CN107083977B - A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion - Google Patents

A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion Download PDF

Info

Publication number
CN107083977B
CN107083977B CN201710484682.1A CN201710484682A CN107083977B CN 107083977 B CN107083977 B CN 107083977B CN 201710484682 A CN201710484682 A CN 201710484682A CN 107083977 B CN107083977 B CN 107083977B
Authority
CN
China
Prior art keywords
hole
tunnel
injected hole
deep
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710484682.1A
Other languages
Chinese (zh)
Other versions
CN107083977A (en
Inventor
张农
潘东江
张成浩
韩昌良
谢正正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201710484682.1A priority Critical patent/CN107083977B/en
Publication of CN107083977A publication Critical patent/CN107083977A/en
Priority to PCT/CN2017/105793 priority patent/WO2018233149A1/en
Application granted granted Critical
Publication of CN107083977B publication Critical patent/CN107083977B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • E21D9/002Injection methods characterised by the chemical composition used

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Chemical & Material Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion, belongs to the grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion.Corresponding geology state is evaluated according to the geological information data in specific tunnel, the boring point of shallow injected hole and deep injected hole is designed in tunnel according to the geology state evaluated, with tunnelling, concrete and silica solution spray-up are anchored and are arranged to tunnel surrounding;It constructs shallow injected hole and hole-sealing grouting, constructs deep injected hole and hole-sealing grouting in the deep injected hole boring point being pre-designed, thus effectively within closed reinforcement to deep protolith area in the portion, side in tunnel and roof and floor.Not only strengthen superficial part fracture area country rock, and the channel that hydrone, air molecule, crevice water enter induration is blocked, to increase its non-deformability and endurance quality, solve the problems, such as the Nonlinear Large Deformation of outstanding behaviours after water is met in argillaceous soft rock tunnel, significant rheology and by disturbing influence etc..

Description

A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion
Technical field
The present invention relates to a kind of grouting strengthening method, the argillaceous soft rock that roadway support is used suitable for a kind of coal mine underground The grouting strengthening method of the more granularities of tunnel subregion.
Background technique
Argillaceous soft rock tunnel is the compound country rock lane with physical features such as high stress, Joint fissured roof, water-swellable softenings It is broken to will lead to roadway surrounding rock large deformation for the physical features of road, especially water-swellable, referred to as one of " cancer " of underground engineering It is bad, or even cause catastrophic engineering accident.The complexity of argillaceous soft rock tunnel stress and the variability for meeting water bar part determine Its complicated deformation mechanism, show as that single support pattern is difficult to effectively to administer in control means practices feature.
It can be divided into along tunnel radial direction according to the different seepage characteristic of country rock: complete vadose region, orientation vadose region, seepage flow shielding Area, protolith vadose region.The supporting problem of processing soft-rock tunnel mostly uses cement injection closed reinforcement at present, and cement injection is most effective Region is complete vadose region, which is located at tunnel surface layer fracture area, and general thickness is 0.4~2.0m, and wall-rock crack reaches full growth, Tunnel is axial close with circumferential permeance property, in an order of magnitude, substantially accomplishes each to the seepage flow same sex, comprehensive can seep Stream.Slurries after shallow-layer is spread completely, into the seepage channel behind deep be based on initial fissure face and structural plane, due to The directionality of beded rock mass primary structural plane makes the seepage characteristic in the section show as very strong directionality, referred to as orientation seepage flow Area, the region slurries seepage flow mainly based on big fracture seepage, are spread in veiny.Continue to increase at a distance from the surface of tunnel Add, being neutralized high confining pressure constraint by stress collection is influenced, and reduce after fracture opening is compressed, has blocked slurries seepage channel, although It is microcosmic, carefully see cranny development, but in view of the minimum of cement grout can infuse width 0.1mm and starting pressure gradient factor, the area Domain is significantly that cement slurry is difficult across the region to deep wall rock seepage flow, so in the area for its shielding action of cement slurry Domain forms the slip casting seepage flow blind zone of cement slurry.Also, after cement slurry grouting and reinforcing over time, induration micropore itself Gap is also developed, and pore surface aquation, slacking are more and more stronger, and the rock mass for reinforcing cement slurry gradually softens disintegration, whole to send out Raw creep, therefore cement slurry can't resolve the problem of argillaceous soft rock tunnel softening rheology large deformation.
In recent years, for the supporting problem in argillaceous soft rock tunnel, a kind of silica solution of argillaceous soft rock seeps reinforcement means quilt slowly It proposes (Chinese invention patent publication No.: CN105201528A), this method carries out high compact slip casting to argillaceous soft rock, before argillization Nanoscale slurry material silica solution (results of grain size analysis 8-20nm) is injected, early period is using grouting pressure in mud stone macroscopic view fissure system Fast Filling, later-stage utilization capillary force slow diffusion for a long time in mud stone, water in Precomplete set argillaceous soft rock matrix Molecule, air molecule microchannel, significantly hinder the microcosmic effects such as absorption, dissolution, weathering, can effectively alleviate microfissure, micro- Security risk caused by hole solves the Large Deformation Support problem of softening rheology.But silica solution only has limited bonding Power, consolidation effect are undesirable.
To sum up, cement slurry reinforcement means can effective dead-end fracture system, reinforce superficial part fracture area country rock, but cement slurry pair The micropore of roadway surrounding rock deep seepage flow blind zone development and thin crack of seeing are almost without effect.Silica solution seeps reinforcement means slowly can With Precomplete set deep soft rock matrix micropores crack, sealing process is preferable, but silica solution cohesive force is insufficient, and the effect of reinforcing is not It is ideal.Therefore, these existing methods have the shortcomings that certain and deficiency.
Summary of the invention
Technical problem: the purpose of the present invention is overcoming the shortcomings of prior art, it is simple to provide a kind of step, implementation cost It is low, the grouting strengthening method of the good more granularities of argillaceous soft rock tunnel subregion of supporting effect.
Technical solution: to realize the above-mentioned technical purpose, the grouting and reinforcing of subregion more granularities in argillaceous soft rock tunnel of the invention Method evaluates corresponding geology state according to the geological information data in specific tunnel, according to the geology state evaluated in lane The boring point that shallow injected hole and deep injected hole are designed in road anchors tunnel surrounding and coagulation is arranged with tunnelling Soil and silica solution spray-up;It constructs in the portion, side in tunnel and roof and floor shallow injected hole and hole-sealing grouting, in the depth note being pre-designed The deep injected hole of hole drilling point construction and hole-sealing grouting are starched, thus effectively within closed reinforcement to deep protolith area.
Specific step is as follows:
A, geological test is carried out to tested tunnel, and obtains corresponding geological information data, according to geological test and ground Matter information material is assessed to obtain roadway surrounding rock lithology, hole cranny development and hydrological geological conditions;
B, according to roadway surrounding rock lithology, the developmental state in hole crack and the hydrological geological conditions evaluated in tunnel side wall With the boring point for designing shallow injected hole and deep injected hole on bottom plate;
C, it with tunnelling, assesses tunnel radial direction country rock hole seam area and draws feature, in time to tunnel four after anchoring The scar gunite concrete in week closes the big crack of scar, stops pulp layer for subsequent grouting construction, concrete setting is waited to be formed later Concrete stops pulp layer, stops in concrete and sprays silica solution composition silica sol layer in pulp layer again, and timely closed concrete stops pulp layer micropore Crack prevents country rock to be etched to form concrete and silica solution spray-up, long-term rear aquation, weathering;
D, after roadway excavation 10~20 days, the shallow injected hole boring point being pre-designed in the portion, side in tunnel and roof and floor is applied The shallow injected hole of work injects cement slurry and sealing of hole to shallow injected hole by Grouting Pipe using grouting equipment, in the slip casting pressure of cement slurry Under the driving of power, cement slurry is by shallow injected hole diffusion filling mud stone superficial part crack to closed reinforcement superficial part fracture area country rock;
E, after Shallow hole grouting terminates 25~35 days, the deep slip casting hole drilling that is pre-designed in the portion, side in tunnel and roof and floor The deep injected hole of point construction injects silica solution and sealing of hole to deep injected hole by Grouting Pipe using grouting equipment, in the drive of capillary force Under dynamic, silica solution, which passes through deep injected hole and seeps slowly, fills soft-rock tunnel deep matrix system micropore crack, so that closed reinforcement is to depth Within protolith area, portion.
The scar shotcrete layer to tunnel surrounding with a thickness of 80mm~120mm;Stop in pulp layer in concrete The silica sol layer sprayed again is with a thickness of 2mm~5mm.
The shallow injected hole hole depth constructed in the portion, side in tunnel and roof and floor is 2.0m~2.5m, across the complete of rock stratum Grouting pressure is improved during slip casting reach and stop after 1~2MPa after 15~20min of pressure stabilizing until orienting vadose region in full vadose region Slip casting and sealing of hole.
The deep injected hole hole depth constructed in the portion, side in tunnel and roof and floor is 4m~6m, and deep injected hole passes through rock stratum Complete vadose region, orientation vadose region, seepage flow blind zone until protolith vadose region, slip casting process improves note silica solution grouting pressure Reach and stops slip casting and sealing of hole after 0.2~0.8MPa after 60~180min of pressure stabilizing.
Seepage distance between described two deep injected holes or between two shallow injected holes, which will exist, to intersect, and designs deep injected hole or shallow note Interaction coefficent is selected as 0.65-0.8 when array pitch between slurry hole, and according to live lithology, hole cranny development and actual observation infiltration away from From, the parameter of array pitch between adjustment, fracture area model that the depth of shallow injected hole and deep injected hole is pried through according to inspection instrument for borehole scene Enclose determination.
Side top, the deep injected hole setting angle of the shallow injected hole of bottom and side bottom and the horizontal direction of being arranged in is pressed from both sides 15 ° of angle, be arranged in top plate two corners deep injected hole and shallow injected hole setting angle with 15 ° of vertical direction angle, remaining injected hole Equal vertical perforating.
The utility model has the advantages that
1) the application stops pulp layer by constituting concrete in the scar gunite concrete to tunnel surrounding, effectively closing scar Big crack, and stop in concrete and spray nano silicone sol layer in pulp layer again, fast and effective closed porosity crack, thus in tunnel table Face forms separation layer, blocks hydrone in tunnel, and air molecule enters the channel of roadway surrounding rock, significantly hinder absorption, dissolution, The microcosmic effects such as weathering, it is therefore prevented that the further long-term aquation in argillaceous soft rock tunnel, weathering;
2) the cement grout diffusion filling injected by shallow injected hole and consolidation are destroyed fissure-plane to be formed or original, Superficial part fracture area country rock is reinforced, rock mass strength is improved, better wall rock condition is provided for tunnel is further stable, participates in tunnel and enclose Rock stress equilibrium process, to give full play to the bearing capacity of rock mass;
3) silica solution is injected to deep hole, provides silica solution diffusion power using capillary force, by slowly seeping for a long time Diffusion thoroughly keeps mud stone microstructure closeer to effectively close argillaceous soft rock tunnel deep nanoscopic matrix system micropore crack It is real, more whole, crack aquaporin is blocked, permeability is reduced, after preventing the rock mass after being reinforced with cement slurry from meeting water again gradually Soften disintegration, weakening strength, dilatancy destruction;
4) combine the silicon of deep injected hole injection molten using the scar shotcrete layer of tunnel surrounding, nano silicone sol layer Glue blocks the channel that hydrone, air molecule, crevice water etc. enter cement slurry induration inside and outside roadway surrounding rock respectively;It infuses simultaneously The cement slurry entered strengthens superficial part fracture area country rock, and the reinforcement means of this stereogenic weakens flood to argillaceous soft rock lane The influence in road increases argillaceous soft rock tunnel non-deformability and endurance quality, and it is prominent to solve argillaceous soft rock tunnel after meeting water The Nonlinear Large Deformation of performance, significant rheology and the problem by disturbing influence etc.;
By the concrete layer and nano silicone sol layer constituted on tunnel surface, in conjunction with to along argillaceous soft rock tunnel radial direction Complete vadose region, orientation fills cement slurry within the scope of vadose region respectively, and injects silicon in seepage flow blind zone, protolith vadose region On the one hand colloidal sol can effectively fill superficial part Fracture System, reinforce superficial part fracture area country rock, on the other hand can close argillaceous soft rock lane The flood that there are problems that may cause due to micropore crack is alleviated in road deep matrix system micropore crack, effectively control country rock Argillization process in deformation process solves the Large Deformation Support problem of argillaceous soft rock tunnel softening rheology.Step is simple, is implemented as This is low, and supporting effect is good.
Detailed description of the invention
Fig. 1 is the section view that injected hole is arranged in the grouting strengthening method of subregion more granularities in argillaceous soft rock tunnel of the invention Figure.
Fig. 2 is portion, side injected hole side view in the grouting strengthening method of subregion more granularities in argillaceous soft rock tunnel of the invention.
Fig. 3 is the grouting strengthening method insole board injected hole top view of subregion more granularities in argillaceous soft rock tunnel of the invention.
In figure: the shallow injected hole of 1-;2- Grouting Pipe;3- depth injected hole;4- concrete and silica solution spray-up.
Specific embodiment
In the following with reference to the drawings and specific embodiments, the present invention is furture elucidated, it should be understood that these examples are merely to illustrate this It invents rather than limits the scope of the invention, after the present invention has been read, those skilled in the art are to of the invention various The modification of equivalent form falls within the application range as defined in the appended claims.
As shown in FIG. 1 to 3, the grouting strengthening method of subregion more granularities in argillaceous soft rock tunnel of the invention, according to specific The geological information data in tunnel evaluates corresponding geology state, and shallow slip casting is designed in tunnel according to the geology state evaluated The boring point in hole 1 and deep injected hole 3 is anchored to tunnel surrounding and is arranged concrete and silica solution spray with tunnelling Layer 4;It constructs in the portion, side in tunnel and roof and floor shallow injected hole 1 and hole-sealing grouting, in the deep injected hole boring point being pre-designed Depth of constructing injected hole 3 and hole-sealing grouting, thus effectively within closed reinforcement to deep protolith area.
Specific step is as follows:
A, geological test is carried out to tested tunnel, and obtains corresponding geological information data, according to geological test and ground Matter information material is assessed to obtain roadway surrounding rock lithology, hole cranny development and hydrological geological conditions;
B, according to roadway surrounding rock lithology, the developmental state in hole crack and the hydrological geological conditions evaluated in tunnel side wall With the boring point for designing shallow injected hole 1 and deep injected hole 3 on bottom plate;
C, it with tunnelling, assesses tunnel radial direction country rock hole seam area and draws feature, in time to tunnel four after anchoring The scar gunite concrete in week closes the big crack of scar, stops pulp layer for subsequent grouting construction, concrete setting is waited to be formed later Concrete stops pulp layer, stops in concrete and sprays silica solution composition silica sol layer in pulp layer again, and timely closed concrete stops pulp layer micropore Crack prevents country rock to be etched to form concrete and silica solution spray-up 4, long-term rear aquation, weathering;It states to tunnel surrounding Scar spray the concrete to be formed and stop pulp layer with a thickness of 80mm~120mm;Stop the silica sol layer sprayed again in pulp layer in concrete With a thickness of 2mm~5mm.
D, after roadway excavation 10~20 days, the shallow injected hole boring point being pre-designed in the portion, side in tunnel and roof and floor is applied The shallow injected hole 1 of work injects cement slurry and sealing of hole, the side in tunnel to shallow injected hole 1 by Grouting Pipe 2 using grouting equipment 1 hole depth of shallow injected hole constructed in portion and roof and floor is 2.0m~2.5m, and the complete vadose region across rock stratum is until orienting seepage flow Area, grouting pressure is improved during slip casting reaches and stop slip casting and sealing of hole after 15~20min of pressure stabilizing after 1~2MPa, in cement slurry Grouting pressure driving under, cement slurry is by shallow injected hole diffusion filling mud stone superficial part crack to which closed reinforcement superficial part is broken Area's country rock;
E, after Shallow hole grouting terminates 25~35 days, the deep slip casting hole drilling that is pre-designed in the portion, side in tunnel and roof and floor The deep injected hole 3 of point construction injects silica solution simultaneously sealing of hole by 2 pairs of Grouting Pipe deep injected holes 3 using grouting equipment, described in tunnel Portion, side and roof and floor on 3 hole depth of deep injected hole constructed be 4m~6m, deep injected hole 3 passes through the complete vadose region, fixed of rock stratum To vadose region, seepage flow blind zone until protolith vadose region, slip casting process improves note silica solution grouting pressure and reaches 0.2~0.8MPa Stop slip casting and sealing of hole after 60~180min of pressure stabilizing afterwards, under the driving of capillary force, silica solution passes through deep injected hole and seeps filling slowly Soft-rock tunnel deep matrix system micropore crack, thus within closed reinforcement to deep protolith area.
Seepage distance between described two deep injected holes or between two shallow injected holes, which will exist, to intersect, and designs deep injected hole or shallow note Interaction coefficent is selected as 0.65-0.8 when array pitch between slurry hole, and according to live lithology, hole cranny development and actual observation infiltration away from From, the parameter of array pitch between adjustment, fracture area model that the depth of shallow injected hole and deep injected hole is pried through according to inspection instrument for borehole scene Enclose determination.Side top, the deep injected hole setting angle of the shallow injected hole of bottom and side bottom and the horizontal direction of being arranged in is pressed from both sides 15 ° of angle, be arranged in top plate two corners deep injected hole and shallow injected hole setting angle with 15 ° of vertical direction angle, remaining injected hole Equal vertical perforating.
Embodiment one:
Certain coal mine rectangular cross section tunnel, wide × height=5.0 × 3.6m, top plate is siltstone, is rich in crevice water;Portion, side and bottom Plate is the mud stone of micropore cranny development, meets cement.To control the large deformation of tunnel rheology, using cement slurry and silica solution subregion Grouting strengthening method slip casting.
It is anchored in time after tunnelling, gunite concrete and silica solution, the jet thickness of concrete is 100mm, sprays silicon again Colloidal sol, silica solution are current material, and by A, B material composition, A material is silicon dioxide colloid, and B material is catalyst sodium chloride solution, institute It is A material: B material=4:1 with its parameter, with a thickness of 2mm.
After tunnelling 15 days, in portion, side and the shallow injected hole 1 of construction of bottom plates, hole depth 2.2m, array pitch 1.5m × 1.5m, side The shallow injected hole of portion's top/bottom part 1 with 15 ° of horizontal direction angle, the shallow injected hole 1 of bottom plate or so two corners with 15 ° of vertical direction angle, The equal vertical perforating of remaining shallow injected hole 1, is detailed in attached drawing 1;Grouting Pipe 2 and sealing of hole are installed, cement slurry, the water ash quality of cement slurry are injected Than=1:1;Grouting pressure is 1.5MPa, stops slip casting after pressure stabilizing 15min.It checks before slip casting to the non-gunite concrete in tunnel or silicon Colloidal sol section carries out gunite concrete and silica solution reinforces closing.
After Shallow hole grouting 30 days, carries out deep and infuse silica solution, silica solution A material: B material=9:1, it is deep in portion, side and construction of bottom plates Injected hole 3, hole depth 5m, array pitch 1.5m × 1.5m, for portion, side depth injected hole 3 according to the shallow injected hole 1 of a row from top to bottom, a row is deep Injected hole 3, which interleaves, is arranged in shallow 1 intermediate arrangement of injected hole, and bottom plate depth injected hole 3 is according to the shallow injected hole 1 of a row from left to right, and one Arrange deep injected hole 3, interleave and be arranged in shallow 1 intermediate arrangement of injected hole, portion, side bottom depth injected hole with 15 ° of horizontal direction angle, bottom Two pull injected hole 3 of plate or so with 15 ° of vertical direction angle, remaining equal vertical perforating of deep injected hole 3 is detailed in attached drawing 1, slip casting pressure Power is 0.5MPa, stops slip casting after pressure stabilizing 120min, and during which under the driving of capillary force, it is micro- that silica solution slowly diffuses into rock mass Crack forms high compact reinforcing body, completes to reinforce country rock.
Scene shows that the grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion can control argillaceous soft rock lane well The softening rheology in road.

Claims (6)

1. a kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion, it is characterised in that: according to the geology in specific tunnel Information material evaluates corresponding geology state, and shallow injected hole and deep slip casting are designed in tunnel according to the geology state evaluated The boring point in hole is anchored to tunnel surrounding and is arranged concrete and silica solution spray-up with tunnelling;Side in tunnel It constructs in portion and roof and floor shallow injected hole and hole-sealing grouting, constructs and deep injected hole and seal in the deep injected hole boring point being pre-designed Hole slip casting, thus effectively within closed reinforcement to deep protolith area;
Specific step is as follows:
A, geological test is carried out to tested tunnel, and obtains corresponding geological information data, believed according to geological test and geology Breath data is assessed to obtain roadway surrounding rock lithology, hole cranny development and hydrological geological conditions;
B, according to roadway surrounding rock lithology, the developmental state in hole crack and the hydrological geological conditions evaluated on tunnel side wall and top The boring point of shallow injected hole and deep injected hole is designed on bottom plate;
C, it with tunnelling, assesses tunnel radial direction country rock hole seam area and draws feature, in time to tunnel surrounding after anchoring Scar gunite concrete closes the big crack of scar, stops pulp layer for subsequent grouting construction, concrete setting is waited to form coagulation later Soil stops pulp layer, stops in concrete and sprays silica solution composition silica sol layer in pulp layer again, and timely closed concrete stops pulp layer micropore crack, To form concrete and silica solution spray-up, country rock is prevented to be etched, long-term rear aquation, weathering;
D, after roadway excavation 10 ~ 20 days, the shallow injected hole boring point construction being pre-designed in the portion, side in tunnel and roof and floor is shallow Injected hole injects cement slurry and sealing of hole to shallow injected hole by Grouting Pipe using grouting equipment, in the grouting pressure of cement slurry Under driving, cement slurry is by shallow injected hole diffusion filling mud stone superficial part crack to closed reinforcement superficial part fracture area country rock;
E, after Shallow hole grouting terminates 25 ~ 35 days, the deep injected hole boring point being pre-designed in the portion, side in tunnel and roof and floor is applied Work depth injected hole injects silica solution and sealing of hole to deep injected hole by Grouting Pipe using grouting equipment, under the driving of capillary force, Silica solution, which passes through deep injected hole and seeps slowly, fills soft-rock tunnel deep matrix system micropore crack, so that closed reinforcement is to deep protolith Within area.
2. the grouting strengthening method of the more granularities of argillaceous soft rock tunnel according to claim 1 subregion, it is characterised in that: described To the scar shotcrete layer of tunnel surrounding with a thickness of 80mm ~ 120mm;Stop the silica sol layer sprayed again in pulp layer in concrete With a thickness of 2mm ~ 5mm.
3. the grouting strengthening method of the more granularities of argillaceous soft rock tunnel according to claim 1 subregion, it is characterised in that: described The shallow injected hole hole depth constructed in the portion, side in tunnel and roof and floor be 2.0m ~ 2.5m, across rock stratum complete vadose region until Vadose region is oriented, grouting pressure is improved during slip casting reaches and stop slip casting and sealing of hole after 15 ~ 20min of pressure stabilizing after 1 ~ 2MPa.
4. the grouting strengthening method of the more granularities of argillaceous soft rock tunnel according to claim 1 subregion, it is characterised in that: described The deep injected hole hole depth constructed in the portion, side in tunnel and roof and floor be 4m ~ 6m, deep injected hole pass through rock stratum complete vadose region, Vadose region, seepage flow blind zone are oriented until protolith vadose region, slip casting process improve note silica solution grouting pressure reach 0.2 ~ Stop slip casting and sealing of hole after 0.8MPa after 60 ~ 180min of pressure stabilizing.
5. the grouting strengthening method of the more granularities of argillaceous soft rock tunnel according to claim 3 or 4 subregion, it is characterised in that: Seepage distance between described two deep injected holes or between two shallow injected holes, which will exist, to intersect, and designs and arranges between deep injected hole or shallow injected hole Away from when interaction coefficent be selected as 0.65-0.8, and according to live lithology, hole cranny development and actual observation seepage distance, adjustment Between array pitch parameter, the depth of shallow injected hole and deep injected hole determines according to the fracture area range that inspection instrument for borehole scene is pried through.
6. the grouting strengthening method of the more granularities of argillaceous soft rock tunnel according to claim 5 subregion, it is characterised in that: described Be arranged in side top, bottom shallow injected hole and help bottom deep injected hole setting angle and 15 ° of horizontal direction angle, be arranged in The deep injected hole of top plate two corners and shallow injected hole setting angle with 15 ° of vertical direction angle, the equal vertical perforating of remaining injected hole.
CN201710484682.1A 2017-06-23 2017-06-23 A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion Active CN107083977B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201710484682.1A CN107083977B (en) 2017-06-23 2017-06-23 A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion
PCT/CN2017/105793 WO2018233149A1 (en) 2017-06-23 2017-10-12 Argillaceous soft rock roadway partition multi-granularity grouting reinforcement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710484682.1A CN107083977B (en) 2017-06-23 2017-06-23 A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion

Publications (2)

Publication Number Publication Date
CN107083977A CN107083977A (en) 2017-08-22
CN107083977B true CN107083977B (en) 2019-05-14

Family

ID=59607154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710484682.1A Active CN107083977B (en) 2017-06-23 2017-06-23 A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion

Country Status (2)

Country Link
CN (1) CN107083977B (en)
WO (1) WO2018233149A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127909A (en) * 2020-09-08 2020-12-25 河海大学 Accurate grouting repairing and reinforcing method for broken surrounding rock of tunnel

Families Citing this family (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107083977B (en) * 2017-06-23 2019-05-14 中国矿业大学 A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion
CN107355226B (en) * 2017-08-23 2023-08-22 中国电建集团成都勘测设计研究院有限公司 Broken area hole section processing structure of TBM construction tunnel fault
CN107313789A (en) * 2017-08-31 2017-11-03 中国电建集团成都勘测设计研究院有限公司 Large underground hole surrounding rock supporting structure under large ground pressure
CN108035738A (en) * 2017-12-08 2018-05-15 中国矿业大学 The anchoring process of more anchor pole simultaneous quantitative slip castings
CN108104845B (en) * 2017-12-14 2019-10-01 中国水利水电第六工程局有限公司 A kind of tunnel sealing stream device and seepage flow processing method
CN109139053A (en) * 2018-09-30 2019-01-04 淮矿西部煤矿投资管理有限公司 A kind of water conductive fault comprehensive treatment parallel construction system and construction method
CN109538244A (en) * 2018-11-15 2019-03-29 合肥工业大学 Method for protecting support in tunnel excavation hole
CN110159305B (en) * 2019-04-12 2020-10-20 平顶山天安煤业股份有限公司 Method for optimizing coal wall grouting parameters of composite roof working surface with large mining depth and large mining height
CN110130316A (en) * 2019-05-13 2019-08-16 南京林业大学 The method of thaw collapse after service channel bottom pre-pouring grout system and control freezing construction
CN111018434B (en) * 2019-11-20 2021-11-09 辽宁工程技术大学 Mudstone hydrophobic modified grouting material and preparation method thereof
CN111365039B (en) * 2020-03-25 2021-08-06 上海同岩土木工程科技股份有限公司 Tunnel water leakage treatment method
CN111335900B (en) * 2020-03-25 2021-04-27 王�琦 High-strength anchoring and grouting self-tunneling method and system
CN111764933B (en) * 2020-07-06 2021-10-15 高军 Construction method for rapid seepage-proofing consolidation grouting plugging of water-rich tunnel
CN112012770A (en) * 2020-07-26 2020-12-01 中铁二院工程集团有限责任公司 Underground water advanced treatment structure and construction method for ultra-deep vertical shaft of railway tunnel
CN112253186A (en) * 2020-07-26 2021-01-22 中铁二院工程集团有限责任公司 Method for stopping leakage of working faces at different layer depths of railway tunnel shaft
CN112539073A (en) * 2020-12-28 2021-03-23 内蒙古上海庙矿业有限责任公司 Grouting reinforcement method for soft rock roadway
CN113605913B (en) * 2021-09-01 2024-05-07 东莞理工学院 Rock underground passage construction method
CN113803087B (en) * 2021-09-07 2023-11-10 山西晋煤集团技术研究院有限责任公司 Small coal pillar gob-side entry driving broken surrounding rock grouting reinforcement method
CN113803086A (en) * 2021-09-07 2021-12-17 山西晋煤集团技术研究院有限责任公司 Segmented layered circulating grouting construction method for soft coal seam multiplexing roadway
CN113550754B (en) * 2021-09-16 2021-12-10 中国矿业大学(北京) Method and system for performing advanced drilling of coal seam roadway based on bottom suction roadway cross-layer drilling
CN114000896B (en) * 2021-10-12 2024-05-07 中煤科工开采研究院有限公司 Composite grouting reinforcement method for deep-section fracture surrounding rock
CN113958324B (en) * 2021-10-19 2024-05-07 金川集团股份有限公司 Method for grouting and reinforcing deep drilling of roadway bottom plate
CN114165268B (en) * 2021-12-03 2023-12-08 兖矿能源集团股份有限公司 Grading coordination strengthening method for coal roadway tunneling broken surrounding rock
CN114875854A (en) * 2022-04-28 2022-08-09 河南安钢集团舞阳矿业有限责任公司 Anti-leakage method for overflow culvert of tailing pond

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102838323A (en) * 2012-09-20 2012-12-26 中铁西南科学研究院有限公司 High-performance concrete gel material for tunnel and application thereof
CN104594914A (en) * 2014-08-18 2015-05-06 河南理工大学 Coal mine tunnel broken surrounding rock layering grouting technology and method
CN105178981A (en) * 2015-09-30 2015-12-23 中国矿业大学 Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway
CN105201528A (en) * 2015-09-21 2015-12-30 中国矿业大学 Silica sol slow infiltration reinforcing method of argillaceous soft rock

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09303077A (en) * 1996-05-14 1997-11-25 Tokai Rubber Ind Ltd Stabilizing-reinforcing construction method of facing
KR100475416B1 (en) * 2002-01-29 2005-03-10 정종주 Micro silica grouting method reinforced with a steel pipe
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
JP2014092020A (en) * 2012-11-07 2014-05-19 Shimizu Corp Grout injection method
CN104594919A (en) * 2015-01-22 2015-05-06 山东科技大学 Soft rock roadway buffering tapered double strong shell support system and construction method thereof
CN107083977B (en) * 2017-06-23 2019-05-14 中国矿业大学 A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102838323A (en) * 2012-09-20 2012-12-26 中铁西南科学研究院有限公司 High-performance concrete gel material for tunnel and application thereof
CN104594914A (en) * 2014-08-18 2015-05-06 河南理工大学 Coal mine tunnel broken surrounding rock layering grouting technology and method
CN105201528A (en) * 2015-09-21 2015-12-30 中国矿业大学 Silica sol slow infiltration reinforcing method of argillaceous soft rock
CN105178981A (en) * 2015-09-30 2015-12-23 中国矿业大学 Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
破碎围岩注浆加固技术研究;张王磊;《中国优秀硕士学位论文全文数据库》;20170315(第3期);第35-51、63-66页 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127909A (en) * 2020-09-08 2020-12-25 河海大学 Accurate grouting repairing and reinforcing method for broken surrounding rock of tunnel

Also Published As

Publication number Publication date
WO2018233149A1 (en) 2018-12-27
CN107083977A (en) 2017-08-22

Similar Documents

Publication Publication Date Title
CN107083977B (en) A kind of grouting strengthening method of the more granularities of argillaceous soft rock tunnel subregion
CN107237651B (en) A kind of multi-level grouting water-tight reinforcement means of coal mine underground reservoir and reservoir dam
CN103821538B (en) J-type horizontal assistant branched hole surface advance grouting paste-making method
CN110318770A (en) A kind of hazy start tunneling method of vcehicular tunnel
CN105201528A (en) Silica sol slow infiltration reinforcing method of argillaceous soft rock
CN106544961A (en) A kind of distress in concrete blocking method
KR20050114193A (en) A grout carrying out mehtod for paste backfill grouting at the cave
CN103485808B (en) Electro-osmosis home position modified roadway anchoring method of underground swelling soft rock
CN110374134A (en) A kind of combined member increased suitable for retaining wall and construction method
CN105064157A (en) Treatment method of settlement of high-speed railway roadbeds in soft-soil areas
CN204112305U (en) Existing railway line excavation section weak subgrade is reinforced and is used multi-functional lobby water system
JP3972260B2 (en) Low concentration grout method
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN107201909A (en) Swelled ground tunnel support structure and method
CN109707422A (en) A kind of goaf roadway fender grouting method for protecting support
CN207331673U (en) A kind of mini-valve tube horizontal grouting constructing device
CN104532855A (en) Combined pile supporting structure in deep and thick peat soil layer
KR100947627B1 (en) The grouting structure of tunnel and tunnel construction method using the same
CN105971637A (en) Application of WSS construction method in shield end reinforcement of water-rich sand layer
CN106761841B (en) Working face tailgate fractured coal grouting reinforcement method
CN109441486A (en) The grouting method reinforced for tunnel grouting
CN103573280A (en) Method for supporting porous ooze invasion compound roof roadway
CN105114099A (en) Poorly consolidated formation roadway support method and system
CN105019427A (en) Bolting-grouting integrated treatment method for railway tunnel base disease
CN206736650U (en) A kind of road structure of deep-lying karst area water sealing consolidation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20170822

Assignee: Anhui Huayao Keli Engineering Technology Co.,Ltd.

Assignor: CHINA University OF MINING AND TECHNOLOGY

Contract record no.: X2021320000191

Denomination of invention: A multi granularity grouting reinforcement method for argillaceous soft rock roadway

Granted publication date: 20190514

License type: Common License

Record date: 20211230