CN107060837B - A kind of Shallow-buried asymmetry formula shield arch construction method - Google Patents

A kind of Shallow-buried asymmetry formula shield arch construction method Download PDF

Info

Publication number
CN107060837B
CN107060837B CN201710179482.5A CN201710179482A CN107060837B CN 107060837 B CN107060837 B CN 107060837B CN 201710179482 A CN201710179482 A CN 201710179482A CN 107060837 B CN107060837 B CN 107060837B
Authority
CN
China
Prior art keywords
shield
shield arch
arch
shallow
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710179482.5A
Other languages
Chinese (zh)
Other versions
CN107060837A (en
Inventor
马栋
刘春辉
王传宗
吕志军
吕秀华
王浪峰
谭朝阳
何旭东
雷保珂
林少军
杨洪飞
赵生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201710179482.5A priority Critical patent/CN107060837B/en
Publication of CN107060837A publication Critical patent/CN107060837A/en
Application granted granted Critical
Publication of CN107060837B publication Critical patent/CN107060837B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of Shallow-buried asymmetry formulas to protect arch construction method, including the gutter construction that intercepts water, asymmetric formula shield arch foundation construction, asymmetric formula shield arch construction and the backfill of hole top.Construction method of the invention is simple, and constructing, each step linking is close, and umbrella arch and arrangement of pile foundation position, structure and size design are reasonable;There is convenient, the rapid advantage of speed of application of constructing using construction method of the present invention construction;Anti- biasing effect of the invention is good, effectively can give railway operation safe bring risk by less Tunnels in Shallow Buried bias.

Description

A kind of Shallow-buried asymmetry formula shield arch construction method
Technical field
The present invention relates to Tunnel Engineering shallow embedding excavation technology fields, it particularly relates to a kind of Shallow-buried asymmetry formula Shield arch construction method.
Background technique
There are the forms that open cut is secretly done for Tunnels in Shallow Buried excavation (buried depth is shallower) currently on the market, but construction method is inadaptable inclined Location is pressed, this product is unable to reach transverse pressure caused by reducing massif bias, and tunnel is easily served as a contrast because lateral pressure acts on Cracking and lining cutting integrally bias are built, tunnel-liner during operation is caused to occupy headroom.
Summary of the invention
For above-mentioned technical problem in the related technology, the present invention proposes a kind of Shallow-buried asymmetry formula shield arch construction party Method can overcome the above-mentioned deficiency of the prior art.
To realize the above-mentioned technical purpose, the technical scheme of the present invention is realized as follows:
A kind of Shallow-buried asymmetry formula shield arch construction method, wherein the both ends of asymmetric formula shield arch are apart from elevation of water It is inconsistent, include the following steps:
S1: the gutter that intercepts water is performed other than 5 meters of tunnel slope excavation line, and the water flow to intercept water in gutter is led into Natural Water Ditch;
S2: asymmetric formula shield arch foundation construction is carried out, is specifically included:
S2.1: reserved top bar Core Soil divides layback slot tunneling shield skewback plinth to shield arch height of foundation;
S2.2: side slope carries out brush slope according to on-site actual situations, by slope ratio, and shield arch foundation width, which meets, at guarantee slope foot sets Meter requires, and side slope linked network carries out spray anchor gib;
S3: asymmetric formula shield arch construction specifically includes:
S3.1: the shield in high versant shield arch abutment portion encircles foundation construction, and shield arch foundation main reinforcement uses 25 spiral of φ, reinforcing rib Using 16 spiral of φ, bar spacing 25cm;
S3.2: the shield in low versant shield arch abutment portion encircles foundation construction, and shield arch foundation main reinforcement uses 25 spiral of φ, reinforcing rib Using 16 spiral of φ, bar spacing 25cm;
S3.3: shield arch construction is carried out, and shield arch is supported after the completion of shield arch construction;
S4: the backfill of hole top refers specifically to: after protecting arch concrete strength and reaching the 70% of design value, being carried out using gravelly soil It is real that packing is rammed in layering.
Further, in step S2.2, spraying the anchor pole used in anchor gib is 22 grouting rock bolt of φ, and the anchor pole is long Degree is 5m, and the spacing between adjacent anchor pole is 1.5 × 1.5 meters, and anchor pole is in quincuncial arrangement, and the length of anchor pole leakage is 70cm.Further, in step S2.2, side slope linked network is paved with using 6 steel mesh of φ, grid spacing 20cm × 20cm, injection Concrete is 10cm thickness C25 in-network processing.
Further, in step S3.1, high versant shield skewback plinth is reinforced using 3 32 grouting rock bolt slip castings of φ, encircles with shield It pours together;And the length of 32 grouting rock bolt of φ is 8.0m, 50cm is reserved in end.
Further, in step S3.2, low versant shield skewback plinth uses C35 steel bar concrete pile plinth, mixed to pile foundation When solidifying soil intensity reaches 85% or more, pile crown is abolished, guarantees that pile foundation reinforcing bar deeply protects skewback plinth 80cm, pile foundation deeply protects skewback plinth 10cm。
Preferably, the stake diameter of the C35 steel bar concrete pile plinth is 1 meter, and stake is 15 meters long, 3 meters of longitudinal stake spacing.
Further, in step S3.3, shield arch uses 80cm thickness C35 armored concrete, and shield arch main reinforcement uses 25 screw thread of φ Reinforcing bar, the spacing of 25 spiral of φ are 20cm;Longitudinal rib uses 16 spiral of φ, and the spacing of 16 spiral of φ is 8 round steel of 25cm, reinforcing rib φ, the spacing of 8 round steel of φ are 25cm.
Preferably, shield arch uses I20 type I-shaped bracing members, and the spacing of the I20 type I-steel is 60cm.
Further, in step S4, layering is rammed packing implementation work and is symmetrically carried out, and ensures that overburden cover is less than In 3m.
Preferably, the compactness that packing implementation work is rammed in layering is more than or equal to 0.8, and the partial size of rubble used is less than or equal to 15cm。
Beneficial effects of the present invention: construction method of the invention is simple, and each step linking of constructing is close, umbrella arch and stake Base fabric seated position, structure and size design are reasonable;Have construction convenient using construction method of the present invention construction, speed of application is rapid The advantages of;Anti- biasing effect of the invention is good, effectively can give railway operation safe bring wind by less Tunnels in Shallow Buried bias Danger.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is the structural schematic diagram of the Shallow-buried asymmetry shield arch described according to embodiments of the present invention;
Fig. 2 is the arrangement of reinforcement schematic diagram described according to embodiments of the present invention;
In figure: 1, tunnel;2, shield arch;3, high versant protects arch abutment portion;4, low versant protects arch abutment portion;5,32 grouting rock bolt of φ; 6,25 spiral of φ;7,16 spiral of φ;8,8 round steel of φ.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
As shown in Figs. 1-2, a kind of Shallow-buried asymmetry formula shield arch construction method, wherein the both ends of asymmetric formula shield arch away from It is inconsistent from elevation of water to include the following steps:
S1: the gutter that intercepts water is performed other than 5 meters of 1 slope excavating line in tunnel, and the water flow to intercept water in gutter is led into nature Ditch, the excavated section in the tunnel 1 are 114m2~140m2
S2: asymmetric formula shield arch foundation construction is carried out, is specifically included:
S2.1: reserved top bar Core Soil divides layback slot tunneling shield skewback plinth to shield arch height of foundation;
S2.2: side slope carries out brush slope according to on-site actual situations, by slope ratio, and shield arch foundation width, which meets, at guarantee slope foot sets Meter requires, and side slope linked network carries out spray anchor gib;
S3: asymmetric 2 construction of formula shield arch specifically includes:
S3.1: the shield in high versant shield arch abutment portion 3 encircles foundation construction, and shield arch foundation main reinforcement uses 25 spiral of φ, reinforces Muscle uses 16 spiral of φ, bar spacing 25cm;
S3.2: the shield in low versant shield arch abutment portion 4 encircles foundation construction, and shield arch foundation main reinforcement uses 25 spiral of φ, reinforces Muscle uses 16 spiral of φ, bar spacing 25cm;
S3.3: 2 construction of shield arch is carried out, and shield arch is supported after the completion of shield arch construction;
S4: the backfill of hole top refers specifically to: after protecting arch concrete strength and reaching the 70% of design value, being carried out using gravelly soil It is real that packing is rammed in layering.
In one embodiment, in step S2.2, spraying the anchor pole used in anchor gib is 22 grouting rock bolt of φ, institute Stating 22 grouting rock bolt length of φ is 5m, and the spacing between adjacent 22 grouting rock bolt of φ is 1.5 × 1.5 meters, and 22 grouting rock bolt of φ In quincuncial arrangement, the length of 22 grouting rock bolt of φ leakage is 70cm.
In one embodiment, in step S2.2, side slope linked network is paved with using 6 steel mesh of φ, and grid spacing 20cm × 20cm, the concrete of injection are 10cm thickness C25 in-network processings.
In one embodiment, in step S3.1, high versant shield skewback plinth is added using 3 32 grouting rock bolt of φ, 5 slip castings By force, it is poured together with shield arch;And the length of 32 grouting rock bolt 5 of φ is 8.0m, 50cm is reserved in end.
In one embodiment, in step S3.2, low versant shield skewback plinth uses C35 steel bar concrete pile plinth, to When pile foundation concrete strength reaches 85% or more, pile crown is abolished, guarantees that pile foundation reinforcing bar deeply protects skewback plinth 80cm, pile foundation is deep Protect skewback plinth 10cm;The stake diameter of the C35 steel bar concrete pile plinth is 1 meter, and stake is 15 meters long, 3 meters of longitudinal stake spacing.
In one embodiment, in step S3.3, shield arch uses 80cm thickness C35 armored concrete, and shield arch main reinforcement uses 25 spiral 6 of φ, the spacing of 25 spiral 6 of φ are 20cm;Longitudinal rib uses 16 spiral 7 of φ, 16 spiral 7 of φ Spacing be 25cm;Reinforcing rib is 8 round steel 8 of φ, and the spacing of 8 round steel 8 of φ is 25cm;The shield arch uses I20 type I-steel Support, the spacing of the I20 type I-steel are 60cm.
In one embodiment, in step S4, layering is rammed packing implementation work and is symmetrically carried out, and ensures to cover thickness Degree is less than or equal to 3m, and the compactness that packing implementation work is rammed in layering is more than or equal to 0.8, and the partial size of rubble used is less than or equal to 15cm.
In order to facilitate understanding above-mentioned technical proposal of the invention, below by way of in specifically used mode to of the invention above-mentioned Technical solution is described in detail.
When specifically used, Shallow-buried asymmetry formula shield arch construction method of the present invention is always divided into 4 steps, including cuts The construction of water gutter, asymmetric formula shield arch foundation construction, asymmetric formula shield arch construction and the backfill of hole top.
Wherein, the gutter construction that intercepts water, which refers to, performs the gutter that intercepts water in addition to 5 meters of tunnel slope excavation line, and leads to certainly Right ditch guarantees that rainwater does not flow into shield arch section, and the excavated section in the tunnel 1 is 114m2~140m2
The asymmetry formula shield arch foundation construction includes: to reserve top bar Core Soil to umbrella arch foundation excavation, divide side Kerve is excavated to shield arch height of foundation, and side slope carries out brush slope according to on-site actual situations, by slope ratio, guarantees to protect skewback plinth at slope foot Width meets design requirement, and side slope linked network carries out spray anchor gib, and the anchor pole of spray anchor gib uses 22 mortar of φ Anchor pole, length 5m are in quincuncial arrangement 1.5 × 1.5 meters of spacing between adjacent anchor pole, and anchor pole leaks outside 70cm, to protect arch It is integral with massif anchoring, to prevent displacement;Side slope linked network is paved with using 6 steel mesh of φ, grid spacing 20cm × 20cm, and injection is mixed Solidifying soil uses 10cm thickness C25 in-network processing.
The asymmetry formula shield arch construction includes: after being excavated to design height, and high versant shield skewback plinth is using 3 with 32 sand of φ It starches bolt grouting to reinforce, 50cm is reserved in length 8.0m, end, pours together with shield arch, enhances stability;Low versant shield arch by In being in coombe location, basic mud is deeper, and using C35 steel bar concrete pile plinth, 1 meter of stake diameter, stake is 15 meters long, between longitudinal stake Away from 3 meters, when pile foundation concrete strength reaches 85% or more, pile crown is abolished, guarantees that pile foundation reinforcing bar deeply protects skewback plinth 80cm, Pile foundation deeply protects skewback plinth 10cm, and shield skewback plinth uses C35 armored concrete, thick 80cm, wide 2.5m, and shield arch foundation main reinforcement uses 25 spiral of φ, reinforcing rib use 16 spiral of φ, bar spacing 25cm;Shield arch constructs and carries out supporting, and shield arch is adopted With 80cm thickness C35 armored concrete, shield arch main reinforcement uses 25 spiral of φ, spacing 20cm;Longitudinal rib uses 16 screw-thread steel of φ Muscle, bar spacing 25cm;8 round steel of reinforcing rib φ, spacing 25cm, shield arch brace use I20 type I-steel, spacing 60cm.
Hole top backfill refers to: after protecting arch concrete strength and reaching the 70% of design value, vault is using gravelly soil point Layer rams packing reality, and compactness is more than or equal to 0.8, and ballast grain sizes used are less than or equal to 15cm, and must not contain expansive clay, return Filling out construction should symmetrically carry out, compaction in layers, and ensure overburden cover no more than 3m.
In conclusion construction method of the invention is simple, each step linking of constructing is close, umbrella arch and arrangement of pile foundation position Set, structure and size design it is reasonable;There is convenient, the rapid advantage of speed of application of constructing using construction method of the present invention construction; Anti- biasing effect of the invention is good, effectively can give railway operation safe bring risk by less Tunnels in Shallow Buried bias.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (8)

1. a kind of Shallow-buried asymmetry formula shield arch construction method, wherein the both ends of asymmetric formula shield arch apart from elevation of water not Unanimously, which comprises the steps of:
S1: the gutter that intercepts water is performed other than 5 meters of tunnel slope excavation line, and the water flow to intercept water in gutter is led into nature ditch;
S2: asymmetric formula shield arch foundation construction is carried out, is specifically included:
S2.1: reserved top bar Core Soil divides layback slot tunneling shield skewback plinth to shield arch height of foundation;
S2.2: side slope carries out brush slope according to on-site actual situations, by slope ratio, and shield arch foundation width meets design and wants at guarantee slope foot It asks, and side slope linked network carries out spray anchor gib;
S3: asymmetric formula shield arch construction specifically includes:
S3.1: the shield in high versant shield arch abutment portion encircles foundation construction, and shield arch foundation main reinforcement uses 25 spiral of φ, and reinforcing rib uses 16 spiral of φ, bar spacing 25cm, and high versant shield skewback plinth is reinforced using 3 32 grouting rock bolt slip castings of φ, with shield Arch pours together;And the length of 32 grouting rock bolt of φ is 8.0m, 50cm is reserved in end;
S3.2: the shield in low versant shield arch abutment portion encircles foundation construction, and shield arch foundation main reinforcement uses 25 spiral of φ, and reinforcing rib uses 16 spiral of φ, bar spacing 25cm, low versant shield skewback plinth uses C35 steel bar concrete pile plinth, mixed to pile foundation When solidifying soil intensity reaches 85% or more, pile crown is abolished, guarantees that pile foundation reinforcing bar deeply protects skewback plinth 80cm, pile foundation deeply protects skewback plinth 10cm;
S3.3: shield arch construction is carried out, and shield arch is supported after the completion of shield arch construction;
S4: the backfill of hole top refers specifically to: after protecting arch concrete strength and reaching the 70% of design value, being layered using gravelly soil It is real to ram packing.
2. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 1, which is characterized in that step S2.2 In, spraying the anchor pole that uses in anchor gib is 22 grouting rock bolt of φ, and the grouting rock bolt length is 5m, adjacent grouting rock bolt it Between spacing be 1.5 × 1.5 meters, and the grouting rock bolt be in quincuncial arrangement, grouting rock bolt leakage length be 70cm.
3. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 1, which is characterized in that step S2.2 In, side slope linked network is paved with using 6 steel mesh of φ, grid spacing 20cm × 20cm, and the concrete of injection is that 10cm thickness C25 net spray is mixed Solidifying soil.
4. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 3, which is characterized in that described The stake diameter of C35 steel bar concrete pile plinth is 1 meter, and stake is 15 meters long, 3 meters of longitudinal stake spacing.
5. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 1, which is characterized in that step S3.3 In, shield arch uses 80cm thickness C35 armored concrete, and shield arch main reinforcement uses 25 spiral of φ, and the spacing of 25 spiral of φ is 20cm;Longitudinal rib uses 16 spiral of φ, and the spacing of 16 spiral of φ is 25cm, 8 round steel of reinforcing rib φ, 8 round steel of φ Spacing is 25cm.
6. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 5, which is characterized in that the shield Arch uses I20 type I-shaped bracing members, and the spacing of the I20 type I-steel is 60cm.
7. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 1, which is characterized in that step S4 In, layering is rammed packing implementation work and is symmetrically carried out, and ensures that overburden cover is less than or equal to 3m.
8. a kind of Shallow-buried asymmetry formula shield arch construction method according to claim 7, which is characterized in that layering is rammed and filled out The compactness of closely knit construction is more than or equal to 0.8, and the partial size of rubble used is less than or equal to 15cm.
CN201710179482.5A 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method Active CN107060837B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710179482.5A CN107060837B (en) 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710179482.5A CN107060837B (en) 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method

Publications (2)

Publication Number Publication Date
CN107060837A CN107060837A (en) 2017-08-18
CN107060837B true CN107060837B (en) 2019-08-13

Family

ID=59620357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710179482.5A Active CN107060837B (en) 2017-03-23 2017-03-23 A kind of Shallow-buried asymmetry formula shield arch construction method

Country Status (1)

Country Link
CN (1) CN107060837B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661668A (en) * 2018-04-28 2018-10-16 中铁六局集团天津铁路建设有限公司 The exposed method for tunnel construction of arch part-structure
CN111608701B (en) * 2020-06-02 2022-04-26 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3307858A1 (en) * 1983-03-05 1984-09-06 Thyssen Industrie Ag, 4300 Essen Support system for a tunnel, in particular a railway tunnel
CN102518453A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Quick tunnel-entrance construction method for bias-pressure shallow-buried or single-pressure tilting arenaceous loess tunnels
CN102839980A (en) * 2012-08-25 2012-12-26 张双茁 Highway tunnel structure and construction method thereof
CN204419195U (en) * 2014-12-29 2015-06-24 山西省交通科学研究院 A kind of supporting and protection structure pattern being applicable to tunnel portal section
CN105736017A (en) * 2015-07-27 2016-07-06 中铁十二局集团有限公司 Asymmetric unit forwardly-reversely arranged arch structure for primary supporting of tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3307858A1 (en) * 1983-03-05 1984-09-06 Thyssen Industrie Ag, 4300 Essen Support system for a tunnel, in particular a railway tunnel
CN102518453A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Quick tunnel-entrance construction method for bias-pressure shallow-buried or single-pressure tilting arenaceous loess tunnels
CN102839980A (en) * 2012-08-25 2012-12-26 张双茁 Highway tunnel structure and construction method thereof
CN204419195U (en) * 2014-12-29 2015-06-24 山西省交通科学研究院 A kind of supporting and protection structure pattern being applicable to tunnel portal section
CN105736017A (en) * 2015-07-27 2016-07-06 中铁十二局集团有限公司 Asymmetric unit forwardly-reversely arranged arch structure for primary supporting of tunnel

Also Published As

Publication number Publication date
CN107060837A (en) 2017-08-18

Similar Documents

Publication Publication Date Title
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN106638673B (en) A kind of construction method of compound retaining structure
CN203741868U (en) Reinforced concrete retaining wall structure with combined anchor wire
CN105239586B (en) Method for supporting foundation pit by adopting support structure
CN101476466B (en) Giant heavy laver land slide pre-stress anchor cable antiskid tunnel construction method and novel prevention structure
CN103758134A (en) Combined double-row pile supporting system and construction method thereof
CN104389320B (en) Construction method of pile foundation anchor rope prestress high retaining wall
CN106703044B (en) One kind stream modeling shape rinse fill soft stratum slope combination supporting method
CN103774675A (en) Combined double-row-pile combined vertical prestress anchor rod supporting system and construction method thereof
CN203729308U (en) Double-row pile supporting system of reinforced concrete pile combined structural steel cement mixing pile wall
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN205387720U (en) Tertiary light -duty retaining structure of double circular pile pile foundation of superelevation embankment
CN102966072A (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN109653222A (en) Friction pile means of defence, anti-slide pile construction method and friction pile safeguard structure
CN203130109U (en) Large-section karst tunnel supporting equipment
CN205382507U (en) Two -way anchored retaining wall by tie rods
CN112377208A (en) Construction method for shallow-buried bias tunnel portal
CN107060837B (en) A kind of Shallow-buried asymmetry formula shield arch construction method
CN108914954A (en) Slope support method of the pre support in conjunction with permanent support
CN111441372A (en) Landslide foundation treatment embankment structure and construction method
CN106120822A (en) A kind of method for protecting support preventing mud stone from coming down and device
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN105821902B (en) The light-duty armored concrete Ecological Retaining Wall construction method of vertical lattice
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB03 Change of inventor or designer information

Inventor after: Ma Dong

Inventor after: Lin Shaojun

Inventor after: Yang Hongfei

Inventor after: Zhao Sheng

Inventor after: Liu Chunhui

Inventor after: Wang Chuanzong

Inventor after: Lv Zhijun

Inventor after: Lv Xiuhua

Inventor after: Wang Langfeng

Inventor after: Tan Chaoyang

Inventor after: He Xudong

Inventor after: Lei Baoke

Inventor before: Liu Chunhui

Inventor before: Wang Chuanzong

Inventor before: Tan Chaoyang

Inventor before: He Xudong

Inventor before: Lei Baoke

Inventor before: Lin Shaojun

Inventor before: Yang Hongfei

Inventor before: Zhao Sheng

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20170814

Address after: 064000 Hebei province Tangshan City Fengrun District Guanghua Road No. 2

Applicant after: China Railway Sixteen Bureau Group Fifth Engineering Company Limited

Applicant after: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Address before: 064000 Hebei province Tangshan City Fengrun District Guanghua Road No. 2

Applicant before: China Railway Sixteen Bureau Group Fifth Engineering Company Limited

TA01 Transfer of patent application right
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant