CN107201908B - Construction method for deep-buried central ditch of tunnel in severe cold region - Google Patents

Construction method for deep-buried central ditch of tunnel in severe cold region Download PDF

Info

Publication number
CN107201908B
CN107201908B CN201710318044.2A CN201710318044A CN107201908B CN 107201908 B CN107201908 B CN 107201908B CN 201710318044 A CN201710318044 A CN 201710318044A CN 107201908 B CN107201908 B CN 107201908B
Authority
CN
China
Prior art keywords
construction
inverted arch
deep
ditch
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710318044.2A
Other languages
Chinese (zh)
Other versions
CN107201908A (en
Inventor
张健
刘林
刘语
申剑
刘玉府
许锡甲
王志强
吴秀雄
朱东平
王九华
蒋志权
解振乙
王开荣
谭奔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201710318044.2A priority Critical patent/CN107201908B/en
Publication of CN107201908A publication Critical patent/CN107201908A/en
Application granted granted Critical
Publication of CN107201908B publication Critical patent/CN107201908B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The invention discloses a construction method of a deep buried central ditch of a tunnel in a severe cold region, which adopts a simple inverted arch trestle to carry out advanced construction on the deep buried central ditch before tunnel inverted arch construction, and then adopts a self-propelled inverted arch trestle to carry out construction on the inverted arch, and the specific construction steps are as follows: step one, adopting blank hole control blasting construction, vertical hole distribution deep hole blasting, layered blasting excavation and water ditch blastholes tilting outwards; step two, excavating the position of the ditch to a designed elevation by adopting a small excavator; step three, cleaning clear water ditch virtual slag and ponding; fourthly, constructing a base; burying and installing culvert pipes; step six, grading backfilling; step seven, pouring heat-preservation concrete; the method effectively solves the problems of difficult construction organization, low work efficiency, slow construction progress, high cost, large disturbance to surrounding rock and the like in the prior art, and achieves a good use effect.

Description

Construction method for deep-buried central ditch of tunnel in severe cold region
Technical Field
The invention relates to a construction method of a tunnel deep-buried central ditch in a severe cold region, in particular to a construction method of a tunnel deep-buried central ditch in a severe cold region in northeast.
Background
The tunnel in the severe cold region, the biggest depth of freezing of soil is about 2.0m, mainly considers the heat preservation requirement that prevents frostbite, has carried out the deep design to the central ditch, and construction team is for reducing the construction process in traditional construction, shortens cycle time, often excavates to the deep central ditch end from the inverted arch filling face once, because of once excavation degree of depth is too high, leads to the inverted arch to dig seriously excessively, and needs in time backfill just can carry out the face operation after the deep central ditch of burying of construction, great to tunnel construction progress influence, and transportation vehicle driving safety has certain risk. At present, a set of safe and simple construction method is not available for the construction of the deep-buried central ditch of the tunnel in the severe cold region.
Disclosure of Invention
The invention aims to solve the technical problems that: the construction method for the deep-buried central ditch in the severe cold region adopts the simple inverted arch trestle and the self-propelled inverted arch trestle to carry out parallel propelling construction, and effectively solves the problems of difficult construction organization, low work efficiency, slow construction progress, high cost, large disturbance to surrounding rocks and the like in the prior art.
The technical scheme of the invention is as follows: before tunnel inverted arch construction, a simple inverted arch trestle is adopted to carry out advanced construction on the deep buried central ditch, and then a self-propelled inverted arch trestle is adopted to carry out construction on the inverted arch, wherein the construction steps are as follows: step one, adopting blank hole control blasting construction, vertical hole distribution deep hole blasting, layered blasting excavation and water ditch blastholes tilting outwards; step two, excavating the position of the ditch to a designed elevation by adopting a small excavator; step three, cleaning clear water ditch virtual slag and ponding; fourthly, constructing a base; step five, burying and installing culvert pipes (prefabrication); step six, grading backfilling; step seven, pouring heat-preservation concrete; step eight, paving an insulation board; and step nine, adopting a simple inverted arch trestle and a self-propelled inverted arch trestle to carry out parallel propelling construction.
In the deep-buried central ditch construction, a self-propelled concrete pouring trestle and a deep-buried central ditch excavation trestle are adopted to separate the inverted arch and the deep-buried central ditch, the self-propelled concrete pouring trestle carries out framing flow operation on the inverted arch (24 m in total), and the deep-buried central ditch excavation trestle carries out advanced construction on the deep-buried central ditch.
In the first step, the specific explosive consumption is 0.6kg/m 3 Controlling the blasting area to be 4.4m 2 The excavation dosage is 11.56kg per 4m of cycle, the single-hole charge on two sides is 0.15kg, and the single-hole charge on two rows of holes in the middle is 1.2kg.
And step two, excavating and deslagging, namely excavating a ditch position to a designed elevation by adopting a small excavator, wherein the top surface position of the inner rail is.
Thirdly, water accumulation and slag deficiency of the clear water ditch are managed: and the high-power water pump is adopted to rapidly pump the accumulated water of the excavated groove, and the virtual slag is cleaned manually.
And step four, constructing a base: the tube seat is formed by casting C20 concrete.
Step five, burying and installing culvert pipes (prefabrication): after the tube seat is installed, M20 cement mortar is needed to fill the peripheral gaps, so that the tube seat is prevented from moving; the culvert pipe is wrapped by geotechnical cloth, the culvert pipe is adjusted to the central ditch by using lifting equipment, the staggered position of the tunnel structure is ensured to ensure the water pipes to be connected in sequence, the drainage pipes are connected by adopting a tongue-and-groove rigid joint mode, and the joint adopts a steel wire mesh cement mortar plastering joint.
Step six, grading backfilling: before the graded broken stone is constructed, the transverse water guide pipe is introduced into the central ditch, and the graded broken stone is backfilled and compacted.
Seventh, pouring heat-preservation concrete: and C20 heat-insulating concrete is poured at the top.
Step eight, paving an insulation board: and a polyurethane heat-insulating plate with the thickness of 5cm is applied between the top of the concrete and the primary support of the inverted arch, and the width of the heat-insulating plate is more than or equal to 2m.
Step nine, adopting simple inverted arch trestle and self-propelled inverted arch trestle to carry out parallel propelling construction: advanced construction is carried out on the deep buried central ditch by adopting a simple inverted arch trestle, and then construction is carried out on the inverted arch by adopting a self-propelled inverted arch trestle.
The method comprises the following steps: after the first ring deep buried central ditch construction is completed, a self-propelled concrete pouring trestle and a deep buried central ditch excavation trestle are adopted to separate the inverted arch and the deep buried central ditch into water for construction, the self-propelled concrete pouring trestle performs framing flow operation on the inverted arch (24 m in total), and the deep buried central ditch excavation trestle performs advanced construction on the deep buried central ditch (see figure 1).
Advantageous effects
Compared with the prior art, the invention has the following beneficial effects:
1) The dust concentration is effectively reduced by controlling the application of the blasting technology, the occupational health of operators is guaranteed, the ventilation and smoke discharge frequency is effectively reduced, and the resource consumption is indirectly reduced;
2) The application of the technology effectively shortens the blasting throwing distance and reduces the occurrence probability of blasting injury;
3) The movable inverted arch trestle belongs to a highly integrated industrial finished product, and compared with the traditional trestle, the stability and safety protection measures of the movable inverted arch trestle are greatly improved, so that the construction efficiency is effectively improved, and the construction cost is reduced;
4) The combined construction mode of the self-propelled inverted arch trestle (the effective length is 24 meters, the whole length is 43 m) and the simple inverted arch trestle is adopted, so that the traditional line production modes of deep-buried central ditch excavation supporting, inverted arch supporting and inverted arch concrete pouring are changed, the construction period is effectively shortened, the progress is improved, and the construction quality is ensured;
5) The invention ensures construction safety, improves construction quality, accelerates construction progress, reduces construction cost and achieves good field actual use effect.
Drawing and description
FIG. 1 is a longitudinal section view of a construction process of the present invention;
FIG. 2 is a construction process diagram of the present invention;
FIG. 3 is a schematic illustration of an excavation blast hole of the present invention;
FIG. 4 is a schematic illustration of excavated slag removal of the present invention;
FIG. 5 is a schematic illustration of culvert pipe laying and overlap joint according to the present invention;
FIG. 6 is a schematic view of a culvert pipe reserved hole and a drain hole according to the present invention;
FIG. 7 is a schematic view of the deep buried central drain structure of the present invention.
The marks in the figure are as follows: 1. a step is arranged; 2. descending a step; 3. deep-buried central ditch excavation trestle; 4. a ditch construction area; 5. a lane crossing turning area; 6. inverted arch ballasting area; 7. a front axle; 8. a front leg trolley area; 9. self-propelled concrete pouring trestle; 10. a reinforcing steel bar binding area; 11. a concrete pouring area; 12. a forming area, 13, an inner rail top; 14. inverted arch excavation of the I part; 15. inverted arch excavation part II; 16. inverted arch excavation of III-1, III-2 parts, 17 and C20 concrete bases; 18. geotextile; 19. Steel wire mesh cement mortar; 20 a water discharge hole; 21. grading crushed stone, 22 and C20 heat preservation concrete; 23. polyurethane insulation board.
Detailed Description
The specific embodiment of the invention comprises the following steps: the utility model provides a cold region tunnel buries central ditch deeply adopts nine steps (see fig. 2) (nine steps) to carry out the construction, excavates the working face to the inverted arch top before the construction, then adopts plain type inverted arch landing stage and self-propelled inverted arch landing stage to buries central ditch deeply and inverted arch framing operation (see fig. 1), specifically includes the following steps:
step one, excavating and blasting: the hole controlled blasting construction (see figure 3) is adopted, the vertical hole-distribution deep hole blasting, the layered blasting excavation and the ditch hole blasting are all inclined outwards of the hole, and the specific explosive consumption is 0.6kg/m 3 Controlling the blasting area to be 4.4m 2 . The excavation dosage is 11.56kg for each cycle of 4 m. 0.15kg of single-hole charge on two sides and 1.2kg of single-hole charge on two rows of holes in the middle.
Step two, deslagging: first the site 14 is excavated, then the site 15 is excavated with a mini-excavator, and finally the sites 16-1, 16-2 (see fig. 4) are excavated. And (5) excavating a deep buried central ditch, wherein the excavation depth of the ditch is 435cm from the filling surface of the inverted arch. And after the ballast discharging is completed, retesting the excavation depth and width by adopting a total station, and if the underexcavation exists, timely processing.
Step three, water accumulation and virtual slag removal of a clear water ditch: the water in the excavated groove is pumped out quickly by adopting a high-power water pump; and cleaning the virtual slag manually.
And fourthly, constructing a concrete base: the pipe seat adopts C20 concrete pouring (17), can be prefabricated outside the hole in advance, and the peripheral gap is filled with M20 cement mortar after the pipe seat is installed, so that the pipe seat is prevented from moving.
Step five, burying and installing culvert pipes (prefabrication): the culvert pipe is wrapped by geotechnical cloth (18), the culvert pipe is adjusted to the central ditch by using hoisting equipment, the water pipe is ensured to be connected in sequence at the staggered position of the tunnel structure, and the gradient of the water pipe is not less than that of the tunnel longitudinal slope. When the longitudinal slope of the line is less than 3 per mill, the drainage slope of the deep buried central ditch is adjusted to 3 per mill. The drainage pipes are connected in a tongue-and-groove rigid joint mode, and the joint adopts a steel wire mesh cement mortar (19) plastering joint (see figure 5).
Step six, grading backfilling: before construction, the graded broken stone (21) is firstly introduced into a deep buried central ditch water discharge hole (20), the deep length is not less than 3cm, then the graded broken stone is backfilled to a position 25cm above the top of the pipe by adopting aggregate with good permeability, difficult efflorescence and good grading, the diameter is between 2.5 and 5.0cm, and the graded broken stone is backfilled tightly.
Step seven, pouring heat-preservation concrete: and pouring C20 heat-insulating concrete (22) at the top after grading macadam construction is completed and leveling is carried out.
Step eight, paving an insulation board: a polyurethane insulation board (23) with the thickness of 5cm and the breadth of 2m is applied between the top of the concrete and the initial support of the inverted arch.
Step nine, adopting a simple inverted arch trestle (3) +a self-propelled inverted arch trestle (9) for parallel propelling construction: advanced construction is carried out on the deep buried central ditch by adopting a simple inverted arch trestle, and then construction is carried out on the inverted arch by adopting a self-propelled inverted arch trestle.
The method comprises the following steps: after the first ring deep buried central ditch construction is completed, a self-propelled concrete pouring trestle and a deep buried central ditch excavation trestle are adopted to separate the inverted arch and the deep buried central ditch into water for construction, the self-propelled concrete pouring trestle performs framing flow operation on the inverted arch (24 m in total), and the deep buried central ditch excavation trestle performs advanced construction on the deep buried central ditch (see figure 1).

Claims (8)

1. A construction method for a deep-buried central ditch of a tunnel in a severe cold region is characterized by comprising the following steps: before tunnel inverted arch construction, advanced construction is carried out on a deep buried central ditch by adopting a simple inverted arch trestle, then construction is carried out on the inverted arch by adopting a self-propelled inverted arch trestle, and the specific construction steps are as follows: step one, adopting blank hole control blasting construction, vertical hole distribution deep hole blasting, layered blasting excavation and water ditch blastholes tilting outwards; step two, excavating the position of the ditch to a designed elevation by adopting a small excavator; step three, cleaning clear water ditch virtual slag and ponding; fourthly, constructing a base; burying and installing culvert pipes; step six, grading backfilling; step seven, pouring heat-preservation concrete; step eight, paving an insulation board; and step nine, adopting a simple inverted arch trestle and a self-propelled inverted arch trestle to carry out parallel propelling construction, adopting the simple inverted arch trestle to carry out advanced construction on the deep buried central ditch, and then adopting the self-propelled inverted arch trestle to carry out construction on the inverted arch.
2. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: in the construction method of the deep-buried central ditch, a self-propelled inverted arch trestle and a simple inverted arch trestle are adopted to separate the inverted arch and the deep-buried central ditch for flow construction, the self-propelled inverted arch trestle carries out framing flow production on the inverted arch, and the simple inverted arch trestle carries out advanced construction on the deep-buried central ditch.
3. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: in the first step, the specific explosive consumption is controlled according to 0.6kg/m < 3 >, the blasting area is 4.4m < 2 >, the excavation dosage is 11.56kg for every cycle of 4m, the single-hole charges on two sides are 0.15kg, and the single-hole charges in two rows in the middle are 1.2kg.
4. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: thirdly, water accumulation and slag deficiency of the clear water ditch are managed: and the high-power water pump is adopted to rapidly pump the accumulated water of the excavated groove, and the virtual slag is cleaned manually.
5. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: step five, burying and installing culvert pipes: after the tube seat is installed, M20 cement mortar is needed to fill the peripheral gaps, so that the tube seat is prevented from moving; the culvert pipe is wrapped by geotechnical cloth (18), the culvert pipe is adjusted to the central ditch by using hoisting equipment, the staggered position of the tunnel structure ensures that water pipes are connected in sequence, a tongue-and-groove rigid joint form is adopted between the drain pipes, and a steel wire mesh cement mortar (19) plastering joint is adopted.
6. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: step six, grading backfilling: before the graded broken stone construction, the transverse water guide pipe is introduced into the central ditch water discharge hole (20), and the graded broken stone (21) is backfilled and compacted.
7. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: seventh, pouring heat-preservation concrete: and C20 heat-insulating concrete (22) is poured at the top.
8. The construction method of the tunnel deep-buried central ditch in the severe cold region according to claim 1, wherein the construction method comprises the following steps: step eight, paving an insulation board: and a polyurethane heat-insulating plate (23) with the thickness of 5cm is applied between the top of the concrete and the initial support of the inverted arch, and the width of the heat-insulating plate is more than or equal to 2m.
CN201710318044.2A 2017-06-16 2017-06-16 Construction method for deep-buried central ditch of tunnel in severe cold region Active CN107201908B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710318044.2A CN107201908B (en) 2017-06-16 2017-06-16 Construction method for deep-buried central ditch of tunnel in severe cold region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710318044.2A CN107201908B (en) 2017-06-16 2017-06-16 Construction method for deep-buried central ditch of tunnel in severe cold region

Publications (2)

Publication Number Publication Date
CN107201908A CN107201908A (en) 2017-09-26
CN107201908B true CN107201908B (en) 2023-10-31

Family

ID=59906141

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710318044.2A Active CN107201908B (en) 2017-06-16 2017-06-16 Construction method for deep-buried central ditch of tunnel in severe cold region

Country Status (1)

Country Link
CN (1) CN107201908B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107630706B (en) * 2017-10-24 2023-05-26 中交第二航务工程局有限公司 Tunnel bottom structure for eliminating tunnel inverted arch bulge in high-earth-pressure area and construction method
CN107725073B (en) * 2017-11-06 2024-04-02 中建八局第一建设有限公司 Tunnel construction method based on simple trestle
CN108005673A (en) * 2017-12-05 2018-05-08 中国铁路设计集团有限公司 A kind of buried Central drain excavation method in tunnel of reserved foundation back-pressure soil
CN108343446A (en) * 2018-03-07 2018-07-31 中铁十六局集团第工程有限公司 A kind of tunnel Deeply buried ditch construction self-propelled lifting combination trestle
CN108457659B (en) * 2018-03-20 2019-04-30 中铁七局集团郑州工程有限公司 Railway single method for tunnel construction of the extremely frigid zones with center Deeply buried ditch
CN108343468A (en) * 2018-04-24 2018-07-31 中铁二院工程集团有限责任公司 Tunnel Engineering crosses underground river transverse direction temporary drainage construction
CN110528545B (en) * 2018-05-24 2021-03-26 中铁二院工程集团有限责任公司 Construction method of foundation deep-buried drainage blind ditch
CN109441489B (en) * 2018-12-29 2024-04-05 中国铁路设计集团有限公司 Tunnel deep-buried central ditch supporting structure and supporting construction method
CN114001608A (en) * 2021-10-20 2022-02-01 中铁三局集团第二工程有限公司 Central ditch blasting excavation method for tunnel without inverted arch

Citations (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027252A (en) * 2002-11-22 2004-04-01 (주)현이앤씨 Construction and design method about center wall of three arch tunnel excavation method
JP2006336259A (en) * 2005-05-31 2006-12-14 Ohbayashi Corp Tunnel invert construction method and movable pier
CN101215970A (en) * 2008-01-02 2008-07-09 中铁五局(集团)有限公司 Tunnel invert operation trolley
CN101225749A (en) * 2008-02-01 2008-07-23 中铁十七局集团第四工程有限公司 Method for supplying water with high voltage in cold area long and large tunnel
JP2008180014A (en) * 2007-01-25 2008-08-07 Tsuchiyagumi:Kk Tunnel construction method
CN101251014A (en) * 2008-04-14 2008-08-27 中铁隧道集团有限公司 Method for wholly mining tunnel invert foundation separating segment and placing concrete as well as inverted arch trestle device
CN201695321U (en) * 2010-06-25 2011-01-05 中铁五局集团第一工程有限责任公司 Multifunctional propelled tunnel inverted arch trestle
CN101967985A (en) * 2010-09-08 2011-02-09 中铁隧道集团三处有限公司 Self-propelled inverted arch template construction method
CN102146796A (en) * 2011-03-10 2011-08-10 中铁二局股份有限公司 Construction technology for inverted arch of two-track tunnel of high-speed railway
JP2011179173A (en) * 2010-02-26 2011-09-15 Kfc Ltd Waterway structure of tunnel and tunnel structure
CN102230383A (en) * 2011-06-14 2011-11-02 中交隧道工程局有限公司 All-hydraulic tunnel inverted arch trestle-type moving die frame
CN202132052U (en) * 2011-06-14 2012-02-01 中交隧道工程局有限公司 Fully-hydraulic tunnel inverted arch trestle-type mobile mold frame
CN102661171A (en) * 2012-05-02 2012-09-12 中铁十一局集团第五工程有限公司 Frost damage prevention drainage system for tunnel
CN202690131U (en) * 2012-05-28 2013-01-23 中交第一公路勘察设计研究院有限公司 Tunnel water discharging system penetrating through long-lasting frozen soil areas and non-frozen soil areas
CN103032096A (en) * 2012-12-13 2013-04-10 中铁四局集团第二工程有限公司 Cold-proof construction method of tunnel central ditch of severe cold area
CN203066990U (en) * 2013-02-05 2013-07-17 重庆铁科轨道交通工程有限公司 Fully-hydraulic and self-walking inverted arch formworking trolley for tunnel
CN103306683A (en) * 2013-06-18 2013-09-18 中铁隧道集团有限公司 Construction method for comprehensive precipitation in hole in deep-buried tunnel excavation process
CN204402511U (en) * 2014-12-31 2015-06-17 中国建筑第五工程局有限公司 Inverted arch trestle
CN104775831A (en) * 2015-02-09 2015-07-15 中交二公局第三工程有限公司 Tunnel secondary lining inverted arch and arch wall combined part short-free side wall arcing construction method
CN104930937A (en) * 2015-02-15 2015-09-23 中国铁建大桥工程局集团有限公司 Circular divided blasting tunnel construction method capable of effectively controlling blasting vibration velocity
CN204960952U (en) * 2015-08-19 2016-01-13 铁道第三勘察设计院集团有限公司 Tunnel structure with hoop heat preservation rubble french drain
CN205025498U (en) * 2015-08-21 2016-02-10 中铁第一勘察设计院集团有限公司 Han qu tunnel drainage system
CN105673074A (en) * 2016-01-19 2016-06-15 铁道第三勘察设计院集团有限公司 Tunnel base local deep-buried drainage ditch structure
CN205349419U (en) * 2016-01-19 2016-06-29 铁道第三勘察设计院集团有限公司 Escape canal structure is buried deeply to tunnel basement part
CN205955749U (en) * 2016-08-03 2017-02-15 西南交通大学 Tunnel invert construction equipment
CN106523028A (en) * 2017-01-05 2017-03-22 中铁工程设计咨询集团有限公司 Tunnel center drainage pipe and laying method thereof
CN106593469A (en) * 2016-12-02 2017-04-26 中铁五局集团第工程有限责任公司 Trolley for construction of inverted arch
CN106761916A (en) * 2016-12-12 2017-05-31 中铁十九局集团第二工程有限公司 Constructing tunnel water discharge method

Patent Citations (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027252A (en) * 2002-11-22 2004-04-01 (주)현이앤씨 Construction and design method about center wall of three arch tunnel excavation method
JP2006336259A (en) * 2005-05-31 2006-12-14 Ohbayashi Corp Tunnel invert construction method and movable pier
JP2008180014A (en) * 2007-01-25 2008-08-07 Tsuchiyagumi:Kk Tunnel construction method
CN101215970A (en) * 2008-01-02 2008-07-09 中铁五局(集团)有限公司 Tunnel invert operation trolley
CN101225749A (en) * 2008-02-01 2008-07-23 中铁十七局集团第四工程有限公司 Method for supplying water with high voltage in cold area long and large tunnel
CN101251014A (en) * 2008-04-14 2008-08-27 中铁隧道集团有限公司 Method for wholly mining tunnel invert foundation separating segment and placing concrete as well as inverted arch trestle device
JP2011179173A (en) * 2010-02-26 2011-09-15 Kfc Ltd Waterway structure of tunnel and tunnel structure
CN201695321U (en) * 2010-06-25 2011-01-05 中铁五局集团第一工程有限责任公司 Multifunctional propelled tunnel inverted arch trestle
CN101967985A (en) * 2010-09-08 2011-02-09 中铁隧道集团三处有限公司 Self-propelled inverted arch template construction method
CN102146796A (en) * 2011-03-10 2011-08-10 中铁二局股份有限公司 Construction technology for inverted arch of two-track tunnel of high-speed railway
CN102230383A (en) * 2011-06-14 2011-11-02 中交隧道工程局有限公司 All-hydraulic tunnel inverted arch trestle-type moving die frame
CN202132052U (en) * 2011-06-14 2012-02-01 中交隧道工程局有限公司 Fully-hydraulic tunnel inverted arch trestle-type mobile mold frame
CN102661171A (en) * 2012-05-02 2012-09-12 中铁十一局集团第五工程有限公司 Frost damage prevention drainage system for tunnel
CN202690131U (en) * 2012-05-28 2013-01-23 中交第一公路勘察设计研究院有限公司 Tunnel water discharging system penetrating through long-lasting frozen soil areas and non-frozen soil areas
CN103032096A (en) * 2012-12-13 2013-04-10 中铁四局集团第二工程有限公司 Cold-proof construction method of tunnel central ditch of severe cold area
CN203066990U (en) * 2013-02-05 2013-07-17 重庆铁科轨道交通工程有限公司 Fully-hydraulic and self-walking inverted arch formworking trolley for tunnel
CN103306683A (en) * 2013-06-18 2013-09-18 中铁隧道集团有限公司 Construction method for comprehensive precipitation in hole in deep-buried tunnel excavation process
CN204402511U (en) * 2014-12-31 2015-06-17 中国建筑第五工程局有限公司 Inverted arch trestle
CN104775831A (en) * 2015-02-09 2015-07-15 中交二公局第三工程有限公司 Tunnel secondary lining inverted arch and arch wall combined part short-free side wall arcing construction method
CN104930937A (en) * 2015-02-15 2015-09-23 中国铁建大桥工程局集团有限公司 Circular divided blasting tunnel construction method capable of effectively controlling blasting vibration velocity
CN204960952U (en) * 2015-08-19 2016-01-13 铁道第三勘察设计院集团有限公司 Tunnel structure with hoop heat preservation rubble french drain
CN205025498U (en) * 2015-08-21 2016-02-10 中铁第一勘察设计院集团有限公司 Han qu tunnel drainage system
CN105673074A (en) * 2016-01-19 2016-06-15 铁道第三勘察设计院集团有限公司 Tunnel base local deep-buried drainage ditch structure
CN205349419U (en) * 2016-01-19 2016-06-29 铁道第三勘察设计院集团有限公司 Escape canal structure is buried deeply to tunnel basement part
CN205955749U (en) * 2016-08-03 2017-02-15 西南交通大学 Tunnel invert construction equipment
CN106593469A (en) * 2016-12-02 2017-04-26 中铁五局集团第工程有限责任公司 Trolley for construction of inverted arch
CN106761916A (en) * 2016-12-12 2017-05-31 中铁十九局集团第二工程有限公司 Constructing tunnel water discharge method
CN106523028A (en) * 2017-01-05 2017-03-22 中铁工程设计咨询集团有限公司 Tunnel center drainage pipe and laying method thereof

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
严寒地区隧道深埋中心水沟施工技术;曹建;邓世超;;建筑与预算(第04期);60-62 *
客运专线铁路长大隧道仰拱衬砌采用简易栈桥施工技术及经济分析;周廷浩;铁道标准设计(第4期);82-85 *
曹建 ; 邓世超 ; .严寒地区隧道深埋中心水沟施工技术.建筑与预算.2016,(第04期),60-62. *
王养锋 ; .高严寒高海拔公路隧道深埋中心水沟施工技术.青海交通科技.2017,(第01期),113-117. *
高严寒高海拔公路隧道深埋中心水沟施工技术;王养锋;;青海交通科技(第01期);117-121 *
高速铁路寒区隧道深埋中心水沟设置与施工技术研究;赵晓青;建筑知识;第37卷(第4期);113-114 *

Also Published As

Publication number Publication date
CN107201908A (en) 2017-09-26

Similar Documents

Publication Publication Date Title
CN107201908B (en) Construction method for deep-buried central ditch of tunnel in severe cold region
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN101864960B (en) Carst region double-arch road tunnel construction method
KR101022382B1 (en) Precast horizontality tubular roof and tunnel construction method using the same
CN106499413A (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN107905799B (en) Reinforced structure of high-speed rail tunnel bottom water passing karst cave and construction method thereof
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN110656959B (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN111577334B (en) Operating tunnel inverted arch repairing method
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN110847929B (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN110700860B (en) Construction method of soil-stone boundary tunnel crossing loess valley
CN110985003B (en) Tunnel construction method for penetrating through earth-rock boundary stratum
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN101538832B (en) Construction method for controlling two-dimension jacking of large-scale case
CN110821500B (en) Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum
CN110905529B (en) Construction method of loess tunnel penetrating through landslide mass
CN110821512B (en) Loess tunnel entrance opening section pre-reinforcing and excavating construction method passing through landslide body
CN110761795B (en) Construction method of shallow tunnel in loess gully
CN110529120B (en) Construction method for removing invasion limiting structure by chiseling VI-level surrounding rock shallow-buried underground excavation loess tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant