CN107060837A - A kind of asymmetric formula shield arch construction method of Shallow-buried - Google Patents

A kind of asymmetric formula shield arch construction method of Shallow-buried Download PDF

Info

Publication number
CN107060837A
CN107060837A CN201710179482.5A CN201710179482A CN107060837A CN 107060837 A CN107060837 A CN 107060837A CN 201710179482 A CN201710179482 A CN 201710179482A CN 107060837 A CN107060837 A CN 107060837A
Authority
CN
China
Prior art keywords
shield arch
shield
shallow
construction method
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710179482.5A
Other languages
Chinese (zh)
Other versions
CN107060837B (en
Inventor
刘春辉
王传宗
谭朝阳
何旭东
雷保珂
林少军
杨洪飞
赵生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority to CN201710179482.5A priority Critical patent/CN107060837B/en
Publication of CN107060837A publication Critical patent/CN107060837A/en
Application granted granted Critical
Publication of CN107060837B publication Critical patent/CN107060837B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of asymmetric formula shield arch construction method of Shallow-buried, including the gutter construction that intercepts water, the foundation construction of asymmetric formula shield arch, the shield arch construction of asymmetric formula and the backfill of hole top.The construction method of the present invention is simple, and constructing, each step linking is close, and umbrella arch and arrangement of pile foundation position, structure and size design are reasonable;There is convenient, the rapid advantage of speed of application of constructing using construction method of the present invention construction;The anti-biasing effect of the present invention is good, effectively can bias the risk come to railway operation safety belt by less Tunnels in Shallow Buried.

Description

A kind of asymmetric formula shield arch construction method of Shallow-buried
Technical field
The present invention relates to Tunnel Engineering shallow embedding excavation technology field, it particularly relates to a kind of asymmetric formula of Shallow-buried Shield arch construction method.
Background technology
Tunnels in Shallow Buried is excavated in the market(Buried depth is shallower)There is the form that open cut is secretly done, but construction method is inadaptable inclined Location is pressed, this product is unable to reach the transverse pressure that reduction massif bias is caused, and tunnel is acted on because of lateral pressure, easily served as a contrast Cracking is built, and lining cutting is integrally biased, and causes tunnel-liner during operation to occupy headroom.
The content of the invention
For the above-mentioned technical problem in correlation technique, the present invention proposes a kind of asymmetric formula shield arch construction party of Shallow-buried Method, can overcome the above-mentioned deficiency of prior art.
To realize above-mentioned technical purpose, the technical proposal of the invention is realized in this way:
A kind of asymmetric formula shield arch construction method of Shallow-buried, comprises the following steps:
S1:In tunnel slope excavation line, 5 meters perform the gutter that intercepts water in addition, and the current intercepted water in gutter are led into nature ditch;
S2:Asymmetric formula shield arch foundation construction is carried out, is specifically included:
S2.1:Reserved top bar Core Soil, point layback groove tunneling shield skewback plinth to shield arch height of foundation;
S2.2:Side slope carries out brush slope according to on-site actual situations by slope ratio, it is ensured that shield arch foundation width meets design and wanted at toe Ask, and side slope linked network carries out spray anchor gib;
S3:Asymmetric formula shield arch construction, is specifically included:
S3.1:The shield arch foundation construction in high versant shield arch abutment portion, shield arch foundation main reinforcement uses the spirals of φ 25, and reinforcement is used The spirals of φ 16, bar spacing is 25cm;
S3.2:The shield arch foundation construction in low versant shield arch abutment portion, shield arch foundation main reinforcement uses the spirals of φ 25, and reinforcement is used The spirals of φ 16, bar spacing is 25cm;
S3.3:Shield arch construction is carried out, and shield arch is supported after the completion of shield arch construction;
S4:The backfill of hole top, is referred specifically to:After shield arch concrete strength reaches the 70% of design load, layering rammer is carried out using gravelly soil Packing is real.
Further, in step S2.2, the anchor pole used in spray anchor gib is the grouting rock bolts of φ 22, and the anchor pole is long Spend for 5m, the spacing between adjacent anchor pole is 1.5 × 1.5 meters, and anchor pole is in quincuncial arrangement, the length of anchor pole leakage is 70cm。
Further, in step S2.2, side slope linked network is paved with using the bar-mat reinforcements of φ 6, grid spacing 20cm × 20cm, injection Concrete be 10cm thickness C25 in-network processings.
Further, in step S3.1, high versant shield skewback plinth is strengthened using 3 with the grouting rock bolt slip castings of φ 32, encircles with shield Pour together;And the length of the described grouting rock bolts of φ 32 is 8.0m, 50cm is reserved in termination.
Further, in step S3.2, low versant shield skewback plinth uses C35 steel bar concrete pile plinth, treats that pile foundation is mixed When solidifying soil intensity reaches more than 85%, pile crown is abolished, it is ensured that pile foundation reinforcing bar deeply protects skewback plinth 80cm, pile foundation deeply protects skewback plinth 10cm。
It is preferred that, the stake footpath of described C35 steel bar concrete pile plinth is 1 meter, and stake is long 15 meters, longitudinal 3 meters of stake spacing.
Further, in step S3.3, shield arch uses 80cm thickness C35 armored concrete, and shield arch cage bar uses the screw threads of φ 25 Reinforcing bar, the spacing of the spirals of φ 25 is 20cm;Longitudinal rib uses the spirals of φ 16, and the spacing of the spirals of φ 16 is 25cm, reinforcement φ 8 round steel, the spacing of the round steel of φ 8 is 25cm.
It is preferred that, described shield arch uses I20 type I-shaped bracing members, and the spacing of the I20 types I-steel is 60cm.
Further, in step S4, described layering is rammed packing implementation work and should symmetrically carried out, and ensures to cover thickness Degree is less than or equal to 3m.
It is preferred that, the compactness that packing implementation work is rammed in layering is more than or equal to 0.8, and the particle diameter of rubble used is less than or equal to 15cm。
Beneficial effects of the present invention:The construction method of the present invention is simple, and each step linking of constructing is close, umbrella arch and stake Base fabric seated position, structure and size design are reasonable;Convenient with constructing using construction method of the present invention construction, speed of application is rapid Advantage;The anti-biasing effect of the present invention is good, effectively can bias the wind come to railway operation safety belt by less Tunnels in Shallow Buried Danger.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment The accompanying drawing needed to use is briefly described, it should be apparent that, drawings in the following description are only some implementations of the present invention Example, for those of ordinary skill in the art, on the premise of not paying creative work, can also be obtained according to these accompanying drawings Obtain other accompanying drawings.
Fig. 1 is the structural representation of the asymmetric shield arch of Shallow-buried described according to embodiments of the present invention;
Fig. 2 is arrangement of reinforcement schematic diagram described according to embodiments of the present invention;
In figure:1st, tunnel;2nd, shield arch;3rd, high versant shield arch abutment portion;4th, low versant shield arch abutment portion;5th, the grouting rock bolts of φ 32;6、φ 25 spirals;7th, the spirals of φ 16;8th, the round steel of φ 8.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belongs to what the present invention was protected Scope.
As shown in Figure 1-2, a kind of asymmetric formula shield arch construction method of Shallow-buried, comprises the following steps:
S1:The gutter that intercepts water is performed beyond 5 meters of 1 slope excavating line in tunnel, and the current intercepted water in gutter are led into nature ditch, The excavated section in the tunnel 1 is 114m2~140m2
S2:Asymmetric formula shield arch foundation construction is carried out, is specifically included:
S2.1:Reserved top bar Core Soil, point layback groove tunneling shield skewback plinth to shield arch height of foundation;
S2.2:Side slope carries out brush slope according to on-site actual situations by slope ratio, it is ensured that shield arch foundation width meets design and wanted at toe Ask, and side slope linked network carries out spray anchor gib;
S3:Asymmetric formula shield arch 2 is constructed, and is specifically included:
S3.1:The shield arch foundation construction in high versant shield arch abutment portion 3, shield arch foundation main reinforcement uses the spirals of φ 25, and reinforcement is adopted With the spirals of φ 16, bar spacing is 25cm;
S3.2:The shield arch foundation construction in low versant shield arch abutment portion 4, shield arch foundation main reinforcement uses the spirals of φ 25, and reinforcement is adopted With the spirals of φ 16, bar spacing is 25cm;
S3.3:Carry out shield arch 2 to construct, and shield arch is supported after the completion of shield arch construction;
S4:The backfill of hole top, is referred specifically to:After shield arch concrete strength reaches the 70% of design load, layering rammer is carried out using gravelly soil Packing is real.
In one embodiment, in step S2.2, the anchor pole used in spray anchor gib is the grouting rock bolts of φ 22, institute The grouting rock bolt length of φ 22 is stated for 5m, the spacing between the adjacent grouting rock bolts of φ 22 is 1.5 × 1.5 meters, and the grouting rock bolts of φ 22 In quincuncial arrangement, the length of the grouting rock bolts of φ 22 leakage is 70cm.
In one embodiment, in step S2.2, side slope linked network is paved with using the bar-mat reinforcements of φ 6, and grid spacing 20cm × 20cm, the concrete of injection is 10cm thickness C25 in-network processings.
In one embodiment, in step S3.1, high versant shield skewback plinth adds using 3 with the slip casting of 32 grouting rock bolts of φ 5 By force, poured together with shield arch;And the length of the described grouting rock bolts 5 of φ 32 is 8.0m, 50cm is reserved in termination.
In one embodiment, in step S3.2, low versant shield skewback plinth uses C35 steel bar concrete pile plinth, treats When pile foundation concrete strength reaches more than 85%, pile crown is abolished, it is ensured that pile foundation reinforcing bar deeply protects skewback plinth 80cm, pile foundation is deep Protect skewback plinth 10cm;The stake footpath of described C35 steel bar concrete pile plinth is 1 meter, and stake is long 15 meters, longitudinal 3 meters of stake spacing.
In one embodiment, in step S3.3, shield arch uses 80cm thickness C35 armored concrete, and shield arch cage bar is used The spirals 6 of φ 25, the spacing of the spirals 6 of φ 25 is 20cm;Longitudinal rib uses the spirals 7 of φ 16, the spirals 7 of φ 16 Spacing be 25cm;Reinforcement is the round steel 8 of φ 8, and the spacing of the round steel 8 of φ 8 is 25cm;Described shield arch uses I20 type I-steel Support, the spacing of the I20 types I-steel is 60cm.
In one embodiment, in step S4, described layering is rammed packing implementation work and should symmetrically carried out, and ensures Overburden cover is less than or equal to 3m, and layering, which rams packing and implements the compactness of work, is more than or equal to 0.8, and the particle diameter of rubble used is less than etc. In 15cm.
Understand for convenience the present invention above-mentioned technical proposal, below by way of in specifically used mode to the present invention it is above-mentioned Technical scheme is described in detail.
When specifically used, the asymmetric formula shield arch construction method of Shallow-buried of the present invention is always divided into 4 steps, including cuts The construction of water gutter, the foundation construction of asymmetric formula shield arch, the shield arch construction of asymmetric formula and the backfill of hole top.
Wherein, the gutter construction that intercepts water refers to that 5 meters perform the gutter that intercepts water in addition to tunnel slope excavation line, and leads to certainly Right ditch, it is ensured that rainwater does not flow into shield arch section, and the excavated section in the tunnel 1 is 114m2~140m2
The asymmetric formula shield arch foundation construction includes:To umbrella arch foundation excavation, top bar Core Soil is reserved, point side Kerve is excavated to shield arch height of foundation, and side slope is according to on-site actual situations, by slope than carrying out brush slope, it is ensured that skewback plinth is protected at toe Width meets design requirement, and side slope linked network carries out spray anchor gib, and the anchor pole of spray anchor gib uses the mortars of φ 22 Anchor pole, length is 5m, 1.5 × 1.5 meters of spacing between adjacent anchor pole, in quincuncial arrangement, anchor pole leakage 70cm, so as to which shield is encircleed It is integral with massif anchoring, to prevent displacement;Side slope linked network is paved with using the bar-mat reinforcements of φ 6, grid spacing 20cm × 20cm, and injection is mixed Solidifying soil uses 10cm thickness C25 in-network processings.
The asymmetric formula shield arch construction includes:It is excavated to after design height, high versant shield skewback plinth is using 3 with the sand of φ 32 Starch bolt grouting to strengthen, length is 8.0m, and 50cm is reserved in termination, poured together with shield arch, strengthen stability;Low versant shield arch by In in coombe location, basic mud is deeper, using C35 steel bar concrete pile plinth, 1 meter of stake footpath, and stake is long 15 meters, between longitudinal stake Away from 3 meters, when pile foundation concrete strength reaches more than 85%, pile crown is abolished, it is ensured that pile foundation reinforcing bar deeply protects skewback plinth 80cm, Pile foundation deeply protects skewback plinth 10cm, and shield skewback plinth uses C35 armored concrete, and thick 80cm, wide 2.5m, shield arch foundation main reinforcement are used The spirals of φ 25, reinforcement uses the spirals of φ 16, and bar spacing is 25cm;Shield arch is constructed and carries out supporting, and shield arch is adopted With 80cm thickness C35 armored concrete, shield arch cage bar uses the spirals of φ 25, spacing 20cm;Longitudinal rib uses the screw-thread steels of φ 16 Muscle, bar spacing is 25cm;The round steel of reinforcement φ 8, spacing 25cm, shield arch brace uses I20 type I-steel, spacing 60cm.
The hole top backfill refers to:After shield arch concrete strength reaches the 70% of design load, vault is layered using gravelly soil Ram packing real, compactness is more than or equal to 0.8, and ballast grain sizes used are less than or equal to 15cm, and must not contain expansive clay, backfills Construction should be carried out symmetrically, compaction in layers, and ensure overburden cover no more than 3m.
In summary, construction method of the invention is simple, and each step linking of constructing is close, umbrella arch and arrangement of pile foundation position Put, structure and size design it is reasonable;There is convenient, the rapid advantage of speed of application of constructing using construction method of the present invention construction; The anti-biasing effect of the present invention is good, effectively can bias the risk come to railway operation safety belt by less Tunnels in Shallow Buried.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention God is with principle, and any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.

Claims (10)

1. a kind of asymmetric formula shield arch construction method of Shallow-buried, it is characterised in that comprise the following steps:
S1:In tunnel slope excavation line, 5 meters perform the gutter that intercepts water in addition, and the current intercepted water in gutter are led into nature ditch;
S2:Asymmetric formula shield arch foundation construction is carried out, is specifically included:
S2.1:Reserved top bar Core Soil, point layback groove tunneling shield skewback plinth to shield arch height of foundation;
S2.2:Side slope carries out brush slope according to on-site actual situations by slope ratio, it is ensured that shield arch foundation width meets design and wanted at toe Ask, and side slope linked network carries out spray anchor gib;
S3:Asymmetric formula shield arch construction, is specifically included:
S3.1:The shield arch foundation construction in high versant shield arch abutment portion, shield arch foundation main reinforcement uses the spirals of φ 25, and reinforcement is used The spirals of φ 16, bar spacing is 25cm;
S3.2:The shield arch foundation construction in low versant shield arch abutment portion, shield arch foundation main reinforcement uses the spirals of φ 25, and reinforcement is used The spirals of φ 16, bar spacing is 25cm;
S3.3:Shield arch construction is carried out, and shield arch is supported after the completion of shield arch construction;
S4:The backfill of hole top, is referred specifically to:After shield arch concrete strength reaches the 70% of design load, layering rammer is carried out using gravelly soil Packing is real.
2. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 1, it is characterised in that step S2.2 In, the anchor pole that uses is the grouting rock bolts of φ 22 in spray anchor gib, and the grouting rock bolt length is 5m, adjacent grouting rock bolt it Between spacing be 1.5 × 1.5 meters, and described grouting rock bolt is in quincuncial arrangement, and the length of grouting rock bolt leakage is 70cm.
3. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 1, it is characterised in that step S2.2 In, side slope linked network is paved with using the bar-mat reinforcements of φ 6, grid spacing 20cm × 20cm, and the concrete of injection is that 10cm thickness C25 net sprays are mixed Solidifying soil.
4. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 1, it is characterised in that step S3.1 In, high versant shield skewback plinth is strengthened using 3 with the grouting rock bolt slip castings of φ 32, is poured together with shield arch;And the described mortars of φ 32 The length of anchor pole is 8.0m, and 50cm is reserved in termination.
5. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 1, it is characterised in that step S3.2 In, low versant shield skewback plinth uses C35 steel bar concrete pile plinth, when pile foundation concrete strength reaches more than 85%, abolishes Pile crown, it is ensured that pile foundation reinforcing bar deeply protects skewback plinth 80cm, pile foundation deeply protects skewback plinth 10cm.
6. the asymmetric formula shield arch construction method of a kind of Shallow-buried according to claim 5, it is characterised in that described The stake footpath of C35 steel bar concrete pile plinth is 1 meter, and stake is long 15 meters, longitudinal 3 meters of stake spacing.
7. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 1, it is characterised in that step S3.3 In, shield arch uses 80cm thickness C35 armored concrete, and shield arch cage bar uses the spirals of φ 25, and the spacing of the spirals of φ 25 is 20cm;Longitudinal rib uses the spirals of φ 16, and the spacing of the spirals of φ 16 is 25cm, the round steel of reinforcement φ 8, the round steel of φ 8 Spacing is 25cm.
8. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 7, it is characterised in that described shield Arch uses I20 type I-shaped bracing members, and the spacing of the I20 types I-steel is 60cm.
9. a kind of asymmetric formula shield arch construction method of Shallow-buried according to claim 1, it is characterised in that step S4 In, described layering is rammed packing implementation work and should symmetrically carried out, and ensures that overburden cover is less than or equal to 3m.
10. the asymmetric formula shield arch construction method of a kind of Shallow-buried according to claim 9, it is characterised in that layering is rammed The compactness that work is implemented in packing is more than or equal to 0.8, and the particle diameter of rubble used is less than or equal to 15cm.
CN201710179482.5A 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method Active CN107060837B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710179482.5A CN107060837B (en) 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710179482.5A CN107060837B (en) 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method

Publications (2)

Publication Number Publication Date
CN107060837A true CN107060837A (en) 2017-08-18
CN107060837B CN107060837B (en) 2019-08-13

Family

ID=59620357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710179482.5A Active CN107060837B (en) 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method

Country Status (1)

Country Link
CN (1) CN107060837B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661668A (en) * 2018-04-28 2018-10-16 中铁六局集团天津铁路建设有限公司 The exposed method for tunnel construction of arch part-structure
CN111608701A (en) * 2020-06-02 2020-09-01 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3307858A1 (en) * 1983-03-05 1984-09-06 Thyssen Industrie Ag, 4300 Essen Support system for a tunnel, in particular a railway tunnel
CN102518453A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Quick tunnel-entrance construction method for bias-pressure shallow-buried or single-pressure tilting arenaceous loess tunnels
CN102839980A (en) * 2012-08-25 2012-12-26 张双茁 Highway tunnel structure and construction method thereof
CN204419195U (en) * 2014-12-29 2015-06-24 山西省交通科学研究院 A kind of supporting and protection structure pattern being applicable to tunnel portal section
CN105736017A (en) * 2015-07-27 2016-07-06 中铁十二局集团有限公司 Asymmetric unit forwardly-reversely arranged arch structure for primary supporting of tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3307858A1 (en) * 1983-03-05 1984-09-06 Thyssen Industrie Ag, 4300 Essen Support system for a tunnel, in particular a railway tunnel
CN102518453A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Quick tunnel-entrance construction method for bias-pressure shallow-buried or single-pressure tilting arenaceous loess tunnels
CN102839980A (en) * 2012-08-25 2012-12-26 张双茁 Highway tunnel structure and construction method thereof
CN204419195U (en) * 2014-12-29 2015-06-24 山西省交通科学研究院 A kind of supporting and protection structure pattern being applicable to tunnel portal section
CN105736017A (en) * 2015-07-27 2016-07-06 中铁十二局集团有限公司 Asymmetric unit forwardly-reversely arranged arch structure for primary supporting of tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661668A (en) * 2018-04-28 2018-10-16 中铁六局集团天津铁路建设有限公司 The exposed method for tunnel construction of arch part-structure
CN111608701A (en) * 2020-06-02 2020-09-01 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section
CN111608701B (en) * 2020-06-02 2022-04-26 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section

Also Published As

Publication number Publication date
CN107060837B (en) 2019-08-13

Similar Documents

Publication Publication Date Title
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN106638673B (en) A kind of construction method of compound retaining structure
CN203741868U (en) Reinforced concrete retaining wall structure with combined anchor wire
CN107201908B (en) Construction method for deep-buried central ditch of tunnel in severe cold region
CN112127900B (en) Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN101476466B (en) Giant heavy laver land slide pre-stress anchor cable antiskid tunnel construction method and novel prevention structure
CN104389320B (en) Construction method of pile foundation anchor rope prestress high retaining wall
CN105298516A (en) Combined supporting structure of steel pipe pile steel-bar-embedded tunnel composite lining used for soft foundation
CN106759376A (en) Anchored Sheet Pile Wall for Excavation system and its construction method for closing on existing underground structure
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN103031839A (en) Construction method of hand-dug piles
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN110241828A (en) The outer sealing construction method for supporting of anchor in a kind of row's grating tubular pole grouting behind shaft or drift lining
CN103696416B (en) A kind of method for processing foundation
CN109653222A (en) Friction pile means of defence, anti-slide pile construction method and friction pile safeguard structure
CN107012875A (en) Basement supporting
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN111441372A (en) Landslide foundation treatment embankment structure and construction method
CN107012874A (en) A kind of upper-soft lower-hard ground subway station building enclosure
CN107060837A (en) A kind of asymmetric formula shield arch construction method of Shallow-buried
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN206070573U (en) It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED
CN215976663U (en) Excavation area composite foundation treatment structure crossing under high-voltage line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB03 Change of inventor or designer information

Inventor after: Ma Dong

Inventor after: Lin Shaojun

Inventor after: Yang Hongfei

Inventor after: Zhao Sheng

Inventor after: Liu Chunhui

Inventor after: Wang Chuanzong

Inventor after: Lv Zhijun

Inventor after: Lv Xiuhua

Inventor after: Wang Langfeng

Inventor after: Tan Chaoyang

Inventor after: He Xudong

Inventor after: Lei Baoke

Inventor before: Liu Chunhui

Inventor before: Wang Chuanzong

Inventor before: Tan Chaoyang

Inventor before: He Xudong

Inventor before: Lei Baoke

Inventor before: Lin Shaojun

Inventor before: Yang Hongfei

Inventor before: Zhao Sheng

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20170814

Address after: 064000 Hebei province Tangshan City Fengrun District Guanghua Road No. 2

Applicant after: China Railway Sixteen Bureau Group Fifth Engineering Company Limited

Applicant after: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Address before: 064000 Hebei province Tangshan City Fengrun District Guanghua Road No. 2

Applicant before: China Railway Sixteen Bureau Group Fifth Engineering Company Limited

TA01 Transfer of patent application right
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant