CN107012875A - Basement supporting - Google Patents

Basement supporting Download PDF

Info

Publication number
CN107012875A
CN107012875A CN201710354673.0A CN201710354673A CN107012875A CN 107012875 A CN107012875 A CN 107012875A CN 201710354673 A CN201710354673 A CN 201710354673A CN 107012875 A CN107012875 A CN 107012875A
Authority
CN
China
Prior art keywords
waist rail
basement
billet
steel
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710354673.0A
Other languages
Chinese (zh)
Other versions
CN107012875B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dezhou Shuanghang Packaging Products Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710354673.0A priority Critical patent/CN107012875B/en
Publication of CN107012875A publication Critical patent/CN107012875A/en
Application granted granted Critical
Publication of CN107012875B publication Critical patent/CN107012875B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0021Mortar

Abstract

The invention discloses a kind of basement supporting, it is characterized in that the first operating mode basement supporting construction is using as follows:Support pile uses cast-in-situ bored pile, water-stop curtain uses three axle cement mixing piles, direction top sets first of steel waist rail on the inside of support pile, prestressed cable anchorage is in first of steel waist rail, the reinforcing sector width of basement passive area is 1m scopes within the tangent line of support pile outward flange, and stabilization zone depth is 1.5m~2m below basement substrate;First time bracing members are set between first of steel waist rail and billet;Second operating mode basement supporting construction is using as follows:Second steel waist rail is set on the inside of support pile in the middle part of direction, second prestressed cable anchorage is in second steel waist rail, billet is set above engineering pile, second of bracing members is set between billet and first of steel waist rail, second of bracing members is set between billet and second steel waist rail.

Description

Basement supporting
Technical field
The present invention relates to a kind of basement supporting, more particularly to the basement supporting without concrete to support.
Background technology
Traditional basement support technology is basement supporting there is provided concrete maintains basement supporting stable to supportting, but It is that concrete can greatly increase basement support cost to support, very big influence also is caused to earthwork outward transport in addition, so as to be delayed Construction period.If by the safe and orderly adjustment of stress in basement Bracing Process, transfer and reallocated, make basement Supporting obviously can obtain significant economic benefit and duration benefit in the case of without inner support.But how in basement branch No concrete is avoided in shield work progress to problem that safety problem in the case of support is that engineering staff faces.
The content of the invention
The present invention is to provide a kind of basement supporting, solves problem of the prior art.
Therefore, the present invention takes certain technical measures plays the inner supporting structure body that temporary support is acted on progressively to replace System, so as to ensure after provisional bracing demolition, engineering construction can continue safely and conveniently to carry out.The present invention is applied to excavate deeply Spend for the basement of 3.5~5m depth.
First operating mode basement supporting construction is using as follows:
Support pile uses cast-in-situ bored pile, a diameter of 600~900mm of cast-in-situ bored pile.From support pile central point outside Water-stop curtain is set to 1.5~2m, and water-stop curtain uses three axle cement mixing piles, and three axle cement mixing pile stake footpaths are 600mm Or 500mm, adjacent three axles cement mixing pile is mutually twisted, and occlusion distance is 200mm or 150mm.Direction on the inside of support pile Top sets first of steel waist rail, first of steel waist rail top mark high, first steel waist rail and supporting identical with support pile top mark height The embedded bar of stake is welded to connect, and prestressed cable anchorage is in first of steel waist rail, and 1.5~2.5m of digging depth positions are in engineering The engineering pile that stake is placed above below billet, billet has 2~4.Billet thickness is 10~12cm, and billet is set Position is fluted in the middle of billet from 13~15m of basement edge, and recessed poor depth is 8~12mm, and length and width is 10~ 15cm, the reinforcing sector width of basement passive area is 1m scopes within the tangent line of support pile outward flange, and stabilization zone depth is basement 1.5m~2m below substrate.First time bracing members are set between first of steel waist rail and billet.
Second operating mode basement supporting construction is using as follows:
Second steel waist rail is set on the inside of support pile in the middle part of direction, and second steel waist bottom elevation is first time earth excavation The embedded bar of depth, second steel waist rail and support pile is welded to connect, and second prestressed cable anchorage is in second steel waist Beam, engineering pile is cut in second of earth excavation, engineering pile top mark height, engineering identical with basement bottom board substrate absolute altitude Stake sets billet above, and second of bracing members, billet and second steel waist are set between billet and first of steel waist rail Second of bracing members is set between beam.
Construction procedure includes:
(1), construction work stake.Set construction elevation and second waist rail elevation of top at the top of the engineering pile of billet neat Flat, Other Engineering stake top portion construction elevation is 10cm below the absolute altitude of basement bottom board bottom.
(2), construction supporting stake.
(3), construction water-stop curtain.
(4) basement passive area, is reinforced.
Basement passive area, which is reinforced, uses churning concrete stake.
(5), first of steel waist rail of construction and prestress anchorage cable.
The embedded bar of first of steel waist rail and support pile is welded.
Steel waist rail presses continuous beam calculating.During the moment of flexure design value of waist rail, anchor cable pulling force takes the base calculated during structural analysis This combined effect is used as fulcrum axial-load effect value.
Steel waist rail is from single channel-section steel or double flute steel or double I-steel, when from double flute steel or double I-steel, steel wale Entirety should be welded as, is welded to connect and uses fillet weld, weld bead height is no less than 8mm.
The construction of first steel waist rail is constructed prestress anchorage cable after finishing.
Prestress anchorage cable technical parameter is using as follows:When anchor rope grouting uses cement mortar, the ratio of mud preferably takes 0.45~ 0.50;During using cement mortar, the ratio of mud preferably takes 0.40~0.45, and cement-sand ratio preferably takes 0.5~1.0, and mix is preferably selected with sand Medium-fine sand, clay content must not exceed the 3% of sand weight.3%.During using secondary pressure grouting process, secondary pressure slip casting is preferably adopted With the cement mortar of the ratio of mud 0.50~0.55, secondary grouting pipe answers lashing on the body of rod, and the end grout outlet of Grouting Pipe should Taking prevents that slurries are into the seal approach of Grouting Pipe before slip casting, and during secondary pressure slip casting, grouting pressure is not preferably less than 1.5MPa; When being segmented secondary grouting technique using anchoring section, slip casting is carried out preferably after the intensity of hole body grouting soil reaches 5MPa, splitting The slurry outlet of Grouting Pipe should be set along anchor rod anchored section of total length, grouting sequence should since anchor pole end, be segmented from inside to outside according to It is secondary to carry out.
Anchor cable construction is using as follows:
1) after the intensity of injecting cement paste reaches the 75% of design strength and not less than 15MPa, the tensioning of anchor cable can be carried out Locking.
2) using the method for the overall tensioning fixation of steel strand wires.
3) anchorage cable stretching should be loaded gently, and loading classification is not preferably greater than 0.3, and the interval time of every grade of load is not less than 3min;Before anchor cable locking, stable a period of time should be kept under maximum stretching force, to sandy soil stratum, stabilization time should be greater than 5min~10min, to cohesive soil stratum, stabilization time should be greater than 15min.
4) anchor cable rope timing, (1.1~1.15) times of the desirable design tensioning lock definite value of tensioning value.
5) in the 48h after anchor cable locking, when anchor cable pulling force is less than design lock value 90%, it should be locked again; Anchor cable locking is still considered as loss of prestress caused by adjacent anchorage cable stretching locking, when anchor cable pulling force is less than design lock value When 90%, it should be locked again.
6) anchor cable outer end preferably uses cold cut segmentation method to cut off after locking;Steel strand wires after being cut outside anchorage retain length not 50mm is should be less than, during using thermal cutting, no less than 80mm.
(6), at the top of local excavation's basement periphery soil to second steel waist rail.
(7), first time bracing members are set.
Billet is placed above after being flattened at the top of engineering pile, first time bracing members withstand on billet groove by bracing members branch Interior blending bolt is fixed.
Because bracing members spacing is most important to basement excavation safety.Using simulation analysis of computer, according to basement Maximum soil deep soil movement is as datum mark at the 0.5m of outside, and maximum soil deep soil movement control is 2mm.First time bracing members set deep Spend for 1.5~2.5m of digging depth positions.Table 1 is first time bracing members spacing and depth relationship, according to simulation analysis of computer As a result, first time bracing members set spacing to be 1.35~3.75m.
Table 1 first time bracing members spacing and depth relationship
(8) soil in the middle of basement, is excavated.
(9), local excavation to basement periphery is native to basement substrate.
(10), second of bracing members are set
Second of bracing members sets two roads.The bracing members of second steel waist rail, the bracing members of first of steel waist rail are first set It is configured again in the case of first first time bracing members of dismantling, method to set up is to set second at once after removing first time bracing members Secondary bracing members.
Second of bracing members sets depth to be 2~3m of digging depth positions.Table 2 is that second of bracing members spacing is closed with depth System, according to simulation analysis of computer result, second of bracing members sets spacing to be 1.70~3.83m.
Second of the bracing members spacing of table 2 and depth relationship
(11) soil in the middle of basement, is excavated.
(12), pour and smash basement bottom board and concrete side walls.Concrete side walls set pre-buried with bracing members junction position Hole.Embedded water stop rubber strip blocks infiltration path in the middle part of the basement bottom board of billet position.
(13), support replacement is set.
Dead slot clogs macadam-aggregate mix between concrete side walls and support pile.Macadam-aggregate mix be packed in concrete side walls with Purpose is to make to be converted to the load of bracing members into the evenly load for acting on support pile in dead slot between support pile, for lower step Bracing members are removed to be ready.
Reasonable macadam-aggregate mix level, which is matched somebody with somebody, can both avoid lacking aerial construction formed by sand packing process between particle after compacting, Ensure that between emery dust particulate has enough bulky grains to form skeleton, meets intensity requirement.
Macadam-aggregate mix use rubble, sand grains, powder compound, ballast grain sizes be 15~2mm, quality volume be 30%~ 40%;Sand grains particle diameter is 2~0.1mm, and quality volume is 40%~50%;Powder particle diameter is less than 0.1mm, and quality volume is 20% ~30%.
(14) bracing members and billet, are removed.
(15) basement roof concrete, is poured.
(16), close that bracing members are pre-buried and billet position underplate concrete with water-proof concrete.
Construction cost of the present invention is low, and the construction period is short.
Brief description of the drawings
Fig. 1 is the first operating mode basement supporting schematic diagram, and Fig. 2 is the second operating mode basement supporting schematic diagram.
In each accompanying drawing:1st, support pile, 2, first of steel waist rail, 3, prestress anchorage cable, 4, water-stop curtain, 5, basement it is passive Area, 6, first of bracing members, 7, billet, 8, engineering pile, 9, second steel waist rail, 10, second of bracing members.
Embodiment
Embodiment one
First operating mode basement supporting construction is using as follows:
Support pile 1 uses cast-in-situ bored pile, a diameter of 600~900mm of cast-in-situ bored pile.From on the outside of the central point of support pile 1 Water-stop curtain 4 is set at 1.5~2m of direction, and water-stop curtain 4 uses three axle cement mixing piles, and three axle cement mixing pile stake footpaths are 600mm or 500mm, adjacent three axles cement mixing pile is mutually twisted, and occlusion distance is 200mm or 150mm.In support pile 1 Side sets first of steel waist rail 2, high, the first steel waist identical with the top mark height of support pile 1 of first of top mark of steel waist rail 2 to top The embedded bar of beam 2 and support pile 1 is welded to connect, and prestress anchorage cable 3 is anchored at first of steel waist rail 2, and digging depth 1.5~ 2.5m positions have 2~4 in the engineering pile 8 that engineering pile 8 is placed above below billet 7, billet 7.The thickness of billet 7 is 10~12cm, the set location of billet 7 is fluted in the middle of billet 7 from 13~15m of basement edge, and recessed poor depth is 8~ 12mm, length and width is 10~15cm, and the reinforcing sector width of basement passive area 5 is 1m within the outward flange tangent line of support pile 1 Scope, stabilization zone depth is 1.5m~2m below basement substrate.Set for the first time between first of steel waist rail 2 and billet 7 Bracing members 6.
Second operating mode basement supporting construction is using as follows:
Second steel waist rail 9 is set in the middle part of the inner side direction of support pile 1, and the bottom absolute altitude of second steel waist rail 9 is the first time earthwork Cutting depth, the embedded bar of second steel waist rail 9 and support pile 1 is welded to connect, and second prestress anchorage cable 3 is anchored at second Road steel waist rail 9, engineering pile 8 is cut in second of earth excavation, the top mark of engineering pile 8 height and basement bottom board substrate absolute altitude Identical, engineering pile 8 sets billet 7 above, and second of bracing members 10, steel pad are set between billet 7 and first of steel waist rail 2 Second of bracing members 10 is set between plate 7 and second steel waist rail 9.
Construction procedure includes:
(1), construction work stake 8.The top construction elevation of engineering pile 8 of billet 7 is set with being marked at the top of second waist rail Height is flushed, and Other Engineering 8 top construction elevations of stake are 10cm below the absolute altitude of basement bottom board bottom.
(2), construction supporting stake 1.
(3), construction water-stop curtain 4.
(4) basement passive area 5, is reinforced.
Basement passive area 5, which is reinforced, uses churning concrete stake.
(5), first of steel waist rail 2 of construction and prestress anchorage cable 3.
The embedded bar of first of steel waist rail 2 and support pile 1 is welded.
Steel waist rail presses continuous beam calculating.During the moment of flexure design value of waist rail, anchor cable pulling force takes the base calculated during structural analysis This combined effect is used as fulcrum axial-load effect value.
Steel waist rail is from single channel-section steel or double flute steel or double I-steel, when from double flute steel or double I-steel, steel wale Entirety should be welded as, is welded to connect and uses fillet weld, weld bead height is no less than 8mm.
Construction prestress anchorage cable 3 after first of construction of steel waist rail 2 is finished.
The technical parameter of prestress anchorage cable 3 is using as follows:When anchor rope grouting uses cement mortar, the ratio of mud preferably takes 0.45~ 0.50;During using cement mortar, the ratio of mud preferably takes 0.40~0.45, and cement-sand ratio preferably takes 0.5~1.0, and mix is preferably selected with sand Medium-fine sand, clay content must not exceed the 3% of sand weight.3%.During using secondary pressure grouting process, secondary pressure slip casting is preferably adopted With the cement mortar of the ratio of mud 0.50~0.55, secondary grouting pipe answers lashing on the body of rod, and the end grout outlet of Grouting Pipe should Taking prevents that slurries are into the seal approach of Grouting Pipe before slip casting, and during secondary pressure slip casting, grouting pressure is not preferably less than 1.5MPa; When being segmented secondary grouting technique using anchoring section, slip casting is carried out preferably after the intensity of hole body grouting soil reaches 5MPa, splitting The slurry outlet of Grouting Pipe should be set along anchor rod anchored section of total length, grouting sequence should since anchor pole end, be segmented from inside to outside according to It is secondary to carry out.
Anchor cable construction is using as follows:
1) after the intensity of injecting cement paste reaches the 75% of design strength and not less than 15MPa, the tensioning of anchor cable can be carried out Locking.
2) using the method for the overall tensioning fixation of steel strand wires.
3) anchorage cable stretching should be loaded gently, and loading classification is not preferably greater than 0.3, and the interval time of every grade of load is not less than 3min;Before anchor cable locking, stable a period of time should be kept under maximum stretching force, to sandy soil stratum, stabilization time should be greater than 5min~10min, to cohesive soil stratum, stabilization time should be greater than 15min.
4) anchor cable rope timing, (1.1~1.15) times of the desirable design tensioning lock definite value of tensioning value.
5) in the 48h after anchor cable locking, when anchor cable pulling force is less than design lock value 90%, it should be locked again; Anchor cable locking is still considered as loss of prestress caused by adjacent anchorage cable stretching locking, when anchor cable pulling force is less than design lock value When 90%, it should be locked again.
6) anchor cable outer end preferably uses cold cut segmentation method to cut off after locking;Steel strand wires after being cut outside anchorage retain length not 50mm is should be less than, during using thermal cutting, no less than 80mm.
(6), at the top of local excavation's basement periphery soil to second steel waist rail 9.
(7), first time bracing members are set.
Billet 7 is placed above after flattening in the top of engineering pile 8, and first time bracing members withstand on billet 7 by bracing members branch Blending bolt is fixed in groove.
First time bracing members set depth to be 1.5~2.5m of digging depth positions, and first time bracing members setting spacing is 1.35~3.75m.
(8) soil in the middle of basement, is excavated.
(9), local excavation to basement periphery is native to basement substrate.
(10), second of bracing members 10 are set
Second of bracing members 10 sets two roads.The bracing members of second steel waist rail 9, the steel of first of steel waist rail 2 are first set It is configured again in the case of the first first time bracing members of dismantling of support, method to set up is set at once after removing first time bracing members Second of bracing members 10.
Second of bracing members 10 sets depth to be 2~3m of digging depth positions, and second of the setting of bracing members 10 spacing is 1.70~3.83m.
(11) soil in the middle of basement, is excavated.
(12), pour and smash basement bottom board and concrete side walls.Concrete side walls set pre-buried with bracing members junction position Hole.Embedded water stop rubber strip blocks infiltration path in the middle part of the position basement bottom board of billet 7.
(13), support replacement is set.
Dead slot clogs macadam-aggregate mix between concrete side walls and support pile 1.Macadam-aggregate mix is packed in concrete side walls Purpose is to make to be converted to the load of bracing members into the evenly load for acting on support pile 1 in dead slot between support pile 1, is Lower step is removed bracing members and is ready.
Macadam-aggregate mix use rubble, sand grains, powder compound, ballast grain sizes be 15~2mm, quality volume be 30%~ 40%;Sand grains particle diameter is 2~0.1mm, and quality volume is 40%~50%;Powder particle diameter is less than 0.1mm, and quality volume is 20% ~30%.
(14) bracing members and billet 7, are removed.
(15) basement roof concrete, is poured.
(16), close that bracing members are pre-buried and the position underplate concrete of billet 7 with water-proof concrete.
From the point of view of the overall process that basement is excavated, maximum soil body deep soil movement is 9mm, and the earth excavation of this engineering is safety Reliably.

Claims (2)

1. a kind of basement supporting, it is characterized in that the first operating mode basement supporting construction is using as follows:Support pile is filled using drilling Note stake, a diameter of 600~900mm of cast-in-situ bored pile;From setting water-stop curtain at 1.5~2m of support pile central point lateral direction, Water-stop curtain uses three axle cement mixing piles, and three axle cement mixing pile stake footpaths are 600mm or 500mm, and adjacent three axles cement is stirred Mix stake to be mutually twisted, occlusion distance is 200mm or 150mm;Direction top sets first of steel waist rail, first on the inside of support pile Road steel waist rail top mark is high identical with support pile top mark height, and the embedded bar of first of steel waist rail and support pile is welded to connect, and in advance should Power anchorage cable anchoring is placed above under billet, billet in first of steel waist rail, 1.5~2.5m of digging depth positions in engineering pile The engineering pile in face has 2~4;Billet thickness be 10~12cm, billet set location from 13~15m of basement edge, Fluted in the middle of billet, recessed poor depth is 8~12mm, and length and width is 10~15cm, the stabilization zone of basement passive area Width is 1m scopes within the tangent line of support pile outward flange, and stabilization zone depth is 1.5m~2m below basement substrate;First of steel First time bracing members are set between waist rail and billet;Second operating mode basement supporting construction is using as follows:Side in support pile To middle part set second steel waist rail, second steel waist bottom elevation be first time earth excavation depth, second steel waist rail with The embedded bar of support pile is welded to connect, and second prestressed cable anchorage is in second steel waist rail, and engineering pile is in second of soil Side is cut when excavating, and engineering pile top mark is high identical with basement bottom board substrate absolute altitude, and billet, steel are set above engineering pile Second of bracing members is set between backing plate and first of steel waist rail, second of steel branch is set between billet and second steel waist rail Support;
Embedded water stop rubber strip blocks infiltration path in the middle part of the basement bottom board of billet position.
2. basement supporting according to claim 1, it is characterized in that construction prestressed cable is using as follows:
1) after the intensity of injecting cement paste reaches the 75% of design strength and not less than 15MPa, the tensioning fixation of anchor cable is carried out;
2) using the method for the overall tensioning fixation of steel strand wires;
3) anchorage cable stretching should be loaded gently, and loading classification is not more than 0.3, and the interval time of every grade of load is not less than 3min;Anchor cable Before locking, stable a period of time should be kept under maximum stretching force, to sandy soil stratum, stabilization time should be greater than 5min~10min, To cohesive soil stratum, stabilization time should be greater than 15min;
4) anchor cable rope timing, tensioning value takes 1.1~1.15 times of design tensioning lock definite value;
5) in the 48h after anchor cable locking, when anchor cable pulling force is less than design lock value 90%, it should be locked again;Anchor cable Locking is considered as loss of prestress caused by adjacent anchorage cable stretching locking, when anchor cable pulling force 90% less than design lock value, It should be locked again;
6) anchor cable outer end is cut off using cold cut segmentation method after locking;Steel strand wires after being cut outside anchorage retain length and are no less than 50mm, during using thermal cutting, no less than 80mm.
CN201710354673.0A 2015-11-24 2015-11-24 Basement supporting Active CN107012875B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710354673.0A CN107012875B (en) 2015-11-24 2015-11-24 Basement supporting

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510915206.1A CN105421468B (en) 2015-11-24 2015-11-24 Basement supporting without concrete to support
CN201710354673.0A CN107012875B (en) 2015-11-24 2015-11-24 Basement supporting

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201510915206.1A Division CN105421468B (en) 2015-11-24 2015-11-24 Basement supporting without concrete to support

Publications (2)

Publication Number Publication Date
CN107012875A true CN107012875A (en) 2017-08-04
CN107012875B CN107012875B (en) 2018-11-09

Family

ID=55499979

Family Applications (5)

Application Number Title Priority Date Filing Date
CN201710354675.XA Active CN107130609B (en) 2015-11-24 2015-11-24 Without the basement supporting to support
CN201710354674.5A Active CN107130608B (en) 2015-11-24 2015-11-24 Without concrete to the basement construction method for supporting of support
CN201510915206.1A Active CN105421468B (en) 2015-11-24 2015-11-24 Basement supporting without concrete to support
CN201710354672.6A Active CN107130607B (en) 2015-11-24 2015-11-24 Building basement supporting
CN201710354673.0A Active CN107012875B (en) 2015-11-24 2015-11-24 Basement supporting

Family Applications Before (4)

Application Number Title Priority Date Filing Date
CN201710354675.XA Active CN107130609B (en) 2015-11-24 2015-11-24 Without the basement supporting to support
CN201710354674.5A Active CN107130608B (en) 2015-11-24 2015-11-24 Without concrete to the basement construction method for supporting of support
CN201510915206.1A Active CN105421468B (en) 2015-11-24 2015-11-24 Basement supporting without concrete to support
CN201710354672.6A Active CN107130607B (en) 2015-11-24 2015-11-24 Building basement supporting

Country Status (1)

Country Link
CN (5) CN107130609B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503355B (en) * 2017-07-20 2023-10-13 广东省建筑工程集团有限公司 Externally-arranged rear-inserted steel type double-row pile foundation pit supporting system and construction method thereof
CN108930273B (en) * 2017-07-30 2020-09-15 叶长青 Basement supporting construction method
CN108385692A (en) * 2018-01-18 2018-08-10 武汉中力岩土工程有限公司 Deep basal pit shear connector support system
CN108643190A (en) * 2018-04-12 2018-10-12 中铁上海工程局集团有限公司 A kind of construction method suitable for the larger deep foundation pit supporting structure of excavation area
CN110130357B (en) * 2019-04-01 2021-05-04 南京市第九建筑安装工程有限公司 Construction method of cast-in-place pile top inserting type steel combined stirring pile foundation pit supporting system
CN111810202B (en) * 2020-07-20 2022-04-15 武汉市市政建设集团有限公司 Underground connecting channel interface construction method
CN112942371B (en) * 2021-02-05 2022-09-06 中冶成都勘察研究总院有限公司 Support method for controlling deformation of subway tunnel
CN113565102B (en) * 2021-07-07 2022-07-29 深圳市中地建设工程有限公司 Construction method for connecting waist beam and support pile for saving concrete

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201671108U (en) * 2010-04-27 2010-12-15 中国科学院武汉岩土力学研究所 Riverside shoulder prestressing anchor cable sheet-pile wall
KR101181619B1 (en) * 2011-10-06 2012-09-13 쌍용건설 주식회사 Building method of high wall block for large scale underground structure using earth anchor represtressing
CN102839672A (en) * 2012-09-19 2012-12-26 广州机施建设集团有限公司 Foundation pit supporting method for preventing displacement limit exceeding of soft base cement mixing pile
CN203307824U (en) * 2013-06-14 2013-11-27 李琳 Supporting structure of high-rise building foundation pit
CN103726495A (en) * 2014-01-10 2014-04-16 上海建工五建集团有限公司 Offshore deep foundation pit supporting structure and construction method thereof
CN104947686A (en) * 2015-06-11 2015-09-30 叶长青 Basement supporting structure in soft soil area

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001317054A (en) * 2000-05-09 2001-11-16 Tokyu Constr Co Ltd Horizontal member for preventing deformation of l- shaped cage for reinforcing embankment slope and reinforced embankment method using the same
JP5439920B2 (en) * 2009-04-15 2014-03-12 新日鐵住金株式会社 Water structure using submerged ground driving member
CN102330431A (en) * 2011-06-16 2012-01-25 兰州理工大学 Flexible support structure of pre-stress anchor rod for lattice type frame and construction method of flexible support structure
CN204163085U (en) * 2014-08-28 2015-02-18 浙江大学城市学院 The supporting of bored pile foundation ditch
CN104264688B (en) * 2014-10-22 2016-06-08 广州市城市规划勘测设计研究院 Manually digging hole non-uniform pile support construction process
CN204919573U (en) * 2015-08-27 2015-12-30 山东科技大学 Combined type side slope supporting construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201671108U (en) * 2010-04-27 2010-12-15 中国科学院武汉岩土力学研究所 Riverside shoulder prestressing anchor cable sheet-pile wall
KR101181619B1 (en) * 2011-10-06 2012-09-13 쌍용건설 주식회사 Building method of high wall block for large scale underground structure using earth anchor represtressing
CN102839672A (en) * 2012-09-19 2012-12-26 广州机施建设集团有限公司 Foundation pit supporting method for preventing displacement limit exceeding of soft base cement mixing pile
CN203307824U (en) * 2013-06-14 2013-11-27 李琳 Supporting structure of high-rise building foundation pit
CN103726495A (en) * 2014-01-10 2014-04-16 上海建工五建集团有限公司 Offshore deep foundation pit supporting structure and construction method thereof
CN104947686A (en) * 2015-06-11 2015-09-30 叶长青 Basement supporting structure in soft soil area

Also Published As

Publication number Publication date
CN107130609B (en) 2018-10-12
CN105421468A (en) 2016-03-23
CN107130609A (en) 2017-09-05
CN107130608B (en) 2018-11-09
CN107130607B (en) 2018-11-09
CN107012875B (en) 2018-11-09
CN107130608A (en) 2017-09-05
CN105421468B (en) 2017-10-10
CN107130607A (en) 2017-09-05

Similar Documents

Publication Publication Date Title
CN105421468B (en) Basement supporting without concrete to support
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN205742213U (en) Foundation pit supporting construction
CN105649089B (en) A kind of excavation of foundation pit closes on existing shallow foundation protection structure construction method
CN102518135A (en) Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN106049505A (en) Construction method for deep foundation pit supporting and protecting system
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN210104758U (en) Foundation pit supporting system of soil nail bored concrete pile anchor cable combination
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN103352477A (en) Vertical pres-stressed anchor rod gravity-type composite retaining wall and method for designing and constructing retaining wall
CN108301273A (en) The fore-telling shaped pile anchor structure and its construction method of guardrail reinforcing integrated with roadbed
CN112982431A (en) Construction method of foundation pit supporting structure
CN107964980A (en) Lattice counterfort wall and construction method with earth anchor
CN107268634A (en) Deep basal pit waist rail construction typified form system
CN112081155A (en) Reinforcing and lifting method for bar-shaped or box-shaped foundation building
CN112761166A (en) Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove
CN102235007A (en) Method for supporting deep foundation with upper nail-lower pile combination
CN110821512B (en) Loess tunnel entrance opening section pre-reinforcing and excavating construction method passing through landslide body
CN110529120B (en) Construction method for removing invasion limiting structure by chiseling VI-level surrounding rock shallow-buried underground excavation loess tunnel
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN107034894A (en) Post-tensioned prestressed tension beam recoverable pattern foundation pit supporting structure prefabricated pile and preparation method thereof and construction method
CN208534486U (en) A kind of Large Diameter Pipeline divides storehouse to excavate artificial push pipe
CN111395375A (en) Open caisson construction method based on thixotropic slurry drag reduction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: No. 16, Tongjiang Avenue, Chengguan Town, Nandan county, Hechi City, Guangxi Zhuang Autonomous Region

Patentee after: Ye Changqing

Address before: 325000 No. 4, Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, China

Patentee before: Ye Changqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211223

Address after: 276000 No. 10, Mengshan fifth road, economic development zone, Mengyin County, Linyi City, Shandong Province

Patentee after: Shandong Nahe Auto Parts Co.,Ltd.

Address before: No.16 Tongjiang Avenue, Chengguan Town, Nandan county, Hechi City, Guangxi Zhuang Autonomous Region 547200

Patentee before: Ye Changqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221223

Address after: 253000 East of 254 Provincial Road, North North Street, Economic Development Zone, Wucheng County, Dezhou City, Shandong Province

Patentee after: Dezhou Shuanghang Packaging Products Co.,Ltd.

Address before: 276000 No. 10, Mengshan fifth road, economic development zone, Mengyin County, Linyi City, Shandong Province

Patentee before: Shandong Nahe Auto Parts Co.,Ltd.