CN107201909A - Swelled ground tunnel support structure and method - Google Patents

Swelled ground tunnel support structure and method Download PDF

Info

Publication number
CN107201909A
CN107201909A CN201710458549.9A CN201710458549A CN107201909A CN 107201909 A CN107201909 A CN 107201909A CN 201710458549 A CN201710458549 A CN 201710458549A CN 107201909 A CN107201909 A CN 107201909A
Authority
CN
China
Prior art keywords
grouting
face
swelled ground
upper half
half section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710458549.9A
Other languages
Chinese (zh)
Other versions
CN107201909B (en
Inventor
王辅圣
刘鹤
唐永利
赵见
王佩哲
黄旭
尹君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 24th Bureau Group Co Ltd
Anhui Engineering Co Ltd of China Railway 24th Bureau Group Co Ltd
Original Assignee
China Railway 24th Bureau Group Co Ltd
Anhui Engineering Co Ltd of China Railway 24th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 24th Bureau Group Co Ltd, Anhui Engineering Co Ltd of China Railway 24th Bureau Group Co Ltd filed Critical China Railway 24th Bureau Group Co Ltd
Priority to CN201710458549.9A priority Critical patent/CN107201909B/en
Publication of CN107201909A publication Critical patent/CN107201909A/en
Application granted granted Critical
Publication of CN107201909B publication Critical patent/CN107201909B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of swelled ground tunnel support structure and method, it includes:Wall for grouting, it is arranged on the upper half section of the face in the swelled ground tunnel;Some Grouting Pipes, it is embedded in the wall for grouting, and the swelled ground country rock for the upper half section periphery to the swelled ground tunnel carries out pre-grouting;The Grouting Pipe is set along the bearing of trend in the swelled ground tunnel, and cross section is towards the upper half section of the face;When carrying out pre-grouting by the Grouting Pipe, the wall for grouting is used to prevent from flowing to the face outside the slurries of grouting.It is of the invention main to prevent grouting pressure from area facial disfigurement and being caved in caused by excessive by wall for grouting, solve the problem of swelled ground tunnel is due to swell-shrinking deformation caused by the mechanical characteristic of swelled ground and destruction.

Description

Swelled ground tunnel support structure and method
Technical field
The present invention relates to Geotechnical Engineering field, more particularly to a kind of swelled ground tunnel support structure and method.
Background technology
Swelled ground China widely dispersed, such as Guangxi, Yunnan, Henan, Hubei, Sichuan, Shaanxi, Hebei, Anhui, There is the distribution of different range on the ground such as Jiangsu.The mineralogical composition of swelled ground is mainly montmorillonite, is a kind of highly plastic clay, typically Bearing capacity is higher, with the deformation of water swelling, dehydration shrinkage and repeated expansion and shrinkage, the decay of immersion bearing capacity, desiccation crack development etc. Characteristic, property is extremely unstable.Because the soil has the property of water swelling, dehydration shrinkage and reciprocal transformation, therefore it is to tunnel The destruction of supporting construction can not be underestimated, and the destruction constituted is not easily repaired.For example, swelled ground tunnel is after excavation The reasons such as the effect due to stresses re-distribution and water, water-swellable, dehydration shrinkage, make tunnel generate squeezing into tunnel repeatedly Pressure and displacement, commonly reach several centimetres, or even over one hundred centimetre, cause country rock cracking, tunnel sinking, wall rock destabilization, cave in, emit The phenomenons such as the disease after top, heave, lining deformation destruction and operation, it can cause extremely tight to engineering construction and operation The consequence of weight, directly affects the security of works.
Therefore, in order to ensure the stabilization of tunnel in a long time, the purpose for reach safety, comfortably driving a vehicle, it is necessary to carry For a kind of supporting construction and method that can be controlled the swell-shrinking deformation of swelled ground country rock, ensure tunnel structure safety.
The content of the invention
The present invention is directed to the drawbacks described above of prior art there is provided a kind of swelled ground tunnel support structure and method, and its is main Prevent grouting pressure from area facial disfigurement and being caved in caused by excessive by wall for grouting, solve swelled ground tunnel due to expansion The problem of swell-shrinking deformation caused by the mechanical characteristic of soil and destruction.
The technical solution adopted for the present invention to solve the technical problems is:
On the one hand there is provided a kind of swelled ground tunnel support structure, it includes:
Wall for grouting, it is arranged on the upper half section of the face in the swelled ground tunnel;
Some Grouting Pipes, it is embedded in the wall for grouting, the expansion for the upper half section periphery to the face Fortifield village's rock carries out pre-grouting;The Grouting Pipe is set along the bearing of trend in the swelled ground tunnel, and the equal direction in cross section The upper half section of the face;
When carrying out pre-grouting by the Grouting Pipe, the wall for grouting is used to prevent the slurries of grouting from flowing out the palm Sub- face.
It is preferred that, wall for grouting includes:Concrete main body;And it is arranged on the shaped steel main body in the concrete main body.
It is preferred that, the shaped steel main body includes:
Some shaped steel of the upper half section of the face are arranged on, each shaped steel is along the upper half of the face Section is laterally set, and is parallel to each other between the shaped steel;And for connecting the reinforcing bar of two adjacent shaped steel.
It is preferred that, the wall for grouting thickness 50-100cm;The shaped steel is 22A I-steel;It is parallel to each other between the reinforcing bar, And uniform intervals are set.
It is preferred that, in addition to:Advance support structure;The advance support structure includes:
The long tube set along the outer uniform intervals of the upper half section of the face;And it is arranged on two adjacent long tubes Between advanced tubule;The advanced tubule uniform intervals are set;
The cross section of the long tube and advanced tubule is towards the upper half section of the face;
The interim inverted arch laterally set along the upper half section of the face;
And the longitudinally disposed interim steelframe of tunnel center line along the upper half section swelled ground tunnel of the swollen face.
It is preferred that, the Grouting Pipe overlaps, be arranged in parallel each other, and the length of overlapping part is 1.0-2.0m.
It is preferred that, the Grouting Pipe is obliquely installed, and it is between the center line of the bearing of trend in the swelled ground tunnel Angle is 10 ° -30 °.
It is preferred that, the Grouting Pipe is mini-valve tube.
On the other hand, a kind of swelled ground tunnel supporting method is also provided, it comprises the following steps:
S1, on the upper half section of the face in the swelled ground tunnel wall for grouting is set;
S2, it is drilled with multiple inlet wells, each inlet well and is embedded with for institute in the wall for grouting The swelled ground country rock for stating the upper half section periphery of face carries out the Grouting Pipe of pre-grouting;The Grouting Pipe is along the expansion The bearing of trend in native tunnel is set, and cross section is towards the section in the upper half section swelled ground tunnel of the face;
S3, pre-grouting:Pre-grouting is carried out by the Grouting Pipe.
It is preferred that, also include before the step S1:S1a, setting advance support structure.
The beneficial effect of technical solution of the present invention is:
The present invention prevents grouting pressure from area facial disfigurement and being caved in caused by excessive by wall for grouting, and Grouting Pipe is noted With good water-stagnating effect during slurry, the risk of the prominent mud of Tunnel Gushing can be effectively reduced, swelled ground tunnel is solved due to swollen Swell-shrinking deformation caused by swollen native mechanical characteristic and destruction the problem of, wall for grouting be conducive to preventing grouting pressure is excessive from causing the palm Sub- facial disfigurement and cave in.And the technical solution adopted by the present invention, succinctly, speed of application is fast, and financial cost is relatively low for engineering method.
Brief description of the drawings
Below in conjunction with drawings and Examples, the invention will be further described, in accompanying drawing:
Fig. 1 is the structural representation of the middle expansive soils tunnel support structure of embodiments of the invention one;
Fig. 2 is the profile of wall for grouting in embodiments of the invention one;
Fig. 3 is the side view of Grouting Pipe in embodiments of the invention one;
Fig. 4 is Grouting Pipe and the angle schematic diagram of tunnel center line in embodiments of the invention one;
Fig. 5 is the method flow diagram of the middle expansive soils tunnel supporting method of embodiments of the invention two;
Fig. 6 is the structural representation of Grouting Pipe in embodiments of the invention two.
Embodiment
In order that the purpose of the present invention, technical scheme and advantage are more clearly understood, below in conjunction with drawings and examples, The present invention will be described in further detail.It should be appreciated that specific embodiment described herein is only used for explaining this hair It is bright, it is not intended to limit the present invention.
Embodiment one:
Fig. 1 shows the swelled ground tunnel support structure of the present invention, and it includes:
Wall for grouting 1, it is arranged on the upper half section S1 of the face in the swelled ground tunnel 100;
Some Grouting Pipes 2, it is embedded in 1 in the wall for grouting, for the face to the swelled ground tunnel 100 The swelled ground country rock progress pre-grouting on half section S1 peripheries, and formation grouting and reinforcing scope (in the present embodiment, the grouting and reinforcing The size of scope is that face both sides stretch out 1-1.5m, and face top upwardly extends 1.5-2m, i.e. Fig. 1 bends frame institute The rectangular area shown);The Grouting Pipe 2 is along the bearing of trend (i.e. perpendicular to the direction of paper) in the swelled ground tunnel 100 Set, and cross section is towards the upper half section S1 of the face;
When carrying out pre-grouting by the Grouting Pipe 2, the wall for grouting 1 is used to prevent that the slurries outflow of grouting to be described Face.
In addition, the steadiness to ensure the swelled ground tunnel 100, the swelled ground tunnel support structure also includes:It is super Preceding supporting construction;The advance support structure includes:
The long tube 4 set along the upper half section S1 of face outer uniform intervals, the long tube 4 constitutes long tube Canopy;And it is arranged on the advanced tubule 3 between two adjacent long tubes 4;And the same uniform intervals of the advanced tubule 3 are set Put;In the present embodiment, the length of the long tube 4 is 20-25m (being preferably 23.05m), and diameter 100-120mm (is preferably 108mm), its ring spacing set is 0.3~0.5m;The length of the advanced tubule 3 is 2-5m (being preferably 3m), diameter 35-50mm (being preferably 42mm), its ring spacing set is similarly 0.3~0.5m;Also, the long tube 4 and advanced small The cross section of conduit 3 is towards the upper half section S1 of the face;
Along the upper half section S1 interim inverted arch 5 that laterally (i.e. X-direction in Fig. 1) is set of the face;
And along the swelled ground tunnel 100 tunnel center line longitudinal direction (i.e. Y-direction in Fig. 1, meanwhile, the X-direction and Y-direction is vertical) interim steelframe 6 that sets, the two ends of interim steelframe 6 connect the top and bottom of the face respectively, use In the support face;In the present embodiment, the steelframe 6 can at least have two Pin, and the spacing of adjacent two Pin steelframes 6 is 0.4- 1m (be preferably 0.5m), and adjacent two Pin steelframes 6 are fixed together by least one retainer ring 61, strengthen its support with this Effect, it is ensured that the stability of structure.
Further, as shown in Fig. 2 the thickness of the wall for grouting 1 can be 50-100cm (being preferably 80cm), its is specific Including:Concrete main body;And it is arranged at least a set of shaped steel main body in the concrete main body.
Specifically, the shaped steel main body includes:
The upper half section S1 of the face some shaped steel 11 are arranged on, the shaped steel 11 is preferably 22A I-steel, Along the upper half section S1 of the face, laterally (i.e. X-direction in Fig. 1) is set each shaped steel 11, and the shaped steel 11 Between be parallel to each other;And for connecting the first reinforcing bar 12 of two adjacent shaped steel;It is parallel to each other between first reinforcing bar 12, And can uniform intervals setting.
Meanwhile, to strengthen the soundness of wall for grouting 1, the wall for grouting 1 also includes some second reinforcing bars 13 and some 3rd reinforcing bar 14;Second reinforcing bar 13 is longitudinal, parallel and uniform intervals are set, and its one end connects the shaped steel 11 of the top, separately One end connects the top of the face;3rd reinforcing bar 14 is longitudinal, parallel and uniform intervals are set, and its one end is connected most The shaped steel 11 of lower section, the other end connects the interim inverted arch 5, and the longitudinal direction is the Y-direction in Fig. 1, namely the swelled ground tunnel The track centre in road 100, meanwhile, the X-direction is vertical with Y-direction.
The reinforcing bar 13 of first reinforcing bar 12 and/or second and/or a diameter of 22mm of the 3rd reinforcing bar 14.
In the present embodiment, the shaped steel main body can be preferably two sets, its bearing of trend in the swelled ground tunnel 100 Upper inside and outside setting (" interior " is the direction away from the face, and " outer " is close to the direction of the face) is that is, a set of close The face, it is a set of away from the face.
To further enhance anti-pressure ability, the shaped steel 11 can also be oriented to wall with fender post and pipe canopy and be connected.
After the completion of the wall for grouting 1, you can some notes for being used to set the Grouting Pipe 2 are drilled with the wall for grouting 1 Slurry 21 (as shown in Figure 6) of drilling, and ball valve can be also provided with the aperture of the inlet well 21.
Such as Fig. 3, described in 6, the Grouting Pipe 2 overlaps, be arranged in parallel each other, and the head end of the Grouting Pipe 2 stretches out The wall for grouting 1, tail end extend into the bottom of the inlet well 21;The length of Grouting Pipe 2 is 6m, and the length of overlapping part Spend for 1.0-2.0m (being preferably 1.5m).In the present embodiment, the Grouting Pipe 2 can be mini-valve tube, and the aperture of Grouting Pipe 2 is 91mm, slip casting splitting penetration radius are 500-1000mm, and end offers some injected holes 22, and the injected hole 22 is in plum blossom Type is arranged, and longitudinal and transverse spacing is 750-1000mm (being preferably 800mm).
Secondly, for ease of carrying out slip casting to different orientation, the Grouting Pipe 2 is obliquely installed, as shown in figure 4, its center Angle theta between the center line Y " of axis Y ' and the bearing of trend in the swelled ground tunnel 100 is 10 ° -30 °.
In the present embodiment, there is advantages below using mini-valve tube as Grouting Pipe 2:
(1) when being restricted on construction ground, directed inclined hole slip casting, soil mass consolidation targetedly can be implemented to faulty section.
(2) mini-valve tube system is mainly made up of plastic valve pipe (outer tube), slip casting core pipe (inner tube), rubber case, sealing ring etc., Therefore, its be one kind can only to outside pipe pulp, it is impossible to the unidirectional closing device of slurry is returned into pipe.During slip casting, pressure is by plastic valve Rubber case outside pipe aperture is washed open, and slurries enter stratum, when such as pipe external pressure is more than in pipe, and the rubber case outside aperture is closed automatically Close.
(3) slip casting can also be repeated as needed to any one slip casting section slip casting.
(4) drilling and slip casting are separated, and improve drilling, the utilization rate of grouting equipment.
(5) due in the stratum being reinforced, having carried out multiple spot, quantitative, slip casting in a balanced way, injecting cement paste is uniform in the earth formation Distribution, uniform connection, therefore, substantially increases the resistance to overturning for being reinforced stratomere.
Embodiment two:
As seen in figs. 5-6, the present invention also show a kind of swelled ground tunnel supporting method, and it comprises the following steps:
S1, the setting wall for grouting 1 on the upper half section S1 of the face in the swelled ground tunnel 100;
S2, it is drilled with to be embedded with multiple inlet wells 21, each inlet well 21 in the wall for grouting 1 and is used for The Grouting Pipe 2 of pre-grouting is carried out to the swelled ground country rock on the upper half section periphery in the swelled ground tunnel 100;The Grouting Pipe 2 are set along the bearing of trend in the swelled ground tunnel, and cross section is towards the upper half section S1 of the face;
S3, pass through the Grouting Pipe 2 carry out pre-grouting.
It is preferred that, also include before the step S1:S1a, setting advance support structure.
Specifically, the step S3 includes:
S31, configuration injecting paste material:In the present embodiment, the injecting paste material is cement-sodium silicate double liquid, and it was configured Journey is as follows:
It is layered from Portland cement (for example, P.O 42.5) as cement, the Portland cement should be new It is fresh and to meet in relevant quality standard, work progress and survey sample without caking, the cement for the caking that makes moist, cement must not be used Pulp density 1.5t/m3;The mixing time of cement mortar, high-speed stirred should be no less than 30s, and normal agitation is no less than 90s, obtains cement Slurry, and the cement slurry prepares to the time of being finished and should be less than 4h, storage temperature is between 5-40 DEG C;The normal silicate The weighing error of cement and water is no more than 5%;
From waterglass, the waterglass enters field concentration for 40 Baume degrees (density 1.38g/cm3) or 3.4 moduluses, by it Concentration dilution is to the Baume degrees of concentration 25 (density 1.25g/cm3) after again with water according to 1:1 (mass ratio) is diluted, and obtains water glass Glass slurry, the waterglass slurry storage temperature is between 5-40 DEG C;The weighing error of the waterglass and water is no more than 5%;
S32, the Grouting Pipe 2 is connected with pump 200 (as shown in Figure 6), regulation is pumped to 1.0-2.0Mpa;
S33, as shown in fig. 6, first passing through the first import 21 and the second import 22 of the head end of Grouting Pipe 2 to the slip casting Pumping Drilling Water, the debris (including body refuse etc.) in the inlet well 21 is gone out in drilling 21;
S34, the cement slurry is pumped into by the first import 21, waterglass slurry is pumped into by second import 22, The cement slurry and waterglass slurry are discharged after being mixed in the Grouting Pipe 2 by injected hole 22, to the swelled ground The swelled ground country rock on the upper half section periphery in tunnel carries out the pre-grouting of the first slip casting section;
After S35, the pre-grouting of completion the first slip casting section, the Grouting Pipe 2 is moved to the second slip casting section, repeats to walk Rapid S34, until completing the pre-grouting of all slip casting sections.
Behind slurries injection stratum, waterglass can generate silica gel with calcium carbonate chemically reactive in soil layer;Cement and soil particle And other in soil layer to fill out thing cementing.Meanwhile, waterglass can promote cement early solidifying, it is to avoid precipitation, bleed, guarantee slurries workability, The property noted.Injection slurry plays splitting and infiltration packing action, shape firmly cementing with soil layer through part by soil layer mesopore Into firm supporting course, foundation bearing capacity is improved, the settlement by soaking (collapse resistance) of soil layer is eliminated, also reduces the permeability of the soil body Can, differential settlement will not be produced again by the soil body is met water, and the soil body that maintains the original state is stablized for a long time, reach sealing, the purpose reinforced.
In the present embodiment, after the pre-grouting for completing all slip casting sections, the reinforcing body 300 obtained has well uniform Property and self-stability, face is without infiltration, and the reinforcing body unconfined compressive strength is 0.5MPa, infiltration coefficient is≤1.0 × 10-6cm/s。
It should be noted that the technical characteristic in above-described embodiment one, two can be combined, the technology combined Scheme belongs to protection scope of the present invention.
In summary, swelled ground tunnel support structure of the invention and method using cement-sodium silicate double liquid due to being entered Row slip casting, therefore, it is conducive to the swell-shrinking deformation for controlling swelled ground country rock, ensures tunnel structure safety;Wall for grouting is conducive to preventing Only grouting pressure is excessive causes area facial disfigurement and caves in;Sleeve valve barrel grouting has good water-stagnating effect, effectively reduces tunnel The risk of the prominent mud of road water burst.
The foregoing is only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.

Claims (10)

1. a kind of swelled ground tunnel support structure, it is characterised in that including:
Wall for grouting, it is arranged on the upper half section of the face in the swelled ground tunnel;
Some Grouting Pipes, it is embedded in the wall for grouting, the expansion fortifield village for the upper half section periphery to the face Rock carries out pre-grouting;The Grouting Pipe is set along the bearing of trend in the swelled ground tunnel, and cross section is towards described The upper half section of face;
When carrying out pre-grouting by the Grouting Pipe, the wall for grouting is used to prevent the slurries of grouting from flowing out the area Face.
2. supporting construction as claimed in claim 1, it is characterised in that wall for grouting includes:Concrete main body;And it is arranged on institute State the shaped steel main body in concrete main body.
3. supporting construction as claimed in claim 2, it is characterised in that the shaped steel main body includes:
Some shaped steel of the upper half section of the face are arranged on, each shaped steel is along the upper half section of the face Laterally set, and be parallel to each other between the shaped steel;And for connecting the reinforcing bar of two adjacent shaped steel.
4. supporting construction as claimed in claim 3, it is characterised in that the wall for grouting thickness 50-100cm;The shaped steel is 22A I-steel;It is parallel to each other between the reinforcing bar, and uniform intervals are set.
5. supporting construction as claimed in claim 1, it is characterised in that also include:Advance support structure;The advance support knot Structure includes:
The long tube set along the outer uniform intervals of the upper half section of the face;And be arranged between two adjacent long tubes Advanced tubule;The advanced tubule uniform intervals are set;
The cross section of the long tube and advanced tubule is towards the upper half section of the face;
The interim inverted arch laterally set along the upper half section of the face;
And the longitudinally disposed interim steelframe of tunnel center line along the swelled ground tunnel.
6. supporting construction as claimed in claim 1, it is characterised in that the Grouting Pipe overlaps, be arranged in parallel each other, and The length of overlapping part is 1.0-2.0m.
7. supporting construction as claimed in claim 6, it is characterised in that the Grouting Pipe is obliquely installed, itself and the swelled ground Angle between the center line of the bearing of trend in tunnel is 10 ° -30 °.
8. the supporting construction as described in claim any one of 1-7, it is characterised in that the Grouting Pipe is mini-valve tube.
9. a kind of swelled ground tunnel supporting method, it is characterised in that comprise the following steps:
S1, on the upper half section of the face in the swelled ground tunnel wall for grouting is set;
S2, it is drilled with multiple inlet wells, each inlet well and is embedded with for the palm in the wall for grouting The swelled ground country rock on the upper half section periphery in sub- face carries out the Grouting Pipe of pre-grouting;The Grouting Pipe is along the swelled ground tunnel The bearing of trend in road is set, and cross section is towards the upper half section of the face;
S3, pre-grouting:Pre-grouting is carried out by the Grouting Pipe.
10. method for protecting support as claimed in claim 1, it is characterised in that also include before the step S1:S1a, setting are advanced Supporting construction.
CN201710458549.9A 2017-06-16 2017-06-16 Expansive soil tunnel supporting structure and method Active CN107201909B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710458549.9A CN107201909B (en) 2017-06-16 2017-06-16 Expansive soil tunnel supporting structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710458549.9A CN107201909B (en) 2017-06-16 2017-06-16 Expansive soil tunnel supporting structure and method

Publications (2)

Publication Number Publication Date
CN107201909A true CN107201909A (en) 2017-09-26
CN107201909B CN107201909B (en) 2023-06-13

Family

ID=59907076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710458549.9A Active CN107201909B (en) 2017-06-16 2017-06-16 Expansive soil tunnel supporting structure and method

Country Status (1)

Country Link
CN (1) CN107201909B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107829747A (en) * 2017-11-02 2018-03-23 安徽建筑大学 Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area
CN108252719A (en) * 2017-12-29 2018-07-06 中铁隆工程集团有限公司 Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN110387887A (en) * 2019-06-28 2019-10-29 同济大学建筑设计研究院(集团)有限公司 It is oriented to the construction method of partition wall and its construction method and foundation pit enclosure structure
CN111691903A (en) * 2020-06-02 2020-09-22 中铁十五局集团第三工程有限公司 Construction method of pipe-curtain-method supporting structure
CN114251107A (en) * 2021-12-16 2022-03-29 中国电建集团成都勘测设计研究院有限公司 Tunnel collapse treatment method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060174549A1 (en) * 2005-01-26 2006-08-10 Dagher Habib J Rapidly-deployable lightweight load resisting arch system
CN102182470A (en) * 2011-03-21 2011-09-14 同济大学 Full-section sealing extrusion grouting method
CN102787846A (en) * 2012-07-31 2012-11-21 中铁隧道集团有限公司 Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN203161249U (en) * 2013-03-08 2013-08-28 中铁二十二局集团第一工程有限公司 Sleeve valve pipe grouting reinforcing system for soil between tunnels
CN103982201A (en) * 2014-05-22 2014-08-13 北京中铁瑞威工程检测有限责任公司 Advanced detection, grouting reinforcement and excavation method of wide separation fracture of high-pressure water-rich tunnel
CN105041325A (en) * 2015-07-13 2015-11-11 长沙理工大学 Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN106121661A (en) * 2016-08-08 2016-11-16 中铁二局集团有限公司 A kind of tunnel trunk is by loess separating surface water rich strata construction method
CN205876348U (en) * 2016-07-28 2017-01-11 中国建筑第六工程局有限公司 Multi -level advance support structure of transverse passage -way vault under complex geological condition
KR20170032838A (en) * 2015-09-15 2017-03-23 주식회사 티에스테크 Double order system adjusting horizontal length of steel pipe supporter in the tunnel and the structure of the pipe supporter and method constructing thereof

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060174549A1 (en) * 2005-01-26 2006-08-10 Dagher Habib J Rapidly-deployable lightweight load resisting arch system
CN102182470A (en) * 2011-03-21 2011-09-14 同济大学 Full-section sealing extrusion grouting method
CN102787846A (en) * 2012-07-31 2012-11-21 中铁隧道集团有限公司 Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN203161249U (en) * 2013-03-08 2013-08-28 中铁二十二局集团第一工程有限公司 Sleeve valve pipe grouting reinforcing system for soil between tunnels
CN103982201A (en) * 2014-05-22 2014-08-13 北京中铁瑞威工程检测有限责任公司 Advanced detection, grouting reinforcement and excavation method of wide separation fracture of high-pressure water-rich tunnel
CN105041325A (en) * 2015-07-13 2015-11-11 长沙理工大学 Construction method of high-tension water-rich extra-large-section weak breccia tunnel
KR20170032838A (en) * 2015-09-15 2017-03-23 주식회사 티에스테크 Double order system adjusting horizontal length of steel pipe supporter in the tunnel and the structure of the pipe supporter and method constructing thereof
CN205876348U (en) * 2016-07-28 2017-01-11 中国建筑第六工程局有限公司 Multi -level advance support structure of transverse passage -way vault under complex geological condition
CN106121661A (en) * 2016-08-08 2016-11-16 中铁二局集团有限公司 A kind of tunnel trunk is by loess separating surface water rich strata construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107829747A (en) * 2017-11-02 2018-03-23 安徽建筑大学 Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area
CN107829747B (en) * 2017-11-02 2019-08-02 安徽建筑大学 Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area
CN108252719A (en) * 2017-12-29 2018-07-06 中铁隆工程集团有限公司 Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN108252719B (en) * 2017-12-29 2019-11-15 中铁隆工程集团有限公司 Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN110387887A (en) * 2019-06-28 2019-10-29 同济大学建筑设计研究院(集团)有限公司 It is oriented to the construction method of partition wall and its construction method and foundation pit enclosure structure
CN111691903A (en) * 2020-06-02 2020-09-22 中铁十五局集团第三工程有限公司 Construction method of pipe-curtain-method supporting structure
CN111691903B (en) * 2020-06-02 2022-03-11 中铁十五局集团第三工程有限公司 Construction method of pipe-curtain-method supporting structure
CN114251107A (en) * 2021-12-16 2022-03-29 中国电建集团成都勘测设计研究院有限公司 Tunnel collapse treatment method

Also Published As

Publication number Publication date
CN107201909B (en) 2023-06-13

Similar Documents

Publication Publication Date Title
CN107201909A (en) Swelled ground tunnel support structure and method
CN107083977A (en) A kind of grouting strengthening method of many granularities of argillaceous soft rock tunnel subregion
CN108119143B (en) A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain
CN103410182B (en) Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
WO2018233320A1 (en) Coal mine underground reservoir and multi-layer grouting-based anti-seepage reinforcement method for reservoir dam
CN105888673B (en) The operating method of deep hole modeling pipe high-pressure slip-casting explosion-protection equipment in soft rich water country rock
CN107246267A (en) Mine Shaft Lining, constructing device and method in a kind of poor strata
CN108252719B (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
WO2021139063A1 (en) Grouting pipe and method of reinforcing tunnel by surface grouting
CN206015669U (en) Pile foundation reinforcement system based on reinforcement synthesis pillared clay
CN109026020B (en) Water-rich tunnel karst cave treatment and excavation method
CN106013078B (en) Construction method of strong permeable stratum reinforcing curtain structure
CN108952727B (en) A kind of grouting water blocking method of the vertical creviced formation of high inclination-angle
CN112408908A (en) High polymer grouting reinforcement method for repairing water-rich bedrock tunnel pavement
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN206110124U (en) Bored concrete pile stake end post grouting device
CN105862872B (en) A kind of deep footing groove enclosing structure joint seal construction method
CN206816272U (en) Swelled ground tunnel support structure
CN106930769A (en) One kind is for specific region direction and location grouting strengthening method in the huge talus loose media of macroporosity
CN107675707A (en) Inclined rock base steel pile casting is fixed and bottom blocking method
CN107035389A (en) A kind of construction method for grouting reinforcement and earth's surface construction method
CN114457790A (en) Cast-in-place pile forming device and method suitable for karst area
CN109441486A (en) The grouting method reinforced for tunnel grouting
CN107905222A (en) Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method
CN104047285A (en) Technical device and construction method for improving bearing capacity of CFG pressure pouring piles

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant