CN106988758B - Construction method for crossing large-scale vertical karst cave group tunnel - Google Patents

Construction method for crossing large-scale vertical karst cave group tunnel Download PDF

Info

Publication number
CN106988758B
CN106988758B CN201710318576.6A CN201710318576A CN106988758B CN 106988758 B CN106988758 B CN 106988758B CN 201710318576 A CN201710318576 A CN 201710318576A CN 106988758 B CN106988758 B CN 106988758B
Authority
CN
China
Prior art keywords
karst cave
concrete
construction
tunnel
karst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710318576.6A
Other languages
Chinese (zh)
Other versions
CN106988758A (en
Inventor
杨炎川
陈金
张登林
吴秀雄
魏毅
宋佳
蒋志权
解振乙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority to CN201710318576.6A priority Critical patent/CN106988758B/en
Publication of CN106988758A publication Critical patent/CN106988758A/en
Application granted granted Critical
Publication of CN106988758B publication Critical patent/CN106988758B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction method for crossing a large-scale vertical karst cave group tunnel, which adopts the technical measure that a water channel is reserved for backfill concrete for the large-scale vertical karst cave group, steel arch frames and pipe sheds are used for reinforcing and supporting karst cave sections, reinforced concrete beam plate structures are used for crossing the tunnel bottoms of the karst cave sections, the bearing capacity of a foundation is greatly improved, municipal corrugated pipes are pre-buried before backfill concrete for peripheral cracks of the vertical karst cave group and arch karst cave, and are led to the water channel, hidden danger of high-pressure karst water caused by long-time ponding is eliminated, and safety during construction and later operation is ensured. The method has the advantages of convenient construction, greatly shortened construction period, improved karst cave treatment filling effect, improved safety of subsequent construction, simple and convenient pouring materials and construction method without special requirements, and good use effect is achieved by on-site implementation.

Description

Construction method for crossing large-scale vertical karst cave group tunnel
Technical Field
The invention relates to a construction method for crossing a large vertical karst cave group tunnel, and belongs to the technical field of karst tunnels for large vertical karst cave group treatment.
Background
For tunnels passing through large vertical karst cave groups, karst cave with large scale and development depth of more than 30m is generally filled and constructed by adopting a roadbed mode. The karst cavity around the tunnel is backfilled by adopting conventional filling slag or M7.5 slurry rubble, the material consumption is huge and the karst cavity cannot be transported to a working surface, the mechanical consumption is large, the construction period cannot be predicted, the construction cost and the safety risk are extremely large, the construction period cannot be ensured, and the difficulty of field treatment is greatly increased.
Disclosure of Invention
The invention aims to solve the technical problems that: the utility model provides a be used for crossing large-scale vertical karst cave crowd tunnel construction method, in handling large-scale vertical karst cave crowd tunnel construction, adopt equipment such as small-size machinery, concrete delivery pump, just can handle the karst cave, overcome the manpower and materials consumption that prior art scheme exists and big, the processing process is long in time, the construction degree of difficulty is big, the high scheduling defect of construction risk improves karst tunnel construction work efficiency, reduce cost, reduction security risk.
The technical scheme adopted by the invention is as follows: a construction method for crossing a large-scale vertical karst cave group tunnel comprises the following specific implementation steps:
step one, removing dangerous rock falling rocks locally existing on the karst cave rock wall, and adopting sprayed C20 concrete for protection. The section of the vertical hole is enlarged and dug to serve as an operation channel, and the later stage is used as an inspection cavity.
And step two, adopting a treatment measure mainly based on backfilling for the large-scale vertical karst cave group, adopting C20 concrete pouring and backfilling for a platform above about 48m of the vertical karst cavity of the tunnel face, reserving a water passage, applying anchor rods to surrounding rock walls to embed rock bodies before concrete pouring, and increasing the integrity of backfilled concrete and the karst cave walls.
And thirdly, expanding and digging the karst cave face to a V-level surrounding rock support type section, and setting an I20a arch frame, shi Zuo pipe sheds and advanced small guide pipe grouting advanced support.
And fourthly, after the construction of the lower step excavation supporting construction is 25 meters, returning to excavate the karst cave section to the tunnel bottom to construct the reinforced concrete slab beam.
Fifthly, constructing an arch wall lining, backfilling the lining with C20 concrete within a range of 3m outside the contour line, blowing sand on the back and adding waste rubber tires as a buffer layer, and backfilling the lining to a height of 2m above the arch crown.
Preferably, the municipal corrugated pipes are pre-buried before backfilling concrete in the peripheral cracks of the vertical karst cave group and the arch karst cave, and are led to the water channel.
The invention adopts the technical measure of reserving a water passage for backfilling concrete, and the aim of quickly and safely treating karst tunnels is achieved by strengthening and supporting the karst cave section and adopting the reinforced concrete beam plate structure to span the bottom of the karst cave section.
The invention has the beneficial effects that: compared with the prior art, the invention has the following effects:
1) Only small-sized machinery, a concrete conveying pump and other equipment are needed, the karst cave can be treated, and the efficiency of the later tunnel construction is improved.
2) Compared with the conventional filling hole slag, the method has the advantages that the backfill concrete is adopted to reserve the water passage, the construction period is short, the materials are saved, the working efficiency is improved, and the foundation bearing capacity requirement can be met.
3) And the plate girder crossing structure is adopted, so that the safety of karst cave treatment is improved. The municipal corrugated pipe pre-buried in the peripheral fissures and the arch dissolution cavity is shot to the water passing channel, so that hidden danger of high-pressure karst water caused by long-time ponding is eliminated, and effective safety guarantee is obtained during construction and later put into operation.
4) The sand is blown to the back of the vault backfill concrete and the waste rubber tire is used as a buffer layer, so that the damage of karst cave roof falling rocks to a two-lining structure can be greatly reduced.
Drawings
FIG. 1 is a schematic view of karst cave backfill according to the present invention;
fig. 2 is a schematic view of the reinforced concrete slab beam structure of the present invention;
the marks in the figure are as follows: 1. the concrete for surface protection comprises 2 parts of concrete, 2 parts of anchor rods, 3 parts of backfill concrete, 4 parts of municipal corrugated pipes, 5 parts of reinforced concrete slab beams, 6 parts of steel arch reinforcing support and middle pipe shed advanced support, 7 parts of concrete, 8 parts of waste rubber tires, 9 parts of water passing channels.
Detailed Description
The invention will be further described with reference to specific examples.
A construction method for crossing a large-scale vertical karst cave group tunnel comprises the following specific implementation steps:
firstly, removing dangerous rock falling rocks locally existing on the karst cave rock wall, adopting sprayed C20 surface protection concrete 1 to protect, enlarging and digging a section at a vertical cave opening to serve as an operation channel, and taking the later stage as an inspection cave.
And secondly, a large-scale vertical karst cave group adopts a treatment measure mainly based on backfilling, C20 backfill concrete 3 is adopted to perform pouring and backfilling on a platform above a position of about 48m of a vertical solution cavity of a tunnel face, a water channel 9 is reserved, anchor rods 2 are applied to surrounding rock walls to be embedded into rock bodies before the backfill concrete 3 is poured, and the integrity of the backfill concrete 3 and the solution cave walls is improved.
And thirdly, expanding and digging the karst cave face to a V-level surrounding rock support type section, setting an I20a steel arch frame, adding an advanced small guide pipe into a Shi Zuo pipe shed, grouting, and carrying out steel arch frame and middle pipe shed reinforcing support 6.
And fourthly, after the construction of the lower step excavation supporting construction is 25 meters, returning to excavate the karst cave section to the tunnel bottom to construct the reinforced concrete slab beam 5.
Fifthly, constructing an arch wall lining, backfilling the lining with C20 concrete 7 within a range of 3m outside the contour line of the lining, blowing sand at the back and adding waste rubber tires 8 to serve as a buffer layer, and backfilling the lining to a height of 2m above the arch roof.
Furthermore, the municipal corrugated pipe 4 is pre-buried before backfilling the concrete 3 for the vertical karst cave group peripheral cracks and arch karst cave, and is led to the water channel 9.
The invention adopts the technical measure of reserving a water passage for backfilling concrete, and the aim of quickly and safely treating karst tunnels is achieved by strengthening and supporting the karst cave section and adopting the reinforced concrete beam plate structure to span the bottom of the karst cave section.
The foregoing is merely illustrative of the present invention, and the scope of the present invention is not limited thereto, and any person skilled in the art can easily think about variations or substitutions within the scope of the present invention, and therefore, the scope of the present invention shall be defined by the scope of the appended claims.

Claims (1)

1. A construction method for crossing a large vertical karst cave group tunnel is characterized by comprising the following steps: the construction steps are as follows: firstly, removing dangerous rock falling stones locally existing on the karst cave rock wall, adopting sprayed surface protection concrete (1) for protection, and enlarging a section of a vertical karst cave opening to serve as an operation channel and serve as an inspection cave in the later period; backfilling the platform above the vertical solution cavity 48m of the tunnel face by adopting a backfill concrete (3) pouring mode, reserving a water channel (9), applying anchor rods (2) to surrounding rock walls to embed rock bodies before pouring the backfill concrete (3), increasing the integral firmness of the backfill concrete (3) and the solution cavity walls, pre-burying municipal corrugated pipes (4) before the backfill concrete (3) for the surrounding cracks and the arch solution cavities of the vertical solution cavity group, and guiding the municipal corrugated pipes to the water channel (9); step three, expanding and digging a karst cave tunnel face to a V-level surrounding rock support type section, setting an I-steel arch frame, and applying a pipe shed and an advanced small guide pipe grouting advanced support (6); fourthly, after the excavation supporting construction of the lower step is 25 meters, returning to excavate the karst cave section to the bottom of the tunnel, and constructing a reinforced concrete slab beam (5); fifthly, constructing an arch wall lining, backfilling the lining contour line by adopting concrete (7) within 3m, blowing sand at the back and adding waste rubber tires (8) as buffer layers, and backfilling the arch wall lining to a height of 2m above the arch roof.
CN201710318576.6A 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel Active CN106988758B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710318576.6A CN106988758B (en) 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710318576.6A CN106988758B (en) 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel

Publications (2)

Publication Number Publication Date
CN106988758A CN106988758A (en) 2017-07-28
CN106988758B true CN106988758B (en) 2023-09-01

Family

ID=59417618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710318576.6A Active CN106988758B (en) 2017-05-08 2017-05-08 Construction method for crossing large-scale vertical karst cave group tunnel

Country Status (1)

Country Link
CN (1) CN106988758B (en)

Families Citing this family (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952766B (en) * 2018-07-25 2021-02-26 广西长长路桥建设有限公司 Construction method for tunnel passing through karst section
CN109538216B (en) * 2018-12-21 2020-11-03 中铁二十五局集团第五工程有限公司 Tunnel construction process for crossing mining and subsidence areas
CN109667262B (en) * 2019-02-25 2024-03-01 中国电建集团贵阳勘测设计研究院有限公司 Karst water falling hole plugging structure and construction method thereof
CN110656955A (en) * 2019-11-06 2020-01-07 四川省交通勘察设计研究院有限公司 Tunnel structure penetrating through karst channel and method for tunnel penetrating through karst channel
CN111119951A (en) * 2019-12-27 2020-05-08 中铁十六局集团第一工程有限公司 Construction method for highway tunnel to pass through fault fracture zone water-rich cavity area
CN111119929A (en) * 2019-12-29 2020-05-08 中铁二院工程集团有限责任公司 Lattice type rockfall prevention structure of large-scale ultrahigh karst cavity tunnel and construction method
CN111119938B (en) * 2019-12-30 2022-02-11 中交路桥华南工程有限公司 Method for processing karst cave at upper part of tunnel
CN111396095B (en) * 2020-04-21 2024-05-24 中铁二院工程集团有限责任公司 Tunnel simple arch open cut tunnel structure penetrating through huge karst cave and construction method thereof
CN111411992A (en) * 2020-04-21 2020-07-14 中铁二院工程集团有限责任公司 Integrated structure system penetrating through giant karst cave and construction method thereof
CN111502748B (en) * 2020-04-21 2021-08-31 中铁二院工程集团有限责任公司 Construction method for backfilling foundation of railway crossing giant karst cave
CN111706362A (en) * 2020-07-02 2020-09-25 天津大学 Karst cave treatment method for tunnel construction
CN111878090A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section anchor rod construction method based on karst cave underground river environment tunnel construction
CN111878088A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section logistics channel construction method based on karst cave underground river environment tunnel construction
CN111878112A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section concrete spraying construction method based on karst cave underground river environment tunnel construction
CN111878092A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section full-filling ventilation method based on karst cave underground river environment tunnel construction
CN111878086A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Peripheral construction channel arrangement method based on karst cave underground river environment tunnel construction
CN111878093A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Construction method for side area of tunnel main tunnel in tunnel construction of karst cave and underground river environment
CN111878089A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave section grouting reinforcement construction method based on karst cave underground river environment tunnel construction
CN112554886A (en) * 2020-07-30 2021-03-26 中铁五局集团有限公司 Tunnel main tunnel area construction method based on karst cave underground river environment tunnel construction
CN111878096A (en) * 2020-07-30 2020-11-03 中铁五局集团有限公司 Karst cave backfilling method based on karst cave underground river environment tunnel construction
CN111894603A (en) * 2020-07-30 2020-11-06 中铁五局集团有限公司 Tunnel construction method based on karst cave underground river environment
CN112065442A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam closure section construction method based on karst cave underground river environment tunnel construction
CN112065445A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Karst cave section excavation supporting construction method based on karst cave underground river environment tunnel construction
CN112065440A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam pipeline grouting construction method based on karst cave underground river environment tunnel construction
CN112095438A (en) * 2020-08-19 2020-12-18 中铁五局集团有限公司 Continuous beam pipeline reinforcing bar friction loss testing method based on karst cave underground river environment
CN112065444A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam construction method based on karst cave underground river environment tunnel construction
CN112065439A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam bell mouth friction loss testing method based on karst cave underground river environment
CN112065438A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam third section construction method based on karst cave underground river environment tunnel construction
CN112065443A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam second section construction method based on karst cave underground river environment tunnel construction
CN112065436A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam prestress tensioning construction method based on karst cave underground river environment tunnel construction
CN112065441A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam concrete pouring construction method based on karst cave underground river environment tunnel construction
CN112065437A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam support pre-pressing construction method based on karst cave underground river environment tunnel construction
CN113503166B (en) * 2021-03-31 2023-07-07 广东冠粤路桥有限公司 Reinforced disposal structure of karst cave at middle and lower parts of tunnel and construction method thereof
CN113669108B (en) * 2021-06-16 2024-01-30 广西交通设计集团有限公司 Comprehensive drainage system penetrating complex karst cave group tunnel
CN116378677B (en) * 2023-05-29 2023-08-29 湖南省交通规划勘察设计院有限公司 Tunnel construction method and tunnel structure of full-span filling karst cave section

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004353175A (en) * 2003-05-27 2004-12-16 Kankyo Zokei:Kk Wastewater passage for tunnel, drainage system, and its construction method
CN101368472A (en) * 2008-10-09 2009-02-18 中国水利水电第十四工程局有限公司 Method for accurately positioning and orienting drill hole of top arch
CN101922300A (en) * 2010-08-30 2010-12-22 中铁第四勘察设计院集团有限公司 Large supporting and protecting system of tunnel in hollow solution cavity
CN102758642A (en) * 2012-07-16 2012-10-31 中铁隧道集团有限公司 Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN103244128A (en) * 2013-05-22 2013-08-14 汇通路桥建设集团有限公司 Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
CN106194196A (en) * 2016-08-22 2016-12-07 北京市政路桥股份有限公司 A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004353175A (en) * 2003-05-27 2004-12-16 Kankyo Zokei:Kk Wastewater passage for tunnel, drainage system, and its construction method
CN101368472A (en) * 2008-10-09 2009-02-18 中国水利水电第十四工程局有限公司 Method for accurately positioning and orienting drill hole of top arch
CN101922300A (en) * 2010-08-30 2010-12-22 中铁第四勘察设计院集团有限公司 Large supporting and protecting system of tunnel in hollow solution cavity
CN102758642A (en) * 2012-07-16 2012-10-31 中铁隧道集团有限公司 Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN103244128A (en) * 2013-05-22 2013-08-14 汇通路桥建设集团有限公司 Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
CN106194196A (en) * 2016-08-22 2016-12-07 北京市政路桥股份有限公司 A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
何江等.溶洞地区的隧道施工技术.《铁道建筑》.2004,第29-31页. *

Also Published As

Publication number Publication date
CN106988758A (en) 2017-07-28

Similar Documents

Publication Publication Date Title
CN106988758B (en) Construction method for crossing large-scale vertical karst cave group tunnel
CN110173267B (en) Construction method for subway shield zone to pass through existing station
CN108204240B (en) Anti-floating reinforcement system and reinforcement method for newly-built tunnel to span existing tunnel in short distance
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN102134998B (en) Construction method for wind-blown sand tunnel
CN106351670A (en) Closed pre-support tunnel structure
CN109026020B (en) Water-rich tunnel karst cave treatment and excavation method
CN105804119A (en) Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN110566223B (en) Deep-buried PBA subway station section design method
CN107401161A (en) High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements
CN110700841A (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN107965325A (en) Just branch bow member replaces construction method to a kind of small interval shallow tunnel
CN206707721U (en) A kind of tunnel structure for passing through large-scale vertical solution cavity group
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN107191206A (en) A kind of step construction method of Shallow-buried Large-span Tunnel Unit two six
CN112983467B (en) Treatment method for tunnel gate closing type large collapse
CN114562289A (en) Rapid treatment method for large-scale cavity collapse of soft broken surrounding rock tunnel vault
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge
CN110042851A (en) Reduce and wears riverway cofferdam and river bed reinforcement means under neighbouring high-speed rail deformation of pile foundation
CN115030731A (en) Pilot tunnel construction method in cross tunnel engineering
CN214832726U (en) Supporting structure for pipe-jacking working well in deep soft soil area
CN115370389A (en) Construction method for radial steel pipe opposite-top support of collapsed cavity of highway tunnel
CN211873014U (en) System for bailey truss protects cable
CN208251118U (en) Slope reinforcement device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant