CN206070573U - It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe - Google Patents
It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe Download PDFInfo
- Publication number
- CN206070573U CN206070573U CN201621032572.9U CN201621032572U CN206070573U CN 206070573 U CN206070573 U CN 206070573U CN 201621032572 U CN201621032572 U CN 201621032572U CN 206070573 U CN206070573 U CN 206070573U
- Authority
- CN
- China
- Prior art keywords
- wall
- reinforced
- open
- steel pipe
- foundation pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
技术领域technical field
本实用新型属于工程技术领域,具体涉及一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构。The utility model belongs to the technical field of engineering, and in particular relates to a combined structure of a large-span open-cut tunnel and a steel pipe reinforced foundation pit suitable for underpassing a heavy-duty road.
背景技术Background technique
近年来,随着我国基础设施建设规模加大,公路等级大幅提高、路网不断加密,出现了大量的隧道与公路相交的情况,其中大跨、浅埋、连拱隧道下穿既有的重载(如运煤)公路是一种比较复杂的工况。In recent years, with the expansion of infrastructure construction in my country, the level of roads has been greatly improved, and the road network has been continuously densified. A large number of tunnels and roads have intersected. Loading (such as coal transport) highway is a more complicated working condition.
对于大跨浅埋隧道下穿既有公路、在具备将公路改移的条件时,采用明挖法施工,在原地面从上往下挖出一基坑,在基坑中浇筑隧道的明洞结构,然后回填,恢复原地面。For long-span and shallow-buried tunnels passing through existing roads, when the conditions for relocating the roads are met, the open-cut method is used for construction. A foundation pit is dug from top to bottom on the original ground, and the open-hole structure of the tunnel is poured in the foundation pit. , and then backfill to restore the original ground.
明挖法的关键工序包括:边坡支护、土方开挖、结构施工及防水工程等。其中边坡支护是确保安全施工的关键技术。边坡支护,也即基坑壁支护的常规方式主要有:放坡开挖、型钢支护、连续墙支护、混凝土灌注桩支护、土钉墙支护、锚杆(索)支护、混凝土和钢结构支撑支护、及前述类型相组合等。The key processes of the open cut method include: slope support, earthwork excavation, structural construction and waterproofing works, etc. Among them, slope support is the key technology to ensure safe construction. Slope support, that is, the conventional methods of foundation pit wall support mainly include: sloping excavation, steel support, continuous wall support, concrete pouring pile support, soil nail wall support, anchor (cable) support support, concrete and steel structure support, and combinations of the aforementioned types, etc.
隧道下穿的是既有重载公路,为防止隧道施工结束后地面的工后沉降、特别是不均匀沉降:一方面,在基坑开挖过程中要尽可能减小对基坑两侧原岩土体扰动,或提前预加固该部分岩土体;另一方面明洞浇筑完成后,对洞顶回填材料及压实度须有较高的要求。基于该背景、前提,本实用新型提出一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构,以克服现有技术的不足,解决工程技术领域亟需解决的问题。The tunnel passes through the existing heavy-duty road. In order to prevent the post-construction settlement of the ground after the tunnel construction is completed, especially the uneven settlement: on the one hand, during the excavation of the foundation pit, the original Disturbance of the rock and soil mass, or pre-reinforce the part of the rock and soil mass in advance; on the other hand, after the pouring of the open cave is completed, there must be higher requirements for the backfill material and compaction degree of the cave roof. Based on this background and premise, the utility model proposes a combination structure of a large-span open-cut tunnel and a steel pipe reinforced foundation pit suitable for underpassing a heavy-duty highway, so as to overcome the deficiencies of the existing technology and solve the problems that need to be solved urgently in the field of engineering technology .
发明内容Contents of the invention
本实用新型的目的是为了解决现有技术的不足,提供一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构,该结构受力合理、经济性较好,具有很强的实用性和推广意义。The purpose of this utility model is to solve the deficiencies of the prior art, and provide a combination structure of a large-span open-cut tunnel and a steel pipe reinforced foundation pit suitable for passing through a heavy-duty road. Strong practicability and promotional significance.
为实现上述目的,本实用新型采用的技术方案如下:In order to achieve the above object, the technical scheme adopted by the utility model is as follows:
一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构,是在原重载公路的路面上,沿基坑顶部汽车行驶方向的两边各设有一个路面开槽,槽底水平;A combination structure of large-span open-cut tunnels and steel pipe reinforced foundation pits suitable for underpassing heavy-duty roads. On the road surface of the original heavy-duty roads, a road surface slot is arranged on both sides of the top of the foundation pit along the driving direction of the car. bottom level;
每个路面开槽均向下打设有第一加固墙和第二加固墙,第一加固墙和第二加固墙的墙面走向均与汽车行驶方向平行;Each road surface slot is drilled downwards with a first reinforcement wall and a second reinforcement wall, and the wall direction of the first reinforcement wall and the second reinforcement wall is parallel to the driving direction of the car;
第一加固墙是由多根大小一致钢管排成一列组成,相邻两根钢管相互平行,且间距为2m;第一加固墙与路面开槽底面垂直;The first reinforcement wall is composed of multiple steel pipes of the same size arranged in a row, two adjacent steel pipes are parallel to each other, and the distance between them is 2m; the first reinforcement wall is perpendicular to the bottom surface of the road groove;
第二加固墙是由多根大小一致钢管排成一列组成,相邻两根钢管相互平行,且间距为1m;第二加固墙与路面开槽底面的夹角为75°;The second reinforcement wall is composed of multiple steel pipes of the same size arranged in a row, two adjacent steel pipes are parallel to each other, and the distance between them is 1m; the angle between the second reinforcement wall and the bottom surface of the road groove is 75°;
以路面开槽底面为截面,第一加固墙与第二加固墙在该截面处的距离为1m;Taking the bottom surface of the pavement groove as the section, the distance between the first reinforcement wall and the second reinforcement wall at the section is 1m;
路面开槽槽内下部设有混凝土连梁层;The lower part of the pavement groove is provided with a concrete connecting beam layer;
沿基坑坡面向坡面内打设有多组第三加固墙,第三加固墙由多根大小一致钢管排成一列组成,相邻两根钢管相互平行,且间距为1.2m;第三加固墙与基坑坡面相垂直,且与水平面呈27°夹角;第三加固墙的墙面走向与其所在坡的基坑坡面从坡顶到坡底的方向一致;相邻两组第三加固墙的间距为2m;Multiple sets of third reinforcement walls are built along the slope of the foundation pit. The third reinforcement wall is composed of multiple steel pipes of the same size arranged in a row. Two adjacent steel pipes are parallel to each other with a distance of 1.2m; the third reinforcement wall The wall is perpendicular to the slope of the foundation pit, and forms an angle of 27° with the horizontal plane; the direction of the wall surface of the third reinforcement wall is consistent with the direction of the slope of the foundation pit on the slope from the top to the bottom of the slope; the adjacent two groups of third The distance between reinforced walls is 2m;
基坑坡面上还设有喷射混凝土层;There is also a sprayed concrete layer on the slope of the foundation pit;
基坑坑底上设有明洞衬砌的基底垫层,在明洞衬砌的基底垫层上设有大跨连拱隧道的明洞衬砌;On the bottom of the foundation pit, there is an open-hole lining base cushion, and on the base cushion of the open-hole lining, there is an open-hole lining for a large-span multi-arch tunnel;
在基坑坡面与明洞衬砌之间从下到上填有片石混凝土层和第一浆砌片石层;在双洞相交拱顶位置明洞衬砌之间设有第二浆砌片石层;第一浆砌片石层、第二浆砌片石层均与明洞衬砌的外顶部在同一水平面;Between the slope of the foundation pit and the lining of the open hole, the concrete layer of rubble and the first layer of rubble are filled from bottom to top; the second layer of rubble is set between the lining of the open hole at the intersection of the double holes; Both the first mortared rubble layer and the second mortared rubble layer are at the same level as the outer top of the open tunnel lining;
在第一浆砌片石层和第二浆砌片石层上铺设有级配碎石填料层;在级配碎石填料层上及混凝土连梁层上均铺设有新的重载公路路面;所述的新的重载公路路面与原重载公路路面在同一水平面上;A graded crushed stone filler layer is laid on the first mortared rubble layer and the second mortared rubble layer; a new heavy-duty highway pavement is laid on the graded crushed stone filler layer and the concrete connecting beam layer; the said The new heavy-duty highway pavement is on the same level as the original heavy-duty highway pavement;
其中,第一加固墙的顶端和第二加固墙的顶端均设于混凝土连梁层中;第一加固墙的底端和第二加固墙的底端均位于明洞衬砌仰拱底标高以下;Wherein, the top of the first reinforced wall and the top of the second reinforced wall are both arranged in the concrete connecting beam layer; the bottom of the first reinforced wall and the bottom of the second reinforced wall are located below the bottom elevation of the open cavity lining inverted arch;
第一加固墙内的钢管、第二加固墙内的钢管和第三加固墙内的钢管均不相交。The steel pipes in the first reinforced wall, the steel pipes in the second reinforced wall and the steel pipes in the third reinforced wall do not intersect.
进一步,优选的是基坑的坡面的坡比为1:0.5。Further, preferably, the slope ratio of the slope of the foundation pit is 1:0.5.
进一步,优选的是路面开槽的槽宽为2m,槽深为0.9m。Further, it is preferable that the groove width of the road surface groove is 2m, and the groove depth is 0.9m.
进一步,优选的是混凝土连梁层的宽为2m,厚度为0.5mFurther, it is preferred that the width of the concrete connecting beam layer is 2m and the thickness is 0.5m
进一步,优选的是第一加固墙的顶端和第二加固墙的顶端均伸入混凝土连梁层0.3m;第一加固墙的底端和第二加固墙的底端均伸入明洞衬砌仰拱底标高以下至少1.5m。Further, it is preferred that both the top of the first reinforced wall and the top of the second reinforced wall extend into the concrete coupling beam layer by 0.3m; the bottom of the first reinforced wall and the bottom of the second reinforced wall both extend into the open hole lining At least 1.5m below the level of the vault bottom.
进一步,优选的是第一加固墙、第二加固墙所采用钢管均为φ108钢管;第三加固墙所采用钢管为φ42钢管,长度为5m。Further, preferably, the steel pipes used in the first and second reinforced walls are both φ108 steel pipes; the steel pipes used in the third reinforced wall are φ42 steel pipes with a length of 5m.
进一步,优选的是明洞衬砌的基底垫层厚度为0.5m。Further, it is preferred that the thickness of the base cushion of the open hole lining is 0.5m.
进一步,优选的是片石混凝土层厚度为6.5m;第一浆砌片石层高度为5.5m;第二浆砌片石层高度为3m;级配碎石填料层高度为1.2m。Further, it is preferred that the thickness of the rubble concrete layer is 6.5m; the height of the first mortared rubble layer is 5.5m; the height of the second mortared rubble layer is 3m; the height of the graded crushed stone filler layer is 1.2m.
进一步,优选的是明洞衬砌拱圈最小厚度为1.1m。Further, it is preferable that the minimum thickness of the open-hole lining arch ring is 1.1m.
进一步,优选的是第一加固墙的钢管内、第二加固墙的钢管内和第三加固墙的钢管内均设有钢筋笼;钢管均为打孔可注浆的钢管。Further, preferably, steel cages are provided in the steel pipes of the first reinforced wall, the steel pipes of the second reinforced wall and the steel pipes of the third reinforced wall; the steel pipes are perforated steel pipes that can be grouted.
本实用新型具有的优点和意义体现在:The advantages and significance that the utility model has are reflected in:
本实用新型一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构,针对新建大跨、浅埋隧道下穿既有重载公路情况,提出一种明挖明筑隧道与加固基坑的组合结构,解决两方面的问题:第一,新建隧道安全、经济地建设问题,即结构具有足够的强度、稳定性和耐久性,建成后能适应营运的需要;第二,原既有公路的恢复问题,特别是其重载功用的恢复问题。The utility model is a combination structure of a large-span open-cut tunnel and a steel pipe reinforced foundation pit suitable for passing under a heavy-duty road. Aiming at the situation that a newly-built long-span and shallow-buried tunnel passes under an existing heavy-duty road, a cut-and-surface construction is proposed. The combined structure of the tunnel and the reinforced foundation pit solves two problems: first, the safe and economical construction of the new tunnel, that is, the structure has sufficient strength, stability and durability, and can meet the needs of operation after completion; , the restoration of the original existing road, especially the restoration of its heavy-duty function.
施工完成后工后沉降是影响原既有公路使用的主要原因,为减小沉降,需防止对原岩土体的扰动:基坑开挖前通过设置第一加固墙和第二加固墙,首先对岩土体可注浆预加固,并且第一加固墙的顶端和第二加固墙的布设参照重力式挡墙断面形状,在原岩土体中形成一道起支挡作用的挡土墙;基坑开挖后通过第三加固墙内的钢管注浆加固坡面下被扰动的岩土体,并采用喷射混凝土对扰动坡面做封闭处理。Post-construction settlement after construction is the main reason affecting the use of the original existing roads. In order to reduce settlement, it is necessary to prevent disturbance to the original rock and soil: before excavation of the foundation pit, the first reinforcement wall and the second reinforcement wall are set, first The rock and soil can be pre-reinforced by grouting, and the layout of the top of the first reinforcement wall and the second reinforcement wall refers to the section shape of the gravity retaining wall, forming a retaining wall that acts as a support in the original rock and soil; the foundation pit After excavation, the disturbed rock and soil mass under the slope is reinforced by grouting steel pipes in the third reinforcement wall, and the disturbed slope is sealed with shotcrete.
隧道为浅埋,直接承受其上方公路的重载,本实用新型设计通过计算确定结构厚度,并将仰拱设为平底以方便施工,将两洞拱部相交部位做填平处理形成第二浆砌片石层,以防止应力集中。The tunnel is shallowly buried and directly bears the heavy load of the road above it. The design of the utility model determines the thickness of the structure through calculation, and sets the inverted arch as a flat bottom to facilitate construction. The intersection of the two arches is filled and leveled to form the second slurry. Laying stone layers to prevent stress concentration.
为减少土石方开挖量,并适当控制基坑预加固的规模,基坑开挖按介于缓放坡和直壁两种开挖方式间的预加固、较陡坡率进行放坡。In order to reduce the excavation volume of earthwork and properly control the pre-reinforcement scale of the foundation pit, the excavation of the foundation pit is carried out according to the pre-reinforcement and steeper slope rate between the two excavation methods of slow slope and straight wall.
另外,将本实用新型结构与可供选择的桥梁、矩形下穿隧道两类结构从造价上做对比:相比于桥梁结构,一跨40m或两跨20m,本实用新型结构可节约造价20%以上;相比于双孔20m矩形断面的下穿隧道,本实用新型结构可节约造价30%以上。另外,从施工快捷程度、工后沉降控制效果等方面对比,本实用新型结构也均优于另两类结构。In addition, compare the structure of the utility model with the alternative bridge and rectangular underpass tunnel in terms of cost: compared with the bridge structure, one span of 40m or two spans of 20m, the utility model structure can save 20% of the cost Above; compared with the underpass tunnel with double-hole 20m rectangular section, the structure of the utility model can save more than 30% of the cost. In addition, the structure of the utility model is also superior to the other two types of structures in terms of the quickness of construction and the control effect of post-construction settlement.
综上,本实用新型一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构选用受力合理的拱形隧道为结构基本,通过加固措施最大程度保护原岩土体不受扰动,采取回填措施控制工后沉降;本实用新型新型结构既安全、经济地新建了下穿隧道,又快速、良好的恢复了隧顶既有重载公路的通行。本结构具有很强的实用性和推广意义。In summary, this utility model is a combination structure of large-span open-cut tunnels and steel pipe reinforced foundation pits suitable for passing heavy-duty highways. The arched tunnel with reasonable stress is selected as the basic structure, and the original rock and soil are protected to the greatest extent through reinforcement measures. Without disturbance, backfill measures are taken to control post-construction settlement; the structure of the utility model not only safely and economically builds a new underpass tunnel, but also quickly and well restores the traffic of the existing heavy-duty road on the tunnel top. This structure has strong practicability and popularization significance.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are only some embodiments of the utility model, and those skilled in the art can also obtain other drawings based on these drawings without creative work.
图1为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构基坑槽两侧φ108钢管布置横断面图。Fig. 1 is a cross-sectional view of the arrangement of φ108 steel pipes on both sides of the foundation pit groove of the combined structure of the large-span open-cut tunnel and the steel pipe reinforced foundation pit of the utility model applicable to the heavy-duty highway.
图2为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构基坑开挖坡面支护φ42钢管布置横断面图。Fig. 2 is a cross-sectional view of the excavation slope support of the utility model for a large-span open-cut tunnel and a steel pipe reinforced foundation pit combined structure foundation pit excavation slope support layout of a heavy-duty highway underneath.
图3为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构基坑开挖坡面支护大样图(以右半基坑坡面为例)。Fig. 3 is a large sample diagram of foundation pit excavation slope support for a large-span open-cut tunnel and a steel pipe reinforced foundation pit combined structure of the utility model (taking the slope of the right half of the foundation pit as an example) for the utility model.
图4为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构φ108钢管和φ42钢管间隔布置关系平面图(以右半基坑侧壁为例)。Fig. 4 is a plan view of the layout relationship between φ108 steel pipes and φ42 steel pipes in the combined structure of large-span open-cut tunnels and steel pipe-reinforced foundation pits of the present invention (taking the side wall of the right half of the foundation pit as an example).
图5为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构明洞衬砌横断面图。Fig. 5 is a cross-sectional view of the open tunnel lining of the combined structure of the large-span open-cut tunnel and the steel pipe reinforced foundation pit of the utility model suitable for passing through heavy-duty highways.
图6为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构明洞回填横断面图。Fig. 6 is a cross-sectional view of the backfilling of the combined structure of the large-span open-cut tunnel and the steel pipe reinforced foundation pit of the utility model suitable for passing through heavy-duty highways.
图7为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构明洞回填分层/分块横断面图。Fig. 7 is a cross-sectional view of backfill layering/blocking of the combined structure of the large-span open-cut tunnel and the steel pipe reinforced foundation pit of the utility model suitable for underpassing the heavy-duty highway.
图8为本实用新型适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构总组成横断面图。Fig. 8 is a cross-sectional view of the combined structure of a large-span open-cut tunnel and a steel pipe reinforced foundation pit suitable for underpassing a heavy-duty road under the utility model.
其中:1、原重载公路的路面;2、基坑;3、预加固支护体系;3a、路面开槽;3b、第一加固墙;3c、第二加固墙;3d、混凝土连梁层;4、基坑坡面;4a、喷射混凝土层;4b、第三加固墙;5、明洞衬砌的基底垫层;6、明洞衬砌;6a、明洞衬砌仰拱;6b、明洞衬砌仰拱以上边墙及拱圈;7、明洞回填结构;7a、片石混凝土;7b、第一浆砌片石;7c、第二浆砌片石;7d、级配碎石填料层;8、新的重载公路路面;Among them: 1. The pavement of the original heavy-duty road; 2. The foundation pit; 3. The pre-reinforcement support system; 3a. Grooving on the road surface; 3b. The first reinforcement wall; 3c. The second reinforcement wall; 3d. The concrete coupling beam layer ;4, foundation pit slope; 4a, sprayed concrete layer; 4b, third reinforcement wall; 5, base cushion of open hole lining; 6, open hole lining; Side wall and arch ring above the inverted arch; 7. Open hole backfill structure; 7a. Rubble concrete; 7b. First mortared rubble; 7c. Second mortared rubble; 7d. Graded crushed stone filling layer; 8. New Heavy-duty highway pavement;
箭头方向为从坡顶到坡底的方向。The direction of the arrow is from the top of the slope to the bottom of the slope.
具体实施方式detailed description
下面结合实施例对本实用新型作进一步的详细描述。Below in conjunction with embodiment the utility model is described in further detail.
本领域技术人员将会理解,下列实施例仅用于说明本实用新型,而不应视为限定本实用新型的范围。实施例中未注明具体技术、连接关系或条件者,按照本领域内的文献所描述的技术、连接关系或条件或者按照产品说明书进行。所用材料或设备未注明生产厂商者,均为可以通过购买获得的常规产品。Those skilled in the art will understand that the following examples are only used to illustrate the utility model, and should not be considered as limiting the scope of the utility model. If no specific technology, connection relationship or condition is indicated in the embodiment, it shall be carried out according to the technology, connection relationship or condition described in the literature in this field or according to the product specification. The materials or equipment used are not indicated by the manufacturer, and they are all conventional products that can be obtained through purchase.
一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构,是在原重载公路的路面1上,沿基坑2顶部汽车行驶方向的两边各设有一个路面开槽3a,槽底水平;A combination structure of large-span open-cut tunnels and steel pipe reinforced foundation pits suitable for underpassing heavy-duty roads. On the road surface 1 of the original heavy-duty road, a road surface slot is arranged on both sides of the top of the foundation pit 2 in the direction of vehicle travel. 3a, tank bottom level;
每个路面开槽3a均向下打设有第一加固墙3b和第二加固墙3c,第一加固墙3b和第二加固墙3c的墙面走向均与汽车行驶方向平行;第一加固墙3b是由多根大小一致钢管排成一列组成,相邻两根钢管相互平行,且间距为2m;第一加固墙3b与路面开槽3a底面垂直;Each road surface slot 3a is drilled downwards with a first reinforced wall 3b and a second reinforced wall 3c, and the wall direction of the first reinforced wall 3b and the second reinforced wall 3c is parallel to the driving direction of the car; the first reinforced wall 3b is composed of multiple steel pipes of the same size arranged in a row, two adjacent steel pipes are parallel to each other, and the distance is 2m; the first reinforcement wall 3b is perpendicular to the bottom surface of the road groove 3a;
第二加固墙3c是由多根大小一致钢管排成一列组成,相邻两根钢管相互平行,且间距为1m;第二加固墙3c与路面开槽3a底面的夹角为75°;The second reinforced wall 3c is composed of multiple steel pipes of the same size arranged in a row, two adjacent steel pipes are parallel to each other, and the distance is 1m; the angle between the second reinforced wall 3c and the bottom surface of the road groove 3a is 75°;
以路面开槽3a底面为截面,第一加固墙3b与第二加固墙3c在该截面处的距离为1m;Taking the bottom surface of the road groove 3a as the section, the distance between the first reinforcement wall 3b and the second reinforcement wall 3c at the section is 1m;
路面开槽3a槽内下部设有混凝土连梁层3d;The lower part of the pavement groove 3a is provided with a concrete connecting beam layer 3d;
路面开槽3a、第一加固墙3b、第二加固墙3c、混凝土连梁层3d共同组成预加固支护体系3;The road surface groove 3a, the first reinforced wall 3b, the second reinforced wall 3c, and the concrete connecting beam layer 3d together form a pre-reinforced support system 3;
沿基坑坡面4向坡面内打设有多组第三加固墙4b,第三加固墙4b由多根大小一致钢管排成一列组成,相邻两根钢管相互平行,且间距为1.2m;第三加固墙4b与基坑坡面4相垂直,且与水平面呈27°夹角;第三加固墙4b的墙面走向与其所在坡的基坑坡面4从坡顶到坡地的方向一致;相邻两组第三加固墙4b的间距为2m;Multiple sets of third reinforcement walls 4b are drilled along the slope 4 of the foundation pit. The third reinforcement walls 4b are composed of multiple steel pipes of the same size arranged in a row. Two adjacent steel pipes are parallel to each other with a distance of 1.2m. The third reinforcement wall 4b is perpendicular to the foundation pit slope 4, and is at an angle of 27° with the horizontal plane; the wall direction of the third reinforcement wall 4b is consistent with the direction of the foundation pit slope 4 of the slope where it is located from the top of the slope to the slope ; The distance between two adjacent groups of third reinforcement walls 4b is 2m;
基坑坡面4上还设有喷射混凝土层4a;A shotcrete layer 4a is also provided on the foundation pit slope 4;
基坑2坑底上设有明洞衬砌的基底垫层5,在明洞衬砌的基底垫层5上设有大跨连拱隧道的明洞衬砌6;明洞衬砌6是由明洞衬砌仰拱6a和明洞衬砌仰拱以上边墙及拱圈6b组成。On the bottom of foundation pit 2, there is a base cushion layer 5 for open hole lining, and on the base cushion layer 5 for open hole lining, there is an open hole lining 6 for a large-span multi-arch tunnel; 6a and the side wall above the inverted arch of the open-hole lining and the arch ring 6b.
在基坑坡面4与明洞衬砌6之间从下到上填有片石混凝土层7a和第一浆砌片石层7b;在双洞相交拱顶位置明洞衬砌之间设有第二浆砌片石层7c;第一浆砌片石层7b、第二浆砌片石层7c均与明洞衬砌6的外顶部在同一水平面;Between the foundation pit slope 4 and the open hole lining 6, a rubble concrete layer 7a and a first grouted rubble layer 7b are filled from bottom to top; a second grouting layer is arranged between the double hole intersecting vault position and the open hole lining The rubble layer 7c; the first grouted rubble layer 7b and the second grouted rubble layer 7c are at the same level as the outer top of the open tunnel lining 6;
在第一浆砌片石层7b和第二浆砌片石层7c上铺设有级配碎石填料层7d;在级配碎石填料层7d上及混凝土连梁层3d上均铺设有新的重载公路路面8;所述的新的重载公路路面8与原重载公路路面1在同一水平面上;A graded crushed stone filler layer 7d is laid on the first mortared rubble layer 7b and the second mortared rubble layer 7c; a new heavy-duty filler layer is laid on the graded crushed stone filler layer 7d and the concrete coupling beam layer 3d. Highway pavement 8; the new heavy-duty highway pavement 8 is on the same level as the original heavy-duty highway pavement 1;
其中,第一加固墙3b的顶端和第二加固墙3c的顶端均设于混凝土连梁层3d中;第一加固墙3b的底端和第二加固墙3c的底端均是位于明洞衬砌仰拱6a底标高以下至少1.5m;Wherein, the top end of the first reinforcement wall 3b and the top end of the second reinforcement wall 3c are both arranged in the concrete connecting beam layer 3d; the bottom end of the first reinforcement wall 3b and the bottom end of the second reinforcement wall 3c are located in the open hole At least 1.5m below the bottom elevation of inverted arch 6a;
第一加固墙内3b的钢管、第二加固墙3c内的钢管和第三加固墙4b内的钢管均不相交。The steel pipes in the first reinforced wall 3b, the steel pipes in the second reinforced wall 3c and the steel pipes in the third reinforced wall 4b do not intersect.
优选的是基坑2的坡面的坡比为1:0.5。基坑2深度根据具体的设计位置、地质条件等条件综合确定。基坑2底宽约36m,顶宽约50m,深约15m左右。Preferably, the slope ratio of the slope of the foundation pit 2 is 1:0.5. The depth of the foundation pit 2 is comprehensively determined according to the specific design location, geological conditions and other conditions. The foundation pit 2 has a bottom width of about 36m, a top width of about 50m, and a depth of about 15m.
路面开槽3a的槽宽为2m,槽深为0.9m。The groove width of the road surface groove 3a is 2m, and the groove depth is 0.9m.
混凝土连梁层3d的宽为2m,厚度为0.5m。The concrete connecting beam layer 3d has a width of 2m and a thickness of 0.5m.
第一加固墙3b的顶端和第二加固墙3c的顶端均伸入混凝土连梁层3d 0.3m;第一加固墙3c的底端和第二加固墙3b的底端均是位于明洞衬砌仰拱6a底标高以下至少1.5m。The top of the first reinforcement wall 3b and the top of the second reinforcement wall 3c both extend into the concrete connecting beam layer 3d 0.3m; At least 1.5m below the bottom elevation of the arch 6a.
第一加固墙3b、第二加固墙3c所采用钢管均为φ108钢管;The steel pipes adopted in the first reinforced wall 3b and the second reinforced wall 3c are all φ108 steel pipes;
第三加固墙4b所采用钢管为φ42钢管,长度为5m。The steel pipe used for the third reinforced wall 4b is a φ42 steel pipe with a length of 5m.
明洞衬砌的基底垫层5厚度为0.5m。片石混凝土层7a厚度为6.5m;第一浆砌片石层7b高度为5.5m;第二浆砌片石层7c高度为3m;级配碎石填料层7d高度为1.2m。明洞衬砌6拱圈最小厚度为1.1m。第一加固墙3b的钢管内、第二加固墙3c的钢管内和第三加固墙4b的钢管内均设有钢筋笼。The base cushion layer 5 of the open hole lining has a thickness of 0.5m. The thickness of the rubble concrete layer 7a is 6.5m; the height of the first mortared rubble layer 7b is 5.5m; the height of the second mortared rubble layer 7c is 3m; the height of the graded crushed stone filler layer 7d is 1.2m. The minimum thickness of the 6 arch rings in the lining of the open cave is 1.1m. Reinforcement cages are all provided in the steel pipes of the first reinforced wall 3b, the steel pipes of the second reinforced wall 3c and the steel pipes of the third reinforced wall 4b.
以上为本实用新型一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构各组成部分及实施要点,其施工过程简述如下:The above are the components and implementation points of a large-span open-cut tunnel and steel pipe reinforced foundation pit composite structure suitable for passing heavy-duty highways under the utility model. The construction process is briefly described as follows:
第一步,施工基坑预支护体系:在隧顶两侧路面开槽;从槽中打设φ108钢管形成第一、第二加固墙。The first step is to construct the foundation pit pre-support system: grooves are made on the road surface on both sides of the tunnel roof; φ108 steel pipes are drilled from the grooves to form the first and second reinforcement walls.
第二步,开挖基坑,对开挖的坡面打设φ42钢管,形成第三加固墙。The second step is to excavate the foundation pit, and lay φ42 steel pipes on the excavated slope to form the third reinforcement wall.
第三步,隧道明洞衬砌浇筑:浇筑前若地基承载力不满足要求需采取措施处理地基;然后在仰拱基底设找平垫层;再然后从下往上先浇筑一洞的衬砌,再浇筑另一洞衬砌。The third step is the pouring of the lining of the tunnel open hole: before pouring, if the bearing capacity of the foundation does not meet the requirements, measures should be taken to deal with the foundation; then a leveling cushion is set on the base of the inverted arch; and then the lining of a hole is poured from bottom to top, and then poured Another hole is lined.
第四步,隧道明洞回填:回填的总体顺序为从下到上;回填须对称进行,两侧回填的土石面高差不得大于0.5m。The fourth step is backfilling of the tunnel open hole: the overall sequence of backfilling is from bottom to top; backfilling must be done symmetrically, and the height difference between the backfilling soil and stone surfaces on both sides shall not be greater than 0.5m.
第五步,最后,恢复原路面:在洞顶级配碎石填料层重新铺筑重载公路的路面层。The fifth step, finally, restore the original pavement: re-pave the pavement layer of the heavy-duty road on the top of the hole with a gravel filler layer.
以上即为本实用新型一种适用于下穿重载公路的大跨明挖隧道与钢管加固基坑组合结构的实施步骤及过程。The above is the implementation steps and process of a combination structure of a large-span open-cut tunnel and a steel pipe reinforced foundation pit suitable for passing through a heavy-duty highway under the present invention.
以上显示和描述了本实用新型的基本原理、主要特征和本实用新型的优点。本行业的技术人员应该了解,本实用新型不受上述实施例的限制,上述实施例和说明书中描述的只是说明本实用新型的原理,在不脱离本实用新型精神和范围的前提下,本实用新型还会有各种变化和改进,这些变化和改进都落入要求保护的本实用新型范围内。本实用新型要求保护范围由所附的权利要求书及其等效物界定。The basic principles, main features and advantages of the present utility model have been shown and described above. Those skilled in the art should understand that the utility model is not limited by the above-mentioned embodiments. The above-mentioned embodiments and descriptions only illustrate the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model The new model also has various changes and improvements, and these changes and improvements all fall within the scope of the claimed utility model. The scope of protection required by the utility model is defined by the appended claims and their equivalents.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621032572.9U CN206070573U (en) | 2016-08-31 | 2016-08-31 | It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621032572.9U CN206070573U (en) | 2016-08-31 | 2016-08-31 | It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206070573U true CN206070573U (en) | 2017-04-05 |
Family
ID=58436827
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201621032572.9U Active CN206070573U (en) | 2016-08-31 | 2016-08-31 | It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206070573U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113818485A (en) * | 2021-09-09 | 2021-12-21 | 中建五局土木工程有限公司 | A fast and safe construction method for reverse working of open-cut arched tunnel in Linjiang sand and pebble stratum |
| CN114482088A (en) * | 2022-01-06 | 2022-05-13 | 中铁工程设计咨询集团有限公司 | Precast pile reinforced structure of tunnel and construction method thereof |
-
2016
- 2016-08-31 CN CN201621032572.9U patent/CN206070573U/en active Active
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113818485A (en) * | 2021-09-09 | 2021-12-21 | 中建五局土木工程有限公司 | A fast and safe construction method for reverse working of open-cut arched tunnel in Linjiang sand and pebble stratum |
| CN113818485B (en) * | 2021-09-09 | 2023-10-13 | 中建五局土木工程有限公司 | Reverse-acting quick and safe construction method for open cut arch tunnel in river facing sandy pebble stratum |
| CN114482088A (en) * | 2022-01-06 | 2022-05-13 | 中铁工程设计咨询集团有限公司 | Precast pile reinforced structure of tunnel and construction method thereof |
| CN114482088B (en) * | 2022-01-06 | 2023-09-12 | 中铁工程设计咨询集团有限公司 | Precast pile reinforcing structure of tunnel and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103883328A (en) | Semi-covering semi-darkened construction method for separated tunnels downwards penetrating through high and steep V-shaped gully eccentric compression section | |
| CN105696427A (en) | Construction method for reinforcing newly-built railway karst foundation and roadbed structure thereof | |
| CN108486976B (en) | Roadbed structure at mountain highway filling and digging junction and construction method thereof | |
| CN115199288A (en) | A construction method of mud-water balance circular pipe jacking down through the subgrade of railway subgrade | |
| CN111322087A (en) | Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area | |
| CN111365005A (en) | Reinforcing structure and method for shield tunnel lower-penetrating elevated bridge foundation | |
| CN116377780A (en) | Construction Method of High Fill Subgrade in Mountainous Highway | |
| CN104846840A (en) | Shallowly-buried soft soil integrated trench reinforcing device and construction method | |
| CN106676993A (en) | Roadbed reinforcing system of reinforced gravel framework structure and reinforcing method of roadbed reinforcing system | |
| CN111305027A (en) | Rapid repairing construction method and repairing structure for subsidence of karst area pavement | |
| CN115125782B (en) | A red sandstone high fill road subgrade structure and construction method | |
| CN111794030A (en) | The method of widening the embankment foundation at the building through the embankment | |
| CN108824412B (en) | Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction | |
| CN107859062A (en) | The earth-filling method of underground pipe gallery | |
| CN116717271B (en) | A mountain-side integrated mid-wall tunnel tunnel structure and construction method | |
| CN101838957A (en) | Integral type T-shaped outer cantilever roads and construction method thereof | |
| CN206625096U (en) | A kind of reinforced rubble frame structure subgrade strengthening system | |
| CN206070573U (en) | It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe | |
| CN208293588U (en) | A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages | |
| CN208455387U (en) | Subgrade structure at the junction of filling and excavation of mountain roads | |
| CN106836034B (en) | A flexible load-reducing system and construction method of high-fill cover slab culvert | |
| CN205576638U (en) | Consolidate roadbed structure who handles newly -built railway karst foundation | |
| CN103866788B (en) | A kind of method of pillar abutment scarp slope barricadeization transformation | |
| CN113430870A (en) | Roadbed structure for green reinforcement treatment of newly-built railway karst foundation and construction method thereof | |
| CN219080361U (en) | Mountain-side abrupt slope terrain channel structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 650051 Yunnan province Kunming City Road No. 9 Xiang Shi Tuo Patentee after: Yunnan Transportation Planning & Design Research Institute Co., Ltd. Address before: 650051 Yunnan province Kunming City Road No. 9 Xiang Shi Tuo Patentee before: Broadvision Engineering Consultants |