CN111339112A - Building material informatization management and control method and system based on building information model - Google Patents

Building material informatization management and control method and system based on building information model Download PDF

Info

Publication number
CN111339112A
CN111339112A CN202010126111.2A CN202010126111A CN111339112A CN 111339112 A CN111339112 A CN 111339112A CN 202010126111 A CN202010126111 A CN 202010126111A CN 111339112 A CN111339112 A CN 111339112A
Authority
CN
China
Prior art keywords
building
virtual
information
real
building material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010126111.2A
Other languages
Chinese (zh)
Other versions
CN111339112B (en
Inventor
江世堂
李洁
袁晶
吴雄辉
陈璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Science and Engineering WUSE
Original Assignee
Wuhan University of Science and Engineering WUSE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Science and Engineering WUSE filed Critical Wuhan University of Science and Engineering WUSE
Priority to CN202010126111.2A priority Critical patent/CN111339112B/en
Publication of CN111339112A publication Critical patent/CN111339112A/en
Application granted granted Critical
Publication of CN111339112B publication Critical patent/CN111339112B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/23Updating
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/24Querying
    • G06F16/245Query processing
    • G06F16/2455Query execution
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L51/00User-to-user messaging in packet-switching networks, transmitted according to store-and-forward or real-time protocols, e.g. e-mail
    • H04L51/04Real-time or near real-time messaging, e.g. instant messaging [IM]
    • H04L51/046Interoperability with other network applications or services

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Engineering & Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Operations Research (AREA)
  • Computational Linguistics (AREA)
  • Geometry (AREA)
  • Quality & Reliability (AREA)
  • Computer Graphics (AREA)
  • Software Systems (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of building monitoring, and provides a building material informatization control method and system based on a building information model, wherein the method comprises the following steps: the building information model is used for respectively carrying out one-to-one informationized association processing on each virtual building material in a real storage area to which the real construction site belongs and each real building material in a virtual storage area to which the virtual construction site belongs to obtain corresponding building material information association results, and dynamically updating all the virtual building materials in the building information model according to all the building material information association results, so that the state of all the virtual building materials in the virtual building site pushed into the virtual construction process is consistent with the state of all the real building materials in the real building site pushed into the real construction process, the operation of repeatedly scanning the bar codes on the real building materials is simplified, the consistency between the state of the virtual building materials and the state of the real building materials is enhanced, and the timeliness of informationized building material control is improved.

Description

Building material informatization management and control method and system based on building information model
Technical Field
The invention relates to the technical field of building monitoring, in particular to a building material informatization management and control method and system based on a building information model.
Background
With the continuous development and wide application of the information technology, the application of the information technology to the informatization monitoring of the construction process plays an important role in accelerating the construction process, greatly saves the manpower and improves the efficiency of the construction engineering.
In the related art, a building material informatization management and control method based on a building material information model comprises the following steps: the method comprises the steps of splitting components of an integrally designed model to form a building information model, simulating a real construction site through the building information model, converting information in the building information model into constructed production data information to manage the production process of real building materials, obtaining position information of the real building materials by scanning bar codes on the real building materials, transmitting the position information into the building information model to manage the transportation process of the real building materials, and obtaining information of the whole life cycle of the real building materials from the building information model by scanning the bar codes again to manage the operation and maintenance process of the real building materials.
However, the building material informatization control method based on the building material information model focuses on applying the building information model to perform full-life cycle control on the building material, and in the full-life cycle control process, the barcode on the real building material needs to be repeatedly scanned, so that the informatization control process of the real building material is complicated, the building material information in the building material information model is easily disconnected from the state of the real building material on the real building site, and the timeliness of the informatization control building material is damaged.
Disclosure of Invention
The invention provides a building material informatization control method and system based on a building material information model, aiming at the defects that the existing building material informatization control method based on the building material information model needs to repeatedly scan bar codes on real building materials, and building material information in the building material information model is easy to be disjointed with the state of the real building materials on a real building site.
According to a first aspect of the invention, a building material informatization management and control method based on a building information model is provided, which comprises the following steps:
constructing a virtual building site corresponding to a real building site through a building information model, wherein the real building site comprises a real storage area and at least one real building material in the real storage area, and the virtual building site comprises a virtual storage area corresponding to the real storage area and at least one virtual building material in the virtual storage area;
respectively carrying out one-to-one informatization association processing on each virtual building material and each real building material through the building information model to obtain corresponding building material information association results, wherein each building material information association result is used for representing the unique corresponding relation between each virtual building material and each real building material;
and dynamically updating all the virtual building materials in the building information model according to all the building material information correlation results, so that the state of all the virtual building materials in the virtual building site pushed into the virtual construction process is consistent with the state of all the real building materials in the real building site pushed into the real construction process.
According to a second aspect of the present invention, there is provided a building material informatization management and control system based on a building information model, including:
the building system comprises a building information model, a building module and a control module, wherein the building information model is used for building a virtual building site corresponding to a real building site, the real building site comprises a real storage area and at least one real building material in the real storage area, and the virtual building site comprises a virtual storage area corresponding to the real storage area and at least one virtual building material in the virtual storage area;
the correlation module is used for performing one-to-one informatization correlation processing on each virtual building material and each real building material through the building information model to obtain corresponding building material information correlation results, and each building material information correlation result is used for representing the unique corresponding relation between each virtual building material and each real building material;
and the updating module is used for dynamically updating all the virtual building materials in the building information model according to all the building material information correlation results, so that the state of all the virtual building materials in the virtual building site pushed into the virtual construction process is consistent with the state of all the real building materials in the real building site pushed into the real construction process.
The building material informatization control method and system based on the building information model have the beneficial effects that: the relevance between each virtual building material and each real building material is respectively enhanced through the building material information relevance result, the bar code on the real building material does not need to be repeatedly scanned, the operation of repeatedly scanning the bar code is simplified, all the virtual building materials are dynamically updated in the building information model through all the building material information relevance results, the consistency between the state that each virtual building material is presented in the virtual construction process at the virtual building site and the state that each real building material is presented in the real construction process at the real building site is enhanced, the defect that building material information in the building material information model is easy to be disconnected from the state that the real building material is presented in the real building site in the existing building material informatization control method based on the building material information model is overcome, the probability that the building material information in the building material information model and the state that the real building material is disconnected at the real building site is reduced, the timeliness of the informationized management and control building materials is also promoted.
Drawings
Fig. 1 is a schematic flow chart of a building material informatization management and control method based on a building information model according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a building material informatization management and control system based on a building information model according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of another building material informatization management and control system based on a building information model according to an embodiment of the present invention.
Detailed Description
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth by way of illustration only and are not intended to limit the scope of the invention.
Example one
Referring to fig. 1, the building material informatization management and control method based on the building information model includes the following operation steps:
step 10, constructing a virtual building site corresponding to a real building site through a building information model, wherein the real building site comprises a real storage area and at least one real building material in the real storage area, and the virtual building site comprises a virtual storage area corresponding to the real storage area and at least one virtual building material in the virtual storage area;
step 20, respectively carrying out one-to-one informatization association processing on each virtual building material and each real building material through a building information model to obtain corresponding building material information association results, wherein each building material information association result is used for representing the unique corresponding relation between each virtual building material and each real building material;
and step 30, dynamically updating the virtual building materials in the building information model according to the correlation results of all the building material information, so that the state of all the virtual building materials in the virtual building site pushed into the virtual construction process is consistent with the state of all the real building materials in the real building site pushed into the real construction process.
Illustratively, the building material informatization management and control method based on the building information model is applied to an intelligent terminal, the intelligent terminal comprises a memory and a processor coupled with the memory, the memory can be configured to store the building information model, the processor can be configured to load and run the building information model, and the intelligent terminal executes any operation step from step 10 to step 30 during the building information model is run by the processor.
Illustratively, the intelligent terminal may be any one of a notebook computer, a desktop computer, a central control computer and a business server, the building information model may include a model formed in advance by a revit program and a construction science program, and the virtual building material and the real building material may be fabricated building components, respectively.
The relevance between each virtual building material and each real building material is respectively enhanced through the building material information relevance result, the bar code on the real building material does not need to be repeatedly scanned, the operation of repeatedly scanning the bar code is simplified, all the virtual building materials are dynamically updated in the building information model through all the building material information relevance results, the consistency between the state that each virtual building material is presented in the virtual construction process at the virtual building site and the state that each real building material is presented in the real construction process at the real building site is enhanced, the defect that building material information in the building material information model is easy to be disconnected from the state that the real building material is presented in the real building site in the existing building material informatization control method based on the building material information model is overcome, the probability that the building material information in the building material information model and the state that the real building material is disconnected at the real building site is reduced, the timeliness of the informationized management and control building materials is also promoted.
As a specific optional manner, step 10 specifically includes the following operation steps:
step 11, detecting a first operation instruction set in the intelligent terminal when the building information model is operated by the intelligent terminal, and inputting a parameter set corresponding to a real building site in the building information model in response to the first operation instruction set;
and 12, after the parameter set is input into the building information model, detecting a second operation instruction set in the intelligent terminal, responding to the second operation instruction set, and three-dimensionally planning out a virtual building site in the building information model according to the parameter set.
Illustratively, the intelligent terminal further includes an operation identifier coupled with the processor, and when a mouse operation occurs on a parameter input interface provided by the building information model on the intelligent terminal, a first operation instruction set corresponding to the mouse operation is identified by the operation identifier, where the first operation instruction set may include a character input instruction, a click instruction, a double click instruction, and the like, referring to the detection mode and the configuration of the first operation instruction set, and those skilled in the art can understand that the first operation instruction set is similar to the second operation instruction set, and for the sake of brief description, details are not repeated here.
The first operation instruction set and the second operation instruction set are detected in the intelligent terminal in a time sequence mode, so that the parameter set is transmitted into the building information model in a time-sharing mode and the virtual building site is built in the building information model, and the reliability of building the virtual building site is improved.
As a specific optional manner, step 20 specifically includes the following operation steps:
step 21, inputting the first building material codes of the real building materials into a building information model respectively, wherein the first building material codes of the real building materials are used for uniquely identifying the real building materials which are in one-to-one correspondence with the virtual building materials respectively;
and step 22, respectively carrying out one-to-one correlation processing on the first building material codes of the real building materials and the second building material codes of the virtual building materials through the building information model, wherein the second building material codes of the virtual building materials are respectively used for uniquely identifying the virtual building materials.
Illustratively, during the building information model is operated by the intelligent terminal, a third operating instruction set is detected in the intelligent terminal, and in response to the third operating instruction set, the first building material code to which each real building material belongs is recorded in the building information model, and the third operating instruction set is similar to the first operating instruction set, and is not repeated here for the sake of brevity.
In the building information model, for example, a first building material code to which each real building material belongs is recorded in each corresponding virtual building material, and a second building material code pre-arranged in each virtual building material is associated with the corresponding first building material code, for example: the first building material code can adopt an RFID code and the second building material code can adopt an ID code, so that the mode of establishing unique association between each virtual building material and each real building material is simplified, and the association efficiency of virtual and real building materials is favorably ensured.
As a specific optional manner, step 30 specifically includes the following operation steps:
step 31, starting an instant messaging program in the intelligent terminal when the building information model is operated by the intelligent terminal, so that the instant messaging program and the building information model are both operated by the intelligent terminal;
step 32, packaging the building material information correlation results through an instant messaging program to obtain corresponding construction information query request messages, and performing automatic communication control on the intelligent terminal, so that the intelligent terminal sends the construction information query request messages to an instant messaging server in communication connection with the intelligent terminal, and after the intelligent terminal receives the response messages respectively, analyzing and processing the response messages respectively to obtain corresponding first update information sets, wherein the response messages are sent by the instant messaging server respectively and are used for responding to the construction information query request messages, and the first update information sets are used for reflecting the state that the building materials are really displayed on a real building site and are pushed into a real construction process;
step 33, according to all the first update information sets, in the building information model, performing three-dimensional dynamic deduction processing on all virtual building materials associated with all the building material information association results to obtain a second update information set, wherein the second update information set is used for reflecting the state that all the virtual building materials are pushed into the virtual construction process on the virtual building site;
and step 34, three-dimensionally planning all virtual building materials in the building information model again according to the second updated information set.
Illustratively, the instant messaging program can comprise a qq application program or a WeChat application program or an enterprise information communication application program oriented to the building engineering, and the like, under the condition that the building information model lacks an instant information communication function, the instant messaging program well makes up a short board of the building information model in the aspect of instant information communication, so that the intelligent terminal is in communication interaction with the instant messaging server in the form of a message, and in the communication interaction process, the message is used as an information carrier, so that the timeliness of each building material information correlation result and each first update information set is ensured.
Illustratively, after receiving any one construction information query request message, the instant messaging server pushes any one construction information query request message to other intelligent terminals, so that the other intelligent terminals upload corresponding first update information sets to the instant messaging server in a message form according to building material information correlation results in any one construction information query request message, and after receiving any one first update information set, the instant messaging server also packs any one first update information set into a corresponding response message.
Illustratively, any first update information set can be input in a man-machine interaction mode or automatically input into other intelligent terminals, and taking a first update information set as an example, the first update information set can include real construction site planning information, real storage area use information, real construction progress information and the like.
And a second updating information set reflecting the states required to be presented by all the virtual building materials is deduced in the building information model through all the first updating information sets, and all the virtual building materials are three-dimensionally reconstructed in the building information model through the second updating information set, so that the dynamic updating efficiency, accuracy and stability of all the virtual building materials in the building information model are ensured, and the authenticity and timeliness of the states presented by all the virtual building materials and the states presented by all the real building materials are promoted to be consistent.
As a specific optional manner, in step 32, the packaging processing is performed on the correlation results of the building material information through the instant messaging program, which specifically includes the following operation steps: respectively storing the correlation results of the building material information in a preset storage space in the intelligent terminal in order; respectively transferring the building material information correlation results from the preset storage space to an instant messaging program according to the sequence of storing the building material information correlation results into the preset storage space; and when the building material information correlation results exist in the instant communication program, respectively packaging the building material information correlation results in the instant communication program according to a preset network communication protocol.
Illustratively, when each building material information correlation result is stored in the preset storage space, the corresponding storage time is recorded, each building material information correlation result and the corresponding storage time are respectively constructed into a corresponding key value pair, each key value pair is respectively stored in the preset storage space, the preset storage space is stored into each building material information correlation result in a time sequence, and the building material information correlation results are transferred to the instant messaging program from the preset storage space time sequence, the instant messaging program is not required to be directly connected with the building information model, the difficulty of transferring each building material information correlation result from the building information model to the instant messaging program is reduced, and the orderliness of storing all building material information correlation results in the instant messaging program is enhanced.
Example two
Referring to fig. 2, the building information management and control system based on the building information model includes: the device comprises a building module, an association module and an updating module.
The building module is used for building a virtual building site corresponding to the real building site through the building information model, the real building site comprises a real storage area and at least one real building material in the real storage area, and the virtual building site comprises a virtual storage area corresponding to the real storage area and at least one virtual building material in the virtual storage area.
The building module is specifically configured to: the method includes detecting a first operating instruction set in the intelligent terminal during operation of the building information model by the intelligent terminal, inputting a parameter set corresponding to a real building site in the building information model in response to the first operating instruction set, detecting a second operating instruction set in the intelligent terminal after the parameter set is input in the building information model, and three-dimensionally planning a virtual building site in the building information model according to the parameter set in response to the second operating instruction set.
And the association module is used for performing one-to-one informationized association processing on each virtual building material and each real building material through the building information model to obtain corresponding building material information association results, and each building material information association result is used for representing the unique corresponding relationship between each virtual building material and each real building material.
The association module is specifically configured to: inputting the first building material codes of the real building materials into a building information model respectively, wherein the first building material codes of the real building materials are used for uniquely identifying the real building materials which are in one-to-one correspondence with the virtual building materials respectively; and respectively carrying out one-to-one correlation processing on the first building material codes of the real building materials and the second building material codes of the virtual building materials through a building information model, wherein the second building material codes of the virtual building materials are respectively used for uniquely identifying the virtual building materials.
And the updating module is used for dynamically updating all the virtual building materials in the building information model according to the correlation results of all the building material information, so that the states of all the virtual building materials in the virtual building site pushed into the virtual construction process are consistent with the states of all the real building materials in the real building site pushed into the real construction process.
Referring to fig. 3, the update module specifically includes a parallel control sub-module, a message processing sub-module, a three-dimensional deduction sub-module, and a re-planning sub-module.
And the parallel control submodule is used for starting an instant communication program in the intelligent terminal when the building information model is operated by the intelligent terminal, so that the instant communication program and the building information model are operated by the intelligent terminal.
And the message processing submodule is used for respectively packaging the correlation results of the building material information through an instant communication program to obtain corresponding construction information query request messages, carrying out automatic communication control on the intelligent terminal to enable the intelligent terminal to send the construction information query request messages to an instant communication server in communication connection with the intelligent terminal, and respectively analyzing and processing the response messages after the intelligent terminal receives the response messages respectively to obtain corresponding first update information sets, wherein the response messages are respectively sent by the instant communication server and used for responding to the construction information query request messages, and the first update information sets are respectively used for reflecting the state that each real building material is displayed on a real building site and is pushed into the real construction process.
The message processing submodule is specifically configured to, during execution of the process of respectively performing the packaging processing on the building material information association results through the instant messaging program: respectively storing the correlation results of the building material information in a preset storage space in the intelligent terminal in order; respectively transferring the building material information correlation results from the preset storage space to an instant messaging program according to the sequence of storing the building material information correlation results into the preset storage space; and when the building material information correlation results exist in the instant communication program, respectively packaging the building material information correlation results in the instant communication program according to a preset network communication protocol.
And the three-dimensional deduction submodule is used for performing three-dimensional dynamic deduction processing of a virtual construction process on all virtual building materials associated with all building material information correlation results in the building information model according to all the first update information sets to obtain a second update information set, and the second update information set is used for reflecting the state that all the virtual building materials are pushed into the virtual construction process on the virtual building site.
And the re-planning submodule is used for re-three-dimensionally planning all the virtual building materials in the building information model according to the second updating information set.
The reader should understand that in the description of this specification, reference to the description of the terms "aspect," "embodiment," "particular manner," and "exemplary" etc., means that a particular feature, step, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention, and the terms "first" and "second," etc., are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second", etc., may explicitly or implicitly include at least one of the feature.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (10)

1. A building material informatization control method based on a building information model is characterized by comprising the following steps:
constructing a virtual building site corresponding to a real building site through a building information model, wherein the real building site comprises a real storage area and at least one real building material in the real storage area, and the virtual building site comprises a virtual storage area corresponding to the real storage area and at least one virtual building material in the virtual storage area;
respectively carrying out one-to-one informatization association processing on each virtual building material and each real building material through the building information model to obtain corresponding building material information association results, wherein each building material information association result is used for representing the unique corresponding relation between each virtual building material and each real building material;
and dynamically updating all the virtual building materials in the building information model according to all the building material information correlation results, so that the state of all the virtual building materials in the virtual building site pushed into the virtual construction process is consistent with the state of all the real building materials in the real building site pushed into the real construction process.
2. A building information management and control method based on a building information model according to claim 1, wherein the building information model is used to construct a virtual building site corresponding to a real building site, and specifically comprises:
detecting a first operating instruction set in the intelligent terminal during the building information model is operated by the intelligent terminal, and inputting a parameter set corresponding to the real building site in the building information model in response to the first operating instruction set;
after the parameter set is input into the building information model, detecting a second operation instruction set in the intelligent terminal, and responding to the second operation instruction set, and three-dimensionally planning out the virtual building site in the building information model according to the parameter set.
3. A building information management and control method based on a building information model according to claim 1, wherein the building information model is used for performing one-to-one informatization association processing on each virtual building material and each real building material, and specifically comprises:
inputting the first building material codes of the real building materials into the building information model respectively, wherein the first building material codes of the real building materials are used for uniquely identifying the real building materials which are in one-to-one correspondence with the virtual building materials respectively;
and respectively carrying out one-to-one correlation processing on the first building material code of each real building material and the second building material code of each virtual building material through the building information model, wherein the second building material code of each virtual building material is respectively used for uniquely identifying each virtual building material.
4. A building material informatization management and control method based on a building material information model according to any one of claims 1-3, wherein the method for dynamically updating all the virtual building materials in the building material information model according to all the building material information correlation results specifically comprises:
starting an instant messaging program in the intelligent terminal when the building information model is operated by the intelligent terminal, so that the instant messaging program and the building information model are both operated by the intelligent terminal;
respectively packaging the building material information correlation results through the instant communication program to obtain corresponding construction information query request messages, and carrying out automatic communication control on the intelligent terminal to enable the intelligent terminal to send the construction information query request messages to an instant communication server in communication connection with the intelligent terminal, and after the intelligent terminal receives the response messages respectively, analyzing the response messages respectively to obtain corresponding first update information sets, wherein the response messages are sent by the instant communication server respectively and are used for responding to the construction information query request messages, and the first update information sets are used for reflecting the state that the real building materials are displayed on the real building site and pushed into the real construction process;
according to all the first update information sets, in the building information model, performing three-dimensional dynamic deduction processing of the virtual construction process on all the virtual building materials associated with all the building material information association results to obtain a second update information set, wherein the second update information set is used for reflecting the state of all the virtual building materials in the virtual construction process promoted by the virtual construction site;
and planning all the virtual building materials in the building information model again in three dimensions according to the second updated information set.
5. A building information management and control method based on a building information model according to claim 4, wherein the packaging processing is performed on each building information correlation result through the instant messaging program, and specifically comprises:
respectively storing the correlation results of the building material information in a preset storage space in the intelligent terminal in order;
respectively transferring the building material information correlation results from the preset storage space to the instant messaging program according to the sequence of storing the building material information correlation results into the preset storage space;
and when the building material information correlation results exist in the instant messaging program, respectively packaging the building material information correlation results in the instant messaging program according to a preset network communication protocol.
6. The utility model provides a building materials informatization management and control system based on building information model which characterized in that includes:
the building system comprises a building information model, a building module and a control module, wherein the building information model is used for building a virtual building site corresponding to a real building site, the real building site comprises a real storage area and at least one real building material in the real storage area, and the virtual building site comprises a virtual storage area corresponding to the real storage area and at least one virtual building material in the virtual storage area;
the association module is used for performing one-to-one informatization association processing on each virtual building material and each virtual building material through the building information model to obtain corresponding building material information association results, and each building material information association result is used for representing the unique corresponding relation between each virtual building material and each real building material;
and the updating module is used for dynamically updating all the virtual building materials in the building information model according to all the building material information correlation results, so that the state of all the virtual building materials in the virtual building site pushed into the virtual construction process is consistent with the state of all the real building materials in the real building site pushed into the real construction process.
7. A building material informatization management and control system based on building information models according to claim 6, wherein the construction module is specifically configured to:
detecting a first operating instruction set in the intelligent terminal during the building information model is operated by the intelligent terminal, and inputting a parameter set corresponding to the real building site in the building information model in response to the first operating instruction set;
after the parameter set is input into the building information model, detecting a second operation instruction set in the intelligent terminal, and responding to the second operation instruction set, and three-dimensionally planning out the virtual building site in the building information model according to the parameter set.
8. A building materials informatization management and control system based on building information models according to claim 6, wherein the correlation module is specifically configured to:
inputting the first building material codes of the real building materials into the building information model respectively, wherein the first building material codes of the real building materials are used for uniquely identifying the real building materials which are in one-to-one correspondence with the virtual building materials respectively;
and respectively carrying out one-to-one correlation processing on the first building material code of each real building material and the second building material code of each virtual building material through the building information model, wherein the second building material code of each virtual building material is respectively used for uniquely identifying each virtual building material.
9. A building materials informatization management and control system based on building information models according to any one of claims 6-8, wherein the update module specifically comprises: the parallel control sub-module, the message processing sub-module, the three-dimensional deduction sub-module and the re-planning sub-module:
the parallel control submodule is used for starting an instant messaging program in the intelligent terminal when the building information model is operated by the intelligent terminal, so that the instant messaging program and the building information model are both operated by the intelligent terminal;
the message processing submodule is used for respectively packaging the correlation results of the building material information through the instant communication program to obtain corresponding construction information query request messages, and performs automatic communication control on the intelligent terminal, so that the intelligent terminal sends each construction information inquiry request message to an instant messaging server in communication connection with the intelligent terminal, and, after the intelligent terminal receives each response message respectively, each response message is analyzed and processed respectively to obtain a corresponding first updating information set, each response message is sent by the instant messaging server and used for responding to each construction information inquiry request message, and each first updating information set is used for reflecting the state that each real building material is pushed into the real construction process on the real building site;
the three-dimensional deduction submodule is used for performing three-dimensional dynamic deduction processing of the virtual construction process on all the virtual building materials related to all the building material information correlation results in the building information model according to all the first updating information sets to obtain a second updating information set, and the second updating information set is used for reflecting the state that all the virtual building materials are pushed into the virtual construction process on the virtual building site;
and the re-planning submodule is used for re-planning all the virtual building materials in the building information model in a three-dimensional manner according to the second updating information set.
10. A building information management and control system based on the building information model according to claim 9, wherein the message processing sub-module is specifically configured to:
respectively storing the correlation results of the building material information in a preset storage space in the intelligent terminal in order;
respectively transferring the building material information correlation results from the preset storage space to the instant messaging program according to the sequence of storing the building material information correlation results into the preset storage space;
and when the building material information correlation results exist in the instant messaging program, respectively packaging the building material information correlation results in the instant messaging program according to a preset network communication protocol.
CN202010126111.2A 2020-02-27 2020-02-27 Building material informatization management and control method and system based on building information model Active CN111339112B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010126111.2A CN111339112B (en) 2020-02-27 2020-02-27 Building material informatization management and control method and system based on building information model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010126111.2A CN111339112B (en) 2020-02-27 2020-02-27 Building material informatization management and control method and system based on building information model

Publications (2)

Publication Number Publication Date
CN111339112A true CN111339112A (en) 2020-06-26
CN111339112B CN111339112B (en) 2023-07-25

Family

ID=71185607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010126111.2A Active CN111339112B (en) 2020-02-27 2020-02-27 Building material informatization management and control method and system based on building information model

Country Status (1)

Country Link
CN (1) CN111339112B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007323497A (en) * 2006-06-02 2007-12-13 Chiyoda Corp Progress management system and management server
TW201001332A (en) * 2008-06-17 2010-01-01 Nat Univ Chung Hsing A device and method for constructing the real object in virtual reality
US20140207774A1 (en) * 2013-01-24 2014-07-24 Mark Walter Virtual Building Browser Systems and Methods
CN105868502A (en) * 2016-04-22 2016-08-17 广州硕品物联网科技有限公司 BIM (building information modeling) based material management system and control method thereof
CN106249607A (en) * 2016-07-28 2016-12-21 桂林电子科技大学 Virtual Intelligent household analogue system and method
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality
CN107879260A (en) * 2017-10-11 2018-04-06 武汉科技大学 Tower crane collision avoidance system and safety-protection system based on BIM
CN108287933A (en) * 2017-11-30 2018-07-17 沈阳工业大学 Assembled architecture intelligence Lift-on/Lift-off System and method based on BIM and virtual reality technology
CN108305328A (en) * 2018-02-08 2018-07-20 网易(杭州)网络有限公司 Dummy object rendering intent, system, medium and computing device
CN109064007A (en) * 2018-07-27 2018-12-21 四川佳科幕墙工程有限公司 Construction material management system
WO2019074139A1 (en) * 2017-10-12 2019-04-18 (주)태성에스엔아이 Method for executing simulation on virtual construction site and management server used therefor
KR102056320B1 (en) * 2019-05-30 2019-12-16 (주)더퍼스트아이씨티 Smart Plant Multidimensional Space 3D Piping Design Collaboration System
CN110728870A (en) * 2019-09-09 2020-01-24 上海同一迅阳科技有限公司 MES simulation teaching system, computer device and computer storage medium

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007323497A (en) * 2006-06-02 2007-12-13 Chiyoda Corp Progress management system and management server
TW201001332A (en) * 2008-06-17 2010-01-01 Nat Univ Chung Hsing A device and method for constructing the real object in virtual reality
US20140207774A1 (en) * 2013-01-24 2014-07-24 Mark Walter Virtual Building Browser Systems and Methods
CN105868502A (en) * 2016-04-22 2016-08-17 广州硕品物联网科技有限公司 BIM (building information modeling) based material management system and control method thereof
CN106249607A (en) * 2016-07-28 2016-12-21 桂林电子科技大学 Virtual Intelligent household analogue system and method
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality
CN107879260A (en) * 2017-10-11 2018-04-06 武汉科技大学 Tower crane collision avoidance system and safety-protection system based on BIM
WO2019074139A1 (en) * 2017-10-12 2019-04-18 (주)태성에스엔아이 Method for executing simulation on virtual construction site and management server used therefor
CN108287933A (en) * 2017-11-30 2018-07-17 沈阳工业大学 Assembled architecture intelligence Lift-on/Lift-off System and method based on BIM and virtual reality technology
CN108305328A (en) * 2018-02-08 2018-07-20 网易(杭州)网络有限公司 Dummy object rendering intent, system, medium and computing device
CN109064007A (en) * 2018-07-27 2018-12-21 四川佳科幕墙工程有限公司 Construction material management system
KR102056320B1 (en) * 2019-05-30 2019-12-16 (주)더퍼스트아이씨티 Smart Plant Multidimensional Space 3D Piping Design Collaboration System
CN110728870A (en) * 2019-09-09 2020-01-24 上海同一迅阳科技有限公司 MES simulation teaching system, computer device and computer storage medium

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
庞瑞;王璐;陈桂香;许启铿;丁永刚;肖昭然;: "土木建筑虚拟仿真实验教学中心建设与实践", 高等建筑教育, no. 06 *
王晓亮;杜志芳;: "基于MR+BIM技术的信息化建筑工程应用研究", 居舍, no. 04 *
肖立, 尚涛: "虚拟现实技术及其在城市建设中的应用", 武汉大学学报(工学版), no. 06 *
蒙少青;: "虚拟仿真技术在建筑装饰专业教学中的应用研究", 建材与装饰, no. 13 *

Also Published As

Publication number Publication date
CN111339112B (en) 2023-07-25

Similar Documents

Publication Publication Date Title
CN111339186B (en) Workflow engine data synchronization method, device, medium and electronic equipment
CN1656468B (en) Method, apparatus and system for synchronizing data storage modes in different data memories
CN108170832B (en) Monitoring system and monitoring method for heterogeneous database of industrial big data
CN112671734A (en) Message processing method facing multiple data sources and related equipment thereof
CN112631924A (en) Automatic testing method and device, computer equipment and storage medium
CN112631911A (en) Automatic testing method and device, computer equipment and storage medium
CN115599769A (en) Data migration method and device, electronic equipment and storage medium
CN111552665A (en) Method, device, equipment and medium for converting label information format
CN112685115A (en) International cue language generating method, system, computer equipment and storage medium
CN111339112B (en) Building material informatization management and control method and system based on building information model
WO2023142924A1 (en) Electronic map operation and maintenance method, electronic map data use method and service system
CN113761016A (en) Data query method, device, equipment and storage medium
CN103944779A (en) WAP service performance monitoring method and system
CN116248526A (en) Method and device for deploying container platform and electronic equipment
CN116187915A (en) Warehouse management method, device, equipment and storage medium
CN114615325A (en) Message pushing method and device, computer equipment and storage medium
CN114143308A (en) File uploading information processing method and device, computer equipment and storage medium
CN113676353A (en) Control method and device for equipment, storage medium and electronic device
CN108470047B (en) Remote platform monitoring system based on Internet of Things
CN111966605A (en) Automatic resource retrieval method, system and storage medium for Redfish
CN111159988A (en) Model processing method and device, computer equipment and storage medium
CN113626409B (en) Test data processing method, device, equipment and storage medium
CN114138509B (en) Data interaction method and device and computer readable storage medium
WO2024065778A1 (en) Method, apparatus, device, and medium for building knowledge graph and executing workflow
CN112532750B (en) Big data push processing method and system and cloud platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20200626

Assignee: Zhejiang Wansai Automobile Parts Co.,Ltd.

Assignor: WUHAN University OF SCIENCE AND TECHNOLOGY

Contract record no.: X2024980002109

Denomination of invention: A Building Material Informatization Control Method and System Based on Building Information Model

Granted publication date: 20230725

License type: Common License