rotary jet pile + plain ground wall + dewatering well, and innovatively proposes the MJS construction method pile +U-shaped plain ground connecting wall + combined end reinforcement method of internal and external dewatering wells, abandoning the traditional single water stop reinforcement concept, and forming a new reinforcement concept based on double-layer water blocking and supplemented by internal and external precipitation;
2、采用MJS+素墙+降水井组合加固施工方法,能摆脱传统加固方法的局限性,可根据场地和竖井情况适时调整,特别适用于超深基坑、超厚砂层、超高承压水等不良地质条件下的端头加固施工。2. The MJS + plain wall + dewatering well combined reinforcement construction method can get rid of the limitations of traditional reinforcement methods, and can be adjusted in time according to the site and shaft conditions, especially suitable for ultra-deep foundation pits, ultra-thick sand layers, ultra-high confined water End reinforcement construction under adverse geological conditions.
3、本发明所述的端头加固方法在传统加固方法简单的以降堵为主、以降为辅的基础上进一步深化成以双层堵水为主、以内外降水为辅的加固方法,外围素墙和MJS加固体的双重隔水并配合内外降水井降水,达到良好接收环境的效果,新工艺MJS工法桩通过调节地内压力,其在深层的成桩直径和质量优于高压旋喷桩。3. The end reinforcement method of the present invention is further deepened on the basis of the simple traditional reinforcement method, which is mainly based on blockage reduction and supplemented by water reduction. The double water-proof wall and MJS reinforcement and combined with the internal and external dewatering wells for dewatering can achieve the effect of good receiving environment. The new technology MJS construction method can adjust the pressure in the ground, and its deep pile diameter and quality are better than high-pressure rotary jet piles.
4、本发明所述的端头加固方法安全、绿色环保,本工法中的MJS工法桩可通过调整强制排浆量来控制地内压力,有效控制了泥浆漫流和地表变形,竖井同步开挖时,先施工内部MJS工法桩稳固端头地层,再施工外部U型素墙,确保基坑同步开挖安全性。4. The end reinforcement method of the present invention is safe, green and environmentally friendly. The MJS construction method pile in this construction method can control the pressure in the ground by adjusting the amount of forced slurry discharge, effectively controlling the overflow of mud and surface deformation. When the shaft is excavated synchronously, First, the internal MJS construction method piles are constructed to stabilize the stratum at the end, and then the external U-shaped plain wall is constructed to ensure the safety of synchronous excavation of the foundation pit.
附图说明Description of drawings
下面结合附图对本发明的具体实施方式做进一步详细的说明,其中:The specific embodiments of the present invention will be described in further detail below in conjunction with the accompanying drawings, wherein:
图1为本发明一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法的施工流程图;Fig. 1 is a construction flow chart of a method for reinforcing the receiving end of the water-rich sand layer of a shield tunnel deep buried in close proximity to the excavation foundation pit of the present invention;
图2为本发明实施例中端头加固的平面示意图;2 is a schematic plan view of end head reinforcement in an embodiment of the present invention;
图3为本发明实施例中端头加固的断面示意图;Fig. 3 is the cross-sectional schematic diagram of the end head reinforcement in the embodiment of the present invention;
图4为本发明实施例中端头加固止水效果的示意图;4 is a schematic diagram of the water-stop effect of end reinforcement in an embodiment of the present invention;
图中:1-内部MJS工法桩,2-素墙接缝处MJS工法桩,3-U型素地连墙,4-内部疏干降水井,5-外部降水井,6-9#竖井,7-盾构隧道。In the picture: 1-Internal MJS construction method pile, 2-MJS construction method pile at the joint of plain wall, 3-U-shaped plain ground connecting wall, 4-Internal drainage and dewatering well, 5-External dewatering well, 6-9# shaft, 7 - Shield Tunnel.
具体实施方式Detailed ways
如图1所示,为本发明一种紧邻开挖基坑深埋盾构富水砂层接收端头加固方法的施工流程图,该端头加固方法包括以下施工步骤:As shown in Figure 1, it is a construction flow chart of a method for reinforcing the receiving end of the water-rich sand layer of a shield that is deeply buried next to the excavation foundation pit of the present invention, and the end reinforcing method comprises the following construction steps:
步骤一:端头加固组合形式及相关参数的设计:Step 1: Design of the end reinforcement combination form and related parameters:
根据传统加固方法并结合加固区域的情况对端头加固组合形式及相关参数进行设计,设计加固理念为以双层堵水为主,以内外降水为辅,即采用A1200@1000mm内部MJS工法桩1进行内层堵水,采用800mmU型素地连墙3作为外层堵水,并在内部MJS工法桩1与U型素地连墙3的中间位置设置有内部疏干降水井4,在U型素地连墙3的外围设置有外部降水井5,如图2和图3所示,为端头加固的平面示意图和断面示意图。According to the traditional reinforcement method and combined with the situation of the reinforcement area, the end reinforcement combination form and related parameters are designed. The design reinforcement concept is to focus on double-layer water blocking, supplemented by internal and external precipitation, that is, using A1200@1000mm internal MJS construction method pile 1 For inner layer water plugging, the 800mm U-shaped plain
步骤二:采用工法桩专用设备进行内部MJS工法桩1加固体的施工:Step 2: Use the special equipment for construction method piles to carry out the construction of the internal MJS construction method pile 1 reinforcement:
采用引孔机、MJS工法主机并配备水泥罐、高压泵、清水泵、挖掘机根据内部MJS工法桩1分布情况合理进行工法桩施工,施工步骤主要为:导向钻头下钻成孔→套管放置→工法桩钻头从套管中下钻至底→套管分节回拔及喷浆至桩顶。Adopt hole-guiding machine, MJS construction method host and equipped with cement tank, high-pressure pump, clean water pump and excavator to reasonably carry out construction method pile construction according to the distribution of internal MJS construction method pile 1. The construction steps are mainly: drilling down the pilot bit to form a hole → casing placement →The drill bit of the construction method is drilled from the casing to the bottom →the casing is pulled back in sections and sprayed to the top of the pile.
步骤三:采用成槽机进行外围U型素地连墙3的施工:Step 3: Use the slotting machine to construct the peripheral U-shaped plain wall 3:
采用成槽机配备泥浆系统、锁口管、导管根据素墙分幅情况进行跳幅施工,施工步骤主要为:导墙制作→泥浆配置→成槽机成槽→锁口管吊放→混凝土浇筑→锁口管顶拔。The slotting machine is equipped with a mud system, a locking pipe and a conduit to perform amplitude jumping construction according to the sizing of the plain wall. The construction steps are mainly: guide wall production → mud configuration → slotting machine forming a slot → locking pipe hanging → concrete pouring → Pull out the locking tube.
步骤四:在U型素地连墙3薄弱处外围进行素墙接缝处MJS工法桩2的加固施工:Step 4: Carry out the reinforcement construction of the
对U型素地连墙3接缝位置外侧的素墙接缝处MJS工法桩2进行局部加固处理,尤其是U型素地连墙3与9#竖井6冠梁衔接的地方,施工步骤与内部MJS工法桩1一致。Perform local reinforcement treatment on the MJS
步骤五:采用反循环钻进行U型素地连墙3内外降水井的施工:Step 5: Use reverse circulation drilling to construct the inner and outer dewatering wells of U-shaped plain connecting wall 3:
根据地质情况采用具备入岩能力的反循环钻进行加固区域降水井施工,施工步骤主要为:钻进成孔→下井管填滤料→止水封孔洗井→下泵抽水。According to the geological conditions, the reverse circulation drill with rock-penetrating ability is used to construct the dewatering well in the reinforced area. The main construction steps are: drilling into the hole → filling the filter material in the downhole pipe → water stop and sealing the hole and washing the well → pumping down the water.
本发明所述的端头加固方法在传统加固方法简单的以降堵为主、以降为辅的基础上进一步深化成以双层堵水为主、以内外降水为辅的加固方法,外围U型素地连墙3和MJS加固体的双重隔水并配合内外降水井降水,达到良好接收环境的效果,新工艺MJS工法桩通过调节地内压力,其在深层的成桩直径和质量优于高压旋喷桩,如图4所示,为本发明端头加固止水效果的示意图。The end reinforcement method of the present invention is further deepened on the basis of the simple traditional reinforcement method, which is mainly based on blocking reduction and supplemented by reduction, and further deepens into a reinforcement method based on double-layer water blocking and supplemented by internal and external precipitation. The peripheral U-shaped plain ground The double water barrier of connecting
MJS工法桩可通过调整强制排浆量来控制地内压力,有效控制了泥浆漫流和地表变形,9#竖井6同步开挖时,先施工内部MJS工法桩1稳固端头地层,再施工外部U型素地连墙3,确保基坑同步开挖安全性。MJS construction method piles can control the pressure in the ground by adjusting the amount of forced slurry discharge, effectively controlling the mud overflow and surface deformation. When the 9
本领域的技术人员容易理解,以上所述仅为本发明的较佳实施例而已,并不用于限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。Those skilled in the art can easily understand that the above are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention, etc., All should be included within the protection scope of the present invention.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010547520.XA CN111733839A (en) | 2020-06-16 | 2020-06-16 | A method for strengthening the receiving end of the water-rich sand layer of the shield deep-buried close to the excavation foundation pit |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010547520.XA CN111733839A (en) | 2020-06-16 | 2020-06-16 | A method for strengthening the receiving end of the water-rich sand layer of the shield deep-buried close to the excavation foundation pit |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111733839A true CN111733839A (en) | 2020-10-02 |
Family
ID=72649333
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010547520.XA Pending CN111733839A (en) | 2020-06-16 | 2020-06-16 | A method for strengthening the receiving end of the water-rich sand layer of the shield deep-buried close to the excavation foundation pit |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111733839A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112813985A (en) * | 2021-01-04 | 2021-05-18 | 上海市机械施工集团有限公司 | Shallow gas protection method for foundation pit |
| CN115341554A (en) * | 2022-08-30 | 2022-11-15 | 中建八局第三建设有限公司 | Construction method for plugging and reinforcing and protecting underground diaphragm wall with defects under water-rich silt stratum |
| CN115749819A (en) * | 2022-12-07 | 2023-03-07 | 中铁十二局集团第二工程有限公司 | A construction method for small clear distance reception of tunnel segment reinforced shield tunnel |
| CN116695779A (en) * | 2023-06-14 | 2023-09-05 | 中铁隧道集团二处有限公司 | Near existing subway tunnel pipe-jacking receiving well end reinforcing configuration system and method |
| CN117072191A (en) * | 2023-08-14 | 2023-11-17 | 启迪设计集团股份有限公司 | A door reinforcement structure and method for jacking pipes through micro-confined aquifers |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4516878A (en) * | 1981-10-13 | 1985-05-14 | Linde Aktiengesellschaft | Tunnel constructing |
| CN106988753A (en) * | 2017-05-08 | 2017-07-28 | 中建三局基础设施工程有限公司 | A kind of U-shaped plain concrete ground-connecting-wall adds steel bushing shield structure and its method of reseptance |
| CN107091095A (en) * | 2017-06-19 | 2017-08-25 | 中建隧道建设有限公司 | Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield |
| CN108625863A (en) * | 2018-03-21 | 2018-10-09 | 浙江大学城市学院 | A kind of weak soil shield receives control and reinforcement means |
| CN108798686A (en) * | 2018-06-27 | 2018-11-13 | 中铁十二局集团有限公司 | Tunneling boring water-rich sand layer shield receives construction method |
-
2020
- 2020-06-16 CN CN202010547520.XA patent/CN111733839A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4516878A (en) * | 1981-10-13 | 1985-05-14 | Linde Aktiengesellschaft | Tunnel constructing |
| CN106988753A (en) * | 2017-05-08 | 2017-07-28 | 中建三局基础设施工程有限公司 | A kind of U-shaped plain concrete ground-connecting-wall adds steel bushing shield structure and its method of reseptance |
| CN107091095A (en) * | 2017-06-19 | 2017-08-25 | 中建隧道建设有限公司 | Existing tunnel MJS engineering methods stake reinforcement system and construction method are worn under water-rich sand layer shield |
| CN108625863A (en) * | 2018-03-21 | 2018-10-09 | 浙江大学城市学院 | A kind of weak soil shield receives control and reinforcement means |
| CN108798686A (en) * | 2018-06-27 | 2018-11-13 | 中铁十二局集团有限公司 | Tunneling boring water-rich sand layer shield receives construction method |
Non-Patent Citations (2)
| Title |
|---|
| 沈中江: "MJS工法在地铁端头盾构洞口加固的应用", 《绿色科技》 * |
| 贲志江等: "地铁过江隧道大型泥水盾构的水中接收技术", 《南京林业大学学报(自然科学版)》 * |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112813985A (en) * | 2021-01-04 | 2021-05-18 | 上海市机械施工集团有限公司 | Shallow gas protection method for foundation pit |
| CN115341554A (en) * | 2022-08-30 | 2022-11-15 | 中建八局第三建设有限公司 | Construction method for plugging and reinforcing and protecting underground diaphragm wall with defects under water-rich silt stratum |
| CN115749819A (en) * | 2022-12-07 | 2023-03-07 | 中铁十二局集团第二工程有限公司 | A construction method for small clear distance reception of tunnel segment reinforced shield tunnel |
| CN116695779A (en) * | 2023-06-14 | 2023-09-05 | 中铁隧道集团二处有限公司 | Near existing subway tunnel pipe-jacking receiving well end reinforcing configuration system and method |
| CN117072191A (en) * | 2023-08-14 | 2023-11-17 | 启迪设计集团股份有限公司 | A door reinforcement structure and method for jacking pipes through micro-confined aquifers |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111733839A (en) | A method for strengthening the receiving end of the water-rich sand layer of the shield deep-buried close to the excavation foundation pit | |
| CN100480475C (en) | Controllable one-well lamina precipitation construction method | |
| CN106638669B (en) | Existing subway station building enclosure hardened system and method are worn under a kind of shield | |
| CN101139838A (en) | Construction method of ultra-deep foundation pit in high confined water area | |
| CN107119691A (en) | One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method | |
| CN101691756A (en) | Construction method of foundation pit confined water inrushing emergency water-lowering well | |
| CN106013078B (en) | A construction method for strengthening curtain structure in highly permeable ground | |
| CN109930613A (en) | Construction method and structure of drainage system of permeable roadbed slope | |
| CN111287794A (en) | A karst tunnel groundwater open drainage structure and method | |
| CN111764396A (en) | Construction method for water-rich stratum pit-in-pit | |
| CN105040705A (en) | Ground foundation treatment construction technology under multi-karst-cave geological conditions | |
| CN212506349U (en) | A device for water sealing well in the dewatering zone of ultra-deep foundation pit tube well | |
| CN115992525A (en) | Precipitation structure and precipitation method of deep foundation pit penetrating through pebble mudstone interface | |
| CN212641468U (en) | Pit-in-pit rapid construction structure | |
| CN212079318U (en) | A water-stop system for shield tunnel initiation under the geological conditions of water-rich sand layer | |
| CN120486314A (en) | Seepage prevention structure and method for dam development and utilization | |
| CN205296194U (en) | Rich irrigated land layer undercut tunnel interlock pipe curtain | |
| CN111173017A (en) | Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well | |
| CN204435321U (en) | A kind of steam power station water intaking open channel | |
| CN114737585A (en) | Construction method of dewatering in deep foundation pit of thin-walled plastic concrete cut-off wall | |
| CN113668585A (en) | Open caisson structure for deep and large water intaking in high-pressure water area and construction method | |
| CN115142452B (en) | Foundation pit dewatering method based on rock strata geology | |
| CN108824465B (en) | Dewatering construction structure and construction method of foundation pit engineering | |
| CN221567101U (en) | A steel slag-sea sand pile composite drainage reinforcement soft soil foundation treatment structure | |
| CN115853024B (en) | Anti-seepage wall structure and cofferdam anti-seepage construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20201002 |
|
| RJ01 | Rejection of invention patent application after publication |