CN107679291A - Construction operation management method, storage device and mobile terminal based on BIM and AR - Google Patents

Construction operation management method, storage device and mobile terminal based on BIM and AR Download PDF

Info

Publication number
CN107679291A
CN107679291A CN201710829274.5A CN201710829274A CN107679291A CN 107679291 A CN107679291 A CN 107679291A CN 201710829274 A CN201710829274 A CN 201710829274A CN 107679291 A CN107679291 A CN 107679291A
Authority
CN
China
Prior art keywords
bim
information
location information
management method
operation management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710829274.5A
Other languages
Chinese (zh)
Inventor
李文建
汪小东
苏章
苏前广
赵恩堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201710829274.5A priority Critical patent/CN107679291A/en
Publication of CN107679291A publication Critical patent/CN107679291A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K7/00Methods or arrangements for sensing record carriers, e.g. for reading patterns
    • G06K7/10Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation
    • G06K7/14Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation using light without selection of wavelength, e.g. sensing reflected white light
    • G06K7/1404Methods for optical code recognition
    • G06K7/1408Methods for optical code recognition the method being specifically adapted for the type of code
    • G06K7/14172D bar codes
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of construction operation management method based on BIM and AR, comprise the following steps:The BIM model datas currently built are obtained, and BIM models are divided into multiple building blocks;When mobile terminal, which receives the AR that user sends, checks instruction, obtain when preceding camera scans outdoor scene place image corresponding to obtained location information and current location information;Show the electromechanical pipeline model corresponding to current location information and information and be superimposed on the image of outdoor scene place so that user checks electromechanical pipeline model hiding inside currently practical region.Construction operation management method proposed by the present invention based on BIM and AR, facilitates and its internal structure is checked after the completion of construction.

Description

Construction operation management method, storage device and mobile terminal based on BIM and AR
Technical field
The present invention relates to BIM technology and augmented reality field, more particularly to a kind of applying based on BIM and AR Labour movement dimension management method, storage device and mobile terminal.
Background technology
In building field, after acceptance of concealed work is completed in work progress, its internal reinforcing bar can not be just viewed Arrangement, complex node internal structure.During later stage O&M, it is necessary to take apart ceiling can just view be hidden in inside pipeline walk To and information, so as to being made troubles to maintenance.
The content of the invention
It is a primary object of the present invention to provide a kind of construction operation management method based on BIM and AR, storage device and Mobile terminal, it is intended to convenient that its internal structure is checked after the completion of construction.
To achieve the above object, the present invention provides a kind of construction operation management method based on BIM and AR, including following step Suddenly:
The BIM model datas currently built are obtained, and BIM models are divided into by multiple building blocks according to location information;
When receiving the AR that user sends and checking instruction, obtain when preceding camera scans obtained location information and current fixed Outdoor scene place image corresponding to the information of position;
Electromechanical pipeline model and information corresponding to display current location information are simultaneously superimposed on the image of outdoor scene place so that user looks into See electromechanical pipeline model hiding inside currently practical region.
Preferably, it is described to show electromechanical pipeline model and information corresponding to current location information and be superimposed on outdoor scene place shadow Also include after the step of checking electromechanical pipeline model hiding inside currently practical region as on for user:
When receiving the VR that user sends and checking instruction, obtain when preceding camera scan obtained location information and with BIM moulds The location information to be prestored in type is matched;
Show that complete professional dummy model and information are so that user checks BIM moulds corresponding to current region corresponding to current location information Type.
Preferably, it is described to show that complete professional dummy model and information are so that user checks currently corresponding to current location information Also include afterwards the step of BIM models corresponding to region:
When receiving the component that user sends according to the BIM models currently shown and checking instruction, show in BIM models and currently select The component information selected.
Preferably, the electromechanical pipeline model and information include hiding electric wire information inside BIM models, water pipe information, Airduct information and crane span structure information.
Preferably, it is described to show electromechanical pipeline model and information corresponding to current location information and be superimposed on outdoor scene place shadow Also include after the step of checking electromechanical pipeline model hiding inside currently practical region as on for user:
When receiving the remote control commands that user sends according to BIM models, the electromechanical equipment chosen to user sends control Instruction.
Preferably, the location information is Quick Response Code.
Present invention further propose that a kind of storage device, is stored with multiple instruction, it is described to instruct for processor loading simultaneously Perform:
The BIM model datas currently built are obtained, and BIM models are divided into by multiple building blocks according to location information;
When receiving the AR that user sends and checking instruction, obtain when preceding camera scans obtained location information and current fixed Outdoor scene place image corresponding to the information of position;
Electromechanical pipeline model and information corresponding to display current location information are simultaneously superimposed on the image of outdoor scene place so that user looks into See electromechanical pipeline model hiding inside currently practical region.
Present invention further propose that a kind of mobile terminal, including processor, for realizing each instruction;And including above-mentioned Storage device.
Preferably, the mobile terminal is tablet personal computer or mobile phone.
Construction operation management method proposed by the present invention based on BIM and AR, solves concealed work in work progress and tests Harvest into afterwards, the problem of its internal reinforcing bar arrangement, complex node internal structure can not be viewed.It need not be torn open during later stage O&M Kaitian's card can also view the pipeline trend and information for being hidden in inside, convenient for users.Believed simultaneously by positioning BIM models are divided into multiple building blocks by breath, realize accurate division.Based on BIM and AR construction operation management side Guttae Phacosylini Reality scene and dummy model are combined with mobile terminal, take virtual technology to scene, enhancing model is true reality True feeling.
Brief description of the drawings
Fig. 1 is mobile terminal of the present invention in the operating diagram using process;
Fig. 2 is the schematic flow sheet of the first embodiment of construction operation management method of the present invention based on BIM and AR;
Fig. 3 is the schematic flow sheet of the second embodiment of construction operation management method of the present invention based on BIM and AR.
In figure, 1-Quick Response Code;2-mobile terminal;3-BIM-AR manages APP;4-real scene.
The realization, functional characteristics and advantage of the object of the invention will be described further referring to the drawings in conjunction with the embodiments.
Embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
The present invention passes in and out a kind of construction operation management method based on BIM and AR.
Reference picture 1, it is proposed by the present invention based on BIM and AR construction operation management method first embodiment in, including Following steps:
Step S10, the BIM model datas currently built are obtained, and BIM models are divided into by multiple building blocks according to location information;
Step S20, when receiving the AR that user sends and checking instruction, obtain when preceding camera scan obtained location information with And outdoor scene place image corresponding to current location information;
Step S30, show current location information corresponding to electromechanical pipeline model and information and be superimposed on the image of outdoor scene place with Electromechanical pipeline model hiding inside currently practical region is checked for user.
Specifically, electromechanical pipeline model information includes the electric wire information inside hiding BIM models, water pipe information, airduct letter Breath and crane span structure information.In the present embodiment, location information is Quick Response Code, and certain location information can also be bar code etc., this hair It is bright that this is not construed as limiting.Electric wire information includes trend, electric current and the magnitude of voltage of circuit.Building block is a certain area in BIM models The models in domain, BIM models are divided into multiple building blocks, the actual area of Current Scan is only shown when such user checks, User is facilitated to check the details of current region.
BIM-AR management APP are may be configured as based on BIM and AR construction operation management method, load on mobile terminal (Mobile phone or tablet personal computer)In.When BIM models import BIM-AR management APP, the lattice BIM model conversions into fbx or max Formula, then the model of this form is loaded into BIM-AR management APP.
The set location of the architectural multiple Quick Response Codes of entity is as two microcode positions in BIM models.Entity is architectural to be set Multiple measurement points are put, each measurement point correspondingly places Quick Response Code.Reach the purpose of positioning by the way that actual situation two Quick Response Codes are overlapping.
User when in use, need to recall BIM models in tablet personal computer, then, it is architectural open camera scanning entity The Quick Response Code of setting, you can model and information are checked by mobile terminal.
The construction operation management method based on BIM and AR that the present embodiment proposes, solves concealed work in work progress Check and accept after completing, the problem of its internal reinforcing bar arrangement, complex node internal structure can not be viewed.Need not during later stage O&M The pipeline trend and information for being hidden in inside can also be viewed by taking ceiling apart, convenient for users.Pass through positioning simultaneously BIM models are divided into multiple building blocks by information, realize accurate division.Can based on BIM and AR construction operation management method Reality scene and dummy model are combined using mobile terminal, take virtual technology to scene, enhancing model is in reality The sense of reality.
Further, also include after step S30:
Step S40, when receiving the VR that user sends and checking instruction, obtain when preceding camera scans obtained location information simultaneously Matched with the location information to be prestored in BIM models;
Step S50, show that complete professional dummy model and information are so that user checks current region pair corresponding to current location information The BIM models answered.
That is, being provided with both of which in mobile terminal, one kind is VR patterns, now, is shown on mobile terminals Full Professional Model, it is seen that be the same angle consistent with reality scene, the entirely virtual BIM models with orientation, realize and moving Dummy model is shown in dynamic terminal.Another is AR patterns, on mobile terminals concealed structure and BUILDINGS MODELS, is opened electromechanical Model, real scene is caught by rear camera, virtual electromechanical pipeline model is superimposed on the basis of real scene, and The information of electromechanical pipeline can be checked, realizes the scene of virtual reality fusion, realizes the effect of augmented reality.
Further, also include after step S50:
Step S60, when receiving the component that user sends according to the BIM models currently shown and checking instruction, show BIM models In the component information that currently selects.
In VR patterns, when user selects some component by mobile terminal, you can show the component details.Specifically Ground, BIM-AR management APP pass through by specialty(Divide the specialties such as building, structure, electromechanics, curtain wall, steel construction), category(Point wall, The classifications such as beam, plate, post, ceiling), by component(Single BIM components)Deng the hiding of selectivity, the function of display model, reach VR and AR mode checks model and information.
The second embodiment of construction operation management method proposed by the present invention based on BIM and AR.The present embodiment and above-mentioned first Unlike embodiment, also include after step S30:
Step S70, when receiving the remote control commands that user sends according to BIM models, to the electromechanical equipment of user's selection Send control instruction.
That is, mobile terminal is additionally provided with IOT(Internet of Things)Pattern, can be by various information sensings Equipment, such as rfid device, infrared inductor, global positioning system, a variety of devices of laser scanner are combined with internet The huge network for getting up and being formed.The BIM models that mobile terminal is shown have individual virtual switch and actual Internet of things hardware It is connected, user is by controlling virtual switch can to realize the opening and closing of control device, while mobile terminal completes letter The display of breath and the control of hardware.User is realized by this mode actual electromechanical equipment can control by mobile terminal, Greatly facilitate user's use.
A kind of present invention further propose that storage device.
In this preferred embodiment, a kind of storage device is stored with multiple instruction, and described instruct loads and held for processor OK:
The BIM model datas currently built are obtained, and BIM models are divided into by multiple building blocks according to location information;
When receiving the AR that user sends and checking instruction, obtain when preceding camera scans obtained location information and current fixed Outdoor scene place image corresponding to the information of position;
Corresponding to display current location information in building block electromechanical pipeline model information and be superimposed on the image of outdoor scene place for User checks electromechanical pipeline model hiding inside currently practical region.
A kind of present invention further propose that mobile terminal.
In this preferred embodiment, a kind of mobile terminal, including processor, for realizing each instruction;And including above-mentioned Storage device.The mobile terminal is tablet personal computer or mobile phone.
The use process of this mobile terminal is as follows.
(1)BIM models are loaded into BIM-AR management APP:Form BIM model conversions into fbx or max, by this lattice The model of formula is loaded into BIM-AR management APP;
(2)It is accurate to place Quick Response Code:Quick Response Code is accurately placed in measurement point, the Quick Response Code is for carrying out the accurate fixed of model Position;
(3)Mobile scanning terminal QRCODE codes position:Use mobile terminal(Tablet personal computer or mobile phone)After scanning Quick Response Code positioning, i.e., Mobile terminal can be passed through(Tablet personal computer or mobile phone)Check model and information;
(4)User's unrestricted choice VR or AR mode check model and information.
The preferred embodiments of the present invention are these are only, are not intended to limit the scope of the invention, it is every to utilize this hair The equivalent structure transformation that bright specification and accompanying drawing content are made, or other related technical areas are directly or indirectly used in, Similarly it is included within the scope of the present invention.

Claims (9)

  1. A kind of 1. construction operation management method based on BIM and AR, it is characterised in that comprise the following steps:
    The BIM model datas currently built are obtained, and BIM models are divided into by multiple building blocks according to location information;
    When receiving the AR that user sends and checking instruction, obtain when preceding camera scans obtained location information and current fixed Outdoor scene place image corresponding to the information of position;
    Electromechanical pipeline model and information corresponding to display current location information are simultaneously superimposed on the image of outdoor scene place so that user looks into See electromechanical pipeline model hiding inside currently practical region.
  2. 2. the construction operation management method based on BIM and AR as claimed in claim 1, it is characterised in that the display is current Electromechanical pipeline model and information corresponding to location information are simultaneously superimposed on the image of outdoor scene place so that user checks currently practical area Also include afterwards the step of hiding electromechanical pipeline model inside domain:
    When receiving the VR that user sends and checking instruction, obtain when preceding camera scan obtained location information and with BIM moulds The location information to be prestored in type is matched;
    Show that complete professional dummy model and information are so that user checks BIM moulds corresponding to current region corresponding to current location information Type.
  3. 3. the construction operation management method based on BIM and AR as claimed in claim 2, it is characterised in that the display is current After complete professional dummy model corresponding to location information and information are for the step of user checks BIM models corresponding to current region Also include:
    When receiving the component that user sends according to the BIM models currently shown and checking instruction, show in BIM models and currently select The component information selected.
  4. 4. the construction operation management method based on BIM and AR as claimed in claim 1, it is characterised in that the electromechanical pipeline Model and information include hiding electric wire information, water pipe information, airduct information and the crane span structure information inside BIM models.
  5. 5. the construction operation management method based on BIM and AR as claimed in claim 1, it is characterised in that the display is current Electromechanical pipeline model and information corresponding to location information are simultaneously superimposed on the image of outdoor scene place so that user checks currently practical area Also include afterwards the step of hiding electromechanical pipeline model inside domain:
    When receiving the remote control commands that user sends according to BIM models, the electromechanical equipment chosen to user sends control Instruction.
  6. 6. the construction operation management method based on BIM and AR as claimed in claim 1, it is characterised in that the location information For Quick Response Code.
  7. 7. a kind of storage device, it is characterised in that be stored with multiple instruction, described instruct loads and performed for processor:
    The BIM model datas currently built are obtained, and BIM models are divided into by multiple building blocks according to location information;
    When receiving the AR that user sends and checking instruction, obtain when preceding camera scans obtained location information and current fixed Outdoor scene place image corresponding to the information of position;
    Electromechanical pipeline model and information corresponding to display current location information are simultaneously superimposed on the image of outdoor scene place so that user looks into See electromechanical pipeline model hiding inside currently practical region.
  8. 8. a kind of mobile terminal, it is characterised in that including processor, for realizing each instruction;And including such as claim 7 institute The storage device stated.
  9. 9. mobile terminal as claimed in claim 8, it is characterised in that the mobile terminal is tablet personal computer or mobile phone.
CN201710829274.5A 2017-09-14 2017-09-14 Construction operation management method, storage device and mobile terminal based on BIM and AR Pending CN107679291A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710829274.5A CN107679291A (en) 2017-09-14 2017-09-14 Construction operation management method, storage device and mobile terminal based on BIM and AR

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710829274.5A CN107679291A (en) 2017-09-14 2017-09-14 Construction operation management method, storage device and mobile terminal based on BIM and AR

Publications (1)

Publication Number Publication Date
CN107679291A true CN107679291A (en) 2018-02-09

Family

ID=61136072

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710829274.5A Pending CN107679291A (en) 2017-09-14 2017-09-14 Construction operation management method, storage device and mobile terminal based on BIM and AR

Country Status (1)

Country Link
CN (1) CN107679291A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108510596A (en) * 2018-03-30 2018-09-07 北京华麒通信科技股份有限公司 A kind of Design of Indoor Signal Distributed System method, apparatus, medium and equipment
CN108874340A (en) * 2018-06-13 2018-11-23 深圳市智汇幕墙科技有限公司 A kind of visualization building curtain wall management method and device
CN108921946A (en) * 2018-06-25 2018-11-30 中国人民解放军陆军工程大学 A kind of hidden pipeline of engineering based on BIM+AR measures and spatial position automatic matching method
CN109242979A (en) * 2018-09-05 2019-01-18 国家电网公司 A kind of hidden pipeline visualization system and method based on mixed reality technology
CN109341001A (en) * 2018-10-15 2019-02-15 珠海格力电器股份有限公司 A kind of method and device that the equipment electricity based on PV air-conditioner is shown
CN109492271A (en) * 2018-10-22 2019-03-19 上海建工四建集团有限公司 A kind of geometrical model light-weight technologg method in the BIM towards operation management
CN109522381A (en) * 2018-11-02 2019-03-26 长江空间信息技术工程有限公司(武汉) The hidden installation security detection method of building based on 3DGIS+BIM
CN109523105A (en) * 2018-08-27 2019-03-26 中铁上海工程局集团有限公司 A kind of visualization Risk Identification and equipment based on bim Yu ar technology
CN110234075A (en) * 2019-06-17 2019-09-13 滁州学院 Fireman's positioning and vital sign monitoring method under a kind of complexity emergency management and rescue environment
CN111179461A (en) * 2019-12-30 2020-05-19 万翼科技有限公司 BIM (building information modeling) -based routing inspection record generation method and equipment and storage medium
CN112102485A (en) * 2020-09-04 2020-12-18 中国十七冶集团有限公司 Method for carrying out space intelligent management based on AR technology
CN112907211A (en) * 2021-03-02 2021-06-04 惠州城际工程咨询有限公司 BIM-based project progress supervision method, device, equipment and storage medium
CN113066195A (en) * 2021-03-17 2021-07-02 广东电网有限责任公司梅州供电局 Power equipment inspection method and device, AR glasses and storage medium
CN113239443A (en) * 2021-06-03 2021-08-10 广州中硕建筑设计院有限公司 Intelligent space display structure design modeling method based on BIM software
CN113496554A (en) * 2020-04-01 2021-10-12 以见科技(上海)有限公司 Method and equipment for processing building information model

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484033A (en) * 2014-11-21 2015-04-01 上海同筑信息科技有限公司 BIM based virtual reality displaying method and system
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN105955463A (en) * 2016-04-26 2016-09-21 王立峰 BIM (Building Information Modeling)-based VR (Virtual Reality) virtual feeling system
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484033A (en) * 2014-11-21 2015-04-01 上海同筑信息科技有限公司 BIM based virtual reality displaying method and system
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN105955463A (en) * 2016-04-26 2016-09-21 王立峰 BIM (Building Information Modeling)-based VR (Virtual Reality) virtual feeling system
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
XIANGYU WANG等: "BIM + AR: Onsite Information Sharing and", <PROCEEDINGS OF THE 2012 IEEE 16TH INTERNATIONAL CONFERENCE ON COMPUTER SUPPORTED COOPERATIVE WORK IN DESIGN> *
互联立方BIM咨询: "看全球顶尖的BIM玩法:在增强现实(AR)领域的BIM应用", 《HTTPS://WWW.SOHU.COM/A/191563900_769918》 *
兰狐狸: "BIM技术在运维管理中的应用,BIM管理", 《HTTP://WWW.360DOC.COM/CONTENT/15/0726/22/9667630_487601832.SHTML》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108510596A (en) * 2018-03-30 2018-09-07 北京华麒通信科技股份有限公司 A kind of Design of Indoor Signal Distributed System method, apparatus, medium and equipment
CN108874340A (en) * 2018-06-13 2018-11-23 深圳市智汇幕墙科技有限公司 A kind of visualization building curtain wall management method and device
CN108921946A (en) * 2018-06-25 2018-11-30 中国人民解放军陆军工程大学 A kind of hidden pipeline of engineering based on BIM+AR measures and spatial position automatic matching method
CN109523105A (en) * 2018-08-27 2019-03-26 中铁上海工程局集团有限公司 A kind of visualization Risk Identification and equipment based on bim Yu ar technology
CN109242979A (en) * 2018-09-05 2019-01-18 国家电网公司 A kind of hidden pipeline visualization system and method based on mixed reality technology
CN109341001A (en) * 2018-10-15 2019-02-15 珠海格力电器股份有限公司 A kind of method and device that the equipment electricity based on PV air-conditioner is shown
CN109341001B (en) * 2018-10-15 2020-03-06 珠海格力电器股份有限公司 Photovoltaic air conditioner-based equipment electric quantity display method and device
CN109492271B (en) * 2018-10-22 2020-06-30 上海建工四建集团有限公司 Operation and maintenance management-oriented geometric model lightweight processing method in BIM
CN109492271A (en) * 2018-10-22 2019-03-19 上海建工四建集团有限公司 A kind of geometrical model light-weight technologg method in the BIM towards operation management
CN109522381A (en) * 2018-11-02 2019-03-26 长江空间信息技术工程有限公司(武汉) The hidden installation security detection method of building based on 3DGIS+BIM
CN109522381B (en) * 2018-11-02 2021-05-04 长江空间信息技术工程有限公司(武汉) Building hidden facility safety detection method based on 3DGIS + BIM
CN110234075A (en) * 2019-06-17 2019-09-13 滁州学院 Fireman's positioning and vital sign monitoring method under a kind of complexity emergency management and rescue environment
CN111179461A (en) * 2019-12-30 2020-05-19 万翼科技有限公司 BIM (building information modeling) -based routing inspection record generation method and equipment and storage medium
CN113496554A (en) * 2020-04-01 2021-10-12 以见科技(上海)有限公司 Method and equipment for processing building information model
CN112102485A (en) * 2020-09-04 2020-12-18 中国十七冶集团有限公司 Method for carrying out space intelligent management based on AR technology
CN112907211A (en) * 2021-03-02 2021-06-04 惠州城际工程咨询有限公司 BIM-based project progress supervision method, device, equipment and storage medium
CN113066195A (en) * 2021-03-17 2021-07-02 广东电网有限责任公司梅州供电局 Power equipment inspection method and device, AR glasses and storage medium
CN113239443A (en) * 2021-06-03 2021-08-10 广州中硕建筑设计院有限公司 Intelligent space display structure design modeling method based on BIM software
CN113239443B (en) * 2021-06-03 2022-07-05 广州中硕建筑设计院有限公司 Intelligent space display structure design modeling method based on BIM software

Similar Documents

Publication Publication Date Title
CN107679291A (en) Construction operation management method, storage device and mobile terminal based on BIM and AR
CN107632824B (en) A kind of generation method of augmented reality module, generating means and generate system
CN103076877B (en) Posture is used to interact with the mobile device in vehicle
O'Neill et al. A testbed for evaluating human interaction with ubiquitous computing environments
KR102442137B1 (en) Apparatus, method and computer-readable storage medium for generating digital twin space linked with webgl-based url link
CN107832712A (en) Biopsy method, device and computer-readable recording medium
CN108876732A (en) Face U.S. face method and device
CN106775328B (en) Multi-person interaction method and system based on digital artistic landscape device
CN109543011A (en) Question and answer data processing method, device, computer equipment and storage medium
CN112927260B (en) Pose generation method and device, computer equipment and storage medium
CN105872201A (en) Method for remotely controlling document display through intelligent terminal, intelligent terminal and computer equipment
CN109657539A (en) Face value evaluation method and device, readable storage medium and electronic equipment
CN111062074B (en) Building space quality virtual simulation and intelligent evaluation method
CN114998491A (en) Digital human driving method, device, equipment and storage medium
CN109508090A (en) A kind of augmented reality display board system having interactivity
CN111381679A (en) AR-based assembly type building construction training method and device and computing equipment
CN106502401B (en) Image control method and device
CN108230202A (en) A kind of fire-fighting simulative training system and method
CN108762726A (en) Basic framework development platform and the method played by Platform Designing
US11423628B2 (en) System and method for converting a two-dimensional floor plan into an interactable three-dimensional simulation
CN108537165A (en) Method and apparatus for determining information
CN114693187B (en) Operation analysis method and device of tower crane cluster, storage medium and terminal
JP7130215B1 (en) Planned building confirmation system
KR20230046380A (en) Method for providing marketing service using Augmented Reality
CN114299271A (en) Three-dimensional modeling method, three-dimensional modeling apparatus, electronic device, and readable storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180209