CN106988758A - One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction - Google Patents

One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction Download PDF

Info

Publication number
CN106988758A
CN106988758A CN201710318576.6A CN201710318576A CN106988758A CN 106988758 A CN106988758 A CN 106988758A CN 201710318576 A CN201710318576 A CN 201710318576A CN 106988758 A CN106988758 A CN 106988758A
Authority
CN
China
Prior art keywords
solution cavity
construction
concrete
scale vertical
vertical solution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710318576.6A
Other languages
Chinese (zh)
Other versions
CN106988758B (en
Inventor
杨炎川
陈金
张登林
吴秀雄
魏毅
宋佳
蒋志权
解振乙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority to CN201710318576.6A priority Critical patent/CN106988758B/en
Publication of CN106988758A publication Critical patent/CN106988758A/en
Application granted granted Critical
Publication of CN106988758B publication Critical patent/CN106988758B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

It is used to pass through large-scale vertical solution cavity group method for tunnel construction the invention discloses one kind, to large-scale vertical solution cavity group, the technical measures of water passage are reserved using fill concrete, by carrying out steel arch-shelf and pipe canopy strengthening supporting to solution cavity section, crossed at solution cavity section tunnel bottom using reinforced concrete beam and plate, greatly improve foundation bearing capacity, to vertical solution cavity group's circumferential crack and arch solution cavity pre-buried municipal bellows before fill concrete, and ejectment is to water passage, eliminate the hidden danger of the high pressure karst water caused by long-time ponding, safety ensured construction period and runed in the future during.The inventive method easy construction, construction period is greatly shortened, and improves karst cave treatment filling effect, improves the security of subsequent construction, and pouring material, construction method are simple and convenient without particular/special requirement, and field conduct achieves good using effect.

Description

One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction
Technical field
It is used to pass through large-scale vertical solution cavity group method for tunnel construction the present invention relates to one kind, belongs to a kind of large-scale vertical solution cavity The Karst Tunnel technical field of group's processing.
Background technology
For the large-scale vertical solution cavity group of Tunnel Passing, scale is big, solution cavity of the Growth Depth more than 30m, and general use is filled Scheme, is passed through using roadbed form.Hole slag is completely filled out using conventional or using karst cavity around M7.5 mortar flag stones backfill tunnel, Material usage is huge and can not be transported to working face, and mechanical usage amount is big, and the construction period can not be, it is expected that construction cost and safety wind Danger is greatly, it is impossible to ensures the completion time of project, considerably increases the difficulty of in-situ processing.
The content of the invention
The technical problem to be solved in the present invention is:There is provided a kind of for passing through large-scale vertical solution cavity group method for tunnel construction, In large-scale vertical solution cavity group constructing tunnel is punished, using small-sized machine, the equipment such as concrete pump can just be carried out to solution cavity Processing, the manpower and materials consumption for overcoming prior art to exist is big, and the treatment procedure time is long, and difficulty of construction is big, construction risk High deficiency, improves Karst Tunnel construction efficiency, reduces cost, reduces security risk.
The technical scheme that the present invention takes is:One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction, and its is specific Implementation steps are as follows:
Step 1: the rockfall locally lain in solution cavity palisades is removed, and using injection C20 concrete protections.Perpendicular Section is digged as operation path to solution cavity mouth, and the later stage is used as inspection cavern.
Step 2: large-scale vertical solution cavity mine massively to backfill based on treatment measures, at the vertical molten chamber of face about 48m More than platform backfilled using C20 concretings, reserve water passage, before concreting periphery palisades are applied with anchor pole insertion Rock mass, the globality of increase fill concrete and solution cavity wall.
Step 3: being digged in solution cavity face to V grades of surrounding rock supporting type sections and setting up I20a bow members, apply φ 89 and manage Canopy adds per-fore pouring liquid with small pipe advance support.
Step 4: after 25 meters of excavation supporting construction of getting out of a predicament or an embarrassing situation, returning and doing reinforced concrete to be excavated to tunnel bottom application in solution cavity section Native plate-girder.
Step 5: arch wall lining cutting is applied, to using C20 concrete backfills in the range of 3m outside lining cutting contour line and rearward blowing Sand plus waste rubber tire do cushion, backfill height to vault above 2m.
It is preferred that, it is above-mentioned to vertical solution cavity group's circumferential crack and arch solution cavity pre-buried municipal ripple before fill concrete Pipe, and ejectment is to water passage.
The present invention reserves the technical measures of water passage using fill concrete, by solution cavity section strengthening supporting, molten Hole section tunnel bottom is crossed over using reinforced concrete beam and plate, reaches quick, the safe purpose to Karst Tunnel processing.
Beneficial effects of the present invention:Compared with prior art, effect of the invention is as follows:
1)Only need small-sized machine, the equipment such as concrete pump can just handle solution cavity, later stage constructing tunnel is improved Efficiency.
2)Hole slag is completely filled out relative to conventional, water passage is reserved using fill concrete, short construction period saves material, Improve operating efficiency and foundation bearing capacity requirement can be reached.
3)Using plate-girder Oil pipeline, the security of karst cave treatment is improved.To the pre-buried municipal ripple of the molten chamber of circumferential crack and arch Line pipe draws bat to water passage, eliminates the hidden danger of the high pressure karst water caused by long-time ponding, makes construction period and put into the future Operation uses and obtains effective safety assurance.
4)Blown sand behind in vault fill concrete plus waste rubber tire does cushion, can greatly reduced at the top of solution cavity Destruction of the falling rocks to two lining structures.
Brief description of the drawings
Fig. 1 is the solution cavity backfill schematic diagram of the present invention;
Fig. 2 is the plate girder of reinforced concrete structural representation of the present invention;
It is designated in figure:1st, surface protection concrete, 2, anchor pole, 3, fill concrete, 4, municipal bellows, 5, armored concrete Plate-girder, 6, steel arch-shelf strengthening supporting and middle barrel vault advanced support, 7, concrete, 8, waste rubber tire, 9, water passage.
Embodiment
The present invention is described further with reference to specific embodiment.
One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction, and its specific implementation step is as follows:
Step 1: the rockfall locally lain in solution cavity palisades is removed, and using injection C20 surface protections concrete 1 Protected, dig section as operation path in vertical solution cavity mouth, the later stage is used as inspection cavern.
Step 2: large-scale vertical solution cavity mine massively to backfill based on treatment measures, at the vertical molten chamber of face about 48m More than platform backfill is poured using the progress of C20 fill concretes 3, reserve water passage 9, fill concrete 3 pours preceding to periphery Palisades apply the insertion rock mass of anchor pole 2, the globality of increase fill concrete 3 and solution cavity wall.
Step 3: being digged in solution cavity face to V grades of surrounding rock supporting type sections and setting up I20a steel arch-shelfs, φ 89 is applied Pipe canopy adds per-fore pouring liquid with small pipe to carry out steel arch-shelf and middle pipe canopy strengthening supporting 6.
Step 4: after 25 meters of excavation supporting construction of getting out of a predicament or an embarrassing situation, returning and doing reinforced concrete to be excavated to tunnel bottom application in solution cavity section Native plate-girder 5.
Step 5: arch wall lining cutting is applied, to being backfilled in the range of 3m outside lining cutting contour line using C20 concrete sevens and rearward Blow sand plus waste rubber tire 8 does cushion, backfill height to vault above 2m.
Further, it is above-mentioned to vertical solution cavity group's circumferential crack and arch solution cavity pre-buried municipal ripple before fill concrete 3 Line pipe 4, and ejectment is to water passage 9.
The present invention reserves the technical measures of water passage using fill concrete, by solution cavity section strengthening supporting, molten Hole section tunnel bottom is crossed over using reinforced concrete beam and plate, reaches quick, the safe purpose to Karst Tunnel processing.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained Cover within protection scope of the present invention, therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (2)

1. one kind is used to pass through large-scale vertical solution cavity group method for tunnel construction, it is characterised in that:Construction procedure is:Step 1: right The rockfall that solution cavity palisades are locally lain in is removed, and protects concrete using jeting surface(1)Protected, vertical Solution cavity mouth digs section as operation path, and the later stage is used as inspection cavern;Step 2: large-scale vertical solution cavity mines massively what is backfilled More than platform fill concrete is used at treatment measures, molten chamber 48m vertical to face(3)The mode poured is backfilled, and Reserved water passage(9), fill concrete(3)Anchor pole is applied to periphery palisades before pouring(2)Embedded rock mass, increase backfill coagulation Soil(3)With the integral firmness of solution cavity wall;Step 3: digging to V grades of surrounding rock supporting type sections and setting up in solution cavity face I-steel bow member, applies pipe canopy plus per-fore pouring liquid with small pipe advance support(6);Step 4: excavation supporting of getting out of a predicament or an embarrassing situation is constructed 25 meters Afterwards, return and do plate girder of reinforced concrete to be excavated to tunnel bottom application in solution cavity section(5);Step 5: arch wall lining cutting is applied, to lining cutting Concrete is used in the range of the outer 3m of contour line(7)Backfill and rearward blow sand plus waste rubber tire(8)Cushion is done, backfill is high Spend to vault above 2m.
2. it is according to claim 1 a kind of for passing through large-scale vertical solution cavity group method for tunnel construction, it is characterised in that:Institute State in step 2, to vertical solution cavity group's circumferential crack and arch solution cavity in fill concrete(3)Preceding pre-buried municipal bellows(4), And ejectment is to water passage(9).
CN201710318576.6A 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel Active CN106988758B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710318576.6A CN106988758B (en) 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710318576.6A CN106988758B (en) 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel

Publications (2)

Publication Number Publication Date
CN106988758A true CN106988758A (en) 2017-07-28
CN106988758B CN106988758B (en) 2023-09-01

Family

ID=59417618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710318576.6A Active CN106988758B (en) 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel

Country Status (1)

Country Link
CN (1) CN106988758B (en)

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952766A (en) * 2018-07-25 2018-12-07 广西长长路桥建设有限公司 The construction method of Tunnel Passing karst location punishment
CN109538216A (en) * 2018-12-21 2019-03-29 中铁二十五局集团第五工程有限公司 Pass through mined out and subsidence area constructing tunnel technique
CN109667262A (en) * 2019-02-25 2019-04-23 中国电建集团贵阳勘测设计研究院有限公司 A kind of karst sinkhole plugging structure and its construction method
CN110656955A (en) * 2019-11-06 2020-01-07 四川省交通勘察设计研究院有限公司 Tunnel structure penetrating through karst channel and method for tunnel penetrating through karst channel
CN111119951A (en) * 2019-12-27 2020-05-08 中铁十六局集团第一工程有限公司 Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area
CN111119929A (en) * 2019-12-29 2020-05-08 中铁二院工程集团有限责任公司 Lattice type rockfall prevention structure of large-scale ultrahigh karst cavity tunnel and construction method
CN111502748A (en) * 2020-04-21 2020-08-07 中铁二院工程集团有限责任公司 Construction method for backfilling foundation of railway crossing giant karst cave
CN111706362A (en) * 2020-07-02 2020-09-25 天津大学 Karst cave treatment method for tunnel construction
CN111878086A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Peripheral construction channel arrangement method based on karst cave underground river environment tunnel construction
CN111878089A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction
CN111878112A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section concrete spraying construction method based on karst cave underground river environment tunnel construction
CN111878096A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave backfilling method based on karst cave underground river environment tunnel construction
CN111878088A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction
CN111878093A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment
CN111878090A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction
CN111878092A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section full-filling ventilation method based on karst cave underground river environment tunnel construction
CN111894603A (en) * 2020-07-30 2020-11-06 中铁五局集团有限公司 Tunnel construction method based on karst cave underground river environment
CN112065439A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam bell mouth friction loss testing method based on karst cave underground river environment
CN112065442A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam closure section construction method based on karst cave underground river environment tunnel construction
CN112065440A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction
CN112065441A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction
CN112065436A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction
CN112065437A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction
CN112065438A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam third section construction method based on karst cave underground river environment tunnel construction
CN112065445A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction
CN112065443A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam second section construction method based on karst cave underground river environment tunnel construction
CN112065444A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam construction method based on karst cave underground river environment tunnel construction
CN112095438A (en) * 2020-08-19 2020-12-18 中铁五局集团有限公司 Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment
CN112554886A (en) * 2020-07-30 2021-03-26 中铁五局集团有限公司 Tunnel main tunnel area construction method based on karst cave underground river environment tunnel construction
CN113503166A (en) * 2021-03-31 2021-10-15 广东冠粤路桥有限公司 Reinforced disposal structure for karst cave at middle lower part of tunnel and construction method thereof
CN113669108A (en) * 2021-06-16 2021-11-19 广西交通设计集团有限公司 Comprehensive drainage system for traversing complex karst cave group tunnel
CN111119938B (en) * 2019-12-30 2022-02-11 中交路桥华南工程有限公司 Method for processing karst cave at upper part of tunnel
CN116378677A (en) * 2023-05-29 2023-07-04 湖南省交通规划勘察设计院有限公司 Tunnel construction method and tunnel structure of full-span filling karst cave section

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004353175A (en) * 2003-05-27 2004-12-16 Kankyo Zokei:Kk Wastewater passage for tunnel, drainage system, and its construction method
CN101368472A (en) * 2008-10-09 2009-02-18 中国水利水电第十四工程局有限公司 Method for accurately positioning and orienting drill hole of top arch
CN101922300A (en) * 2010-08-30 2010-12-22 中铁第四勘察设计院集团有限公司 Large supporting and protecting system of tunnel in hollow solution cavity
CN102758642A (en) * 2012-07-16 2012-10-31 中铁隧道集团有限公司 Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN103244128A (en) * 2013-05-22 2013-08-14 汇通路桥建设集团有限公司 Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
CN106194196A (en) * 2016-08-22 2016-12-07 北京市政路桥股份有限公司 A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004353175A (en) * 2003-05-27 2004-12-16 Kankyo Zokei:Kk Wastewater passage for tunnel, drainage system, and its construction method
CN101368472A (en) * 2008-10-09 2009-02-18 中国水利水电第十四工程局有限公司 Method for accurately positioning and orienting drill hole of top arch
CN101922300A (en) * 2010-08-30 2010-12-22 中铁第四勘察设计院集团有限公司 Large supporting and protecting system of tunnel in hollow solution cavity
CN102758642A (en) * 2012-07-16 2012-10-31 中铁隧道集团有限公司 Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN103244128A (en) * 2013-05-22 2013-08-14 汇通路桥建设集团有限公司 Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
CN106194196A (en) * 2016-08-22 2016-12-07 北京市政路桥股份有限公司 A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
何江等: "溶洞地区的隧道施工技术" *

Cited By (37)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952766A (en) * 2018-07-25 2018-12-07 广西长长路桥建设有限公司 The construction method of Tunnel Passing karst location punishment
CN109538216A (en) * 2018-12-21 2019-03-29 中铁二十五局集团第五工程有限公司 Pass through mined out and subsidence area constructing tunnel technique
CN109667262B (en) * 2019-02-25 2024-03-01 中国电建集团贵阳勘测设计研究院有限公司 Karst water falling hole plugging structure and construction method thereof
CN109667262A (en) * 2019-02-25 2019-04-23 中国电建集团贵阳勘测设计研究院有限公司 A kind of karst sinkhole plugging structure and its construction method
CN110656955A (en) * 2019-11-06 2020-01-07 四川省交通勘察设计研究院有限公司 Tunnel structure penetrating through karst channel and method for tunnel penetrating through karst channel
CN111119951A (en) * 2019-12-27 2020-05-08 中铁十六局集团第一工程有限公司 Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area
CN111119929A (en) * 2019-12-29 2020-05-08 中铁二院工程集团有限责任公司 Lattice type rockfall prevention structure of large-scale ultrahigh karst cavity tunnel and construction method
CN111119938B (en) * 2019-12-30 2022-02-11 中交路桥华南工程有限公司 Method for processing karst cave at upper part of tunnel
CN111502748A (en) * 2020-04-21 2020-08-07 中铁二院工程集团有限责任公司 Construction method for backfilling foundation of railway crossing giant karst cave
CN111502748B (en) * 2020-04-21 2021-08-31 中铁二院工程集团有限责任公司 Construction method for backfilling foundation of railway crossing giant karst cave
CN111706362A (en) * 2020-07-02 2020-09-25 天津大学 Karst cave treatment method for tunnel construction
CN111878112A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section concrete spraying construction method based on karst cave underground river environment tunnel construction
CN111878088A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction
CN111878093A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment
CN111878090A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction
CN111878092A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section full-filling ventilation method based on karst cave underground river environment tunnel construction
CN111894603A (en) * 2020-07-30 2020-11-06 中铁五局集团有限公司 Tunnel construction method based on karst cave underground river environment
CN111878096A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave backfilling method based on karst cave underground river environment tunnel construction
CN112554886A (en) * 2020-07-30 2021-03-26 中铁五局集团有限公司 Tunnel main tunnel area construction method based on karst cave underground river environment tunnel construction
CN111878089A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction
CN111878086A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Peripheral construction channel arrangement method based on karst cave underground river environment tunnel construction
CN112065442A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam closure section construction method based on karst cave underground river environment tunnel construction
CN112065436A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction
CN112065438A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam third section construction method based on karst cave underground river environment tunnel construction
CN112065445A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction
CN112065443A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam second section construction method based on karst cave underground river environment tunnel construction
CN112065444A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam construction method based on karst cave underground river environment tunnel construction
CN112095438A (en) * 2020-08-19 2020-12-18 中铁五局集团有限公司 Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment
CN112065437A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction
CN112065441A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction
CN112065439A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam bell mouth friction loss testing method based on karst cave underground river environment
CN112065440A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction
CN113503166A (en) * 2021-03-31 2021-10-15 广东冠粤路桥有限公司 Reinforced disposal structure for karst cave at middle lower part of tunnel and construction method thereof
CN113669108A (en) * 2021-06-16 2021-11-19 广西交通设计集团有限公司 Comprehensive drainage system for traversing complex karst cave group tunnel
CN113669108B (en) * 2021-06-16 2024-01-30 广西交通设计集团有限公司 Comprehensive drainage system penetrating complex karst cave group tunnel
CN116378677A (en) * 2023-05-29 2023-07-04 湖南省交通规划勘察设计院有限公司 Tunnel construction method and tunnel structure of full-span filling karst cave section
CN116378677B (en) * 2023-05-29 2023-08-29 湖南省交通规划勘察设计院有限公司 Tunnel construction method and tunnel structure of full-span filling karst cave section

Also Published As

Publication number Publication date
CN106988758B (en) 2023-09-01

Similar Documents

Publication Publication Date Title
CN106988758A (en) One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN102134998B (en) Construction method for wind-blown sand tunnel
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN103321653B (en) Method of treating lining after collapse of underground cavern crown
CN106703814A (en) Mined metro station hole pile construction method
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN104564128A (en) Deformation monitoring method for shallow-buried excavation tunnel construction
CN111706362A (en) Karst cave treatment method for tunnel construction
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN102758458B (en) Underground continuous wall repairing method
CN109778869A (en) Foundation ditch construction method
CN106121675A (en) Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch
CN110107310A (en) A kind of construction method at tunnel slope hole
CN103899318A (en) Medium ground tunnel milling excavating and mating mechanized construction method
CN107503754A (en) A kind of construction method of VI grade of country rock rich water Shallow tunnel with large cross-section
CN113153308B (en) Construction method for collapse section of double-arch tunnel
CN206707721U (en) A kind of tunnel structure for passing through large-scale vertical solution cavity group
CN109162298A (en) A kind of construction method of hydrous fluids pipe gallery
CN107401161A (en) High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements
CN107489433A (en) A kind of tunnel CRD engineering methods anti-leakage structure and Antiseep method
CN110284885A (en) Shield inspection-pit construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant