CN112253186A - Method for stopping leakage of working faces at different layer depths of railway tunnel shaft - Google Patents

Method for stopping leakage of working faces at different layer depths of railway tunnel shaft Download PDF

Info

Publication number
CN112253186A
CN112253186A CN202010728472.4A CN202010728472A CN112253186A CN 112253186 A CN112253186 A CN 112253186A CN 202010728472 A CN202010728472 A CN 202010728472A CN 112253186 A CN112253186 A CN 112253186A
Authority
CN
China
Prior art keywords
grouting
deep
holes
plugging
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010728472.4A
Other languages
Chinese (zh)
Inventor
王唤龙
杨昌宇
朱廷宇
范圣明
邸成
宋智来
李昕晖
王贵虎
朱勇
范磊
刘黎
黄智�
徐军
刘建兵
曾云川
曾劲
桂林岗
胡金星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN202010728472.4A priority Critical patent/CN112253186A/en
Publication of CN112253186A publication Critical patent/CN112253186A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The method for plugging the working surfaces of different layer depths of the railway tunnel shaft effectively plugs underground water of different layer depths, provides a safe and waterless operation environment for the working surface of the shaft, and ensures the safety of shaft digging construction, comprising the following steps: drilling a vertically extending shallow grouting hole on a working surface of a vertical shaft, wherein the depth of the shallow grouting hole is greater than the height of a circulating digging and building section of the vertical shaft; secondly, shallow low-pressure grouting plugging is conducted, low-pressure grouting is conducted through each shallow grouting hole, and the complete plugging of water gushing on the working face of the vertical shaft is completed; drilling deep grouting holes on the working surface of the vertical shaft, wherein the deep grouting holes comprise outer ring deep inclined holes and inner ring deep vertical holes, and the depth of the deep grouting holes is more than twice that of the shallow grouting holes; and fourthly, deep high-pressure grouting plugging, wherein high-pressure grouting is carried out through deep inclined holes of the outer ring and deep vertical holes of the inner ring, and grouting reinforcement is carried out on rock mass in front of the working face of the vertical shaft and advanced plugging is carried out on deep underground water.

Description

Method for stopping leakage of working faces at different layer depths of railway tunnel shaft
Technical Field
The invention relates to a railway tunnel, in particular to a method for plugging working faces of different layer depths of a railway tunnel shaft.
Background
Railway engineering can emerge a large number of extra-long tunnels in western severe mountainous areas, and is controlled by the landforms of the mountainous areas, particularly for mountainous areas with difficult terrain crossing conditions, and deep and large vertical shafts with higher construction risks have to be adopted to solve the problems of ventilation, construction period, drainage, slag removal and the like in the construction of extra-long tunnels due to the fact that mountains are thick and surface ditches are not developed very much.
The underground water is used as a main cause of disasters such as shaft inrush flooding, shaft wall collapse and the like, is a problem which needs to be treated in the construction of a railway tunnel shaft, and particularly, the underground water at the working face of the shaft can cause disastrous results if the underground water is not treated properly due to the gathering of operators. At present, underground water treatment at the working face of a railway tunnel shaft in China mainly refers to advanced grouting water plugging with a large section height of the working face adopted by the coal mine industry, the treatment method can achieve a good effect on a slowly-inclined sedimentary rock stratum with obvious water-bearing layer and good rock fracture hydraulic connectivity, but the geological structure of western areas in China is very complex, railway tunnel shaft engineering mostly penetrates through the rock-slurry rock stratum, the water-bearing layer is unevenly distributed, the rock fracture is irregularly developed, the underground water hydraulic connectivity is poor, and conventional advanced grouting of the working face generates grouting blind areas for steeply-inclined irregular fracture water, so that potential safety hazards are left for subsequent shaft digging and building. Therefore, how to effectively plug underground water at the working face so as to expect that the working face of the vertical shaft is constructed in a safe and waterless state is a big problem for constructing the deep and large vertical shaft of the railway tunnel.
Disclosure of Invention
The invention aims to solve the technical problem of providing a method for plugging underground water of different depths of working faces of a vertical shaft of a railway tunnel, which can effectively plug the underground water of different depths of the working faces of the vertical shaft, provide a safe and waterless working environment for the working faces of the vertical shaft, ensure the safety of the driving and laying construction of the vertical shaft,
the technical scheme adopted by the invention for solving the technical problems is as follows:
the invention discloses a method for plugging working faces of different layer depths of a railway tunnel shaft, which comprises the following steps:
drilling a vertically extending shallow grouting hole on a working surface of a vertical shaft, wherein the depth of the shallow grouting hole is greater than the height of a circulating digging and building section of the vertical shaft;
secondly, shallow low-pressure grouting plugging is conducted, low-pressure grouting is conducted through each shallow grouting hole, and the complete plugging of water gushing on the working face of the vertical shaft is completed;
drilling deep grouting holes on the working surface of the vertical shaft, wherein the deep grouting holes comprise outer ring deep inclined holes and inner ring deep vertical holes, and the depth of the deep grouting holes is more than twice that of the shallow grouting holes;
and fourthly, deep high-pressure grouting plugging, wherein high-pressure grouting is carried out through deep inclined holes of the outer ring and deep vertical holes of the inner ring, and grouting reinforcement is carried out on rock mass in front of the working face of the vertical shaft and advanced plugging is carried out on deep underground water.
The invention has the advantages that the deep underground water plugging of different layers can be realized by combining shallow hole low-pressure grouting plugging and deep hole high-pressure grouting plugging according to the underground water exposure condition of the working surface of the vertical shaft, a safe and waterless working environment is provided for the working surface of the vertical shaft, the rock mass in front of the working surface is reinforced, the safety of the driving and building construction of the vertical shaft is ensured, and the invention has very obvious social and economic benefits and application values.
Drawings
The specification includes the following four figures:
FIG. 1 is a schematic view of the arrangement of the vertical faces of shallow grouting holes in the method for plugging the working faces at different depths of a railway tunnel shaft;
FIG. 2 is a schematic plan view of shallow grouting holes in the method for plugging a deep working face of different layers of a railway tunnel shaft;
FIG. 3 is a schematic diagram showing the vertical arrangement of deep grouting holes in the method for plugging the working face at different depths of the railway tunnel shaft;
fig. 4 is a schematic plan view of deep grouting holes in the method for plugging working faces at different depths of the railway tunnel shaft.
The figure shows the components, the part names and the corresponding marks: the vertical shaft comprises a vertical shaft 10, a shallow grouting hole 11, an outer ring deep inclined hole 12a, an inner ring deep vertical hole 12b and a vertical shaft working surface D.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
Referring to fig. 1 to 4, the method for stopping leakage of the working surface of the railway tunnel shaft at different layer depths comprises the following steps:
drilling a shallow grouting hole 11 extending vertically on a working surface D of a vertical shaft, wherein the depth of the shallow grouting hole 11 is greater than the height of a circulating excavation section of a vertical shaft 10;
secondly, shallow low-pressure grouting plugging is conducted, low-pressure grouting is conducted through each shallow grouting hole 11, and complete plugging of water gushing on the working surface D of the vertical shaft is completed;
drilling deep grouting holes on the working surface D of the vertical shaft, wherein the deep grouting holes comprise outer ring deep inclined holes 12a and inner ring deep vertical holes 12b, and the depth of the deep grouting holes is more than twice of that of the shallow grouting holes 11;
and fourthly, deep high-pressure grouting plugging, wherein high-pressure grouting is carried out through the outer ring deep inclined holes 12a and the inner ring deep vertical holes 12b, and grouting reinforcement is carried out on rock mass in front of the shaft working surface D and advanced plugging is carried out on deep groundwater.
According to the invention, the shallow hole low-pressure grouting plugging and the deep hole high-pressure grouting plugging are combined, so that the plugging of different layers of deep underground water is realized, a safe and waterless operation environment is provided for the working surface of the vertical shaft, the rock mass in front of the working surface is reinforced, and the safety of the driving and building construction of the vertical shaft is ensured.
Referring to fig. 1 and 2, the shallow grouting holes 11 are vertical holes, are arranged on the shaft working surface D at intervals in the radial direction and the circumferential direction, and are densely distributed near the water outlet point. The hole distribution quantity and the hole spacing are determined according to the water outlet condition of the working surface D of the vertical shaft, and the depth of the grouting hole is larger than the height of the circulating digging and building section of the vertical shaft 10.
Referring to fig. 3 and 4, the outer ring deep inclined holes 12a and the inner ring deep vertical holes 12b are radially and annularly arranged on the working surface D of the shaft at intervals, the holes are uniformly arranged in a quincunx shape, and the hole depth is more than twice of the depth of the shallow grouting holes 11, so that the safety of circular digging and building of the shaft is ensured. The outer ring deep inclined holes 12a are mainly used for plugging underground water around the vertical shaft 10 to form a water-resisting layer with a certain thickness, and the inner ring deep vertical holes 12b are used for plugging the underground water in front of the working surface D of the vertical shaft.
The orifices of the shallow grouting hole 11, the outer ring deep inclined hole 12a and the inner ring deep vertical hole 12b are all sealed by winding hemp threads on a horsetooth pipe, the horsetooth pipe is firmly fixed in a drilled hole, and the horsetooth pipe is wound with more hemp threads and tightened as much as possible so as to prevent the horsetooth pipe from being ejected by grouting pressure during grouting.
The foregoing is illustrative of the principles of the method for plugging a working surface at different depths in a railway tunnel shaft of the present invention and is not intended to limit the invention to the exact construction and applications shown and described, and accordingly, all modifications and equivalents that may be resorted to are intended to fall within the scope of the invention.

Claims (4)

1. The method for plugging the working surfaces of different layer depths of the railway tunnel shaft comprises the following steps:
firstly, drilling a shallow grouting hole (11) which extends vertically in a shaft working surface (D), wherein the depth of the shallow grouting hole (11) is greater than the height of a circulating digging and building section of a shaft (10);
shallow low-pressure grouting plugging is carried out, low-pressure grouting is carried out through each shallow grouting hole (11), and the complete plugging of water burst of a vertical shaft working surface (D) is completed;
drilling deep grouting holes in the working surface (D) of the vertical shaft, wherein the deep grouting holes comprise outer ring deep inclined holes (12a) and inner ring deep vertical holes (12b), and the depth of the deep grouting holes is more than twice of that of the shallow grouting holes (11);
and fourthly, deep high-pressure grouting plugging, wherein high-pressure grouting is carried out through the outer ring deep inclined holes (12a) and the inner ring deep vertical holes (12b), and grouting reinforcement is carried out on rock mass in front of the working surface (D) of the vertical shaft and advanced plugging is carried out on deep groundwater.
2. The method for plugging the working surface of the railway tunnel shaft at different depths of the layer as claimed in claim 1, which is characterized in that: the shallow grouting holes (11) are vertical holes with multiple circles, are arranged on the working surface (D) of the vertical shaft at intervals in the radial direction and the circumferential direction, and are densely distributed near the water outlet point.
3. The method for plugging the working surface of the railway tunnel shaft at different depths of the layer as claimed in claim 1, which is characterized in that: the outer ring deep inclined holes (12a) and the inner ring deep vertical holes (12b) are arranged on the vertical shaft working surface (D) at intervals in the radial direction and the circumferential direction, and all the holes are uniformly arranged in a quincunx shape.
4. The method for plugging the working surface of the railway tunnel shaft at different depths of the layer as claimed in claim 1, which is characterized in that: the orifices of the shallow grouting hole (11), the outer ring deep inclined hole (12a) and the inner ring deep vertical hole (12b) are all sealed by adopting a crenella tube twined with hemp threads, and the crenella tube is firmly fixed in a drilled hole.
CN202010728472.4A 2020-07-26 2020-07-26 Method for stopping leakage of working faces at different layer depths of railway tunnel shaft Pending CN112253186A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010728472.4A CN112253186A (en) 2020-07-26 2020-07-26 Method for stopping leakage of working faces at different layer depths of railway tunnel shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010728472.4A CN112253186A (en) 2020-07-26 2020-07-26 Method for stopping leakage of working faces at different layer depths of railway tunnel shaft

Publications (1)

Publication Number Publication Date
CN112253186A true CN112253186A (en) 2021-01-22

Family

ID=74224430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010728472.4A Pending CN112253186A (en) 2020-07-26 2020-07-26 Method for stopping leakage of working faces at different layer depths of railway tunnel shaft

Country Status (1)

Country Link
CN (1) CN112253186A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114370252A (en) * 2021-12-17 2022-04-19 核工业北京地质研究院 Shallow hole reinforcing method suitable for high-temperature geothermal well

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
CN103277120A (en) * 2013-06-19 2013-09-04 西安科技大学 Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft
CN103628894A (en) * 2013-10-24 2014-03-12 重庆大学 Water-rich fault fracture zone collapsed roadway repairing method based on angle-variable umbrella-shaped advancing grouting
CN103696775A (en) * 2013-12-20 2014-04-02 中煤第一建设有限公司 Large-stage-height multi-group water-containing layer segmented downward grouting method
CN105041345A (en) * 2015-08-18 2015-11-11 山东大学 Life-cycle treatment method of water inrush in tunnel
CN105927232A (en) * 2016-05-19 2016-09-07 安徽理工大学 Deep-blocking and shallow-grouting grouting method for no-blank area of mine and grouting safety protecting device
CN107083977A (en) * 2017-06-23 2017-08-22 中国矿业大学 A kind of grouting strengthening method of many granularities of argillaceous soft rock tunnel subregion
CN207177933U (en) * 2016-11-23 2018-04-03 中国电建集团华东勘测设计研究院有限公司 A kind of advanced plugging structure of high-pressure high-flow underground water
CN108661650A (en) * 2018-04-23 2018-10-16 中铁隧道局集团有限公司 A kind of rich water magmatic body area depth pozo shaft construction method
CN108756893A (en) * 2018-04-19 2018-11-06 济南城建集团有限公司 A kind of city shallow tunnel vault soil stabilization method
CN108868776A (en) * 2018-07-06 2018-11-23 中钢集团马鞍山矿山研究院有限公司 The high pressure-bearing broken rock of deep-well induces pre-pouring grout reinforcement means in advance
CN109162731A (en) * 2018-08-16 2019-01-08 山东科技大学 Iron producing area deep mining gushing water grouting treatment method
CN109209287A (en) * 2018-09-12 2019-01-15 中国矿业大学 A kind of shaft of vertical well crosses high inclination-angle tomography working face segmentation Curtain Grouting Construction method
CN109505628A (en) * 2018-12-06 2019-03-22 中铁三局集团广东建设工程有限公司 A kind of water-rich fault zone method for tunnel construction
CN109681214A (en) * 2019-03-01 2019-04-26 中国水利水电第八工程局有限公司 A kind of construction method of Full-face pouring strengthening stratum
US20190316454A1 (en) * 2017-05-10 2019-10-17 China University Of Mining And Technology Stress-transfer method in tunnel with high ground pressure based on fracturing ring
CN110656951A (en) * 2019-09-27 2020-01-07 中国科学院武汉岩土力学研究所 Disaster safety control method for full-face tunnel boring machine excavation extrusion deformation card machine

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
CN103277120A (en) * 2013-06-19 2013-09-04 西安科技大学 Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft
CN103628894A (en) * 2013-10-24 2014-03-12 重庆大学 Water-rich fault fracture zone collapsed roadway repairing method based on angle-variable umbrella-shaped advancing grouting
CN103696775A (en) * 2013-12-20 2014-04-02 中煤第一建设有限公司 Large-stage-height multi-group water-containing layer segmented downward grouting method
CN105041345A (en) * 2015-08-18 2015-11-11 山东大学 Life-cycle treatment method of water inrush in tunnel
CN105927232A (en) * 2016-05-19 2016-09-07 安徽理工大学 Deep-blocking and shallow-grouting grouting method for no-blank area of mine and grouting safety protecting device
CN207177933U (en) * 2016-11-23 2018-04-03 中国电建集团华东勘测设计研究院有限公司 A kind of advanced plugging structure of high-pressure high-flow underground water
US20190316454A1 (en) * 2017-05-10 2019-10-17 China University Of Mining And Technology Stress-transfer method in tunnel with high ground pressure based on fracturing ring
CN107083977A (en) * 2017-06-23 2017-08-22 中国矿业大学 A kind of grouting strengthening method of many granularities of argillaceous soft rock tunnel subregion
CN108756893A (en) * 2018-04-19 2018-11-06 济南城建集团有限公司 A kind of city shallow tunnel vault soil stabilization method
CN108661650A (en) * 2018-04-23 2018-10-16 中铁隧道局集团有限公司 A kind of rich water magmatic body area depth pozo shaft construction method
CN108868776A (en) * 2018-07-06 2018-11-23 中钢集团马鞍山矿山研究院有限公司 The high pressure-bearing broken rock of deep-well induces pre-pouring grout reinforcement means in advance
CN109162731A (en) * 2018-08-16 2019-01-08 山东科技大学 Iron producing area deep mining gushing water grouting treatment method
CN109209287A (en) * 2018-09-12 2019-01-15 中国矿业大学 A kind of shaft of vertical well crosses high inclination-angle tomography working face segmentation Curtain Grouting Construction method
CN109505628A (en) * 2018-12-06 2019-03-22 中铁三局集团广东建设工程有限公司 A kind of water-rich fault zone method for tunnel construction
CN109681214A (en) * 2019-03-01 2019-04-26 中国水利水电第八工程局有限公司 A kind of construction method of Full-face pouring strengthening stratum
CN110656951A (en) * 2019-09-27 2020-01-07 中国科学院武汉岩土力学研究所 Disaster safety control method for full-face tunnel boring machine excavation extrusion deformation card machine

Non-Patent Citations (13)

* Cited by examiner, † Cited by third party
Title
刘家军,等: ""隧道工程中涌水现象的综合治理技术"", 《建筑施工》 *
史勇,等: ""壁后注浆快速堵水技术在麻家梁矿主立井的应用"", 《同煤科技》 *
孙勇,姜玉松: ""利用注浆法加固斜井表土段地层"", 《矿山建设工程新进展——2006全国矿山建设学术会议文集(下册)》 *
惠冰,等: ""高孔隙率砂岩涌水渗流场特征与注浆治理"", 《煤炭学报》 *
曹栩: ""孔庄矿深井水泵房硐室围岩结构稳定性分析及控制技术"", 《中国优秀硕士论文全文库工程科技I辑》 *
李志强: ""软弱砂质泥岩修建竖井的处理方法及应用"", 《中国高新技术企业》 *
杨木桂,等: ""冻结法在地铁隧道施工中的应用"", 《广州建筑》 *
栗军昌: ""斜井井筒破坏原因分析与加固实践"", 《 第十届全国采矿学术会议论文集——专题一:采矿与井巷工程》 *
王晓健: ""煤矿深立井马头门围岩历时稳定性及其控制技术"", 《中国优秀博士论文全文库工程科技I辑》 *
王档良,姜振泉: ""在建矿井井壁渗漏水的地质成因分析与化学注浆治理"", 《建井技术》 *
邓凡阔,陈洁: ""深竖井高压涌水治理技术"", 《东北水利水电》 *
邓新: ""铁路隧道超深竖井工作面预注浆堵水关键技术"", 《城市建设理论研究(电子版)》 *
马银,等: ""思山岭铁矿深井工作面预注浆技术"", 《现代矿业》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114370252A (en) * 2021-12-17 2022-04-19 核工业北京地质研究院 Shallow hole reinforcing method suitable for high-temperature geothermal well

Similar Documents

Publication Publication Date Title
CN107642360B (en) Full-section advanced pre-grouting construction method
CN106640120B (en) Layered grouting construction method for fixed-point deep holes on earth surface
CN105178326B (en) Upper soft lower hard water rich strata base pit engineering building enclosure water-stopping method
CN102787846B (en) Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN103835648B (en) One improves rock stratum performance mine shaft rising boring technique by surface grout injection
CN101173516B (en) Method for preventing slurry leakage and hole collapse of large-diameter deep-borehole cast-in-situ bored pile by casting curtain method
CN109653777B (en) High-speed railway open cut tunnel water leakage and crack regional integral treatment method
CN207177933U (en) A kind of advanced plugging structure of high-pressure high-flow underground water
AU2020257049B2 (en) Construction method for forming water-proof grouting curtain in water-rich porous rock stratum by blasting
CN107762533A (en) A kind of front pre-grouting method of high-pressure water-enriched weak surrounding rock mountain tunnel
CN106089296A (en) A kind of prevention and treatment method of roof absciss layer water
CN102011591A (en) Grouting process for working surface of deep well
JP7292772B2 (en) External expansion pipe construction method for drilling in the mining zone
CN113107589B (en) Advanced pre-drainage method for coal seam roof aquifer ground
CN112253186A (en) Method for stopping leakage of working faces at different layer depths of railway tunnel shaft
CN112482415B (en) Consolidation grouting method for underground cavern under high external water pressure and flowing water condition
CN112012746A (en) Construction method of railway tunnel deep and large vertical shaft under condition of thick-layer water-rich broken zone
CN109505633B (en) Lining back guide pipe grouting water plugging device for muddy stratum and construction method
CN106320397A (en) Advanced prediction and renovation method for foundation pit seepage
CN113153364B (en) Water inflow treatment method suitable for inclined shaft under steep water-rich rock stratum
CN110670614B (en) Relay type waterproof curtain construction method
CN210127858U (en) A lining cutting back of body uide tube slip casting water shutoff device for muddy stratum
CN108561082B (en) Method for modifying limestone aquifer by mutually-embedded jet grouting
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
CN113217036A (en) Post-grouting construction method for tunnel structure at water burst section of fault fracture zone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20210122

WD01 Invention patent application deemed withdrawn after publication