CN112065441A - Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction - Google Patents

Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction Download PDF

Info

Publication number
CN112065441A
CN112065441A CN202010838134.6A CN202010838134A CN112065441A CN 112065441 A CN112065441 A CN 112065441A CN 202010838134 A CN202010838134 A CN 202010838134A CN 112065441 A CN112065441 A CN 112065441A
Authority
CN
China
Prior art keywords
tunnel
karst cave
section
underground river
cave
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010838134.6A
Other languages
Chinese (zh)
Inventor
黄泽
周浩
周晓磊
邹琳
陈国辉
李雅钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Fourth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN202010838134.6A priority Critical patent/CN112065441A/en
Publication of CN112065441A publication Critical patent/CN112065441A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Abstract

A continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction comprises the following steps of S1: excavating a tunnel section A to a penetration karst cave; s2: the underground river is redirected; s3: backfilling the karst cave to the foundation surface of the tunnel; s4: protecting the hole wall and applying a plurality of anchor cables; s5: filling the karst cave and connecting the anchor cable with the backfill body; s6: excavating the backfill body to form a tunnel section B; s7: constructing an abutment at the section A of the tunnel; s8: dividing a first section, a second section, a third section and a closure section; s9: constructing a supporting foundation of the tunnel section A; s10: and constructing continuous beams from the first section to the closure section according to the sequence of the sections. Has the advantages of stability, reliability, high safety and capability of preventing sedimentation.

Description

Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction
Technical Field
The invention mainly relates to a tunnel construction technology in a karst cave underground river environment, in particular to a continuous beam concrete pouring construction method based on tunnel construction in the karst cave underground river environment.
Background
The Yujing mountain tunnel is located in Wexin county of Yunnan province, has the total length of 6306m and is a double-line tunnel. In 2016, 7, 23 days, a cave is detected by drilling a hole in advance on the small-mileage end face of a cross-cave working area, and a huge cave hall and a river are discovered after the cave is revealed. The karst cave is about 230m in transverse length and about 93m in width and is approximately rectangular, the top of the karst cave is in a vault shape, the vertical heights of halls are different from 50 m to 130m, the right side of the karst cave in the line direction is high, and the left side of the karst cave is low; and a river develops at the slope toe at the left side of the karst cave, and the river surface is 5-15 m wide. The tunnel passes through the huge karst cave hall, the two sides of the huge karst cave hall are provided with a tunnel section A, and the tunnel passes through the karst cave hall and is provided with a tunnel section B.
Because the tunnel needs to pass through a huge karst cave hall and the bottom is provided with a river, high risks are brought to early construction and later operation, such as block falling at the top of the karst cave, sinking at the bottom due to the river and the like.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a continuous beam concrete pouring construction method which is stable, reliable, high in safety and capable of preventing settlement and is based on tunnel construction in a karst cave and underground river environment.
In order to solve the technical problems, the invention adopts the following technical scheme:
a continuous beam concrete pouring construction method based on tunnel construction in a karst cave and underground river environment is characterized in that the environment comprises a karst cave and an underground river positioned at the bottom of the karst cave, the tunnel penetrates through the karst cave, tunnels at two ends of the karst cave are tunnel A sections, and the tunnel penetrating through the karst cave is a tunnel B section; the construction method comprises the following steps:
s1: excavating a tunnel section A to a penetration karst cave;
s2: the underground river is diverted so that the underground river does not flow through the karst cave;
s3: backfilling the karst cave until the karst cave is backfilled to the foundation surface of the tunnel;
s4: protecting the cave wall of the karst cave, and uniformly applying a plurality of anchor cables on the cave wall;
s5: filling the karst cave and connecting the anchor cable with the filled backfill body;
s6: excavating the backfill body to form a tunnel section B communicated with the tunnel section A;
s7: constructing abutment, main piers and temporary buttresses on the section A of the tunnel to form abutments arranged at intervals, and ensuring that all the abutments are positioned on the section A of the tunnel;
s8: dividing an area above a pier close to a section B of the tunnel into a first section, dividing two sides of the first section into second sections, dividing the side parts of the two second sections into third sections, dividing a joint section between the two middle third sections, and setting the total length of all the sections as the construction length of the continuous beam;
s9: constructing a supporting foundation of the tunnel section A;
s10: constructing a continuous beam template, installing a prestressed pipeline, pouring concrete, penetrating a prestressed cable, tensioning the prestressed cable and grouting the pipeline according to the sequence of the segments from a first segment to a closure segment, wherein the following sequence is adopted when concrete is poured: the joint of the top surface of the bottom plate and the web is filled from one end to the other end in a layered mode → the concrete at the chamfer of the bottom plate and the web is symmetrically poured from one end to the other end through the web → the insufficient concrete in the middle of the bottom plate is poured from two ends of the central pouring hole of the top plate to the middle → the concrete of the two side webs is symmetrically poured from one end to the other end → the concrete of the top plate is poured from one end to the other end.
As a further improvement of the above technical solution:
in step S1, the lining construction is performed while performing support while excavating.
In step S2, a drainage tunnel is formed in communication with the river upstream so that the river does not flow through the cavern.
And plugging and backfilling the underground river at the downstream of the junction of the drainage tunnel and the underground river.
In step S4, steel fibers are applied to the cave wall and concrete is sprayed.
In step S5, grouting is performed in the gap between the backfill body and the cavern wall to seal the gap.
In step S6, the lining construction is performed while performing support while excavating.
Compared with the prior art, the invention has the advantages that:
the continuous beam concrete pouring construction method based on the karst cave underground river environment tunnel construction comprises the following steps of changing the way of the underground river so that the underground river does not flow through the karst cave and the influence of a water area on the bottom of the karst cave is eliminated; the karst cave is backfilled until the karst cave is filled, which is equivalent to the reconstruction treatment of the karst cave, so that the top of the karst cave is prevented from dropping blocks, and the safety is improved; the backfill body is connected with the cave wall of the karst cave by using the anchor cable, and then the diversion of the underground river is matched, so that the backfill body can be prevented from settling, and the stability and the reliability of the section B of the tunnel are improved; the tunnel section B and the tunnel section A at two ends are connected by adopting a continuous beam spanning bridge, and segmental construction is implemented, so that the load of the bridge is positioned at the tunnel section A at two ends, the backfill body and the stability and reliability of the tunnel section B are further improved, and the quality of pouring construction is ensured by carrying out concrete pouring in layers and in different positions.
Drawings
Fig. 1 is a plan view of the cave-underground river environment of the present invention.
Fig. 2 is a plan view of the cave river environment of the present invention (with a spillway tunnel).
Fig. 3 is a sectional view of a continuous beam according to the present invention.
The reference numerals in the figures denote:
1. karst cave; 2. a river under the river; 3. a first segment; 4. a second segment; 5. a third segment; 6. a closure section; 7. a water drainage hole.
Detailed Description
The invention will be described in further detail below with reference to the drawings and specific examples.
As shown in fig. 1 to 3, an embodiment of the continuous beam concrete pouring construction method based on tunnel construction in a karst cave and underground river environment of the invention includes a karst cave 1 and an underground river 2 located at the bottom of the karst cave 1, the tunnel passes through the karst cave 1, the tunnels at two ends of the karst cave 1 are tunnel a sections, and the tunnel passing through the karst cave 1 is tunnel B sections; the construction method comprises the following steps:
s1: excavating a tunnel section A to penetrate through the karst cave 1;
s2: the underground river 2 is diverted, so that the underground river 2 does not flow through the karst cave 1;
s3: backfilling the karst cave 1 until the karst cave is backfilled to the foundation surface of the tunnel;
s4: protecting the cave wall of the karst cave 1, and uniformly applying a plurality of anchor cables on the cave wall;
s5: filling the karst cave 1, and connecting the anchor cable with the filled backfill body;
s6: excavating the backfill body to form a tunnel section B communicated with the tunnel section A;
s7: constructing abutment, main piers and temporary buttresses on the section A of the tunnel to form abutments arranged at intervals, and ensuring that all the abutments are positioned on the section A of the tunnel;
s8: dividing an area above a pier close to a section B of the tunnel into a first section 3, dividing two sides of the first section 3 into second sections 4, dividing the side parts of the two second sections 4 into third sections 5, dividing a space between the two middle third sections 5 into closure sections 6, and setting the total length of all the sections as the construction length of the continuous beam;
s9: constructing a supporting foundation of the tunnel section A;
s10: constructing a continuous beam template, installing a prestressed pipeline, pouring concrete, penetrating a prestressed cable, tensioning the prestressed cable and grouting the pipeline according to the sequence of the segments from the first segment 3 to the closure segment 6, wherein the following sequence is adopted when concrete is poured: the joint of the top surface of the bottom plate and the web is filled from one end to the other end in a layered mode → the concrete at the chamfer of the bottom plate and the web is symmetrically poured from one end to the other end through the web → the insufficient concrete in the middle of the bottom plate is poured from two ends of the central pouring hole of the top plate to the middle → the concrete of the two side webs is symmetrically poured from one end to the other end → the concrete of the top plate is poured from one end to the other end.
In the method, the underground river 2 is diverted so that the underground river 2 does not flow through the karst cave 1, and the influence of a water area on the bottom of the karst cave 1 is eliminated; the karst cave 1 is backfilled until the karst cave is filled, namely the karst cave 1 is subjected to reconstruction treatment, so that the top of the karst cave 1 is prevented from dropping blocks, and the safety is improved; the backfill body is connected with the cave wall of the karst cave 1 by using the anchor cable, and then the diversion of the underground river 2 is matched, so that the backfill body can be prevented from settling, and the stability and reliability of the section B of the tunnel are improved; the tunnel section B and the tunnel section A at two ends are connected by adopting a continuous beam spanning bridge, and segmental construction is implemented, so that the load of the bridge is positioned at the tunnel section A at two ends, the backfill body and the stability and reliability of the tunnel section B are further improved, and the quality of pouring construction is ensured by carrying out concrete pouring in layers and in different positions.
In this embodiment, in step S1, lining construction is performed while performing support while excavating. By adopting the mode, the stability and the reliability of the excavated cavern can be ensured.
In this embodiment, in step S2, a drainage tunnel 7 communicating with the upstream of the underground river 2 is implemented so that the underground river 2 does not flow through the cavern 1. The water at the upstream of the underground river 2 is diverted by the drainage tunnel 7 and flows out from the area outside the karst cave 1, so that the subsequent backfill body can be prevented from generating settlement.
In this embodiment, the underground river 2 downstream of the junction of the drainage tunnel 7 and the underground river 2 is plugged and backfilled. Therefore, the phenomenon of water immersion can be prevented, and the subsequent backfilling construction is facilitated.
In this embodiment, in step S4, steel fibers are applied to the cavity wall of the cavern 1, and concrete is sprayed. The arrangement is convenient for the implementation of the anchor cable, and simultaneously, the block falling at the top of the karst cave 1 can be prevented.
In this embodiment, in step S5, grouting is performed in the gap between the backfill body and the cave wall of the cavern 1 to seal the gap. The stability and the reliability of the backfill body are further improved.
In this embodiment, in step S6, lining construction is performed while performing support while excavating. By adopting the mode, the stability and the reliability of the excavated cavern can be ensured.
Although the present invention has been described with reference to the preferred embodiments, it is not intended to be limited thereto. Those skilled in the art can make numerous possible variations and modifications to the present invention, or modify equivalent embodiments to equivalent variations, without departing from the scope of the invention, using the teachings disclosed above. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical spirit of the present invention should fall within the protection scope of the technical scheme of the present invention, unless the technical spirit of the present invention departs from the content of the technical scheme of the present invention.

Claims (7)

1. A continuous beam concrete pouring construction method based on tunnel construction in a karst cave and underground river environment is characterized in that the environment comprises a karst cave (1) and an underground river (2) located at the bottom of the karst cave (1), the tunnel penetrates through the karst cave (1), tunnels at two ends of the karst cave (1) are a tunnel section A, and a tunnel penetrating through the karst cave (1) is a tunnel section B; the construction method comprises the following steps:
s1: excavating a tunnel section A to a through karst cave (1);
s2: the underground river (2) is diverted, so that the underground river (2) does not flow through the karst cave (1);
s3: backfilling the karst cave (1) until the karst cave is backfilled to the tunnel foundation surface;
s4: protecting the cave wall of the karst cave (1), and uniformly applying a plurality of anchor cables on the cave wall;
s5: filling the karst cave (1) and connecting the anchor cable with the filled backfill body;
s6: excavating the backfill body to form a tunnel section B communicated with the tunnel section A;
s7: constructing abutment, main piers and temporary buttresses on the section A of the tunnel to form abutments arranged at intervals, and ensuring that all the abutments are positioned on the section A of the tunnel;
s8: dividing an area above a pier close to a section B of the tunnel into a first section (3), dividing two sides of the first section (3) into second sections (4), dividing the side parts of the two second sections (4) into third sections (5), dividing a space between the two middle third sections (5) into closure sections (6), wherein the total length of all the sections is the construction length of the continuous beam;
s9: constructing a supporting foundation of the tunnel section A;
s10: constructing a continuous beam template, installing a prestressed pipeline, pouring concrete, penetrating a prestressed cable, tensioning the prestressed cable and performing pipeline grouting according to the sequence from a first segment (3) to a closure segment (6), wherein the following sequence is performed when the concrete is poured: the joint of the top surface of the bottom plate and the web is filled from one end to the other end in a layered mode → the concrete at the chamfer of the bottom plate and the web is symmetrically poured from one end to the other end through the web → the insufficient concrete in the middle of the bottom plate is poured from two ends of the central pouring hole of the top plate to the middle → the concrete of the two side webs is symmetrically poured from one end to the other end → the concrete of the top plate is poured from one end to the other end.
2. The continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction according to claim 1, characterized in that: in step S1, the lining construction is performed while performing support while excavating.
3. The continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction according to claim 2, characterized in that: in step S2, a drainage tunnel (7) communicating with the upstream of the underground river (2) is constructed so that the underground river (2) does not flow through the cavern (1).
4. The continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction according to claim 3, characterized in that: and plugging and backfilling the underground river (2) at the downstream of the junction of the drainage tunnel (7) and the underground river (2).
5. The continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction according to claim 4, characterized in that: in step S4, steel fibers are applied to the cavity wall of the cave (1), and concrete is sprayed.
6. The continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction according to claim 5, characterized in that: in step S5, grouting is performed in the gap between the backfill body and the cavity wall of the cavern (1) to seal the gap.
7. The continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction according to claim 6, characterized in that: in step S6, the lining construction is performed while performing support while excavating.
CN202010838134.6A 2020-08-19 2020-08-19 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction Pending CN112065441A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010838134.6A CN112065441A (en) 2020-08-19 2020-08-19 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010838134.6A CN112065441A (en) 2020-08-19 2020-08-19 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction

Publications (1)

Publication Number Publication Date
CN112065441A true CN112065441A (en) 2020-12-11

Family

ID=73661331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010838134.6A Pending CN112065441A (en) 2020-08-19 2020-08-19 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction

Country Status (1)

Country Link
CN (1) CN112065441A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383806A (en) * 2011-07-18 2012-03-21 广东华盟路桥工程有限公司 Construction technology for allowing tunnel to pass through ultra-large karst cave
CN104532821A (en) * 2014-10-29 2015-04-22 中铁三局集团有限公司 Extra-large karst cave bottom treatment construction method
CN106702910A (en) * 2016-12-29 2017-05-24 中交第三航务工程局有限公司 Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes
CN106837353A (en) * 2017-01-22 2017-06-13 中南大学 Filling karst constructing tunnel processing method
CN106988758A (en) * 2017-05-08 2017-07-28 中铁五局集团第五工程有限责任公司 One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction
CN107574762A (en) * 2017-08-24 2018-01-12 中铁三局集团有限公司 A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN109630137A (en) * 2019-01-31 2019-04-16 中铁十四局集团建筑工程有限公司 An a kind of tunnel high position passes through the backfill processing construction method of huge molten chamber
CN111396095A (en) * 2020-04-21 2020-07-10 中铁二院工程集团有限责任公司 Tunnel simply-supported arch open cut tunnel structure penetrating through giant karst cave and construction method thereof
CN111411993A (en) * 2020-04-21 2020-07-14 中铁二院工程集团有限责任公司 Large-section tunnel supporting system penetrating through huge karst cave hall and construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383806A (en) * 2011-07-18 2012-03-21 广东华盟路桥工程有限公司 Construction technology for allowing tunnel to pass through ultra-large karst cave
CN104532821A (en) * 2014-10-29 2015-04-22 中铁三局集团有限公司 Extra-large karst cave bottom treatment construction method
CN106702910A (en) * 2016-12-29 2017-05-24 中交第三航务工程局有限公司 Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes
CN106837353A (en) * 2017-01-22 2017-06-13 中南大学 Filling karst constructing tunnel processing method
CN106988758A (en) * 2017-05-08 2017-07-28 中铁五局集团第五工程有限责任公司 One kind is used to pass through large-scale vertical solution cavity group method for tunnel construction
CN107574762A (en) * 2017-08-24 2018-01-12 中铁三局集团有限公司 A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN109630137A (en) * 2019-01-31 2019-04-16 中铁十四局集团建筑工程有限公司 An a kind of tunnel high position passes through the backfill processing construction method of huge molten chamber
CN111396095A (en) * 2020-04-21 2020-07-10 中铁二院工程集团有限责任公司 Tunnel simply-supported arch open cut tunnel structure penetrating through giant karst cave and construction method thereof
CN111411993A (en) * 2020-04-21 2020-07-14 中铁二院工程集团有限责任公司 Large-section tunnel supporting system penetrating through huge karst cave hall and construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张广泽等: "高速铁路隧道岩溶灾害及防治关键技术研究", 《铁道标准设计》 *
张祥等: "隧道穿越巨型溶洞弃碴回填体注浆加固技术研究", 《现代隧道技术》 *
陆士平等: "波形钢腹板预应力混凝土箱梁施工技术", 《公路交通科技》 *

Similar Documents

Publication Publication Date Title
CN110173267B (en) Construction method for subway shield zone to pass through existing station
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN104631475A (en) Safe and fast construction method of down-traversing river shallow depth bored tunnel
CN205012288U (en) Embankment dam pitch core -wall base
CN113565133A (en) Semi-covered excavation sequential urban tunnel structure next to subway and construction method
CN105804097A (en) Cantilever structure way for treating landslides in cooperation with h-shaped anti-sliding piles and construction method of cantilever structure way
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN112065444A (en) Continuous beam construction method based on karst cave underground river environment tunnel construction
CN112065442A (en) Continuous beam closure section construction method based on karst cave underground river environment tunnel construction
CN112065441A (en) Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction
CN112065437A (en) Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction
CN112065436A (en) Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction
CN112049646A (en) Continuous beam first section construction method based on karst cave underground river environment tunnel construction
CN111894603A (en) Tunnel construction method based on karst cave underground river environment
CN112065443A (en) Continuous beam second section construction method based on karst cave underground river environment tunnel construction
CN112065438A (en) Continuous beam third section construction method based on karst cave underground river environment tunnel construction
CN112065445A (en) Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction
CN112095438A (en) Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment
CN112065440A (en) Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction
CN112065439A (en) Continuous beam bell mouth friction loss testing method based on karst cave underground river environment
CN115821949A (en) Support system and support method for existing high and steep slope in narrow space
CN111878089A (en) Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction
CN111878088A (en) Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction
CN111878093A (en) Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment
CN111878090A (en) Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201211