CN107905222A - Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method - Google Patents

Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method Download PDF

Info

Publication number
CN107905222A
CN107905222A CN201711188732.8A CN201711188732A CN107905222A CN 107905222 A CN107905222 A CN 107905222A CN 201711188732 A CN201711188732 A CN 201711188732A CN 107905222 A CN107905222 A CN 107905222A
Authority
CN
China
Prior art keywords
pile
bellend
lining material
prefabricated band
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711188732.8A
Other languages
Chinese (zh)
Inventor
徐立军
侯彤岩
张国杰
李建军
孙璐
张德志
刘绍文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONGYE SHENKAN ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
ZHONGYE SHENKAN ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONGYE SHENKAN ENGINEERING TECHNOLOGY Co Ltd filed Critical ZHONGYE SHENKAN ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201711188732.8A priority Critical patent/CN107905222A/en
Publication of CN107905222A publication Critical patent/CN107905222A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A kind of pile foundation lining material and the lining material prefabricated band bellend prestressing pipe pile construction method is applied, it is iron milltailings that pile foundation lining material, which includes component and its weight proportion,:Cement:Flyash:Water=(4~5):(1~1.2):(0.15):(1.2~1.4).Construction method step is:After drilling, sill must be served as a contrast by taking raw material to mix by proportioning, inject in borer drill rod, perfusion extremely perfusion absolute altitude, prefabricated band bellend pile for prestressed pipe is pressed into projected depth, compacted lining sill makes that it is combined closely with prefabricated band bellend pile for prestressed pipe and its liquid level of lifting is to 0.5~1.0m of stake top at the same time, pile foundation lining material is conserved to design strength, completion and applies the lining material prefabricated band bellend prestressing pipe pile construction process.The problems such as pile foundation lining material of the present invention is environmentally protective, and saves pile foundation concrete, and solution Pile Bearing Capacity, stake are combined with ground interlayer load transmission, stake with superstructure, while production cost is substantially reduced, production efficiency is improved, is had wide range of applications.

Description

Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method
Technical field:
The invention belongs to industrial residue utilization and building foundation domain technology field, and in particular to a kind of pile foundation lining material And the prefabricated band bellend prestressing pipe pile construction method using the lining material.
Background technology:
Existing prestressing pipe pile construction technique generally uses and squeezes into two methods of method or static pressure method.For harder ground Layer squeezes into method or the presence of static pressure method both of which is difficult to through firm hard formation and pile top is seated suitable bearing course at pile end Difficulty;And due in the construction of existing pile for prestressed pipe, to meet the requirement of injection stratum penetrativeness in pile driving construction, stake Body concrete and the arrangement of reinforcement of stake have all especially carried out strengthening design, cause the waste of material to a certain extent.
It is the common processes of foundation pile using auger boring technique, there is wide application environment, applicable cohesive soil, The formation conditions such as sandy soil, rubble class soil and strongly weathered sand-rock.At present, the construction of spiral pore-creating filling pile uses present walling pile substantially The technique of body concrete, rear insertion steel reinforcement cage.Pile concrete quality easily is influenced to make by stratum extruding and casting concrete process Into isolation, necking down, broken pile can be caused when serious.
Iron milltailings are the ore waste residues formed with iron ore digging and ore dressing.Generally about 3~5m can be formed by adopting one ton of iron ore3 Tailing, the annual mining activity in China forms substantial amounts of iron tailings.Discharge, the accumulation of tailing occupy substantial amounts of soil money Source, while the dust formed also pollutes environment.The comprehensive utilization of tailing is all subject to national policy emphasis to rouse all the time Encourage and support.Technology more ripe in terms of building has the blockwork being such as laid with for ground, for partly replacing at present Concrete fine aggregate etc..The pile foundation lining material that iron milltailings mortar is used as to bored pile still belongs to blank.
Pile foundation is divided to mainly by construction technology two class of prefabricated pile and bored concrete pile, and wherein prefabricated pile has hammering, static pressure, shake Dynamic, spiral four kinds of technique;Bored concrete pile has two kinds of mechanical hole building, manual pore-forming techniques.Auger is not used in the prior art The design and construction of the pile for prestressed pipe of prefabricated band bellend are pressed into after the compound iron milltailings mortar of hole pumping.
The content of the invention:
The purpose of the present invention is overcome above-mentioned the shortcomings of the prior art, there is provided a kind of pile foundation lining material and apply the lining material Prefabricated band bellend prestressing pipe pile construction method.
To achieve the above object, the present invention uses following technical scheme:
A kind of pile foundation lining material, including component and its weight proportion are iron milltailings:Cement:Flyash:Water=(4~5):(1 ~1.2):(0.15):(1.2~1.4).
The pile foundation lining material, according to the presetting period, the requirement of engineering such as final setting time and microthermal climate are antifreeze, corresponding Add adulterating agent on the basis of cement proportion amount, the adulterating agent is retarder, the one or more in early strength agent or antifreezing agent.
Using the prefabricated band bellend prestressing pipe pile construction method of the pile foundation lining material, comprise the following steps:
Step 1, pile hole construction:
Stake holes is bored in relevant position, the diameter and depth of the stake holes are by depending on design requirement;
In the step 1, brill stake holes is carried out using twist bit.
In the step 1, a diameter of Dz of the stake holes, bottom hole depth reaches design bearing course at pile end.
Step 2, pile foundation lining material is prepared:
By proportioning, take respectively, iron milltailings:Cement:Flyash:Water=(4~5):(1~1.2):(0.15):(1.2~ 1.4);It is stirred after mixing, compound iron milltailings mortar is formed, as pile foundation lining material;
In the step 2, the pile foundation lining material is in preparation process, according to the presetting period, final setting time and low The requirement of engineering such as warm weather is antifreeze, add adulterating agent on the basis of corresponding cement proportion amount, and the adulterating agent is retarder, early One or more in strong agent or antifreezing agent.
In the step 2, iron milltailings are the iron milltailings by radiation examinations qualification, and the iron milltailings are thin for tail powder Sand and tail coarse sand are used as mortar fine aggregate in sand, tail.
Step 3, poured pile base lining material:
By in the pile foundation lining material injection borer drill rod of preparation, drilling rod is lifted in poured pile base lining material, pile foundation lining material is filled The perfusion absolute altitude of note extremely design;
In the step 3, the injection mode of pile foundation lining material is:Using auger hollow conduit, filled using pumping mode Pile foundation lining material is noted to the perfusion absolute altitude designed.
Step 4, piling:
By design position, press-in prefabricated band bellend pile for prestressed pipe is to projected depth, while compacted pile foundation lining material makes it Combine closely with pile pile and its liquid level of lifting is to 0.5~1.0m of stake top, conserved to design strength, form solidifying body, completed Using the prefabricated band bellend prestressing pipe pile construction process of the pile foundation lining material.
In the step 4, for pile foundation lining material after maintenance, compression strength reaches 6~12MPa.
In the step 4, prefabricated band bellend pile for prestressed pipe uses concrete prefabricated making, wherein, bellend with Prefabricated band bellend pile for prestressed pipe one-time-concreting is molded.
In the step 4, prefabricated band bellend pile for prestressed pipe uses single-unit or more piece, except stake end pipe stake pile section band expands Big end, bellend overall diameter are D, remaining pile pile pile section pile body overall diameter is d, prefabricated band bellend pile for prestressed pipe entirety ruler It is very little so as to be completely placed into subject to stake holes, wherein, a diameter of D in enlarged end partial cross-section, Dz > D > d.
In the step 4, prefabricated band bellend pile for prestressed pipe pile extension position set pile protection hoop, the pile protection hoop with Prefabricated band bellend pile for prestressed pipe pile section one-time-concreting is molded.
In the step 4, when prefabricated band bellend pile for prestressed pipe makes, shearing resistance rib is made in each pile section side surface Bar, the shearing resistance cord are molded when making with pile pile one-time-concreting.
In the step 4, when being pressed into prefabricated band bellend pile for prestressed pipe, it will be enlarged by end and be placed in bottom, and jacked pile Hold supporting course.
In the step 4, the pile section that prefabricated band bellend pile for prestressed pipe is located at bearing course at pile end part uses band to expand The pile section of big end, the pile section of other parts use the pile section identical with pile body diameter.
In the step 4, the press mode of prefabricated band bellend pile for prestressed pipe is to be pressed into using static pressure method.
In the step 4, prefabricated band bellend pile for prestressed pipe process of press in is:After stake machine is in place, prefabricated band is expanded Big end pile for prestressed pipe is hung to stake holes center, corrects pile body verticality, downward static pressure to projected depth.
Beneficial effects of the present invention:
(1) present invention forms compound iron milltailings mortar as pilework stake using industrial residues such as iron milltailings as raw material Base lining material, the intensity of pile foundation lining material depend on the match ratio of compound iron milltailings mortar, batching mode using the present invention, its intensity 6~12MPa can be reached, can meet requirement of the prestressed pipe pile bearing capacity of prefabricated band bellend to intensity completely.Pile foundation The load of pilework effectively can be transferred to stratum by the reinforcing body that lining material is formed, and give full play to the bearing capacity on stratum;
(2) pile for prestressed pipe with bellend is by setting shearing resistance cord to add the knot of compound iron milltailings mortar and pile pile With joint efforts.The present invention is by setting bellend to improve bearing capacity of pile tip;
(3) present invention uses precasting process, can carry out industrialized production, substantially reduces production cost, improves production effect Rate.The present invention is suitable for Design of Foundation and the construction on the stratum such as cohesive soil, sandy soil, rubble class soil and strongly weathered sand-rock, should With in extensive range;
(4) compound iron milltailings mortar is formed by using industrial residue iron milltailings combination flyash and other adulterating agents, will It is used as the pile foundation lining material of pile foundation, on the one hand advantageously accounts for environmental pollution caused by industrial residue;On the other hand also save significantly About pile foundation concrete, reduces unnecessary waste of material, belongs to a kind of green environmental protection technique;
(5) the prefabricated band bellend prestressing pipe pile construction method of pile foundation lining material of the invention and the application lining material is well Solves the problems such as bearing capacity, stake and load transmission, stake and combination of superstructure of ground interlayer of pile foundation;Present invention press-in resistance Power is small, and drilling is easier to, and suitable for stratum such as cohesive soil, sand, rubble class soil and strong-weathered rocks, has a wide range of application, applicability By force.
Brief description of the drawings:
Fig. 1 is the prefabricated band bellend pile for prestressed pipe structure chart of the embodiment of the present invention;
Fig. 2 is the sectional view of Fig. 1, wherein, figure (a) is Figure 1A-A faces sectional view, and figure (b) is Figure 1B-B faces sectional view;
Fig. 3 is the prefabricated band bellend pile for prestressed pipe and stake holes plan of the embodiment of the present invention;
Fig. 4 is the prefabricated band bellend pile for prestressed pipe and stake holes profile of the embodiment of the present invention;Wherein:
D0 is prefabricated band bellend prestressed pipe stake body interior diameter;
D is prefabricated band bellend prestressed pipe stake body overall diameter;
T is prefabricated band bellend prestressed pipe stake body thickness;
D is the bellend overall diameter of prefabricated band bellend pile for prestressed pipe;
B is the bellend circumferential direction width of prefabricated band bellend pile for prestressed pipe;
Dz is stake holes diameter.
Embodiment:
With reference to embodiment, the present invention is described in further detail.
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only the part of the embodiment in the present invention, and those of ordinary skill in the art exist All other embodiments obtained under the premise of creative work are not made, belong to the scope of protection of the invention.
It is to be appreciated that the directional instruction (such as up, down, left, right, before and after ...) of institute is only used in the embodiment of the present invention In explaining the relative position relation under a certain particular pose (as shown in drawings) between each component, motion conditions etc., if should When particular pose changes, then directionality instruction also correspondingly changes correspondingly.
Vertical ultimate bearing capacity of single pile formula in technical code for building pile foundation is analyzed as follows:
Work as hb/d<When 5, λp=16hb/d (2)
Work as hbDuring/d >=5, λp=0.8 (3)
Q in formulauk:Vertical ultimate bearing capacity of single pile standard value;
u:The girth of stake;
qsi:The all i-th layer of native ultimate frictional resistance standard values of stake;
li:I-th layer of native thickness in the long scope of stake;
qpk:Stake end standard ultimate bearing capacity;
Aj:Hollow pile stake end net area,
Ap1:Hollow pile opening area,
Λp:Pile-end soil plug effect coefficient, for closing pile λp=1, for open stake by formula (2), (3) value;
hb:Stake end enters bearing stratum depth;
d:Hollow pile outside diameter;
d1:Hollow pile internal diameter.
Formula (1) shows that bearing capacity of single pile is mainly made of pile side friction and end resistance.
Vertical ultimate bearing capacity of single pile formula in technical code for building pile foundation is analyzed as follows:
The pile body stirrup of 5d scopes is not more than 100mm below stake top, and when meeting constructional reinforcement regulation as defined in specification:
N≤ΨcfcAps+0.9fy’As’ (4)
When pile body arrangement of reinforcement does not meet above-mentioned condition:
N≤ΨcfcAps (5)
In formula:N:Stake top axial compressive force design load;
Ψc:Foundation pile pile-formation process coefficient;
fc:Concrete axial compressive strength design load;
Aps:Pile body area of section;
fy’:Lengthways main steel bar compression strength design load;
As’:Lengthways main steel bar area of section.
Formula (4) and (5) show that stake top axial compressive force is undertaken by lengthways main steel bar in pile concrete and stake.
According to material mechanics principle, when the collateral resistance of stake plays a role, passed by composite mortar pile foundation lining material after solidification Its side surface with stake is handed to, the shearing resistance rib as set by the cohesive force and stake side of composite mortar pile foundation lining material after solidifying and stake side surface Bar is passed to pile body;When the end resistance of stake plays a role, served as a contrast by widened stake end section and mortar pile foundation after solidification Material basal cross section shared, wherein passing through mortar and stake side table again by the end resistance that mortar pile foundation lining material basal cross section is shared after solidifying Shearing resistance cord set by the cohesive force and pile body in face is passed to pile body.During simple computation, shearing resistance cord set by stake side can be made For a kind of measure, composite mortar pile foundation lining material and the cohesive force of stake side surface after checking computations solidification are only considered.
Based on above theoretical foundation, the present invention provides a kind of pile foundation lining material and in advance should using the prefabricated band bellend of the lining material Solenoid pile construction method, the prefabricated band bellend prestressing force being implanted into by being previously implanted the pile foundation lining material prepared in advance with rear static pressure Pile pile, prefabricated band bellend pile for prestressed pipe have the bearing capacity of pile tip of bigger, form a kind of Novel pile foundation.According to building pile foundation Technical specification combination the technology of the present invention feature, bearing capacity of single pile calculation formula are:
Q in formulauk:Vertical ultimate bearing capacity of single pile standard value;
u:The girth of stake;
qsi:The all i-th layer of native ultimate frictional resistance standard values of stake;
li:I-th layer of native thickness in the long scope of stake;
qpk:Stake end standard ultimate bearing capacity;
Ap:The total end area of prefabricated band bellend pile for prestressed pipe,
d:Prefabricated band bellend prestressed pipe stake body outside diameter.
Q in formula (6)pkApItem is due to that pile foundation lining material provides end resistance, can be fully achieved and closed by the present invention Mouth stake effect.The pile foundation lining material designed by the present invention and the prefabricated band bellend prestressing pipe pile construction method using the lining material The application range of pile for prestressed pipe can be expanded, and reduce the difficulty of former technique, improve the bearing capacity of stake.
In example 1 below~4:
Prefabricated band bellend prestressed pipe stake body mechanism is using national building standard design atlas 10G409《Prestressing force mixes Solidifying soil pile pile》, what is be different from is that prefabricated band bellend prestressed pipe stake body adds shearing resistance cord, and especially adds expansion Big end, prefabricated band bellend pile for prestressed pipe is interior to press technical code for building pile foundation configuration reinforcement, prefabricated band bellend prestressed pipe Stake uses concrete through formwork, pours, health making, and concrete grade uses C20-C80, and bellend uses and prefabricated band expands Pile for prestressed pipe is held with concrete and one-time-concreting shaping;Prefabricated band bellend pile for prestressed pipe structure diagram such as Fig. 1 It is shown, shown in the sectional view such as Fig. 2 (a) of A-A faces, shown in the sectional view such as Fig. 2 (b) of B-B faces;
The prefabricated band bellend pile for prestressed pipe is multi-section structure, and it is 6~12m often to save length, equal in pile section connecting pin Equipped with pile protection hoop, pile protection hoop is molded with prefabricated band bellend pile for prestressed pipe pile section one-time-concreting;On the outside of pile body every spacing 1~ 2m sets a shearing resistance cord, and shearing resistance cord is highly 20~50mm, and width is 10~20mm, and shearing resistance cord uses and prefabricated band Bellend pile for prestressed pipe is with concrete and pours together;Bellend circumferential direction width b is 200~800mm;With bellend Pile section is located at bearing course at pile end, and bellend overall diameter is D, and the pile section of other parts uses the pile section identical with pile body diameter, outside Diameter is d, and interior diameter is d0, prefabricated band bellend pile for prestressed pipe overall dimensions so as to be completely placed into subject to stake holes, Stake holes a diameter of Dz, Dz > D > d > d0.
Embodiment 1
A kind of pile foundation lining material, including component and its weight proportion are iron milltailings:Cement:Flyash:Water=4:1:0.15: 1.2。
Using the prefabricated band bellend prestressing pipe pile construction method of the pile foundation lining material, comprise the following steps:
Step 1, pile hole construction:
Stake holes is bored in relevant position using twist bit, depending on the diameter Dz of the stake holes presses design requirement with depth, hole Bottom depth reaches design bearing course at pile end;
Step 2, pile foundation lining material is prepared:
By proportioning, take respectively, iron milltailings:Cement:Flyash:Water=4:1:0.15:1.2;It is stirred, is formed after mixing Compound iron milltailings mortar, as pile foundation lining material, the iron milltailings are iron milltailings by radiation examinations qualification, the iron tail Sand is tail Extra-fine sand, sand and tail coarse sand are used as mortar fine aggregate in tail.
Step 3, poured pile base lining material:
By in the pile foundation lining material injection borer drill rod of preparation, using auger hollow conduit, using pumping mode, side irrigates Pile foundation lining material side lifts drilling rod, and pile foundation lining material is irrigated to the perfusion absolute altitude of design;
Step 4, piling:
After stake machine is in place, by design position, prefabricated band bellend pile for prestressed pipe is hung to stake holes center, bellend is placed in Bottom, corrects pile body verticality, and downward static-pressure precast band bellend pile for prestressed pipe makes bellend jacked pile to projected depth Hold supporting course, while compacted pile foundation lining material makes that it is combined closely with pile pile and its liquid level of lifting is to stake top 0.7m, conserved to Compression strength reaches 8.5MPa, forms solidifying body, and the prefabricated band bellend pile for prestressed pipe for completing the application pile foundation lining material is applied Work process, prefabricated band bellend pile for prestressed pipe is with stake holes plan as shown in figure 3, profile is as shown in Figure 4.
Embodiment 2
A kind of pile foundation lining material, including component and its weight proportion are iron milltailings:Cement:Flyash:Water:Retarder=4: 1.2:0.15:1.2:0.002.
Using the prefabricated band bellend prestressing pipe pile construction method of the pile foundation lining material, comprise the following steps:
Step 1, pile hole construction:
Stake holes is bored in relevant position using twist bit, depending on the diameter Dz of the stake holes presses design requirement with depth, hole Bottom depth reaches design bearing course at pile end;
Step 2, pile foundation lining material is prepared:
By proportioning, take respectively, iron milltailings:Cement:Flyash:Water:Retarder=4:1.2:0.15:1.2:0.002;Mixing After be stirred, form compound iron milltailings mortar, as pile foundation lining material, the iron milltailings are iron by radiation examinations qualification Tailings, the iron milltailings are tail Extra-fine sand, sand and tail coarse sand are used as mortar fine aggregate in tail.
Step 3, poured pile base lining material:
By in the pile foundation lining material injection borer drill rod of preparation, using auger hollow conduit, using pumping mode, side irrigates Pile foundation lining material side lifts drilling rod, and pile foundation lining material is irrigated to the perfusion absolute altitude of design;
Step 4, piling:
After stake machine is in place, by design position, prefabricated band bellend pile for prestressed pipe is hung to stake holes center, bellend is placed in Bottom, corrects pile body verticality, and downward static-pressure precast band bellend pile for prestressed pipe makes bellend jacked pile to projected depth Hold supporting course, while compacted pile foundation lining material makes that it is combined closely with pile pile and its liquid level of lifting is to stake top 0.5m, conserved to Compression strength reaches 12MPa, forms solidifying body, completes the prefabricated band bellend prestressing pipe pile construction of the application pile foundation lining material Process, prefabricated band bellend pile for prestressed pipe is with stake holes plan as shown in figure 3, profile is as shown in Figure 4.
Embodiment 3
A kind of pile foundation lining material, including component and its weight proportion are iron milltailings:Cement:Flyash:Water:Early strength agent=5: 1:0.15:1.4:0.015.
Using the prefabricated band bellend prestressing pipe pile construction method of the pile foundation lining material, comprise the following steps:
Step 1, pile hole construction:
Stake holes is bored in relevant position using twist bit, depending on the diameter Dz of the stake holes presses design requirement with depth, hole Bottom depth reaches design bearing course at pile end;
Step 2, pile foundation lining material is prepared:
By proportioning, take respectively, iron milltailings:Cement:Flyash:Water:Early strength agent=5:1:0.15:1.4:0.015;After mixing It is stirred, forms compound iron milltailings mortar, as pile foundation lining material, the iron milltailings is the iron tail by radiation examinations qualification Sand, the iron milltailings are tail Extra-fine sand, sand and tail coarse sand are used as mortar fine aggregate in tail.
Step 3, poured pile base lining material:
By in the pile foundation lining material injection borer drill rod of preparation, using auger hollow conduit, using pumping mode, side irrigates Pile foundation lining material side lifts drilling rod, and pile foundation lining material is irrigated to the perfusion absolute altitude of design;
Step 4, piling:
After stake machine is in place, by design position, prefabricated band bellend pile for prestressed pipe is hung to stake holes center, bellend is placed in Bottom, corrects pile body verticality, and downward static-pressure precast band bellend pile for prestressed pipe makes bellend jacked pile to projected depth Hold supporting course, while compacted pile foundation lining material makes that it is combined closely with pile pile and its liquid level of lifting is to stake top 0.8m, conserved to Compression strength reaches 6MPa, forms solidifying body, completes the prefabricated band bellend prestressing pipe pile construction of the application pile foundation lining material Process, prefabricated band bellend pile for prestressed pipe is with stake holes plan as shown in figure 3, profile is as shown in Figure 4.
Embodiment 4
A kind of pile foundation lining material, including component and its weight proportion are iron milltailings:Cement:Flyash:Water:Antifreezing agent=5: 1.2:0.15:1.4:0.03.
Using the prefabricated band bellend prestressing pipe pile construction method of the pile foundation lining material, comprise the following steps:
Step 1, pile hole construction:
Stake holes is bored in relevant position using twist bit, depending on the diameter Dz of the stake holes presses design requirement with depth, hole Bottom depth reaches design bearing course at pile end;
Step 2, pile foundation lining material is prepared:
By proportioning, take respectively, iron milltailings:Cement:Flyash:Water:Antifreezing agent=5:1.2:0.15:1.4:0.03;Mixing After be stirred, form compound iron milltailings mortar, as pile foundation lining material, the iron milltailings are iron by radiation examinations qualification Tailings, the iron milltailings are tail Extra-fine sand, sand and tail coarse sand are used as mortar fine aggregate in tail.
Step 3, poured pile base lining material:
By in the pile foundation lining material injection borer drill rod of preparation, using auger hollow conduit, using pumping mode, side irrigates Pile foundation lining material side lifts drilling rod, and pile foundation lining material is irrigated to the perfusion absolute altitude of design;
Step 4, piling:
After stake machine is in place, by design position, prefabricated band bellend pile for prestressed pipe is hung to stake holes center, bellend is placed in Bottom, corrects pile body verticality, and downward static-pressure precast band bellend pile for prestressed pipe makes bellend jacked pile to projected depth Hold supporting course, while compacted pile foundation lining material makes that it is combined closely with pile pile and its liquid level of lifting is to stake top 1.0m, conserved to Compression strength reaches 10.5MPa, forms solidifying body, and the prefabricated band bellend pile for prestressed pipe for completing the application pile foundation lining material is applied Work process, prefabricated band bellend pile for prestressed pipe is with stake holes plan as shown in figure 3, profile is as shown in Figure 4.
Above example muscle is to illustrate technical scheme and unrestricted, although with reference to preferred embodiment to this hair Bright to be described in detail, those skilled in the art, which should be appreciated that, to modify or wait to technical scheme With replacing, without departing from the purpose and scope of the invention, it should all cover in scope of the presently claimed invention.

Claims (9)

1. a kind of pile foundation lining material, it is characterised in that be including component and its weight proportion, iron milltailings:Cement:Flyash:Water= (4~5):(1~1.2):(0.15):(1.2~1.4).
2. pile foundation lining material according to claim 1, it is characterised in that the pile foundation lining material, according to presetting period, final set The requirement of engineering such as time and microthermal climate are antifreeze, add adulterating agent, the adulterating agent on the basis of corresponding cement proportion amount For retarder, the one or more in early strength agent or antifreezing agent.
3. the prefabricated band bellend prestressing pipe pile construction method of pile foundation lining material described in application claim 1, it is characterised in that bag Include following steps:
Step 1, pile hole construction:
Stake holes is bored in relevant position, the diameter and depth of the stake holes are by depending on design requirement;
Step 2, pile foundation lining material is prepared:
By proportioning, take respectively, iron milltailings:Cement:Flyash:Water=(4~5):(1~1.2):(0.15):(1.2~1.4);It is mixed It is stirred after conjunction, compound iron milltailings mortar is formed, as pile foundation lining material;
Step 3, poured pile base lining material:
By in the pile foundation lining material of preparation injection borer drill rod, drilling rod is lifted in poured pile base lining material, by pile foundation lining material irrigate to The perfusion absolute altitude of design;
Step 4, piling:
By design position, press-in prefabricated band bellend pile for prestressed pipe is to projected depth, while compacted pile foundation lining material makes itself and pipe Stake is combined closely and its liquid level of lifting is to 0.5~1.0m of stake top, is conserved to design strength, forms solidifying body, completes application The prefabricated band bellend prestressing pipe pile construction process of the pile foundation lining material.
4. prefabricated band bellend prestressing pipe pile construction method according to claim 3, it is characterised in that the step In 3, the injection mode of pile foundation lining material is:Using auger hollow conduit, using pumping mode poured pile base lining material to design Irrigate absolute altitude.
5. prefabricated band bellend prestressing pipe pile construction method according to claim 3, it is characterised in that the step In 4, for pile foundation lining material after maintenance, compression strength reaches 6~12MPa.
6. prefabricated band bellend prestressing pipe pile construction method according to claim 3, it is characterised in that the step In 4, prefabricated band bellend pile for prestressed pipe uses concrete prefabricated making, wherein, bellend and prefabricated band bellend prestressing force Pile pile one-time-concreting is molded.
7. prefabricated band bellend prestressing pipe pile construction method according to claim 3, it is characterised in that the step In 4, prefabricated band bellend pile for prestressed pipe pile extension position sets pile protection hoop, the pile protection hoop and prefabricated band bellend prestressing force Pile pile pile section one-time-concreting is molded.
8. prefabricated band bellend prestressing pipe pile construction method according to claim 3, it is characterised in that the step In 4, when prefabricated band bellend pile for prestressed pipe makes, shearing resistance cord, the shearing resistance cord are made in each pile section side surface It is molded when making with pile pile one-time-concreting.
9. prefabricated band bellend prestressing pipe pile construction method according to claim 3, it is characterised in that the step In 4, the pile section that prefabricated band bellend pile for prestressed pipe is located at bearing course at pile end part uses the pile section with bellend, other parts Pile section use the pile section identical with pile body diameter.
CN201711188732.8A 2017-11-24 2017-11-24 Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method Pending CN107905222A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711188732.8A CN107905222A (en) 2017-11-24 2017-11-24 Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711188732.8A CN107905222A (en) 2017-11-24 2017-11-24 Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method

Publications (1)

Publication Number Publication Date
CN107905222A true CN107905222A (en) 2018-04-13

Family

ID=61847605

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711188732.8A Pending CN107905222A (en) 2017-11-24 2017-11-24 Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method

Country Status (1)

Country Link
CN (1) CN107905222A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842837A (en) * 2018-07-25 2018-11-20 青岛理工大学 End-sealed cast pile with precast concrete enlarged footing
CN109024562A (en) * 2018-10-29 2018-12-18 中南大学 A kind of long prefabricated tubular pile of major diameter and its construction method of classification propulsion
CN112281829A (en) * 2020-11-09 2021-01-29 中国瑞林工程技术股份有限公司 Composite pile foundation structure and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102491702A (en) * 2011-11-07 2012-06-13 江苏建华管桩有限公司 Concrete pile and preparation method thereof
CN104929109A (en) * 2015-05-20 2015-09-23 骆嘉成 Replaceable press-grouted cement soil composite pile, construction method of replaceable press-grouted cement soil composite pile and long twist drill employed in construction method
CN105421449A (en) * 2015-11-18 2016-03-23 杭州江润科技有限公司 Construction method of composite pile composed of nail-shaped active material plastic sleeve and concrete stiffened core

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102491702A (en) * 2011-11-07 2012-06-13 江苏建华管桩有限公司 Concrete pile and preparation method thereof
CN104929109A (en) * 2015-05-20 2015-09-23 骆嘉成 Replaceable press-grouted cement soil composite pile, construction method of replaceable press-grouted cement soil composite pile and long twist drill employed in construction method
CN105421449A (en) * 2015-11-18 2016-03-23 杭州江润科技有限公司 Construction method of composite pile composed of nail-shaped active material plastic sleeve and concrete stiffened core

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴立等: "《岩土加固技术与方法》", 30 June 2015, 武汉大学出版社 *
唐复平: "《全球铁矿行业技术发展指南》", 30 November 2015, 冶金工业出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842837A (en) * 2018-07-25 2018-11-20 青岛理工大学 End-sealed cast pile with precast concrete enlarged footing
CN109024562A (en) * 2018-10-29 2018-12-18 中南大学 A kind of long prefabricated tubular pile of major diameter and its construction method of classification propulsion
CN109024562B (en) * 2018-10-29 2024-03-15 中南大学 Graded-propulsion large-diameter long prefabricated pipe pile and construction method thereof
CN112281829A (en) * 2020-11-09 2021-01-29 中国瑞林工程技术股份有限公司 Composite pile foundation structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN106368214B (en) A kind of casing formula cement mixing method at pile operation method
CN106958208A (en) A kind of novel reinforced method of double curvature arched bridge
CN105625294A (en) Composite foundation and construction method thereof
CN206784372U (en) Injection forming club-footed pile
CN103184734A (en) Implanted and grouted compound pile and construction method
CN207348879U (en) Tailwater tunnel structure
CN206737118U (en) A kind of prefabricated regeneration concrete bean column node of reinforcement
CN107905222A (en) Pile foundation lining material and apply the lining material prefabricated band bellend prestressing pipe pile construction method
CN106996104A (en) Injection forming club-footed pile and its construction method
CN104563147A (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN205501843U (en) Consolidate rigid framed arch bridge
CN107034894A (en) Post-tensioned prestressed tension beam recoverable pattern foundation pit supporting structure prefabricated pile and preparation method thereof and construction method
CN207959202U (en) A kind of CFG bracing means
CN105484230A (en) Pile and soil concreted and integrated composite pile and construction method thereof
CN107964949A (en) A kind of pile foundation lining material and apply the pile foundation lining material prefabricated prestressing pipe pile construction method
CN204174955U (en) Reinforced concrete post connects steel core concrete column syndeton
CN208235562U (en) A kind of static pressure pile structure for Collapsible Loess Stabilized
CN107938695A (en) A kind of special-shaped construction of prefabricated piles method of pile foundation lining material and application the pile foundation lining material
CN106065608B (en) A kind of premixing high strength cement soil foundation
CN202672161U (en) Cement-soil mixing drum sheet-pile united slope structure with soil nails
CN202644518U (en) Post-inserted reinforcement cage cement fly ash gravel pile
CN205999887U (en) Boring steel reinforcement cage hoop slip casting broken stone pile
CN104480947A (en) Construction method of prestress cast-in-place pile and soil cement pile engagement support
CN108385674A (en) High-bearing capacity thin-wall steel tube concrete pile construction method and device and its application
CN205475211U (en) A mix soil extrusion solidification precast pile for soft base is handled

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180413