CN106988758A - One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction - Google Patents
One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction Download PDFInfo
- Publication number
- CN106988758A CN106988758A CN201710318576.6A CN201710318576A CN106988758A CN 106988758 A CN106988758 A CN 106988758A CN 201710318576 A CN201710318576 A CN 201710318576A CN 106988758 A CN106988758 A CN 106988758A
- Authority
- CN
- China
- Prior art keywords
- solution cavity
- construction
- concrete
- scale vertical
- vertical solution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D13/00—Large underground chambers; Methods or apparatus for making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F16/00—Drainage
- E21F16/02—Drainage of tunnels
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Abstract
It is used to pass through large-scale vertical solution cavity group method for tunnel construction the invention discloses one kind, to large-scale vertical solution cavity group, the technical measures of water passage are reserved using fill concrete, by carrying out steel arch-shelf and pipe canopy strengthening supporting to solution cavity section, crossed at solution cavity section tunnel bottom using reinforced concrete beam and plate, greatly improve foundation bearing capacity, to vertical solution cavity group's circumferential crack and arch solution cavity pre-buried municipal bellows before fill concrete, and ejectment is to water passage, eliminate the hidden danger of the high pressure karst water caused by long-time ponding, safety ensured construction period and runed in the future during.The inventive method easy construction, construction period is greatly shortened, and improves karst cave treatment filling effect, improves the security of subsequent construction, and pouring material, construction method are simple and convenient without particular/special requirement, and field conduct achieves good using effect.
Description
Technical field
It is used to pass through large-scale vertical solution cavity group method for tunnel construction the present invention relates to one kind, belongs to a kind of large-scale vertical solution cavity
The Karst Tunnel technical field of group's processing.
Background technology
For the large-scale vertical solution cavity group of Tunnel Passing, scale is big, solution cavity of the Growth Depth more than 30m, and general use is filled
Scheme, is passed through using roadbed form.Hole slag is completely filled out using conventional or using karst cavity around M7.5 mortar flag stones backfill tunnel,
Material usage is huge and can not be transported to working face, and mechanical usage amount is big, and the construction period can not be, it is expected that construction cost and safety wind
Danger is greatly, it is impossible to ensures the completion time of project, considerably increases the difficulty of in-situ processing.
The content of the invention
The technical problem to be solved in the present invention is:There is provided a kind of for passing through large-scale vertical solution cavity group method for tunnel construction,
In large-scale vertical solution cavity group constructing tunnel is punished, using small-sized machine, the equipment such as concrete pump can just be carried out to solution cavity
Processing, the manpower and materials consumption for overcoming prior art to exist is big, and the treatment procedure time is long, and difficulty of construction is big, construction risk
High deficiency, improves Karst Tunnel construction efficiency, reduces cost, reduces security risk.
The technical scheme that the present invention takes is:One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction, and its is specific
Implementation steps are as follows:
Step 1: the rockfall locally lain in solution cavity palisades is removed, and using injection C20 concrete protections.Perpendicular
Section is digged as operation path to solution cavity mouth, and the later stage is used as inspection cavern.
Step 2: large-scale vertical solution cavity mine massively to backfill based on treatment measures, at the vertical molten chamber of face about 48m
More than platform backfilled using C20 concretings, reserve water passage, before concreting periphery palisades are applied with anchor pole insertion
Rock mass, the globality of increase fill concrete and solution cavity wall.
Step 3: being digged in solution cavity face to V grades of surrounding rock supporting type sections and setting up I20a bow members, apply φ 89 and manage
Canopy adds per-fore pouring liquid with small pipe advance support.
Step 4: after 25 meters of excavation supporting construction of getting out of a predicament or an embarrassing situation, returning and doing reinforced concrete to be excavated to tunnel bottom application in solution cavity section
Native plate-girder.
Step 5: arch wall lining cutting is applied, to using C20 concrete backfills in the range of 3m outside lining cutting contour line and rearward blowing
Sand plus waste rubber tire do cushion, backfill height to vault above 2m.
It is preferred that, it is above-mentioned to vertical solution cavity group's circumferential crack and arch solution cavity pre-buried municipal ripple before fill concrete
Pipe, and ejectment is to water passage.
The present invention reserves the technical measures of water passage using fill concrete, by solution cavity section strengthening supporting, molten
Hole section tunnel bottom is crossed over using reinforced concrete beam and plate, reaches quick, the safe purpose to Karst Tunnel processing.
Beneficial effects of the present invention:Compared with prior art, effect of the invention is as follows:
1)Only need small-sized machine, the equipment such as concrete pump can just handle solution cavity, later stage constructing tunnel is improved
Efficiency.
2)Hole slag is completely filled out relative to conventional, water passage is reserved using fill concrete, short construction period saves material,
Improve operating efficiency and foundation bearing capacity requirement can be reached.
3)Using plate-girder Oil pipeline, the security of karst cave treatment is improved.To the pre-buried municipal ripple of the molten chamber of circumferential crack and arch
Line pipe draws bat to water passage, eliminates the hidden danger of the high pressure karst water caused by long-time ponding, makes construction period and put into the future
Operation uses and obtains effective safety assurance.
4)Blown sand behind in vault fill concrete plus waste rubber tire does cushion, can greatly reduced at the top of solution cavity
Destruction of the falling rocks to two lining structures.
Brief description of the drawings
Fig. 1 is the solution cavity backfill schematic diagram of the present invention;
Fig. 2 is the plate girder of reinforced concrete structural representation of the present invention;
It is designated in figure:1st, surface protection concrete, 2, anchor pole, 3, fill concrete, 4, municipal bellows, 5, armored concrete
Plate-girder, 6, steel arch-shelf strengthening supporting and middle barrel vault advanced support, 7, concrete, 8, waste rubber tire, 9, water passage.
Embodiment
The present invention is described further with reference to specific embodiment.
One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction, and its specific implementation step is as follows:
Step 1: the rockfall locally lain in solution cavity palisades is removed, and using injection C20 surface protections concrete 1
Protected, dig section as operation path in vertical solution cavity mouth, the later stage is used as inspection cavern.
Step 2: large-scale vertical solution cavity mine massively to backfill based on treatment measures, at the vertical molten chamber of face about 48m
More than platform backfill is poured using the progress of C20 fill concretes 3, reserve water passage 9, fill concrete 3 pours preceding to periphery
Palisades apply the insertion rock mass of anchor pole 2, the globality of increase fill concrete 3 and solution cavity wall.
Step 3: being digged in solution cavity face to V grades of surrounding rock supporting type sections and setting up I20a steel arch-shelfs, φ 89 is applied
Pipe canopy adds per-fore pouring liquid with small pipe to carry out steel arch-shelf and middle pipe canopy strengthening supporting 6.
Step 4: after 25 meters of excavation supporting construction of getting out of a predicament or an embarrassing situation, returning and doing reinforced concrete to be excavated to tunnel bottom application in solution cavity section
Native plate-girder 5.
Step 5: arch wall lining cutting is applied, to being backfilled in the range of 3m outside lining cutting contour line using C20 concrete sevens and rearward
Blow sand plus waste rubber tire 8 does cushion, backfill height to vault above 2m.
Further, it is above-mentioned to vertical solution cavity group's circumferential crack and arch solution cavity pre-buried municipal ripple before fill concrete 3
Line pipe 4, and ejectment is to water passage 9.
The present invention reserves the technical measures of water passage using fill concrete, by solution cavity section strengthening supporting, molten
Hole section tunnel bottom is crossed over using reinforced concrete beam and plate, reaches quick, the safe purpose to Karst Tunnel processing.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any
Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained
Cover within protection scope of the present invention, therefore, protection scope of the present invention should be based on the protection scope of the described claims.
Claims (2)
1. one kind is used to pass through large-scale vertical solution cavity group method for tunnel construction, it is characterised in that:Construction procedure is:Step 1: right
The rockfall that solution cavity palisades are locally lain in is removed, and protects concrete using jeting surface(1)Protected, vertical
Solution cavity mouth digs section as operation path, and the later stage is used as inspection cavern;Step 2: large-scale vertical solution cavity mines massively what is backfilled
More than platform fill concrete is used at treatment measures, molten chamber 48m vertical to face(3)The mode poured is backfilled, and
Reserved water passage(9), fill concrete(3)Anchor pole is applied to periphery palisades before pouring(2)Embedded rock mass, increase backfill coagulation
Soil(3)With the integral firmness of solution cavity wall;Step 3: digging to V grades of surrounding rock supporting type sections and setting up in solution cavity face
I-steel bow member, applies pipe canopy plus per-fore pouring liquid with small pipe advance support(6);Step 4: excavation supporting of getting out of a predicament or an embarrassing situation is constructed 25 meters
Afterwards, return and do plate girder of reinforced concrete to be excavated to tunnel bottom application in solution cavity section(5);Step 5: arch wall lining cutting is applied, to lining cutting
Concrete is used in the range of the outer 3m of contour line(7)Backfill and rearward blow sand plus waste rubber tire(8)Cushion is done, backfill is high
Spend to vault above 2m.
2. it is according to claim 1 a kind of for passing through large-scale vertical solution cavity group method for tunnel construction, it is characterised in that:Institute
State in step 2, to vertical solution cavity group's circumferential crack and arch solution cavity in fill concrete(3)Preceding pre-buried municipal bellows(4),
And ejectment is to water passage(9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710318576.6A CN106988758B (en) | 2017-05-08 | 2017-05-08 | Construction method for crossing large-scale vertical karst cave group tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710318576.6A CN106988758B (en) | 2017-05-08 | 2017-05-08 | Construction method for crossing large-scale vertical karst cave group tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106988758A true CN106988758A (en) | 2017-07-28 |
CN106988758B CN106988758B (en) | 2023-09-01 |
Family
ID=59417618
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710318576.6A Active CN106988758B (en) | 2017-05-08 | 2017-05-08 | Construction method for crossing large-scale vertical karst cave group tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106988758B (en) |
Cited By (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952766A (en) * | 2018-07-25 | 2018-12-07 | 广西长长路桥建设有限公司 | The construction method of Tunnel Passing karst location punishment |
CN109538216A (en) * | 2018-12-21 | 2019-03-29 | 中铁二十五局集团第五工程有限公司 | Pass through mined out and subsidence area constructing tunnel technique |
CN109667262A (en) * | 2019-02-25 | 2019-04-23 | 中国电建集团贵阳勘测设计研究院有限公司 | A kind of karst sinkhole plugging structure and its construction method |
CN110656955A (en) * | 2019-11-06 | 2020-01-07 | 四川省交通勘察设计研究院有限公司 | Tunnel structure penetrating through karst channel and method for tunnel penetrating through karst channel |
CN111119951A (en) * | 2019-12-27 | 2020-05-08 | 中铁十六局集团第一工程有限公司 | Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area |
CN111119929A (en) * | 2019-12-29 | 2020-05-08 | 中铁二院工程集团有限责任公司 | Lattice type rockfall prevention structure of large-scale ultrahigh karst cavity tunnel and construction method |
CN111502748A (en) * | 2020-04-21 | 2020-08-07 | 中铁二院工程集团有限责任公司 | Construction method for backfilling foundation of railway crossing giant karst cave |
CN111706362A (en) * | 2020-07-02 | 2020-09-25 | 天津大学 | Karst cave treatment method for tunnel construction |
CN111878086A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Peripheral construction channel arrangement method based on karst cave underground river environment tunnel construction |
CN111878089A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction |
CN111878112A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section concrete spraying construction method based on karst cave underground river environment tunnel construction |
CN111878096A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave backfilling method based on karst cave underground river environment tunnel construction |
CN111878088A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction |
CN111878093A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment |
CN111878090A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction |
CN111878092A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section full-filling ventilation method based on karst cave underground river environment tunnel construction |
CN111894603A (en) * | 2020-07-30 | 2020-11-06 | 中铁五局集团有限公司 | Tunnel construction method based on karst cave underground river environment |
CN112065439A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam bell mouth friction loss testing method based on karst cave underground river environment |
CN112065442A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam closure section construction method based on karst cave underground river environment tunnel construction |
CN112065440A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction |
CN112065441A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction |
CN112065436A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction |
CN112065437A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction |
CN112065438A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam third section construction method based on karst cave underground river environment tunnel construction |
CN112065445A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction |
CN112065443A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam second section construction method based on karst cave underground river environment tunnel construction |
CN112065444A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam construction method based on karst cave underground river environment tunnel construction |
CN112095438A (en) * | 2020-08-19 | 2020-12-18 | 中铁五局集团有限公司 | Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment |
CN112554886A (en) * | 2020-07-30 | 2021-03-26 | 中铁五局集团有限公司 | Tunnel main tunnel area construction method based on karst cave underground river environment tunnel construction |
CN113503166A (en) * | 2021-03-31 | 2021-10-15 | 广东冠粤路桥有限公司 | Reinforced disposal structure for karst cave at middle lower part of tunnel and construction method thereof |
CN113669108A (en) * | 2021-06-16 | 2021-11-19 | 广西交通设计集团有限公司 | Comprehensive drainage system for traversing complex karst cave group tunnel |
CN111119938B (en) * | 2019-12-30 | 2022-02-11 | 中交路桥华南工程有限公司 | Method for processing karst cave at upper part of tunnel |
CN116378677A (en) * | 2023-05-29 | 2023-07-04 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method and tunnel structure of full-span filling karst cave section |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004353175A (en) * | 2003-05-27 | 2004-12-16 | Kankyo Zokei:Kk | Wastewater passage for tunnel, drainage system, and its construction method |
CN101368472A (en) * | 2008-10-09 | 2009-02-18 | 中国水利水电第十四工程局有限公司 | Method for accurately positioning and orienting drill hole of top arch |
CN101922300A (en) * | 2010-08-30 | 2010-12-22 | 中铁第四勘察设计院集团有限公司 | Large supporting and protecting system of tunnel in hollow solution cavity |
CN102758642A (en) * | 2012-07-16 | 2012-10-31 | 中铁隧道集团有限公司 | Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof |
CN103244128A (en) * | 2013-05-22 | 2013-08-14 | 汇通路桥建设集团有限公司 | Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods |
CN106194196A (en) * | 2016-08-22 | 2016-12-07 | 北京市政路桥股份有限公司 | A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method |
-
2017
- 2017-05-08 CN CN201710318576.6A patent/CN106988758B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004353175A (en) * | 2003-05-27 | 2004-12-16 | Kankyo Zokei:Kk | Wastewater passage for tunnel, drainage system, and its construction method |
CN101368472A (en) * | 2008-10-09 | 2009-02-18 | 中国水利水电第十四工程局有限公司 | Method for accurately positioning and orienting drill hole of top arch |
CN101922300A (en) * | 2010-08-30 | 2010-12-22 | 中铁第四勘察设计院集团有限公司 | Large supporting and protecting system of tunnel in hollow solution cavity |
CN102758642A (en) * | 2012-07-16 | 2012-10-31 | 中铁隧道集团有限公司 | Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof |
CN103244128A (en) * | 2013-05-22 | 2013-08-14 | 汇通路桥建设集团有限公司 | Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods |
CN106194196A (en) * | 2016-08-22 | 2016-12-07 | 北京市政路桥股份有限公司 | A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method |
Non-Patent Citations (1)
Title |
---|
何江等: "溶洞地区的隧道施工技术" * |
Cited By (37)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952766A (en) * | 2018-07-25 | 2018-12-07 | 广西长长路桥建设有限公司 | The construction method of Tunnel Passing karst location punishment |
CN109538216A (en) * | 2018-12-21 | 2019-03-29 | 中铁二十五局集团第五工程有限公司 | Pass through mined out and subsidence area constructing tunnel technique |
CN109667262B (en) * | 2019-02-25 | 2024-03-01 | 中国电建集团贵阳勘测设计研究院有限公司 | Karst water falling hole plugging structure and construction method thereof |
CN109667262A (en) * | 2019-02-25 | 2019-04-23 | 中国电建集团贵阳勘测设计研究院有限公司 | A kind of karst sinkhole plugging structure and its construction method |
CN110656955A (en) * | 2019-11-06 | 2020-01-07 | 四川省交通勘察设计研究院有限公司 | Tunnel structure penetrating through karst channel and method for tunnel penetrating through karst channel |
CN111119951A (en) * | 2019-12-27 | 2020-05-08 | 中铁十六局集团第一工程有限公司 | Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area |
CN111119929A (en) * | 2019-12-29 | 2020-05-08 | 中铁二院工程集团有限责任公司 | Lattice type rockfall prevention structure of large-scale ultrahigh karst cavity tunnel and construction method |
CN111119938B (en) * | 2019-12-30 | 2022-02-11 | 中交路桥华南工程有限公司 | Method for processing karst cave at upper part of tunnel |
CN111502748A (en) * | 2020-04-21 | 2020-08-07 | 中铁二院工程集团有限责任公司 | Construction method for backfilling foundation of railway crossing giant karst cave |
CN111502748B (en) * | 2020-04-21 | 2021-08-31 | 中铁二院工程集团有限责任公司 | Construction method for backfilling foundation of railway crossing giant karst cave |
CN111706362A (en) * | 2020-07-02 | 2020-09-25 | 天津大学 | Karst cave treatment method for tunnel construction |
CN111878112A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section concrete spraying construction method based on karst cave underground river environment tunnel construction |
CN111878088A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction |
CN111878093A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment |
CN111878090A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction |
CN111878092A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section full-filling ventilation method based on karst cave underground river environment tunnel construction |
CN111894603A (en) * | 2020-07-30 | 2020-11-06 | 中铁五局集团有限公司 | Tunnel construction method based on karst cave underground river environment |
CN111878096A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave backfilling method based on karst cave underground river environment tunnel construction |
CN112554886A (en) * | 2020-07-30 | 2021-03-26 | 中铁五局集团有限公司 | Tunnel main tunnel area construction method based on karst cave underground river environment tunnel construction |
CN111878089A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction |
CN111878086A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Peripheral construction channel arrangement method based on karst cave underground river environment tunnel construction |
CN112065442A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam closure section construction method based on karst cave underground river environment tunnel construction |
CN112065436A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction |
CN112065438A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam third section construction method based on karst cave underground river environment tunnel construction |
CN112065445A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction |
CN112065443A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam second section construction method based on karst cave underground river environment tunnel construction |
CN112065444A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam construction method based on karst cave underground river environment tunnel construction |
CN112095438A (en) * | 2020-08-19 | 2020-12-18 | 中铁五局集团有限公司 | Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment |
CN112065437A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction |
CN112065441A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction |
CN112065439A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam bell mouth friction loss testing method based on karst cave underground river environment |
CN112065440A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction |
CN113503166A (en) * | 2021-03-31 | 2021-10-15 | 广东冠粤路桥有限公司 | Reinforced disposal structure for karst cave at middle lower part of tunnel and construction method thereof |
CN113669108A (en) * | 2021-06-16 | 2021-11-19 | 广西交通设计集团有限公司 | Comprehensive drainage system for traversing complex karst cave group tunnel |
CN113669108B (en) * | 2021-06-16 | 2024-01-30 | 广西交通设计集团有限公司 | Comprehensive drainage system penetrating complex karst cave group tunnel |
CN116378677A (en) * | 2023-05-29 | 2023-07-04 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method and tunnel structure of full-span filling karst cave section |
CN116378677B (en) * | 2023-05-29 | 2023-08-29 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method and tunnel structure of full-span filling karst cave section |
Also Published As
Publication number | Publication date |
---|---|
CN106988758B (en) | 2023-09-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106988758A (en) | One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction | |
CN106499413B (en) | A kind of Shallow-buried section tunnel stratum consolidation construction method | |
CN104500077B (en) | A kind of shallow-depth-excavation tunnel passes through cottage area construction method | |
CN106761778B (en) | A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground | |
CN102134998B (en) | Construction method for wind-blown sand tunnel | |
CN103696784B (en) | Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure | |
CN102061923B (en) | Tunnel construction method capable of protecting existing building | |
CN103321653B (en) | Method of treating lining after collapse of underground cavern crown | |
CN106703814A (en) | Mined metro station hole pile construction method | |
CN105672348A (en) | Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region | |
CN104564128A (en) | Deformation monitoring method for shallow-buried excavation tunnel construction | |
CN111706362A (en) | Karst cave treatment method for tunnel construction | |
CN107965325B (en) | A kind of small interval shallow tunnel just branch arch replacement construction method | |
CN102758458B (en) | Underground continuous wall repairing method | |
CN109778869A (en) | Foundation ditch construction method | |
CN106121675A (en) | Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch | |
CN110107310A (en) | A kind of construction method at tunnel slope hole | |
CN103899318A (en) | Medium ground tunnel milling excavating and mating mechanized construction method | |
CN107503754A (en) | A kind of construction method of VI grade of country rock rich water Shallow tunnel with large cross-section | |
CN113153308B (en) | Construction method for collapse section of double-arch tunnel | |
CN206707721U (en) | A kind of tunnel structure for passing through large-scale vertical solution cavity group | |
CN109162298A (en) | A kind of construction method of hydrous fluids pipe gallery | |
CN107401161A (en) | High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements | |
CN107489433A (en) | A kind of tunnel CRD engineering methods anti-leakage structure and Antiseep method | |
CN110284885A (en) | Shield inspection-pit construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |