CN106897817A - A kind of construction speed Visualized management system and method based on augmented reality - Google Patents
A kind of construction speed Visualized management system and method based on augmented reality Download PDFInfo
- Publication number
- CN106897817A CN106897817A CN201710047631.2A CN201710047631A CN106897817A CN 106897817 A CN106897817 A CN 106897817A CN 201710047631 A CN201710047631 A CN 201710047631A CN 106897817 A CN106897817 A CN 106897817A
- Authority
- CN
- China
- Prior art keywords
- construction
- scene
- augmented reality
- data
- reality
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 120
- 230000003190 augmentative effect Effects 0.000 title claims abstract description 50
- 238000000034 method Methods 0.000 title claims abstract description 27
- 230000000694 effects Effects 0.000 claims abstract description 10
- 238000013480 data collection Methods 0.000 claims abstract description 7
- 230000008447 perception Effects 0.000 claims abstract description 6
- 238000007726 management method Methods 0.000 claims description 24
- 238000005516 engineering process Methods 0.000 claims description 16
- 238000007405 data analysis Methods 0.000 claims description 11
- 230000008569 process Effects 0.000 claims description 5
- 230000005540 biological transmission Effects 0.000 claims description 4
- 238000012546 transfer Methods 0.000 claims description 4
- 238000012800 visualization Methods 0.000 description 5
- 230000008901 benefit Effects 0.000 description 3
- 238000009430 construction management Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 210000004556 brain Anatomy 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000013070 change management Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 235000009508 confectionery Nutrition 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000003340 mental effect Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 239000000779 smoke Substances 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Processing Or Creating Images (AREA)
Abstract
The invention provides a kind of construction speed Visualized management system based on augmented reality.The construction speed Visualized management system based on augmented reality includes:Construction control unit, for the Internet of Things perception data and manual entry information of automatic data collection job site, and the data to gathering carry out sorted generalization and arrangement, the work progress at scene is resolved into some progress nodes with reference to WBS, be compiled into construction schedule and be managed;Dummy modeling unit, based on the data that the construction control unit is provided, carries out building the related dummy model of construction;Augmented reality unit, for being scanned to reality scene and being recognized, and the dummy model that the Dummy modeling unit is provided is added in identified reality scene, so as to be presented or show the augmented reality effect of construction speed.The present invention also provides a kind of method of the construction speed Visualized management system based on augmented reality.
Description
Technical field
The invention belongs to capital construction technical field, more particularly to a kind of construction speed visualization based on augmented reality
Management system and method.
Background technology
Capital construction management is through the important leverage of the process of whole building activity.Traditional construction management is all based on
Substantial amounts of drawing information, the simple mental labour by people carries out construction effect reduction, and various texts are carried out by manual labor
Shelves, report messages are arranged, filing, and efficiency is very low, error-prone and extremely serious to the wasting phenomenon of material.These problems are returned
Root is that human brain cannot complete for whole work progress to think deeply complete on earth, it is impossible to visualize the result of whole building activity
Come.Therefore, can only want to do while changing.
The content of the invention
Defect it is an object of the invention to be directed to prior art, there is provided a kind of construction speed based on augmented reality is visual
Change management system and method such that it is able to whole work progress is visualized completely, including construction model, construction technology, construction
Parameter, construction document information etc., it is real with reference to construction project time management system by augmented reality with threedimensional model as tie
Existing actual situation is integrally.
Technical scheme is as follows:A kind of construction speed Visualized management system based on augmented reality, including:Apply
Work control unit, for the Internet of Things perception data and manual entry information of automatic data collection job site, and to gather data enter
Row sorted generalization and arrangement, some progress nodes are resolved into reference to WBS by the work progress at scene, are compiled into construction schedule
It is managed;Dummy modeling unit, based on the data that the construction control unit is provided, carries out building the related virtual mould of construction
Type;Augmented reality unit, for being scanned to reality scene and being recognized, and the virtual mould that the Dummy modeling unit is provided
Type is added in identified reality scene, so as to be presented or show the augmented reality effect of construction speed.
Preferably, the construction control unit includes being used for the Internet of Things sensing module of collection site data, is used for into line number
According to the interconnection transport module of transmission and data analysis module for carrying out data analysis, the Internet of Things sensing module will be gathered
Field data is sent to the data analysis module by the interconnection transport module.
Preferably, the Dummy modeling unit is reconstructed, renders and reduces to virtual construction environment and model, and will
It is converted to unified form, to facilitate the augmented reality unit to transfer and load.
Preferably, the augmented reality unit includes the hardware module and the reception hardware mould for obtaining reality scene
The software module of the reality scene that block is obtained, the hardware module includes camera assembly and is communicated with the camera assembly to be connected
Image processor, camera assembly scanning reality scene obtains the scene image of the reality scene, and by the scene
Image is sent to described image processor;The software module is integrated in described image processor, by algorithm to the field
Scape image carries out feature recognition, and the dummy model that the Dummy modeling unit is obtained virtual information be added to it is identified
In reality scene.
Preferably, the virtual information includes virtual scene, virtual animation, file, form and statistics.
Preferably, the virtual model includes the dummy model of construction model, construction scene and construction technology animation.
A kind of method according to any of the above-described described construction speed Visualized management system based on augmented reality includes
Following steps:
First, the Internet of Things perception data and manual entry information of automatic data collection job site, and to gather data divided
Class is concluded and arranged, and the work progress at scene is resolved into some progress nodes with reference to WBS, and being compiled into construction schedule is carried out
Management;
2nd, the data provided based on step one, carry out building the related virtual information of construction;
3rd, reality scene is scanned and is recognized, and the dummy model that step 2 is provided is added to identified showing
In real field scape, so as to be presented or show the augmented reality effect of construction speed.
Preferably, in step one, construction schedule table and sweet is worked out to capital construction process using construction speed control platform
Spy schemes, and each construction node of the correspondence Gantt chart is collected and arranges corresponding construction flow chart, construction drawing, applies
The data of work inventory data and the people being related to, machine, thing, method and ring.
Preferably, in step 2, virtual construction environment and model are reconstructed, rendered and are reduced, and by its turn
It is changed to unified form.
Preferably, following steps are specifically included in step 3:
The scene image of the reality scene is obtained using camera assembly scanning reality scene;
Feature recognition is carried out to the scene image by algorithm, and the dummy model that the step 2 is obtained is virtual
Information superposition is in identified reality scene.
The technical scheme that the present invention is provided has the advantages that:
Model that the construction speed Visualized management system and method based on augmented reality create modeling with
The relevant information of construction managing and control system is associated and binds, and each threedimensional model is carried construction attribute information, then
The threedimensional model with attribute information is added in the construction scene of reality by augmented reality system, realizes that construction speed can
Depending on changing management, construction technology visualization and construction information visualization.
Brief description of the drawings
Fig. 1 is the structural frames of the construction speed Visualized management system based on augmented reality provided in an embodiment of the present invention
Figure;
Fig. 2 is the system framework schematic diagram of the construction speed Visualized management system based on augmented reality shown in Fig. 1;
Fig. 3 is the flow of the method for the construction speed Visualized management system based on augmented reality according to based on Fig. 1
Block diagram;
Fig. 4 is the schematic flow sheet of method shown in Fig. 3.
Specific embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples
The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and
It is not used in the restriction present invention.
The description of specific distinct unless the context otherwise, element and component in the present invention, quantity both can be with single shape
Formula is present, it is also possible to which multiple forms is present, and the present invention is defined not to this.Although the step in the present invention is entered with label
Arrangement is gone, but has been not used to limit the precedence of step, unless expressly stated the order of step or holding for certain step
Row is needed based on other steps, and the relative rank of otherwise step is adjustable.It is appreciated that used herein
Term "and/or" is related to and covers one of associated Listed Items or one or more of any and all possible group
Close.
Please refer to Fig. 1 and Fig. 2, the construction speed visualized management based on augmented reality provided in an embodiment of the present invention
System includes construction control unit 10, Dummy modeling unit 20 and augmented reality unit 30.
Wherein, the construction control unit 10 perceives number in construction operation layer for the Internet of Things of automatic data collection job site
According to manual entry information, and to gather data carry out sorted generalization and arrangement, with reference to WBS by scene work progress decompose
Into some progress nodes, it is compiled into construction schedule and is managed.
And, the construction control unit 10 is including the Internet of Things sensing module 11 for collection site data, for carrying out
The interconnection transport module 12 and the data analysis module 13 for carrying out data analysis of data transfer, the Internet of Things sensing module 11
The field data of collection is sent to the data analysis module 13 by the interconnection transport module 12.It is selectable, it is described
Internet of Things sensing module 11 is by multiple sensor groups into such as temperature sensor, humidity sensor and Smoke Sensor etc.;It is described
Interconnection transport module 12 can be data transmission bus, such as RS485 fieldbus etc., or Wireless Data Transmission mould
Block, such as bluetooth module, WALN modules or WIFI module etc.;The data analysis module 13 can be that inside is provided with corresponding
The processor of data processing algorithm, for example, programmable logic controller (PLC) or single-chip microcomputer etc..
Specifically, the construction control unit 10 works out construction speed meter using construction speed control platform to capital construction process
Draw table and Gantt chart, correspondence Gantt chart each construction node collect and arrange corresponding construction flow chart, construction drawing,
The data such as construction inventory data and the people, machine, thing, method, the ring that are related to.
The data that the Dummy modeling unit 20 is provided based on the construction control unit 10, carry out building construction correlation
Dummy model.Wherein, the dummy model includes but is not limited to the virtual mould of construction model, construction scene and construction technology animation
Type.And, the virtual information included in the dummy model including but not limited to virtual scene, virtual animation, file, form and
Statistics.In the present embodiment, data analysis module 13 of the construction control unit 10 from the construction control unit 10
Obtain data after treatment.
Specifically, the Dummy modeling unit 20 pairs virtual construction environment and model is reconstructed, renders and reduces, and
Unified form is converted into, to facilitate the augmented reality unit 30 to transfer and load.For example, using modeling tool
(3dmax, UG, Revit etc.) builds corresponding construction model according to the construction node of construction schedule table, with reference to construction drawing
Reduction construction threedimensional model, related construction technology animation is built according to construction flow chart, and applying that model is related to
Work drawing, the construction data information such as inventory and people, machine, thing, method, ring are associated with corresponding model in the way of attribute respectively,
Implementation model is inquired about with the two-way linkage of information.
The augmented reality unit 30 is used to that reality scene to be scanned and recognized, and by the Dummy modeling unit 20
The dummy model of offer is added in identified reality scene, so as to be presented or show the augmented reality effect of construction speed.
Specifically, the augmented reality unit 30 is included for obtaining the hardware module 31 of reality scene and receiving described hard
Part module 31 obtain reality scene software module 32, the hardware module 31 include camera assembly 311 and with the shooting
Component 311 communicates the image processor 312 of connection, and the scanning reality scene of the camera assembly 311 obtains the reality scene
Scene image, and the scene image is sent to described image processor 312.Selectable, the camera assembly 311 can
With including at least one high accuracy video camera.
The software module 32 is integrated in described image processor 312, and spy is carried out to the scene image by algorithm
Identification is levied, and the virtual information of the dummy model that the Dummy modeling unit 20 is obtained is added to identified reality scene
In.In the present embodiment, the image processor 312 of the augmented reality unit 30 and the communication link of Dummy modeling unit 20
Connect, such that it is able to being transferred from the Dummy modeling unit 20 and loading the dummy model, and based on the software module 32
Algorithm realize that the virtual information of dummy model for obtaining the Dummy modeling unit 20 is added to identified reality scene
In.
In the augmented reality unit 30, based on augmented reality layer, scan and know by the camera assembly 311
Not corresponding reality scene, and its corresponding virtual reality module is added in reality scene, by speech recognition technology or
Body-sensing peripheral technologies are browsed and checked to related model or information.
It should be appreciated that augmented reality layer (AR technology layers) in the augmented reality unit 30 is combined including actual situation
Technology, three-dimensional registration technology and human-computer interaction technology, three technologies cooperate so as to realize that the augmented reality unit 30 will
The information superposition such as realtime construction progress and the people being related to, machine, thing, method, ring in reality scene, finally by voice or body
Sense peripheral technologies realize man-machine interaction, to reach the target of management and control.
Please refer to Fig. 3 and Fig. 4 simultaneously again, it is a kind of based on the construction speed visualized management based on augmented reality shown in Fig. 1
The method of system, specifically includes following steps:
S1, the Internet of Things perception data of automatic data collection job site and manual entry information, and to gather data divided
Class is concluded and arranged, and the work progress at scene is resolved into some progress nodes with reference to WBS, and being compiled into construction schedule is carried out
Management.
Specifically, in step sl, using construction speed control platform to capital construction process establishment construction schedule table and
Gantt chart, and the correspondence Gantt chart each construction node collect and arrange corresponding construction flow chart, construction drawing,
The data of construction inventory data and the people, machine, thing, method and the ring that are related to.
S2, the data provided based on step S1, carry out building the related virtual information of construction.
Specifically volume, in step s 2, is reconstructed, renders and reduces to virtual construction environment and model, and by its
Be converted to unified form.
S3, reality scene is scanned and recognized, and the dummy model that step S2 is provided is added to identified showing
In real field scape, so as to be presented or show the augmented reality effect of construction speed.
Specifically, following steps are specifically included in step s3:
The scene image of the reality scene is obtained using camera assembly scanning reality scene;
Feature recognition is carried out to the scene image by algorithm, and the dummy model that the step 2 is obtained is virtual
Information superposition is in identified reality scene.
Compared to prior art, the technical scheme that the present invention is provided has the advantages that:
Model that the construction speed Visualized management system and method based on augmented reality create modeling with
The relevant information of construction managing and control system is associated and binds, and each threedimensional model is carried construction attribute information, then
The threedimensional model with attribute information is added in the construction scene of reality by augmented reality system, realizes that construction speed can
Depending on changing management, construction technology visualization and construction information visualization.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie
In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be in other specific forms realized.Therefore, no matter
From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power
Profit requires to be limited rather than described above, it is intended that all in the implication and scope of the equivalency of claim by falling
Change is included in the present invention.Any reference in claim should not be considered as the claim involved by limitation.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each implementation method is only wrapped
Containing an independent technical scheme, this narrating mode of specification is only that for clarity, those skilled in the art should
Specification an as entirety, the technical scheme in each embodiment can also be formed into those skilled in the art through appropriately combined
May be appreciated other embodiment.
Claims (10)
1. a kind of construction speed Visualized management system based on augmented reality, it is characterised in that:Including:
Construction control unit, for the Internet of Things perception data and manual entry information of automatic data collection job site, and to collection
Data carry out sorted generalization and arrangement, with reference to WBS by scene work progress resolve into some progress nodes, be compiled into construct into
Degree plan is managed;
Dummy modeling unit, based on the data that the construction control unit is provided, carries out building the related dummy model of construction;
Augmented reality unit, for being scanned to reality scene and being recognized, and by the Dummy modeling unit provide it is virtual
Model is added in identified reality scene, so as to be presented or show the augmented reality effect of construction speed.
2. the construction speed Visualized management system based on augmented reality according to claim 1, it is characterised in that:It is described
Construction control unit includes Internet of Things sensing module, the interconnection transport module for carrying out data transmission for collection site data
With the data analysis module for carrying out data analysis,
The Internet of Things sensing module sends to the data analysis mould field data of collection by the interconnection transport module
Block.
3. the construction speed Visualized management system based on augmented reality according to claim 1, it is characterised in that:It is described
Dummy modeling unit is reconstructed, renders and reduces to virtual construction environment and model, and is converted into unified form,
To facilitate the augmented reality unit to transfer and load.
4. the construction speed Visualized management system based on augmented reality according to claim 1, it is characterised in that:It is described
Augmented reality unit includes the reality scene that hardware module and the reception hardware module for obtaining reality scene are obtained
Software module,
The hardware module includes camera assembly and the image processor being connected, the shooting group is communicated with the camera assembly
Part scanning reality scene obtains the scene image of the reality scene, and the scene image is sent to described image treatment
Device;
The software module is integrated in described image processor, and feature recognition is carried out to the scene image by algorithm, and
The virtual information of the dummy model that the Dummy modeling unit is obtained is added in identified reality scene.
5. the construction speed Visualized management system based on augmented reality according to claim 4, it is characterised in that:It is described
Virtual information includes virtual scene, virtual animation, file, form and statistics.
6. the construction speed Visualized management system based on augmented reality according to claim 1, it is characterised in that:It is described
Virtual model includes the dummy model of construction model, construction scene and construction technology animation.
7. a kind of side according to any described construction speed Visualized management systems based on augmented reality of claim 1-6
Method, it is characterised in that:Comprise the following steps:
First, the Internet of Things perception data and manual entry information of automatic data collection job site, and data to gathering carry out classification and return
Receive and arrange, the work progress at scene is resolved into some progress nodes with reference to WBS, be compiled into construction schedule and managed
Reason;
2nd, the data provided based on step one, carry out building the related virtual information of construction;
3rd, reality scene is scanned and is recognized, and the dummy model that step 2 is provided is added to identified real field
Jing Zhong, so as to be presented or show the augmented reality effect of construction speed.
8. method according to claim 7, it is characterised in that:In step one, using construction speed control platform to base
Process establishment construction schedule table and Gantt chart are built, and each construction node of the correspondence Gantt chart collects corresponding with arrangement
Construction flow chart, construction drawing, construction inventory data and the people, machine, thing, method and the ring that are related to data.
9. method according to claim 7, it is characterised in that:In step 2, virtual construction environment and model are entered
Line reconstruction, render and reduce, and be converted into unified form.
10. method according to claim 7, it is characterised in that:Following steps are specifically included in step 3:
The scene image of the reality scene is obtained using camera assembly scanning reality scene;
Feature recognition is carried out to the scene image by algorithm, and the dummy model that the step 2 is obtained virtual information
It is added in identified reality scene.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710047631.2A CN106897817A (en) | 2017-01-22 | 2017-01-22 | A kind of construction speed Visualized management system and method based on augmented reality |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710047631.2A CN106897817A (en) | 2017-01-22 | 2017-01-22 | A kind of construction speed Visualized management system and method based on augmented reality |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106897817A true CN106897817A (en) | 2017-06-27 |
Family
ID=59198154
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710047631.2A Pending CN106897817A (en) | 2017-01-22 | 2017-01-22 | A kind of construction speed Visualized management system and method based on augmented reality |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106897817A (en) |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107679291A (en) * | 2017-09-14 | 2018-02-09 | 中建三局第建设工程有限责任公司 | Construction operation management method, storage device and mobile terminal based on BIM and AR |
CN107729686A (en) * | 2017-11-08 | 2018-02-23 | 江苏国泰新点软件有限公司 | Component methods of exhibiting, device, electronic equipment and the storage medium of BUILDINGS MODELS |
CN107742259A (en) * | 2017-10-31 | 2018-02-27 | 国网山东省电力公司济阳县供电公司 | A kind of distribution line construction training system with AR functions |
CN108550086A (en) * | 2018-04-13 | 2018-09-18 | 北京市轨道交通设计研究院有限公司 | A kind of recognition methods of Station construction speed and system |
CN108551519A (en) * | 2018-03-05 | 2018-09-18 | 腾讯科技(深圳)有限公司 | A kind of information processing method, device, storage medium and system |
CN108647929A (en) * | 2018-03-26 | 2018-10-12 | 崔战宾 | Construction Visualized management system with feedback and method |
CN109165329A (en) * | 2018-07-09 | 2019-01-08 | 中兵勘察设计研究院有限公司 | A kind of the underground pipe network intelligence control technology and system of fusion augmented reality and Internet of Things |
CN109377066A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | A kind of live Schedule monitoring system and method based on threedimensional model |
CN109785091A (en) * | 2018-12-10 | 2019-05-21 | 大象慧云信息技术有限公司 | A kind of invoice management method and system based on AR technology |
CN109829693A (en) * | 2019-01-21 | 2019-05-31 | 浙江浙东建设有限公司 | One kind being used for Construction Schedule management system and management method |
CN110473286A (en) * | 2019-08-02 | 2019-11-19 | 广州彩构网络有限公司 | A kind of construction tracking and system based on three dimensional design scheme |
CN110544226A (en) * | 2019-09-26 | 2019-12-06 | 天津大学 | real-time display system of water and electricity engineering grouting information based on augmented reality technology |
CN111311741A (en) * | 2020-03-23 | 2020-06-19 | 重庆忽米网络科技有限公司 | 5G communication-based interactive indoor space construction device and method |
CN111339112A (en) * | 2020-02-27 | 2020-06-26 | 武汉科技大学 | Building material informatization management and control method and system based on building information model |
CN113010936A (en) * | 2021-02-23 | 2021-06-22 | 上海巡智科技有限公司 | Auxiliary construction method, device and readable storage medium |
CN114636440A (en) * | 2022-01-29 | 2022-06-17 | 上海建工集团股份有限公司 | Equipment, system and method for assisting construction progress management |
CN114910125A (en) * | 2022-05-12 | 2022-08-16 | 武汉理工大学 | AR and IoT based pipeline monitoring system and method |
CN117094065A (en) * | 2023-10-19 | 2023-11-21 | 巴斯夫一体化基地(广东)有限公司 | Digital auxiliary construction method |
-
2017
- 2017-01-22 CN CN201710047631.2A patent/CN106897817A/en active Pending
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107679291A (en) * | 2017-09-14 | 2018-02-09 | 中建三局第建设工程有限责任公司 | Construction operation management method, storage device and mobile terminal based on BIM and AR |
CN107742259A (en) * | 2017-10-31 | 2018-02-27 | 国网山东省电力公司济阳县供电公司 | A kind of distribution line construction training system with AR functions |
CN107729686A (en) * | 2017-11-08 | 2018-02-23 | 江苏国泰新点软件有限公司 | Component methods of exhibiting, device, electronic equipment and the storage medium of BUILDINGS MODELS |
CN107729686B (en) * | 2017-11-08 | 2021-07-27 | 国泰新点软件股份有限公司 | Building model component display method and device, electronic equipment and storage medium |
CN108551519A (en) * | 2018-03-05 | 2018-09-18 | 腾讯科技(深圳)有限公司 | A kind of information processing method, device, storage medium and system |
CN108647929A (en) * | 2018-03-26 | 2018-10-12 | 崔战宾 | Construction Visualized management system with feedback and method |
CN108550086A (en) * | 2018-04-13 | 2018-09-18 | 北京市轨道交通设计研究院有限公司 | A kind of recognition methods of Station construction speed and system |
CN109165329A (en) * | 2018-07-09 | 2019-01-08 | 中兵勘察设计研究院有限公司 | A kind of the underground pipe network intelligence control technology and system of fusion augmented reality and Internet of Things |
CN109377066A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | A kind of live Schedule monitoring system and method based on threedimensional model |
CN109785091A (en) * | 2018-12-10 | 2019-05-21 | 大象慧云信息技术有限公司 | A kind of invoice management method and system based on AR technology |
CN109829693A (en) * | 2019-01-21 | 2019-05-31 | 浙江浙东建设有限公司 | One kind being used for Construction Schedule management system and management method |
CN110473286A (en) * | 2019-08-02 | 2019-11-19 | 广州彩构网络有限公司 | A kind of construction tracking and system based on three dimensional design scheme |
CN110544226A (en) * | 2019-09-26 | 2019-12-06 | 天津大学 | real-time display system of water and electricity engineering grouting information based on augmented reality technology |
CN111339112A (en) * | 2020-02-27 | 2020-06-26 | 武汉科技大学 | Building material informatization management and control method and system based on building information model |
CN111311741A (en) * | 2020-03-23 | 2020-06-19 | 重庆忽米网络科技有限公司 | 5G communication-based interactive indoor space construction device and method |
CN113010936A (en) * | 2021-02-23 | 2021-06-22 | 上海巡智科技有限公司 | Auxiliary construction method, device and readable storage medium |
CN114636440A (en) * | 2022-01-29 | 2022-06-17 | 上海建工集团股份有限公司 | Equipment, system and method for assisting construction progress management |
CN114636440B (en) * | 2022-01-29 | 2023-12-19 | 上海建工集团股份有限公司 | Equipment, system and method for assisting construction progress management |
CN114910125A (en) * | 2022-05-12 | 2022-08-16 | 武汉理工大学 | AR and IoT based pipeline monitoring system and method |
CN117094065A (en) * | 2023-10-19 | 2023-11-21 | 巴斯夫一体化基地(广东)有限公司 | Digital auxiliary construction method |
CN117094065B (en) * | 2023-10-19 | 2024-02-20 | 巴斯夫一体化基地(广东)有限公司 | Digital auxiliary construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106897817A (en) | A kind of construction speed Visualized management system and method based on augmented reality | |
JP7037204B2 (en) | Smart factory monitoring methods and systems | |
Longo et al. | Smart operators in industry 4.0: A human-centered approach to enhance operators’ capabilities and competencies within the new smart factory context | |
JP2020518079A (en) | Smart factory parallel control method and system | |
CN106649773A (en) | Big data collaborative analysis tool platform | |
CN113325816A (en) | Industrial Internet-oriented digital twin body data management method | |
CN110853746A (en) | Intelligent hospital system based on digital twin and construction method thereof | |
CN105043379B (en) | A kind of scenic spot browse path planing method based on space-time restriction, device | |
CN108983729A (en) | A kind of twin method and system of industrial production line number | |
CN106774192A (en) | Heat treatment intelligence system and its control method based on MES | |
CN105807628B (en) | Robot flexibility controller and its implementation for complicated CPS | |
CN115203842A (en) | Digital twinning system of hot stamping forming production line and construction method | |
CN115328068A (en) | Digital twinning system applied to industrial production | |
Kumar et al. | Computers in manufacturing: towards successful implementation of integrated automation system | |
CN107229794A (en) | A kind of CAE and VR model construction system and its management method | |
CN104460950A (en) | Implementation of simulation interactions between users and virtual objects by utilizing virtual reality technology | |
CN107845045A (en) | The various dimensions Digital Teaching Resources and its construction method of school workshop and application | |
CN104504175A (en) | Simulation system and simulation method for spacecraft assembling | |
CN116414081A (en) | Intelligent workshop real-time monitoring method based on digital twinning | |
Di Sia | Industry 4.0 revolution: introduction | |
CN107665500A (en) | Use the interior design system of Real-time Rendering Technology | |
CN114359478A (en) | Building modeling method based on BIM modular modeling | |
CN107667349A (en) | It is used for the method and system clustered to project data in multidisciplinary engineering system | |
CN105807725A (en) | SCADA intelligent monitoring scheduling system based on GDI and application method | |
Peng et al. | A networked virtual manufacturing system for SMEs |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170627 |