CN106988758B - Construction method for crossing large-scale vertical karst cave group tunnel - Google Patents
Construction method for crossing large-scale vertical karst cave group tunnel Download PDFInfo
- Publication number
- CN106988758B CN106988758B CN201710318576.6A CN201710318576A CN106988758B CN 106988758 B CN106988758 B CN 106988758B CN 201710318576 A CN201710318576 A CN 201710318576A CN 106988758 B CN106988758 B CN 106988758B
- Authority
- CN
- China
- Prior art keywords
- karst cave
- concrete
- construction
- tunnel
- karst
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 239000004567 concrete Substances 0.000 claims abstract description 30
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 8
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 5
- 239000010959 steel Substances 0.000 claims abstract description 5
- 239000011435 rock Substances 0.000 claims description 18
- 239000002699 waste material Substances 0.000 claims description 5
- 239000004576 sand Substances 0.000 claims description 4
- 238000009412 basement excavation Methods 0.000 claims description 3
- 238000007664 blowing Methods 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 8
- 239000000463 material Substances 0.000 abstract description 4
- 230000002093 peripheral effect Effects 0.000 abstract description 4
- 230000000694 effects Effects 0.000 abstract description 3
- 238000000034 method Methods 0.000 abstract description 3
- 230000003014 reinforcing effect Effects 0.000 abstract description 3
- 239000002893 slag Substances 0.000 description 2
- 238000005728 strengthening Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000004090 dissolution Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D13/00—Large underground chambers; Methods or apparatus for making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F16/00—Drainage
- E21F16/02—Drainage of tunnels
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses a construction method for crossing a large-scale vertical karst cave group tunnel, which adopts the technical measure that a water channel is reserved for backfill concrete for the large-scale vertical karst cave group, steel arch frames and pipe sheds are used for reinforcing and supporting karst cave sections, reinforced concrete beam plate structures are used for crossing the tunnel bottoms of the karst cave sections, the bearing capacity of a foundation is greatly improved, municipal corrugated pipes are pre-buried before backfill concrete for peripheral cracks of the vertical karst cave group and arch karst cave, and are led to the water channel, hidden danger of high-pressure karst water caused by long-time ponding is eliminated, and safety during construction and later operation is ensured. The method has the advantages of convenient construction, greatly shortened construction period, improved karst cave treatment filling effect, improved safety of subsequent construction, simple and convenient pouring materials and construction method without special requirements, and good use effect is achieved by on-site implementation.
Description
Technical Field
The invention relates to a construction method for crossing a large vertical karst cave group tunnel, and belongs to the technical field of karst tunnels for large vertical karst cave group treatment.
Background
For tunnels passing through large vertical karst cave groups, karst cave with large scale and development depth of more than 30m is generally filled and constructed by adopting a roadbed mode. The karst cavity around the tunnel is backfilled by adopting conventional filling slag or M7.5 slurry rubble, the material consumption is huge and the karst cavity cannot be transported to a working surface, the mechanical consumption is large, the construction period cannot be predicted, the construction cost and the safety risk are extremely large, the construction period cannot be ensured, and the difficulty of field treatment is greatly increased.
Disclosure of Invention
The invention aims to solve the technical problems that: the utility model provides a be used for crossing large-scale vertical karst cave crowd tunnel construction method, in handling large-scale vertical karst cave crowd tunnel construction, adopt equipment such as small-size machinery, concrete delivery pump, just can handle the karst cave, overcome the manpower and materials consumption that prior art scheme exists and big, the processing process is long in time, the construction degree of difficulty is big, the high scheduling defect of construction risk improves karst tunnel construction work efficiency, reduce cost, reduction security risk.
The technical scheme adopted by the invention is as follows: a construction method for crossing a large-scale vertical karst cave group tunnel comprises the following specific implementation steps:
step one, removing dangerous rock falling rocks locally existing on the karst cave rock wall, and adopting sprayed C20 concrete for protection. The section of the vertical hole is enlarged and dug to serve as an operation channel, and the later stage is used as an inspection cavity.
And step two, adopting a treatment measure mainly based on backfilling for the large-scale vertical karst cave group, adopting C20 concrete pouring and backfilling for a platform above about 48m of the vertical karst cavity of the tunnel face, reserving a water passage, applying anchor rods to surrounding rock walls to embed rock bodies before concrete pouring, and increasing the integrity of backfilled concrete and the karst cave walls.
And thirdly, expanding and digging the karst cave face to a V-level surrounding rock support type section, and setting an I20a arch frame, shi Zuo pipe sheds and advanced small guide pipe grouting advanced support.
And fourthly, after the construction of the lower step excavation supporting construction is 25 meters, returning to excavate the karst cave section to the tunnel bottom to construct the reinforced concrete slab beam.
Fifthly, constructing an arch wall lining, backfilling the lining with C20 concrete within a range of 3m outside the contour line, blowing sand on the back and adding waste rubber tires as a buffer layer, and backfilling the lining to a height of 2m above the arch crown.
Preferably, the municipal corrugated pipes are pre-buried before backfilling concrete in the peripheral cracks of the vertical karst cave group and the arch karst cave, and are led to the water channel.
The invention adopts the technical measure of reserving a water passage for backfilling concrete, and the aim of quickly and safely treating karst tunnels is achieved by strengthening and supporting the karst cave section and adopting the reinforced concrete beam plate structure to span the bottom of the karst cave section.
The invention has the beneficial effects that: compared with the prior art, the invention has the following effects:
1) Only small-sized machinery, a concrete conveying pump and other equipment are needed, the karst cave can be treated, and the efficiency of the later tunnel construction is improved.
2) Compared with the conventional filling hole slag, the method has the advantages that the backfill concrete is adopted to reserve the water passage, the construction period is short, the materials are saved, the working efficiency is improved, and the foundation bearing capacity requirement can be met.
3) And the plate girder crossing structure is adopted, so that the safety of karst cave treatment is improved. The municipal corrugated pipe pre-buried in the peripheral fissures and the arch dissolution cavity is shot to the water passing channel, so that hidden danger of high-pressure karst water caused by long-time ponding is eliminated, and effective safety guarantee is obtained during construction and later put into operation.
4) The sand is blown to the back of the vault backfill concrete and the waste rubber tire is used as a buffer layer, so that the damage of karst cave roof falling rocks to a two-lining structure can be greatly reduced.
Drawings
FIG. 1 is a schematic view of karst cave backfill according to the present invention;
fig. 2 is a schematic view of the reinforced concrete slab beam structure of the present invention;
the marks in the figure are as follows: 1. the concrete for surface protection comprises 2 parts of concrete, 2 parts of anchor rods, 3 parts of backfill concrete, 4 parts of municipal corrugated pipes, 5 parts of reinforced concrete slab beams, 6 parts of steel arch reinforcing support and middle pipe shed advanced support, 7 parts of concrete, 8 parts of waste rubber tires, 9 parts of water passing channels.
Detailed Description
The invention will be further described with reference to specific examples.
A construction method for crossing a large-scale vertical karst cave group tunnel comprises the following specific implementation steps:
firstly, removing dangerous rock falling rocks locally existing on the karst cave rock wall, adopting sprayed C20 surface protection concrete 1 to protect, enlarging and digging a section at a vertical cave opening to serve as an operation channel, and taking the later stage as an inspection cave.
And secondly, a large-scale vertical karst cave group adopts a treatment measure mainly based on backfilling, C20 backfill concrete 3 is adopted to perform pouring and backfilling on a platform above a position of about 48m of a vertical solution cavity of a tunnel face, a water channel 9 is reserved, anchor rods 2 are applied to surrounding rock walls to be embedded into rock bodies before the backfill concrete 3 is poured, and the integrity of the backfill concrete 3 and the solution cave walls is improved.
And thirdly, expanding and digging the karst cave face to a V-level surrounding rock support type section, setting an I20a steel arch frame, adding an advanced small guide pipe into a Shi Zuo pipe shed, grouting, and carrying out steel arch frame and middle pipe shed reinforcing support 6.
And fourthly, after the construction of the lower step excavation supporting construction is 25 meters, returning to excavate the karst cave section to the tunnel bottom to construct the reinforced concrete slab beam 5.
Fifthly, constructing an arch wall lining, backfilling the lining with C20 concrete 7 within a range of 3m outside the contour line of the lining, blowing sand at the back and adding waste rubber tires 8 to serve as a buffer layer, and backfilling the lining to a height of 2m above the arch roof.
Furthermore, the municipal corrugated pipe 4 is pre-buried before backfilling the concrete 3 for the vertical karst cave group peripheral cracks and arch karst cave, and is led to the water channel 9.
The invention adopts the technical measure of reserving a water passage for backfilling concrete, and the aim of quickly and safely treating karst tunnels is achieved by strengthening and supporting the karst cave section and adopting the reinforced concrete beam plate structure to span the bottom of the karst cave section.
The foregoing is merely illustrative of the present invention, and the scope of the present invention is not limited thereto, and any person skilled in the art can easily think about variations or substitutions within the scope of the present invention, and therefore, the scope of the present invention shall be defined by the scope of the appended claims.
Claims (1)
1. A construction method for crossing a large vertical karst cave group tunnel is characterized by comprising the following steps: the construction steps are as follows: firstly, removing dangerous rock falling stones locally existing on the karst cave rock wall, adopting sprayed surface protection concrete (1) for protection, and enlarging a section of a vertical karst cave opening to serve as an operation channel and serve as an inspection cave in the later period; backfilling the platform above the vertical solution cavity 48m of the tunnel face by adopting a backfill concrete (3) pouring mode, reserving a water channel (9), applying anchor rods (2) to surrounding rock walls to embed rock bodies before pouring the backfill concrete (3), increasing the integral firmness of the backfill concrete (3) and the solution cavity walls, pre-burying municipal corrugated pipes (4) before the backfill concrete (3) for the surrounding cracks and the arch solution cavities of the vertical solution cavity group, and guiding the municipal corrugated pipes to the water channel (9); step three, expanding and digging a karst cave tunnel face to a V-level surrounding rock support type section, setting an I-steel arch frame, and applying a pipe shed and an advanced small guide pipe grouting advanced support (6); fourthly, after the excavation supporting construction of the lower step is 25 meters, returning to excavate the karst cave section to the bottom of the tunnel, and constructing a reinforced concrete slab beam (5); fifthly, constructing an arch wall lining, backfilling the lining contour line by adopting concrete (7) within 3m, blowing sand at the back and adding waste rubber tires (8) as buffer layers, and backfilling the arch wall lining to a height of 2m above the arch roof.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710318576.6A CN106988758B (en) | 2017-05-08 | 2017-05-08 | Construction method for crossing large-scale vertical karst cave group tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710318576.6A CN106988758B (en) | 2017-05-08 | 2017-05-08 | Construction method for crossing large-scale vertical karst cave group tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106988758A CN106988758A (en) | 2017-07-28 |
CN106988758B true CN106988758B (en) | 2023-09-01 |
Family
ID=59417618
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710318576.6A Active CN106988758B (en) | 2017-05-08 | 2017-05-08 | Construction method for crossing large-scale vertical karst cave group tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106988758B (en) |
Families Citing this family (35)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952766B (en) * | 2018-07-25 | 2021-02-26 | 广西长长路桥建设有限公司 | Construction method for tunnel passing through karst section |
CN109538216B (en) * | 2018-12-21 | 2020-11-03 | 中铁二十五局集团第五工程有限公司 | Tunnel construction process for crossing mining and subsidence areas |
CN109667262B (en) * | 2019-02-25 | 2024-03-01 | 中国电建集团贵阳勘测设计研究院有限公司 | Karst water falling hole plugging structure and construction method thereof |
CN110656955A (en) * | 2019-11-06 | 2020-01-07 | 四川省交通勘察设计研究院有限公司 | Tunnel structure penetrating through karst channel and method for tunnel penetrating through karst channel |
CN111119951A (en) * | 2019-12-27 | 2020-05-08 | 中铁十六局集团第一工程有限公司 | Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area |
CN111119929A (en) * | 2019-12-29 | 2020-05-08 | 中铁二院工程集团有限责任公司 | Lattice type rockfall prevention structure of large-scale ultrahigh karst cavity tunnel and construction method |
CN111119938B (en) * | 2019-12-30 | 2022-02-11 | 中交路桥华南工程有限公司 | Method for processing karst cave at upper part of tunnel |
CN111396095B (en) * | 2020-04-21 | 2024-05-24 | 中铁二院工程集团有限责任公司 | Tunnel simple arch open cut tunnel structure penetrating through huge karst cave and construction method thereof |
CN111411992A (en) * | 2020-04-21 | 2020-07-14 | 中铁二院工程集团有限责任公司 | Integrated structure system penetrating through giant karst cave and construction method thereof |
CN111502748B (en) * | 2020-04-21 | 2021-08-31 | 中铁二院工程集团有限责任公司 | Construction method for backfilling foundation of railway crossing giant karst cave |
CN111706362A (en) * | 2020-07-02 | 2020-09-25 | 天津大学 | Karst cave treatment method for tunnel construction |
CN111878090A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction |
CN111878088A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction |
CN111878112A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section concrete spraying construction method based on karst cave underground river environment tunnel construction |
CN111878092A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section full-filling ventilation method based on karst cave underground river environment tunnel construction |
CN111878086A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Peripheral construction channel arrangement method based on karst cave underground river environment tunnel construction |
CN111878093A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment |
CN111878089A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction |
CN112554886A (en) * | 2020-07-30 | 2021-03-26 | 中铁五局集团有限公司 | Tunnel main tunnel area construction method based on karst cave underground river environment tunnel construction |
CN111878096A (en) * | 2020-07-30 | 2020-11-03 | 中铁五局集团有限公司 | Karst cave backfilling method based on karst cave underground river environment tunnel construction |
CN111894603A (en) * | 2020-07-30 | 2020-11-06 | 中铁五局集团有限公司 | Tunnel construction method based on karst cave underground river environment |
CN112065442A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam closure section construction method based on karst cave underground river environment tunnel construction |
CN112065445A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction |
CN112065440A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction |
CN112095438A (en) * | 2020-08-19 | 2020-12-18 | 中铁五局集团有限公司 | Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment |
CN112065444A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam construction method based on karst cave underground river environment tunnel construction |
CN112065439A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam bell mouth friction loss testing method based on karst cave underground river environment |
CN112065438A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam third section construction method based on karst cave underground river environment tunnel construction |
CN112065443A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam second section construction method based on karst cave underground river environment tunnel construction |
CN112065436A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction |
CN112065441A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction |
CN112065437A (en) * | 2020-08-19 | 2020-12-11 | 中铁五局集团有限公司 | Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction |
CN113503166B (en) * | 2021-03-31 | 2023-07-07 | 广东冠粤路桥有限公司 | Reinforced disposal structure of karst cave at middle and lower parts of tunnel and construction method thereof |
CN113669108B (en) * | 2021-06-16 | 2024-01-30 | 广西交通设计集团有限公司 | Comprehensive drainage system penetrating complex karst cave group tunnel |
CN116378677B (en) * | 2023-05-29 | 2023-08-29 | 湖南省交通规划勘察设计院有限公司 | Tunnel construction method and tunnel structure of full-span filling karst cave section |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004353175A (en) * | 2003-05-27 | 2004-12-16 | Kankyo Zokei:Kk | Wastewater passage for tunnel, drainage system, and its construction method |
CN101368472A (en) * | 2008-10-09 | 2009-02-18 | 中国水利水电第十四工程局有限公司 | Method for accurately positioning and orienting drill hole of top arch |
CN101922300A (en) * | 2010-08-30 | 2010-12-22 | 中铁第四勘察设计院集团有限公司 | Large supporting and protecting system of tunnel in hollow solution cavity |
CN102758642A (en) * | 2012-07-16 | 2012-10-31 | 中铁隧道集团有限公司 | Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof |
CN103244128A (en) * | 2013-05-22 | 2013-08-14 | 汇通路桥建设集团有限公司 | Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods |
CN106194196A (en) * | 2016-08-22 | 2016-12-07 | 北京市政路桥股份有限公司 | A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method |
-
2017
- 2017-05-08 CN CN201710318576.6A patent/CN106988758B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004353175A (en) * | 2003-05-27 | 2004-12-16 | Kankyo Zokei:Kk | Wastewater passage for tunnel, drainage system, and its construction method |
CN101368472A (en) * | 2008-10-09 | 2009-02-18 | 中国水利水电第十四工程局有限公司 | Method for accurately positioning and orienting drill hole of top arch |
CN101922300A (en) * | 2010-08-30 | 2010-12-22 | 中铁第四勘察设计院集团有限公司 | Large supporting and protecting system of tunnel in hollow solution cavity |
CN102758642A (en) * | 2012-07-16 | 2012-10-31 | 中铁隧道集团有限公司 | Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof |
CN103244128A (en) * | 2013-05-22 | 2013-08-14 | 汇通路桥建设集团有限公司 | Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods |
CN106194196A (en) * | 2016-08-22 | 2016-12-07 | 北京市政路桥股份有限公司 | A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method |
Non-Patent Citations (1)
Title |
---|
何江等.溶洞地区的隧道施工技术.《铁道建筑》.2004,第29-31页. * |
Also Published As
Publication number | Publication date |
---|---|
CN106988758A (en) | 2017-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106988758B (en) | Construction method for crossing large-scale vertical karst cave group tunnel | |
CN110173267B (en) | Construction method for subway shield zone to pass through existing station | |
CN108204240B (en) | Anti-floating reinforcement system and reinforcement method for newly-built tunnel to span existing tunnel in short distance | |
CN107313431B (en) | Close on not contour foundation pit method for synchronously constructing | |
CN102134998B (en) | Construction method for wind-blown sand tunnel | |
CN106351670A (en) | Closed pre-support tunnel structure | |
CN109026020B (en) | Water-rich tunnel karst cave treatment and excavation method | |
CN105804119A (en) | Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure | |
CN103628885A (en) | Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel | |
CN110566223B (en) | Deep-buried PBA subway station section design method | |
CN107401161A (en) | High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements | |
CN110700841A (en) | Double-side-wall guide pit type excavation method for tunnel excavation | |
CN107965325A (en) | Just branch bow member replaces construction method to a kind of small interval shallow tunnel | |
CN206707721U (en) | A kind of tunnel structure for passing through large-scale vertical solution cavity group | |
CN114109442B (en) | Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method | |
CN107191206A (en) | A kind of step construction method of Shallow-buried Large-span Tunnel Unit two six | |
CN112983467B (en) | Treatment method for tunnel gate closing type large collapse | |
CN114562289A (en) | Rapid treatment method for large-scale cavity collapse of soft broken surrounding rock tunnel vault | |
CN203891047U (en) | Equipment equipped with steel platform for foundation construction of land bridge | |
CN110042851A (en) | Reduce and wears riverway cofferdam and river bed reinforcement means under neighbouring high-speed rail deformation of pile foundation | |
CN115030731A (en) | Pilot tunnel construction method in cross tunnel engineering | |
CN214832726U (en) | Supporting structure for pipe-jacking working well in deep soft soil area | |
CN115370389A (en) | Construction method for radial steel pipe opposite-top support of collapsed cavity of highway tunnel | |
CN211873014U (en) | System for bailey truss protects cable | |
CN208251118U (en) | Slope reinforcement device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |