CN203174616U - Clay foundation rain falling and water saving system - Google Patents

Clay foundation rain falling and water saving system Download PDF

Info

Publication number
CN203174616U
CN203174616U CN 201320159825 CN201320159825U CN203174616U CN 203174616 U CN203174616 U CN 203174616U CN 201320159825 CN201320159825 CN 201320159825 CN 201320159825 U CN201320159825 U CN 201320159825U CN 203174616 U CN203174616 U CN 203174616U
Authority
CN
China
Prior art keywords
foundation
conduit
water
precipitation
saving system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320159825
Other languages
Chinese (zh)
Inventor
史建峰
熊业亮
杨静
付国松
封玉堃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN 201320159825 priority Critical patent/CN203174616U/en
Application granted granted Critical
Publication of CN203174616U publication Critical patent/CN203174616U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a clay foundation rain falling and water saving system. The clay foundation rain falling and water saving system is distributed in a clay foundation range and comprises blind ditches, water collecting wells and recycle settling ponds, wherein the recycle settling ponds are connected with the water collecting wells, the blind ditches are respectively arranged at the bottom lower sides of plan-to-cast ground beams in a horizontal direction and a vertical direction, the water collecting wells are sequentially arranged beside foundation platforms above junction positions of each blind ditch, a mesh-shaped water drainage structure is formed as the water collecting wells are communicated with the blind ditches through communication ditches, the water collecting wells are internally and intermediately provided with corrugated pipes which are as high as the well walls of the water collecting wells in the vertical direction, the corrugated pipes are internally provided with rain falling guide pipes which are higher than the well walls of the water collecting wells, the rain falling guide pipes are internally provided with water pumps, the water pumps are connected with water collecting pipelines, and the water collecting pipelines stretch out of the well walls of the water collecting wells and are communicated with the recycle settling ponds. According to the clay foundation rain falling and water saving system disclosed by the utility model, the technical problem that rain falling cannot effectively be carried out or rain falling amount is too much under a clay foundation environment in an existing rain falling scheme, and thus underground water is wasted is solved.

Description

一种粘土地基降水节水系统A Clay Foundation Precipitation and Water Saving System

技术领域 technical field

本实用新型涉及一套地基降水节水系统,特别是一种用于粘土地基的降水节水系统。 The utility model relates to a set of foundation precipitation and water-saving system, in particular to a precipitation and water-saving system for clay foundation.

背景技术 Background technique

长期以来,为了避免地表和地下水大量侵入,造成地基浸泡或出现管涌、流砂、坑底隆起、坑外地层变形等问题,高层建筑地下室施工前,公知的降水方案是采取井点降水。但对于地基土层为粘土的基坑,由于粘土渗透率低,为了达到降水目的,往往需要加密井点布置、加大井点长度,从而导致大量地下水被抽取,造成地下水资源浪费。为了节约水资源,建设部颁布了《绿色施工导则》,要求基坑降水应尽可能少地抽取地下水,当基坑开挖抽水量大于50万立方米时,应进行地下回灌,并避免地下水被污染。 For a long time, in order to avoid a large amount of surface and groundwater intrusion, causing foundation immersion or problems such as piping, quicksand, pit bottom uplift, and stratum deformation outside the pit, before the construction of the basement of high-rise buildings, the known dewatering scheme is to use well point dewatering. However, for foundation pits where the foundation soil layer is clay, due to the low permeability of clay, in order to achieve the purpose of precipitation, it is often necessary to intensify the arrangement of well points and increase the length of well points, resulting in the extraction of a large amount of groundwater and the waste of groundwater resources. In order to save water resources, the Ministry of Construction promulgated the "Green Construction Guidelines", which requires that groundwater should be pumped as little as possible for foundation pit precipitation. Groundwater is polluted.

实用新型内容 Utility model content

本实用新型的目的是提供一种粘土地基降水节水系统,解决现有的降水方案在粘土地基环境下不能有效降水或降水过多,造成地下水浪费的不足的技术问题。 The purpose of the utility model is to provide a clay foundation precipitation and water-saving system, which solves the technical problem that the existing precipitation scheme cannot effectively reduce water or the precipitation is too much in the clay foundation environment, resulting in insufficient groundwater waste.

为实现上述目的,本实用新型采用如下技术方案: In order to achieve the above object, the utility model adopts the following technical solutions:

一种粘土地基降水节水系统,分布于粘土地基范围内,包括暗沟、集水井以及与集水井相连的回收沉淀池,所述暗沟截面为矩形,分别设置在横、纵两个方向上拟浇筑地梁的底部下侧,所述暗沟的宽度不大于拟浇筑地梁的宽度,所述集水井依次间隔设置在每个暗沟交汇处上方的基础承台的旁边,集水井通过连通沟与暗沟连通成网状排水结构,所述连通沟的沟底标高与暗沟的沟底标高相同,所述暗沟和连通沟的沟内均填满砾石,所述暗沟、连通沟和集水井的顶部表面均铺设有薄膜隔离层,所述连通沟和集水井的薄膜隔离层上浇筑有基础垫层,所述暗沟的薄膜隔离层上浇筑有地梁垫层,所述地梁垫层上砌筑有地梁的砖胎模,所述砖胎模上浇筑有基础垫层, A clay foundation dewatering and water saving system, distributed within the range of clay foundations, including culverts, water collection wells and recovery sedimentation tanks connected to the water collection wells, the section of the culverts is rectangular, respectively set in the horizontal and vertical directions to be poured On the lower side of the bottom of the ground beam, the width of the underground ditch is not greater than the width of the ground beam to be poured, and the water collection wells are arranged at intervals next to the foundation cap above the intersection of each underground ditch, and the water collection wells are connected with the underground ditch through the connecting ditch Form a network drainage structure, the elevation of the bottom of the connecting ditch is the same as that of the underground ditch, the inside of the underground ditch and the connecting ditch are all filled with gravel, and the top surfaces of the underground ditch, the connecting ditch and the water collection well are all paved There is a film isolation layer, a base cushion is poured on the film isolation layer of the communicating ditch and the water collection well, a ground beam cushion is poured on the film isolation layer of the dark ditch, and a ground beam is built on the ground beam cushion A brick tire mold, the brick tire mold is poured with a foundation cushion,

所述集水井的井内居中竖向放置有与集水井井壁同高的波纹管,所述波纹管的管壁外侧还缠裹有过滤网,波纹管的管壁周围、集水井范围内填满砾石,所述波纹管的管内设有高出集水井井壁的降水导管,所述波纹管和降水导管的管壁位于基础垫层以下的部分均钻有梅花形花眼,所述波纹管与降水导管之间的缝隙内填有密封层,所述降水导管内放置有水泵,所述水泵与集水管线相连,所述集水管线伸出集水井井壁并连通至回收沉淀池。 A corrugated pipe with the same height as the well wall of the water collection well is vertically placed in the center of the well of the water collection well, and the outside of the pipe wall of the bellows is also wrapped with a filter screen, and the surrounding of the pipe wall of the bellows and the range of the water collection well are filled with gravel, the pipe of the bellows is provided with a precipitation conduit higher than the well wall of the water collection well, and the part of the pipe wall of the bellows and the precipitation conduit below the foundation cushion is drilled with a quincunx-shaped flower eye. The gaps between the conduits are filled with a sealing layer, and a water pump is placed in the dewatering conduit, and the water pump is connected to a water collection pipeline, and the water collection pipeline extends out of the well wall of the water collection well and is connected to a recovery sedimentation tank.

所述降水导管的管壁外侧、位于基础垫层范围内、沿圆周方向呈放射状焊有一圈L形定位钢筋,所述定位钢筋的竖边垂直且紧贴降水导管的管壁,横边水平伸入至基础垫层内。 The outer side of the pipe wall of the downfall conduit is located within the scope of the foundation cushion and is radially welded with a circle of L-shaped positioning reinforcement along the circumferential direction. The vertical side of the positioning reinforcement is vertical and close to the pipe wall of the downfall conduit, and the horizontal edge into the base layer.

所述降水导管使用钢管制作,直径不小于230mm。 The downfall conduit is made of steel pipe with a diameter not less than 230mm.

所述定位钢筋沿圆周方向至少焊接3个。 The positioning steel bars are welded at least three along the circumferential direction.

所述降水导管的管壁外侧、位于基础底板范围内、沿管壁长度方向上、下焊有两圈止水翼环,分别为上止水翼环和下止水翼环。 The outer side of the pipe wall of the dewatering conduit is located within the scope of the foundation floor, and along the length direction of the pipe wall, there are two rings of hydrostop rings welded up and down, which are the upper hydrofoil ring and the lower hydrofoil ring respectively.

所述降水导管与基础垫层的混凝土之间的阴角处设有防水附加层。 An additional waterproof layer is provided at the inner corner between the downfall conduit and the concrete of the foundation cushion.

所述基础垫层上铺设有防水层,所述防水层上铺设有混凝土的防水保护层,所述防水保护层上浇筑有基础底板。 A waterproof layer is laid on the base cushion, a concrete waterproof protective layer is laid on the waterproof layer, and a foundation base plate is poured on the waterproof protective layer.

所述降水导管的顶标高至少低于基础底板的顶标高50mm。 The top elevation of the downfall conduit is at least 50mm lower than the top elevation of the foundation floor.

所述集水井的底标高至少深于暗沟的底标高500mm。 The bottom elevation of the water collection well is at least 500mm deeper than the bottom elevation of the dark ditch.

所述过滤网的网眼尺寸为60~80目。 The mesh size of the filter is 60-80 mesh.

与现有技术相比本实用新型具有以下特点和有益效果: Compared with the prior art, the utility model has the following characteristics and beneficial effects:

本实用新型提供一种降水节水系统,该系统不仅能实现有效降低地下水位使其控制在预定标高,而且具备施工简便、造价低、工期短的效果,相比传统的先降水后开挖的施工顺序,降水是在土方开挖完成后进行,降水的同时不影响基础底板的施工,从而缩短了施工周期。 The utility model provides a dewatering and water-saving system. The system can not only effectively lower the groundwater level so that it can be controlled at a predetermined elevation, but also has the effects of simple construction, low cost and short construction period. Compared with the traditional method of dewatering first and then excavating In the construction sequence, the precipitation is carried out after the earth excavation is completed, and the precipitation does not affect the construction of the foundation floor at the same time, thereby shortening the construction period.

本实用新型使用土方开挖机械完成集水井的施工,相对于传统技术节省了土方开挖前机械钻井并设置井点管的工序,从而节约成本。 The utility model uses earthwork excavation machinery to complete the construction of the water collection well, which saves the process of mechanical drilling and setting well point pipes before earthwork excavation compared with the traditional technology, thereby saving costs.

本实用新型通过地梁底部设置暗沟、连通沟以及暗沟交汇处旁边设置的集水井,使得地下水形成贯通的网络,从而避免了由于地质不均造成的局部地下水侵害地基的风险。 In the utility model, the underground ditch, the connecting ditch, and the water collecting well arranged beside the intersection of the underground ditch are arranged at the bottom of the ground beam, so that the groundwater forms a continuous network, thereby avoiding the risk of local groundwater encroaching on the foundation due to geological unevenness.

本实用新型由于暗沟和集水井相结合的方式提高了粘土地基降水效率,从而避免了钻深井在降低表层地下水的同时,抽取了深层地下水,减少地下水的抽取量,减少地下水的流失,节约水资源,有利于节约能源和环境保护。同时,抽取的地下水经沉淀可回收利用于冲洗车辆、混凝土养护、场地降尘等,提高了非传统水源的利用率。 The utility model improves the dewatering efficiency of the clay foundation due to the combination of the culvert and the water collection well, thereby avoiding drilling deep wells while reducing the surface groundwater and extracting deep groundwater, reducing the extraction of groundwater, reducing the loss of groundwater, and saving water resources , conducive to energy saving and environmental protection. At the same time, the extracted groundwater can be recycled and used for washing vehicles, concrete maintenance, and dust reduction on the site after precipitation, which improves the utilization rate of non-traditional water sources.

本实用新型在降水导管的管壁上预先焊接了定位钢筋,使导管固定在基础垫层范围内,上、下止水翼环可使渗透水阻隔在基础底板之下,以及防水附加层的设置均增强了结构的防水能力为以后的施工工序打好基础。 In the utility model, positioning steel bars are pre-welded on the pipe wall of the downwater conduit, so that the conduit is fixed within the scope of the foundation cushion, and the upper and lower water stop rings can block the seepage water under the foundation floor, and the additional waterproof layer is set Both enhance the waterproof ability of the structure and lay a solid foundation for the future construction process.

本实用新型可广泛应用于粘土地基降水施工。  The utility model can be widely used in clay foundation precipitation construction. the

附图说明 Description of drawings

下面结合附图对本实用新型做进一步详细的说明。 Below in conjunction with accompanying drawing, the utility model is described in further detail.

图1是本实用新型梁底暗沟和集水井的平面布置示意图。 Fig. 1 is the schematic diagram of the plane layout of the gutter at the bottom of the beam and the water collecting well of the utility model.

图2是图1中A-A剖面的结构示意图。 Fig. 2 is a structural schematic diagram of section A-A in Fig. 1 .

图3是图2中降水导管管壁外侧焊接定位钢筋和上、下止水翼环的结构示意图。 Fig. 3 is a structural schematic diagram of the welded positioning steel bars and the upper and lower hydrostop rings on the outer side of the downwater conduit wall in Fig. 2 .

图4是图3的俯视结构示意图。 FIG. 4 is a top view structural diagram of FIG. 3 .

图5是降水导管封堵的结构示意图。 Fig. 5 is a schematic diagram of the structure of the downwater conduit plugging.

附图标记:1-拟浇筑地梁、2-暗沟、3-连通沟、4-集水井、5-基础承台、6-砾石、7-薄膜隔离层、8-波纹管、9-水泵、10-基础垫层、11-砖胎模、12-定位钢筋、13-下止水翼环、14-上止水翼环、15-降水导管、16-密封层、17-中粗砂、18-防水层、19-防水保护层、20-基础底板、21-堵漏剂、22-微膨胀混凝土、23-钢盖板、24-集水管线、25-回收沉淀池、26-地梁垫层。 Reference signs: 1-beam to be poured, 2-underground ditch, 3-connecting ditch, 4-collection well, 5-foundation cap, 6-gravel, 7-membrane isolation layer, 8-bellows, 9-water pump, 10 - foundation cushion, 11 - brick tire mold, 12 - positioning steel bar, 13 - lower hydrofoil ring, 14 - upper hydrofoil ring, 15 - precipitation conduit, 16 - sealing layer, 17 - medium coarse sand, 18 - waterproof layer, 19 - waterproof protective layer, 20 - base plate, 21 - plugging agent, 22 - micro-expansion concrete, 23 - steel cover plate, 24 - water collection pipeline, 25 - recovery sedimentation tank, 26 - ground beam pad layer.

具体实施方式 Detailed ways

实施例参见图1-4所示,一种粘土地基降水节水系统,分布于粘土地基范围内,包括暗沟2、集水井4以及与集水井4相连的回收沉淀池25,所述暗沟2截面为矩形,分别设置在横、纵两个方向上拟浇筑地梁1的底部下侧,所述暗沟2的宽度不大于拟浇筑地梁1的宽度,所述集水井4依次间隔设置在每个暗沟2交汇处上方的基础承台5的旁边,集水井4通过连通沟3与暗沟2连通成网状排水结构,所述连通沟3的沟底标高与暗沟2的沟底标高相同,所述暗沟2和连通沟3的沟内均填满砾石6,所述暗沟2、连通沟3和集水井4的顶部表面均铺设有薄膜隔离层7,所述连通沟3和集水井4的薄膜隔离层7上浇筑有基础垫层10,所述暗沟2的薄膜隔离层7上浇筑有地梁垫层26,所述地梁垫(26上砌筑有地梁的砖胎模11,所述砖胎模11上浇筑有基础垫层10,所述薄膜隔离层7的尺寸应满足各边尺寸均超过暗沟、连通沟和集水井的截面尺寸,每边均长150mm。 Referring to the embodiment shown in Figures 1-4, a clay foundation dewatering and water-saving system is distributed within the scope of the clay foundation and includes a culvert 2, a water collection well 4 and a recovery sedimentation tank 25 connected to the water collection well 4. The section of the culvert 2 is They are rectangular, and are respectively arranged on the lower side of the bottom of the ground beam 1 to be poured in the horizontal and vertical directions. The width of the underground ditch 2 is not greater than the width of the ground beam 1 to be poured. Next to the foundation cap 5 above the intersection of the underground ditch 2, the water collection well 4 is connected to the underground ditch 2 to form a network drainage structure through the communication ditch 3, and the elevation of the bottom of the communication ditch 3 is the same as that of the underground ditch 2. Both the underground ditch 2 and the communication ditch 3 are filled with gravel 6, and the top surfaces of the underground ditch 2, the communication ditch 3 and the water collection well 4 are all laid with a film isolation layer 7, and the film isolation of the communication ditch 3 and the water collection well 4 Layer 7 is poured with a base cushion 10, and the film isolation layer 7 of the underground ditch 2 is poured with a ground beam cushion 26, and the ground beam cushion (26 is built with a brick tire mold 11 of a ground beam, and the brick The base cushion 10 is poured on the tire mold 11, and the size of the film isolation layer 7 should meet the requirement that the size of each side exceeds the section size of the dark ditch, the communication ditch and the water collection well, and the average length of each side is 150mm.

所述集水井4的井内居中竖向放置有与集水井井壁同高的波纹管8,所述波纹管8的管壁外侧还缠裹有过滤网,波纹管8的管壁周围、集水井范围内填满砾石6,所述波纹管8的管内设有高出集水井井壁的降水导管15,所述波纹管和降水导管的管壁位于基础垫层以下的部分均钻有梅花形花眼,所述波纹管8与降水导管15之间的缝隙内填有密封层16,所述降水导管15内放置有水泵9,所述水泵9与集水管线24相连,所述集水管线24伸出集水井井壁并连通至回收沉淀池25。 The bellows 8 with the same height as the well wall of the water collection well is placed vertically in the center of the well of the water collection well 4, and the outside of the pipe wall of the bellows 8 is also wrapped with a filter screen. Around the pipe wall of the bellows 8, the water collection well The range is filled with gravel 6, and the pipe of the bellows 8 is provided with a downwater conduit 15 that is higher than the well wall of the water collection well. , the gap between the bellows 8 and the downwater conduit 15 is filled with a sealing layer 16, and a water pump 9 is placed in the downwater conduit 15, and the water pump 9 is connected to the water collection pipeline 24, and the water collection pipeline 24 extends Out of the well wall of the water collection well and connected to the recovery sedimentation tank 25.

所述降水导管15的管壁外侧、位于基础垫层10范围内、沿圆周方向呈放射状焊有一圈L形定位钢筋12,所述定位钢筋12的竖边垂直且紧贴降水导管15的管壁,横边水平伸入至基础垫层10内。 The outside of the pipe wall of the downfall conduit 15 is located within the scope of the foundation cushion 10 and is radially welded with a circle of L-shaped positioning steel bars 12 along the circumferential direction. , the transverse edge horizontally extends into the base cushion 10.

所述定位钢筋12沿圆周方向至少焊接3个。 The positioning steel bars 12 are at least three welded along the circumferential direction.

所述降水导管15的管壁外侧、位于基础底板20范围内、沿管壁长度方向上、下焊有两圈止水翼环,分别为上止水翼环13和下止水翼环14。 On the outer side of the pipe wall of the downwater conduit 15 , within the range of the base plate 20 , two circles of water stop rings are welded up and down along the length direction of the pipe wall, namely the upper water stop ring 13 and the lower water stop ring 14 .

所述基础垫层10上铺设有防水层18,所述防水层18上铺设有混凝土的防水保护层19,所述防水保护层19上浇筑有基础底板20。 A waterproof layer 18 is laid on the base cushion layer 10 , a concrete waterproof protective layer 19 is laid on the waterproof layer 18 , and a foundation base plate 20 is poured on the waterproof protective layer 19 .

所述降水导管15与基础垫层10的混凝土之间的阴角处设有防水附加层。 An additional waterproof layer is provided at the inner corner between the downfall conduit 15 and the concrete of the foundation cushion 10 .

所述降水导管15的顶标高至少低于基础底板20的顶标高50mm。 The top elevation of the downfall conduit 15 is at least 50 mm lower than the top elevation of the foundation floor 20 .

所述集水井4的底标高至少深于暗沟2的底标高500mm。 The bottom elevation of the water collection well 4 is at least 500mm deeper than the bottom elevation of the dark ditch 2 .

所述过滤网的网眼尺寸为60~80目。 The mesh size of the filter is 60-80 mesh.

本实施例的施工方法如下: The construction method of the present embodiment is as follows:

步骤一:参见图1,地梁1和基础承台5开挖至基底标高后,在地梁1底部开挖暗沟2,所述暗沟尺寸及布置间距根据基坑涌水量经计算确定,本实施例中暗沟的截面为方形,宽300mm、深300mm;在纵横暗沟相交点的旁边以隔一设一的方式设置集水井4,集水井平面尺寸1m×1m,其深度为设计为地梁高度-基础底板厚度+防水保护层厚度+基础垫层厚度+300mm+500mm,其中300mm为暗沟的深度,集水井4的底标高深于暗沟2的底标高500mm;暗沟2与集水井4通过连通沟3相连接,连通沟底标高与暗沟底标高相同。 Step 1: Referring to Figure 1, after the ground beam 1 and the foundation cap 5 are excavated to the base level, the underground ditch 2 is excavated at the bottom of the ground beam 1. The section of the underground ditch in the example is square, with a width of 300mm and a depth of 300mm; water collection wells 4 are arranged one by one next to the intersection point of the vertical and horizontal underground ditches. Base plate thickness + waterproof protective layer thickness + foundation cushion thickness + 300mm + 500mm, of which 300mm is the depth of the dark ditch, and the bottom elevation of the water collecting well 4 is 500mm deeper than the bottom elevation of the dark ditch 2; the dark ditch 2 and the water collecting well 4 pass through the connecting ditch 3 connected, the elevation of the bottom of the connected ditch is the same as that of the bottom of the dark ditch.

步骤二:参见图2所示,暗沟2、连通沟3和集水井4内填充砾石6,砾石应级配良好,回填密实,在集水井4中心位置竖向放置波纹管8,波纹管8的顶标高与基础垫层混凝土的标高平齐,波纹管8外缠裹密目滤网;波纹管8内放置水泵9进行降水,地下水通过集水管线24输送到回收沉淀池25,回收沉淀池内的地下水经三级沉淀后回收利用。 Step 2: As shown in Figure 2, gravel 6 is filled in the underground ditch 2, the connecting ditch 3 and the water collection well 4. The gravel should be well graded and backfilled densely. Place the bellows 8 vertically in the center of the water collection well 4, and the bellows 8 The elevation of the top is equal to the elevation of the foundation cushion concrete, and the corrugated pipe 8 is wrapped with a dense mesh filter; the water pump 9 is placed in the corrugated pipe 8 for dewatering, and the groundwater is transported to the recovery sedimentation tank 25 through the water collection pipeline 24, and the water in the sedimentation tank is recovered The groundwater is recycled after tertiary sedimentation.

步骤三:实现初步降水后,在暗沟2、连通沟3和集水井4上方均铺设塑料薄膜隔离层7,连通沟3和集水井4的薄膜隔离层7上浇筑的基础垫层10,暗沟的薄膜隔离层7上浇筑地梁垫层26,在地梁垫层26上砌筑砖胎膜11,在砖胎膜11上浇筑基础垫层10。 Step 3: After the preliminary precipitation is realized, a plastic film isolation layer 7 is laid above the dark ditch 2, the communication ditch 3 and the water collection well 4, and the foundation cushion 10 poured on the film isolation layer 7 of the communication ditch 3 and the water collection well 4, and the culvert The ground beam cushion 26 is poured on the film isolation layer 7 , the brick tire membrane 11 is built on the ground beam cushion 26 , and the foundation cushion 10 is poured on the brick mold 11 .

步骤四:在波纹管8内放置直径小于波纹管8的降水导管12,所述降水导管可使用钢管制作,直接不小于230mm,应能满足在其内放置水泵的要求;降水导管12的设计长度为:集水井4深度+基础垫层10厚度+防水保护层19厚度+基础底板20厚度-50mm,其中50mm表示降水导管15的顶标高低于基础底板20的顶标高50mm;在降水导管12与波纹管8之间的缝隙上端填密封层16,本实施例中可使用塞麻丝加油膏做密封层16进行封堵密实。  Step 4: Place a downwater conduit 12 with a diameter smaller than the bellows 8 in the bellows 8. The downwater conduit can be made of a steel pipe, directly not less than 230mm, and should be able to meet the requirements for placing a water pump therein; the design length of the downwater conduit 12 It is: the depth of the water collection well 4 + the thickness of the foundation cushion 10 + the thickness of the waterproof protective layer 19 + the thickness of the foundation floor 20 - 50mm, wherein 50mm means that the top elevation of the downfall conduit 15 is lower than the top elevation of the foundation bottom plate 20 by 50mm; The upper end of the gap between the corrugated pipes 8 is filled with a sealing layer 16. In this embodiment, the sealing layer 16 can be sealed and compacted by using the oil-filling paste of hemp silk. the

步骤五:参见图2-4所示,降水导管15的管壁外侧、位于基础垫层10范围内、沿圆周方向呈放射状焊有一圈L形定位钢筋12,所述定位钢筋12的竖边垂直且紧贴降水导管15的管壁,横边水平伸入至基础垫层10内,竖边紧贴降水导管是为了防止后续铺贴防水卷材时无法上翻;降水导管15的管壁外侧、位于基础底板20范围内、沿管壁长度方向上、下分别焊有上止水翼环13和下止水翼环14,本实施例中在基础底板20底标高上方100mm处焊接下止水翼环13,在基础底板20顶标高下方100mm处焊接上止水翼环14,止水翼环的内环内侧与管壁的外侧均满焊。 Step 5: As shown in Figure 2-4, the outside of the pipe wall of the downfall conduit 15 is located within the scope of the foundation cushion 10 and is radially welded with a circle of L-shaped positioning steel bars 12 along the circumferential direction, and the vertical sides of the positioning steel bars 12 are vertical And it is close to the pipe wall of the dewatering conduit 15, and the horizontal edge extends horizontally into the base cushion 10, and the vertical edge is close to the dewatering conduit in order to prevent the subsequent laying of the waterproof membrane from being unable to turn up; the outside of the pipe wall of the dewatering conduit 15, Located within the scope of the foundation floor 20, the upper and lower water stop rings 13 and 14 are respectively welded up and down along the length direction of the pipe wall. In this embodiment, the lower water stop ring is welded 100mm above the bottom elevation of the foundation floor 20 For the ring 13, the hydrostop ring 14 is welded at 100 mm below the elevation of the top of the base plate 20, and the inside of the inner ring of the hydrostop ring is fully welded to the outside of the pipe wall.

步骤六:参见图5所示,浇筑基础垫层10,在基础垫层10上依次防水层18、防水保护层19和基础底板20,防水层18沿降水导管15的管壁上翻,直至降水导管15在基础底板范围内设置的下止水翼环13处密封。 Step 6: Referring to Fig. 5, pour the foundation cushion 10, on the foundation cushion 10 successively waterproof layer 18, waterproof protective layer 19 and foundation floor 20, waterproof layer 18 turns up along the pipe wall of the downwater conduit 15, until the precipitation The duct 15 is sealed at a lower hydrofoil ring 13 arranged in the region of the foundation floor.

步骤七:降水与步骤六同时进行,待建筑物荷载达到设计要求后,停止降水;从降水导管中取出水泵9,在降水导管12内填充中粗砂17至基础垫层10标高,然后将堵漏剂21蘸水湿润,揉成饼状,压在降水导管内中粗砂层17上,然后在降水导管12内浇筑比基础底板高一个强度等级的微膨胀混凝土22至降水导管15的顶标高。降水导管12顶部焊接钢盖板23封堵后,钢盖板23上浇筑比基础底板高一个强度等级的微膨胀混凝土22与基础底板20顶标高平齐,从而完成封井。 Step 7: Dewatering is carried out at the same time as Step 6. After the building load reaches the design requirements, stop the dewatering; take out the water pump 9 from the dewatering conduit, fill the medium coarse sand 17 in the dewatering conduit 12 to the level of the foundation cushion 10, and then plug the Wet the leakage agent 21 with water, knead it into a cake shape, press it on the medium-coarse sand layer 17 in the downfall conduit, and then pour micro-expansion concrete 22 with a strength level higher than that of the foundation floor in the downfall conduit 12 to the top level of the downfall conduit 15 . After the top of the downfall conduit 12 is sealed with a welded steel cover plate 23, the steel cover plate 23 is poured with micro-expansion concrete 22 with a strength level higher than that of the base plate to be level with the top level of the base plate 20, thereby completing well sealing.

Claims (10)

1. clay foundation precipitation water-saving system, be distributed in the clay foundation scope, it is characterized in that: comprise covered conduit (2), collecting well (4) and the recovery sedimentation basin (25) that links to each other with collecting well (4), described covered conduit (2) cross section is rectangle, be separately positioned on horizontal stroke, intend building the bottom downside of grade beam (1) on the vertical both direction, the width of described covered conduit (2) is not more than the width of intending building grade beam (1), described collecting well (4) is disposed on the next door of the foundation platform (5) of each covered conduit (2) intersection top successively, collecting well (4) is communicated with covered conduit (2) and reticulates discharge structure by being communicated with ditch (3), the bottom of trench absolute altitude of described connection ditch (3) is identical with the bottom of trench absolute altitude of covered conduit (2), all fill up gravel (6) in the ditch of described covered conduit (2) and connection ditch (3), described covered conduit (2), the top surface that is communicated with ditch (3) and collecting well (4) all is equipped with film separation layer (7), built foundation pad (10) on the film separation layer (7) of described connection ditch (3) and collecting well (4), built grade beam bed course (26) on the film separation layer (7) of described covered conduit (2), build the brick loose tool (11) of grade beam on the described grade beam bed course (26) by laying bricks or stones, built foundation pad (10) on the described brick loose tool (11)
Vertically be placed with the collecting well borehole wall with high bellows (8) between two parties in the well of described collecting well (4), the tube wall outside of described bellows (8) has also swathed screen pack, around the tube wall of bellows (8), fill up gravel (6) in the collecting well scope, be provided with the precipitation conduit (15) that exceeds the collecting well borehole wall in the pipe of described bellows (8), the tube wall of described bellows and precipitation conduit is positioned at the following part of foundation pad and all is drilled with quincunx presbyopia, be filled with sealant (16) in the slit between described bellows (8) and the precipitation conduit (15), be placed with water pump (9) in the described precipitation conduit (15), described water pump (9) links to each other with the pipeline that catchments (24), and the described pipeline that catchments (24) stretches out the collecting well borehole wall and is communicated to and reclaims sedimentation basin (25).
2. a kind of clay foundation precipitation water-saving system according to claim 1 is characterized in that: described precipitation conduit (15) uses steel pipe manufacturing, and diameter is not less than 230mm.
3. a kind of clay foundation precipitation water-saving system according to claim 1, it is characterized in that: the tube wall of described precipitation conduit (15) outside, be positioned at foundation pad (10) scope, along the circumferential direction be radial and be welded with one and enclose L shaped spacer bars (12), the vertical edge of described spacer bars (12) is vertical and be close to the tube wall of precipitation conduit (15), and the horizontal edge level stretches in the foundation pad (10).
4. a kind of clay foundation precipitation water-saving system according to claim 3, it is characterized in that: described spacer bars (12) along the circumferential direction welds 3 at least.
5. a kind of clay foundation precipitation water-saving system according to claim 1, it is characterized in that: the tube wall of described precipitation conduit (15) outside, be positioned at sole plate (20) scope, be welded with two and enclose sealing wing rings along the tube wall length direction is upper and lower, be respectively sealing wing ring (13) and following sealing wing ring (14).
6. a kind of clay foundation precipitation water-saving system according to claim 1; it is characterized in that: be equipped with waterproofing course (18) on the described foundation pad (10); be equipped with concrete fish tail and waterproof layer (19) on the described waterproofing course (18), built sole plate (20) on the described fish tail and waterproof layer (19).
7. a kind of clay foundation precipitation water-saving system according to claim 1, it is characterized in that: the inner corner trim place between the concrete of described precipitation conduit (15) and foundation pad (10) is provided with the waterproof extra play.
8. a kind of clay foundation precipitation water-saving system according to claim 1, it is characterized in that: the top mark height of described precipitation conduit (15) is lower than the high 50mm of top mark of sole plate (20) at least.
9. a kind of clay foundation precipitation water-saving system according to claim 1, it is characterized in that: the end absolute altitude of described collecting well (4) is deeper than the end absolute altitude 500mm of covered conduit (2) at least.
10. a kind of clay foundation precipitation water-saving system according to claim 1, it is characterized in that: the mesh size of described screen pack is 60~80 orders.
CN 201320159825 2013-04-02 2013-04-02 Clay foundation rain falling and water saving system Expired - Fee Related CN203174616U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320159825 CN203174616U (en) 2013-04-02 2013-04-02 Clay foundation rain falling and water saving system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320159825 CN203174616U (en) 2013-04-02 2013-04-02 Clay foundation rain falling and water saving system

Publications (1)

Publication Number Publication Date
CN203174616U true CN203174616U (en) 2013-09-04

Family

ID=49071340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320159825 Expired - Fee Related CN203174616U (en) 2013-04-02 2013-04-02 Clay foundation rain falling and water saving system

Country Status (1)

Country Link
CN (1) CN203174616U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821158A (en) * 2014-03-21 2014-05-28 中国十九冶集团有限公司 Construction excavation drainage method under high groundwater condition
CN103967028A (en) * 2014-05-27 2014-08-06 江苏南通三建集团有限公司 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN104005418A (en) * 2014-06-17 2014-08-27 中铁城建集团第二工程有限公司 Method for rapidly treating underground piping
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN107956221A (en) * 2017-12-12 2018-04-24 中国冶集团有限公司 Downcast well pipe proof protecting device and construction method
CN108729851A (en) * 2018-05-22 2018-11-02 山西省工业设备安装集团有限公司 A kind of depositing dust excavation of foundation pit equipment that water utilization rate is high
CN110219314A (en) * 2018-03-01 2019-09-10 中铁西北科学研究院有限公司深圳南方分院 Collecting system
CN110258660A (en) * 2019-06-18 2019-09-20 广东龙越建筑工程有限公司 The manufacture craft and shut-in well technique of the decompression drainage sump of basement anti-floating
CN110284876A (en) * 2019-06-25 2019-09-27 徐清清 A kind of method and apparatus carrying out multiple water-bearing layer bailing tests in single gun drilling
CN117513428A (en) * 2023-09-27 2024-02-06 广西建工第一建筑工程集团有限公司 A high groundwater level post-pouring belt structure and post-pouring belt sealing construction method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821158B (en) * 2014-03-21 2016-04-13 中国十九冶集团有限公司 Construction excavation drainage method under high groundwater condition
CN103821158A (en) * 2014-03-21 2014-05-28 中国十九冶集团有限公司 Construction excavation drainage method under high groundwater condition
CN103967028A (en) * 2014-05-27 2014-08-06 江苏南通三建集团有限公司 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN104005418A (en) * 2014-06-17 2014-08-27 中铁城建集团第二工程有限公司 Method for rapidly treating underground piping
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN107956221A (en) * 2017-12-12 2018-04-24 中国冶集团有限公司 Downcast well pipe proof protecting device and construction method
CN110219314A (en) * 2018-03-01 2019-09-10 中铁西北科学研究院有限公司深圳南方分院 Collecting system
CN108729851A (en) * 2018-05-22 2018-11-02 山西省工业设备安装集团有限公司 A kind of depositing dust excavation of foundation pit equipment that water utilization rate is high
CN108729851B (en) * 2018-05-22 2019-11-08 山西省工业设备安装集团有限公司 A kind of depositing dust excavation of foundation pit equipment that water utilization rate is high
CN110258660A (en) * 2019-06-18 2019-09-20 广东龙越建筑工程有限公司 The manufacture craft and shut-in well technique of the decompression drainage sump of basement anti-floating
CN110284876A (en) * 2019-06-25 2019-09-27 徐清清 A kind of method and apparatus carrying out multiple water-bearing layer bailing tests in single gun drilling
CN110284876B (en) * 2019-06-25 2023-04-18 徐清清 Method and device for carrying out multiple aquifer water pumping tests in single deep borehole
CN117513428A (en) * 2023-09-27 2024-02-06 广西建工第一建筑工程集团有限公司 A high groundwater level post-pouring belt structure and post-pouring belt sealing construction method

Similar Documents

Publication Publication Date Title
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN104762982B (en) The construction method that a kind of rich water red sandstone geology level of ground water controls
CN207892653U (en) Decompression hydrophobic structure suitable for Weathering-residual soil layer fissure zone
CN103046565A (en) Draining method for ultra-deep batholith deep foundation pit
CN105464074B (en) High polymer grouting protective structure of manual digging pile and its construction method
CN203530996U (en) Multi-well-point combined type precipitation facility
CN105133581A (en) Three-in-one construction method for uplift pile, lattice column and precipitation well in supporting structure
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN205152970U (en) Underground structure oozes drainage system
CN105089072A (en) Anti-seepage structure of basement bottom board and construction method
CN103643689B (en) A kind of pipe type underground water drainage blind ditch and construction technology thereof and application
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN206204972U (en) A kind of prefabricated tubular pile as well-points dewatering
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN101413269A (en) Vacuum curtain water stop and atmospheric pressure support deep pit digging construction method
CN115992525A (en) A dewatering structure and dewatering method for a deep foundation pit passing through the pebble-mudstone interface
CN212336250U (en) Pipe jacking connection guide row structure
CN205907658U (en) Be used for anti - structure that seeps water of concrete -faced rockfill dam construction time dam body
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN111501807A (en) Large-diameter buried pipe laying structure and construction method in collapsible loess area
CN107268364A (en) The construction method that mud bag builds road is filled on reclaimed ground
CN203741852U (en) Tubular groundwater drainage and seepage blind ditch
CN115897759A (en) Construction method of post-pouring belt drainage and water supply circulation system on bottom of deep foundation pit
CN205444218U (en) Foundation pit dewatering tubular well based on environmental control
CN204435321U (en) A kind of steam power station water intaking open channel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130904

Termination date: 20140402