CN107053440A - A kind of precast plate girder pedestal preparation method - Google Patents

A kind of precast plate girder pedestal preparation method Download PDF

Info

Publication number
CN107053440A
CN107053440A CN201710323617.0A CN201710323617A CN107053440A CN 107053440 A CN107053440 A CN 107053440A CN 201710323617 A CN201710323617 A CN 201710323617A CN 107053440 A CN107053440 A CN 107053440A
Authority
CN
China
Prior art keywords
pedestal
steel plate
plate
girder
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710323617.0A
Other languages
Chinese (zh)
Other versions
CN107053440B (en
Inventor
王福明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710323617.0A priority Critical patent/CN107053440B/en
Publication of CN107053440A publication Critical patent/CN107053440A/en
Application granted granted Critical
Publication of CN107053440B publication Critical patent/CN107053440B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/22Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of precast plate girder pedestal preparation method, step is as follows:1st, the armored concrete and the pre-buried angle steel bound edge of surrounding at an upper portion thereof of pedestal are poured;2nd, processing and fabricating steel plate and several split bolt holes are cut in its longitudinal both sides correspondence;3rd, after the concrete strength of pedestal reaches requirement, lift steel plate and be placed on pedestal and welded with the angle steel of bound edge on pedestal;4th, below steel plate, the angle clip that pedestal longitudinal direction both sides set several and the angle steel of surrounding bound edge is welded on steel plate and pedestal;5th, lift side template and adjust lateral separation position of the side template on steel plate, sealant tape is put between steel plate and side template, with bolt by side template and Interal fixation;6th, steady pin offside template tightening and support are coordinated with inclined support bar.It is prefabricated that the present invention can be widely applied to plate-girder, and model sheetinstallat is quick, flexibly, and workload is few, and dismounting is also convenient for, and greatly shortens the plate-girder prefabricated construction time, and accelerating construction progress reduces engineering cost.

Description

A kind of precast plate girder pedestal preparation method
Technical field
The present invention is to be related to building field, more particularly to a kind of precast plate girder pedestal preparation method.
Background technology
It is a very important link in precast plate girder production that highway and municipal works precast plate girder pedestal, which make,.Mesh Before, there are two kinds of forms using post stretching precast plate girder in same bridge block:Side bar, central sill, its beam slab bottom width are also different, therefore When making precast plate girder pedestal, two kinds of different side bars of bottom width, central sill pedestals are often made.Side bar in bridge typically compares Less, its pedestal is short using the time, and because side bar and central sill pedestal bottom width are different, they, which can not circulate turnover from each other, makes With, poor universality, and it is big to cause Liang Chang to take up an area, side bar pedestal resources idle is wasted, and increases cost of manufacture.
When being made in bridge construction using post stretching precast plate girder pedestal, typically using reinforced concrete foundation, in basis At a certain distance, Screw arbor with nut at both-ends hole is buried, Screw arbor with nut at both-ends fixes two side templates through the pulling eye of template.And side template Support on the ground, activity adjustment screw collet is set come adjusting side mould plate setting height(from bottom) by wood block filler and template back rib, This method model sheetinstallat and supporting process is complicated, dumb, model sheetinstallat and adjustment are slow, influences construction speed;Meanwhile, to drawing spiral shell Tightening latch hole, split bolt bar, the making of set screw collet also increase construction cost.
Accordingly, it would be desirable to which one kind can effective solution to the problems described above.
The content of the invention
The technical problem to be solved in the present invention is:A kind of precast plate girder pedestal preparation method is provided, can using the present invention The problem of solving complex process when precast plate girder pedestal makes, too high cost and slow construction speed, meanwhile, it is used in the present invention Construction material it is recyclable be used in turn, economize on resources, cost is low, with very strong practicality.
The technical scheme that the present invention solves technical problem is as follows:
A kind of precast plate girder pedestal preparation method of the present invention, comprises the following steps:
Step one:The armored concrete of pedestal is poured according to the requirement of design drawing, when pouring, in the top surrounding of pedestal Pre-buried angle steel bound edge;
Step 2:According to the plate-girder width requirement of design drawing, processing and fabricating steel plate, and corresponded on longitudinal both sides of steel plate Cut several split bolt holes;
Step 3:After the concrete strength of pedestal reaches more than 90%, with crane hanging component steel plate and pedestal is placed on On, the position of steel plate is adjusted, the angle steel of surrounding bound edge on steel plate and pedestal is welded;
Step 4:Below steel plate, the longitudinal both sides of pedestal several angle steel with surrounding bound edge on steel plate and pedestal are set The angle clip of welding;
Step 5:With crane, both sides lift side template above steel plate, according to the plate-girder width requirement of design drawing, adjust Lateral separation position of the whole side template on steel plate, is put into sealant tape, then in split bolt between steel plate and side template Side template is fixed with steel plate with bolt at hole;
Step 6:Finally steady pin is coordinated to tense and support side template with inclined support bar.
Further, the armored concrete of pedestal is that strength grade is C25 armored concrete in the step one.
Further, the angle steel specification of pedestal surrounding bound edge is hem width 56mm~70mm, Bian Houwei in the step one 8mm。
Further, the step 2 light plate uses the steel plate that specification is 5mm~6mm for Q235 thickness.
Further, one of a diameter of 24mm and 26mm of the step 2 split shed bolt hole.
Further, the specification of angle clip is hem width 56mm~70mm, side thickness 8mm in the step 4.
Further, bolt, inclined support bar and steady pin are that tool steel makes in the step 5 and step 6, wherein One of a diameter of 22mm and 24mm of bolt.
Further, side template is made of steel plate in the step 5.
Further, step 2 light plate longitudinal direction per side on adjacent apertures bolt hole spacing for 1000mm~ 2000mm。
Further, in the step 4 pedestal longitudinal direction per side adjacent angle clip between spacing for 800mm~ 1200mm。
Compared with prior art, the present invention has advantages below:(1) construction technology is simple and convenient to operate, with very strong Practicality and economic benefit;(2) side template of precast plate girder is directly installed on the steel plate of pedestal, because of the Interal fixation of pedestal, Without as two side templates be fixed through the pulling eye of side template using Screw arbor with nut at both-ends in the prior art, without with wood block filler and Template back rib sets activity adjustment screw collet to carry out adjusting side mould plate setting height(from bottom), but directly uses bolt by split bolt hole It is fixed, so model sheetinstallat is quick, flexible, workload is few, and dismounting is also convenient for, and greatly shortens the plate-girder prefabricated construction time, Accelerating construction progress, reduces engineering cost;(3) the steel plate both sides of the precast plate girder pedestal are because being the split bolt being correspondingly arranged Hole, can carry out the regulation of lateral separation, a type pedestal can prefabricated different in width beam according to beam slab width when side template is installed Plate, without making the different side bar of two or more bottom width, central sill pedestal, can so save beam floor space, reduce beam processed Pedestal quantity, reduces construction cost;(4) side template coordinates steady pin to be supported fixation using inclined support bar, without with to drawing Bar so facilitates concreting, vibrates, wipes one's face to carrying out fixing to drawing on side template top;(5) bolt used in fixed bolster plate (including nut, screw rod, pad), inclined support bar make easy to process, can turnaround cycle use, economize on resources, cost is low, simultaneously Installing/dismounting speed is fast, construction safety.
Brief description of the drawings
Fig. 1 is the construction schematic diagram of the present invention;
Fig. 2 is the structural representation of inclined support bar in the present invention;
In figure:1. the side template of 4. split bolt hole of pedestal 2. steel plate, 3. angle clip, 5. bolt, 6. inclined support bar 7. 8. steady pin.
Embodiment
In order to preferably explain the present invention, come below in conjunction with the accompanying drawings with specific embodiment in the present invention is furture elucidated Hold, but present disclosure is not limited only to following examples.
As depicted in figs. 1 and 2, a kind of precast plate girder pedestal preparation method, comprises the following steps:
Step one:The armored concrete of pedestal 1 is poured according to the requirement of design drawing, when pouring, on the top four of pedestal 1 All pre-buried angle steel bound edges;
Step 2:According to the plate-girder width requirement of design drawing, processing and fabricating steel plate 2, and on longitudinal both sides pair of steel plate 2 Several split bolt holes 4 should be cut;
Step 3:After the concrete strength of pedestal 1 reaches more than 90%, with crane hanging component steel plate 2 and platform is placed on On seat 1, the position of steel plate 2 is adjusted, the angle steel of surrounding bound edge on steel plate 2 and pedestal 1 is welded;
Step 4:Below steel plate 2, the longitudinal both sides of pedestal 1 several and surrounding bound edge on steel plate 2 and pedestal 1 are set The angle clip 3 of angle steel welding;
Step 5:Side template 7 is lifted in the top both sides of steel plate 2 with crane, according to the plate-girder width requirement of design drawing, Lateral separation position of the side template 7 on steel plate 2 is adjusted, sealant tape is put between steel plate 2 and side template 7, is then being opened Side template 7 is fixed with steel plate 2 with bolt 5 at mouth bolt hole 4;
Step 6:Finally steady pin 8 is coordinated to tense and support side template 7 with inclined support bar 6.
According to the requirement of design drawing in the present embodiment, the width of steel plate 2 here is more than the width of pedestal 1, when steel plate 2 When being placed on pedestal 1, the split bolt hole 4 on steel plate 2 can be caused in the outside of the longitudinal direction of pedestal 1, in order to work progress In, in that context it may be convenient to be fixed at split bolt hole 4, and the lower section clip 3 of steel plate 2 setting;By precast plate girder Side template 7 is directly installed on the steel plate 2 of pedestal, because of the Interal fixation of pedestal 2, it is only necessary to directly use spiral shell at split bolt hole 4 The row of bolt 5 is fixed, and such side template is quick for installation, flexible, and workload is few, and dismounting is also convenient for, when greatly shortening plate-girder prefabricated construction Between, accelerating construction progress reduces engineering cost;The both sides of steel plate 2 of the precast plate girder pedestal are cut with several openings because of correspondence Bolt hole 4, can carry out lateral separation regulation between two opposite sides template 7 according to plate-girder width requirement when side template 7 is installed, make A type of precast plate girder pedestal, can prefabricated different in width plate-girder, without make the different side bar of two or more bottom width, Central sill pedestal, can so save Liang Chang floor space, reduce beam making bench quantity, reduce construction cost;Side template 7 is using tiltedly Support bar 6 coordinate steady pin 8 be supported fixation, without with to pull bar to side template 7 top on carry out to draw fix, so conveniently Concreting, vibrate and wipe one's face;Bolt 5 used in fixed bolster plate 7 (including nut, screw rod, pad), inclined support bar 6 make It is easy to process, can turnaround cycle use, economize on resources, cost is low, while installing/dismounting speed is fast, construction safety;Under steel plate 2 Side, the longitudinal both sides of pedestal 1 set the angle clip 3 that the angle steel of several and surrounding bound edge on steel plate 2 and pedestal 1 is welded, and so do Benefit be to prevent plate-girder side template 7 from installing and occurring during later stage concreting the downwarp of steel plate 2;Steel plate 2 and side template 7 it Between be put into sealant tape benefit be when preventing concreting generation spillage phenomenon.
The armored concrete of pedestal 1 can be further arranged to strength grade for C25 steel in step one described in the present embodiment Reinforced concrete.
Described in the present embodiment in step one the angle steel specification of the surrounding bound edge of pedestal 1 can be further arranged to hem width 56mm~ 70mm, side thickness is 8mm.
Step 2 light plate described in the present embodiment 2 uses specification to be further arranged to Q235 thickness for 5mm~6mm's Steel plate.
The diameter of the bolt hole of step 2 split shed described in the present embodiment 4 can be further arranged to it in 24mm and 26mm One.
The specification of angle clip 3 can be further arranged to hem width 56mm~70mm in step 4 described in the present embodiment, and side is thick 8mm。
Bolt 5, inclined support bar 6 and steady pin 8 can further be set in step 5 described in the present embodiment and step 6 Made for tool steel, wherein the diameter of bolt 5 can be further arranged to one of 22mm and 24mm.
Side template 7 can be further arranged to be made of steel plate in step 5 described in the present embodiment.
The spacing of adjacent apertures bolt hole 4 on the every side in the longitudinal direction of step 2 light plate described in the present embodiment 2 can be further It is set to 1000mm~2000mm.
Spacing described in the present embodiment in step 4 between adjacent angle clip 3 of the longitudinal direction of pedestal 1 per side can further be set It is set to 800mm~1200mm.
To the further restriction of construction material specification, the further restriction to the diameter of opening bolt hole 4, right in the present embodiment The longitudinal direction of steel plate 2 per side on the further restriction of spacing of adjacent apertures bolt hole 4 and adjacent short per side to the longitudinal direction of pedestal 1 Spacing between angle steel 3 is further limited, and advantage of this is that pass through the preferred of these materials and construction technology so that this hair Bright methods described can produce the plate-girder of satisfactory different in width specification, the need for meeting construction.

Claims (10)

1. a kind of precast plate girder pedestal preparation method, comprises the following steps:
Step one:The armored concrete of pedestal (1) is poured according to the requirement of design drawing, when pouring, on the top four of pedestal (1) All pre-buried angle steel bound edges;
Step 2:According to the plate-girder width requirement of design drawing, processing and fabricating steel plate (2), and on longitudinal both sides pair of steel plate (2) Several split bolt holes (4) should be cut;
Step 3:After the concrete strength of pedestal (1) reaches more than 90%, with crane hanging component steel plate (2) and platform is placed on On seat (1), the position of steel plate (2) is adjusted, the angle steel of surrounding bound edge on steel plate (2) and pedestal (1) is welded;
Step 4:In steel plate (2) lower section, the longitudinal both sides of pedestal (1), several and surrounding bag on steel plate (2) and pedestal (1) are set The angle clip (3) of the angle steel welding on side;
Step 5:With crane, both sides lift side template (7) above steel plate (2), according to the plate-girder width requirement of design drawing, Lateral separation position of the side template (7) on steel plate (2) is adjusted, sealant tape is put between steel plate (2) and side template (7), Then side template (7) is fixed with steel plate (2) with bolt (5) at split bolt hole (4) place;
Step 6:Finally steady pin (8) is coordinated to tense and support side template (7) with inclined support bar (6).
2. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:Pedestal in the step one (1) armored concrete is that strength grade is C25 armored concrete.
3. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:Pedestal in the step one (1) the angle steel specification of surrounding bound edge is hem width 56mm~70mm, and side thickness is 8mm.
4. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:The step 2 light plate (2) steel plate that specification is 5mm~6mm for Q235 thickness is used.
5. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:The step 2 split shed spiral shell One of a diameter of 24mm and 26mm of keyhole (4).
6. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:Angle clip in the step 4 (3) specification is hem width 56mm~70mm, side thickness 8mm.
7. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:The step 5 and step 6 Middle bolt (5), inclined support bar (6) and steady pin (8) are that tool steel makes, the wherein a diameter of 22mm and 24mm of bolt (5) One of.
8. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:Side template in the step 5 (7) it is made of steel plate.
9. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:The step 2 light plate (2) spacing of the adjacent apertures bolt hole (4) on the every side in longitudinal direction is 1000mm~2000mm.
10. a kind of precast plate girder pedestal preparation method according to claim 1, it is characterised in that:Pedestal in the step 4 (1) spacing between adjacent angle clip (3) of the longitudinal direction per side is 800mm~1200mm.
CN201710323617.0A 2017-05-10 2017-05-10 A kind of precast plate girder pedestal production method Active CN107053440B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710323617.0A CN107053440B (en) 2017-05-10 2017-05-10 A kind of precast plate girder pedestal production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710323617.0A CN107053440B (en) 2017-05-10 2017-05-10 A kind of precast plate girder pedestal production method

Publications (2)

Publication Number Publication Date
CN107053440A true CN107053440A (en) 2017-08-18
CN107053440B CN107053440B (en) 2019-03-15

Family

ID=59597187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710323617.0A Active CN107053440B (en) 2017-05-10 2017-05-10 A kind of precast plate girder pedestal production method

Country Status (1)

Country Link
CN (1) CN107053440B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587519A (en) * 2017-09-18 2018-01-16 中国三冶集团有限公司 A kind of beam prefabricated field pedestal structure of T and construction method
CN110788984A (en) * 2019-10-28 2020-02-14 中建三局基础设施建设投资有限公司 Precast beam making pedestal side width device and implementation method thereof
CN111827577A (en) * 2020-06-29 2020-10-27 中铁广州工程局集团有限公司 Construction method of supporting beam
CN113172754A (en) * 2021-04-22 2021-07-27 中电建十一局工程有限公司 Method for manufacturing prefabricated pedestal of pipe gallery
CN113756496A (en) * 2021-09-17 2021-12-07 中建四局第一建设有限公司 Structure and construction method of small-space floor bearing plate under roof reverse-procedure construction
CN115091607A (en) * 2022-07-14 2022-09-23 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2874349A1 (en) * 2004-08-20 2006-02-24 Jean Paul Martinez Pre-fabricated mortar and concrete product e.g. reinforced concrete beam, fabricating device for e.g. building industry, has two beams, where each beam has three pairs of chisels to constitute lift table vertically moved by two jacks
CN201728733U (en) * 2010-07-20 2011-02-02 浙江天晟梁板有限公司 Special forming mold for bridge precast beam slabs
CN202934696U (en) * 2012-11-29 2013-05-15 甘肃路桥建设集团有限公司 Sizing jack horse
CN103231446A (en) * 2013-05-02 2013-08-07 李和光 Factory production device for inner wallboards of buildings
CN104260199A (en) * 2014-09-26 2015-01-07 中铁二十局集团第五工程有限公司 Prefabricating construction process for corrugated steel web prestressed concrete I-shaped beam
CN105196405A (en) * 2015-10-21 2015-12-30 宁夏路桥工程股份有限公司 Supporting equipment for bridge precast hollow slab lateral mould and using method of supporting equipment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2874349A1 (en) * 2004-08-20 2006-02-24 Jean Paul Martinez Pre-fabricated mortar and concrete product e.g. reinforced concrete beam, fabricating device for e.g. building industry, has two beams, where each beam has three pairs of chisels to constitute lift table vertically moved by two jacks
CN201728733U (en) * 2010-07-20 2011-02-02 浙江天晟梁板有限公司 Special forming mold for bridge precast beam slabs
CN202934696U (en) * 2012-11-29 2013-05-15 甘肃路桥建设集团有限公司 Sizing jack horse
CN103231446A (en) * 2013-05-02 2013-08-07 李和光 Factory production device for inner wallboards of buildings
CN104260199A (en) * 2014-09-26 2015-01-07 中铁二十局集团第五工程有限公司 Prefabricating construction process for corrugated steel web prestressed concrete I-shaped beam
CN105196405A (en) * 2015-10-21 2015-12-30 宁夏路桥工程股份有限公司 Supporting equipment for bridge precast hollow slab lateral mould and using method of supporting equipment

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587519A (en) * 2017-09-18 2018-01-16 中国三冶集团有限公司 A kind of beam prefabricated field pedestal structure of T and construction method
CN110788984A (en) * 2019-10-28 2020-02-14 中建三局基础设施建设投资有限公司 Precast beam making pedestal side width device and implementation method thereof
CN111827577A (en) * 2020-06-29 2020-10-27 中铁广州工程局集团有限公司 Construction method of supporting beam
CN111827577B (en) * 2020-06-29 2022-04-26 中铁广州工程局集团有限公司 Construction method of supporting beam
CN113172754A (en) * 2021-04-22 2021-07-27 中电建十一局工程有限公司 Method for manufacturing prefabricated pedestal of pipe gallery
CN113756496A (en) * 2021-09-17 2021-12-07 中建四局第一建设有限公司 Structure and construction method of small-space floor bearing plate under roof reverse-procedure construction
CN113756496B (en) * 2021-09-17 2022-08-19 中建四局第一建设有限公司 Structure and construction method of small-space floor bearing plate under roof reverse-procedure construction
CN115091607A (en) * 2022-07-14 2022-09-23 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal
CN115091607B (en) * 2022-07-14 2024-01-16 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal

Also Published As

Publication number Publication date
CN107053440B (en) 2019-03-15

Similar Documents

Publication Publication Date Title
CN107053440B (en) A kind of precast plate girder pedestal production method
CN107217839A (en) Cast-in-situ concrete beam plate form bracing system and its construction method
CN101041974A (en) Structure conversion layer type steel concrete girder mould suspension construction method
CN211447708U (en) Super high-rise building construction elevator feeding platform support system that encorbelments
CN105696747A (en) Construction method for aerial large-span reinforced concrete beam
CN101391438A (en) Whole dismounting and whole mounting integral slippage large formwork for thin wall U-shaped beam
CN204023411U (en) Novel assembled bracket bracket construction equipment
CN103276895B (en) Die supporting method of reversed-cone-shaped column cap die
CN206942131U (en) Cast-in-situ concrete beam plate form bracing system
CN106351445A (en) Bracing reinforcement system and installation construction method of steel reinforced concrete inclined shear wall form assembly
CN108277977A (en) A kind of column mould reinforcement system and preparation method thereof
CN114770706B (en) Light T-beam prefabrication equipment and prefabrication installation construction method
CN209817430U (en) Template supporting structure of tower crane reserved hole
CN110005200B (en) Construction process for concrete pouring compaction of horizontal hidden beam
CN205894670U (en) Concrete connects template structure of stubble construction between floor
CN206625553U (en) For pouring the formwork bracing system of high-low bay structure simultaneously
CN205935419U (en) Cover to reinforcement bracket of big cross -section roof beam
CN209990143U (en) Floor template support system of suspension type
CN206448272U (en) Roadbed side slope arched framework one-time-shaped mould
CN107882243B (en) A kind of cassette ceiling and construction method of concrete-filled rectangular steel tube waffle beam structure
CN203361642U (en) Assembled-structure cast-in-place stair steel molding plate
CN109853928A (en) Set up the interior posture workbench and its erection method of elevator shear wall formwork for placing
CN203856482U (en) Whole truss template device for arc top arch
CN108222503A (en) A kind of combined large pier stud steel form
CN210614974U (en) Multilayer reinforcing bar net high accuracy processing bed-jig of adjustable type of size

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant