CN108647929A - Construction Visualized management system with feedback and method - Google Patents

Construction Visualized management system with feedback and method Download PDF

Info

Publication number
CN108647929A
CN108647929A CN201810254208.4A CN201810254208A CN108647929A CN 108647929 A CN108647929 A CN 108647929A CN 201810254208 A CN201810254208 A CN 201810254208A CN 108647929 A CN108647929 A CN 108647929A
Authority
CN
China
Prior art keywords
employee
work
management
intelligent terminal
feedback
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810254208.4A
Other languages
Chinese (zh)
Inventor
崔战宾
刘攀峰
吴万兴
曹杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810254208.4A priority Critical patent/CN108647929A/en
Publication of CN108647929A publication Critical patent/CN108647929A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C1/00Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people
    • G07C1/10Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people together with the recording, indicating or registering of other data, e.g. of signs of identity
    • G07C1/12Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people together with the recording, indicating or registering of other data, e.g. of signs of identity wherein the time is indicated in figures
    • G07C1/14Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people together with the recording, indicating or registering of other data, e.g. of signs of identity wherein the time is indicated in figures with apparatus adapted for use with individual cards

Abstract

The invention discloses a kind of construction Visualized management systems of band feedback, including attendance module, video monitoring module, employee's cloth bitmap module, inspection video module and progress control module.The invention also discloses a kind of construction visual management methods of band feedback comprising following steps:A, the method for establishing artificial cloth bitmap;B, progress control method.The present invention has the advantages that can ensure that the accuracy of data is avoided that artificial play tricks and non-standard operation again.

Description

Construction Visualized management system with feedback and method
Technical field
The present invention relates to project management software, and artificial work is avoided that again more particularly, to a kind of accuracy can ensure that data The construction Visualized management system and method that false and non-standard operation band is fed back.
Background technology
Currently there are panoramic project management software, construction visualized management of their specifications with feedback Modules, allow with feedback construction visualized management it is apparent with it is transparent;They convert traditional papery operation to electricity Subjob has greatly accelerated information transfer rate;Their frameworks partial interior logic, effectively saves workload, improves Working efficiency;Project management software on the market is limited to legacy systems framework and imagines, and system software update speed is slow, does not have Have and save labour to greatest extent, many softwares are to change traditional papery operation for electronic homework, while these are managed It manages software and carries out modularization management, lack pool system, logical connection is not strong, the afunction of associated verification, in addition, market On project management software use scope it is limited, be only limitted to contractor unit and unit in charge of construction use, lack inclusiveness.
Invention content
It is a kind of by being in many ways mutually authenticated present invention aims at providing, form accuracy that one can ensure that data again It is avoided that the artificial construction visual management method fed back with the band of non-standard operation of playing tricks.
The present invention realized by following technical measures, a kind of construction Visualized management system of band feedback, including attendance Module, video monitoring module, employee's cloth bitmap module, inspection video module and progress control module;
The attendance module identifies that employee check card by human bioequivalence device and turns out for work and transmit information to management meter Calculation machine generates person chart of turning out for work;
The video monitoring module confirms the labo attendant that turns out for work by the camera real-time capture difference face of laying, with Generate employee's cloth bitmap horizontal coordinate;
Employee's cloth bitmap module acquires real-time position information by employee's intelligent terminal and is sent to management computer, Management computer establishes artificial cloth bitmap, in real time clearly reflection person people work hours cloth position section, is set on employee's intelligent terminal It is equipped with UHF labels;
The inspection video module is provided with UHF reading circuits on logging, and UHF reading circuit rapid batch is utilized to read The information in UHF labels is taken to be sent to management computer, to can ensure that when employee's intelligent terminal breaks down or is disturbed The accuracy of artificial cloth bitmap, the camera on logging worn by inspector, whole process records its inspection process, and passes through Image automatic identification shows that it does not conform to rule, unsafe action or arranges in simultaneously its patrol record of the typing of automatic selectivity simultaneously It is transferred to management computer, determines employee work performance and labo attendant;
The progress control module generates same day worker according to work schedule by managing computer and goes to work quantity, work Make region, task amount, in the real-time reminding employees job schedule of employee's intelligent terminal and further work content, accomplishes scene The inventory of management and visualization.
Employee's intelligent terminal is smartwatch as a preferred method,.
The human bioequivalence device is fingerprint identification device, face identification device or the two as a preferred method, In conjunction with.
The logging with camera and is equipped with open and close secret code as a preferred method,.
The invention also discloses a kind of construction visual management methods of band feedback, include the following steps:
A, the method for establishing artificial cloth bitmap, the method for establishing artificial cloth bitmap include the following steps,
A. employee information is identified by human bioequivalence device and transmits information to management computer;
B. employee's real-time position information is acquired by employee's intelligent terminal and is sent to management computer, management computer is established Artificial cloth bitmap is simultaneously compared and adjusts with work person's demand of progress control module, in real time clearly reflection person people work hours Cloth position section;
C. inspection monitors, and the camera on logging worn by inspector, whole process records its inspection process, and passes through Image automatic identification shows that it does not conform to rule, unsafe action or arranges in simultaneously its patrol record of the typing of automatic selectivity simultaneously It is transferred to management computer, compares headcount and position and goes out number with worker on the day of being generated in the job schedule of management computer Whether amount, working region and task amount manually coincide, and are sent out to employee's intelligent terminal if misfitting by managing computer Send deployment information;
D. by the UHF reading circuits of setting, the rapid batch in inspection reads UHF on each employee's intelligent terminal to logging Information in label is simultaneously sent to management computer, artificial to can ensure that when employee's intelligent terminal breaks down or is disturbed The accuracy of cloth bitmap;
E. it when work at present is completed, is inputted by employee's intelligent terminal and completes information, employee's intelligent terminal generates in real time The prompting message of job schedule and further work content accomplishes the inventory of field management to establish new artificial cloth bitmap Change and visualized management;
B, progress control method, the progress control method include the following steps,
A. it is drawn according to work schedule input service gauge by managing computer, which at least generates the same day Worker goes to work quantity, working region and task amount;
B. work schedule is associated with live artificial cloth bitmap, and management computer judges the artificial cloth bitmap in scene and pipe It manages and generates whether the same day go to work quantity, working region and task amount of worker manually coincide in the job schedule of computer, such as It misfits and then sends deployment information to employee's intelligent terminal by managing computer.
As a preferred method, when the data and monitor video system catcher's face data of the upload of human bioequivalence device It is not consistent, management computer generates prompting message.
As a preferred method, when employee's cloth bitmap is not consistent with the data that human bioequivalence device uploads, management calculates Machine generates prompting message.
As a preferred method, when the same day worker generated in the data and job schedule that human bioequivalence device uploads goes out Work incremental data is not consistent, and management computer generates prompting message.
As a preferred method, when camera catcher's face in the data and logging that human bioequivalence device uploads It is not consistent, management computer generates prompting message.
As a preferred method, when labo attendant, process of work and the work that the camera on logging captures Go to work quantity, process of work data of the same day worker generated in progress are not consistent, and management computer generates prompting message.
The system and method for the present invention form a closed logic checking chain, both really by being mutually authenticated in many ways The accuracy for having protected data, in turn avoids artificially playing tricks and non-standard operation;Occur the case where not being consistent, meeting during verification It is reminded in time, ensure that administrative staff can rectify a deviation in time, the improvement of management is forced with machine and equipment;Various video monitors The use in conjunction of equipment, it is ensured that monitoring is without dead angle.UHF on each employee's intelligent terminal is read by UHF reading circuit rapid batch Information in label feeds back to management computer, carries out the amendment of artificial cloth bitmap, it is ensured that its accuracy.
Description of the drawings
Fig. 1 is the structural schematic diagram of the embodiment of the present invention.
Specific implementation mode
With reference to embodiment and compares attached drawing invention is further described in detail.
A kind of the construction Visualized management system and method for band feedback, with reference to figure 1, including attendance module 200, video monitoring Module 300, employee's cloth bitmap module 100, inspection video module 400 and progress control module 500;
The attendance module 200 by human bioequivalence device identification employee check card and turns out for work and transmit information to pipe Computer is managed, person chart of turning out for work is generated;
The video monitoring module 300 confirms the people that goes to work that turns out for work by the camera real-time capture difference face of laying Number, to generate employee's cloth bitmap horizontal coordinate;
Employee's cloth bitmap module 100 acquires real-time position information by employee's intelligent terminal and is sent to management calculating Machine, management computer establish artificial cloth bitmap, in real time clearly reflection person people work hours cloth position section, on employee's intelligent terminal It is provided with UHF labels;
The inspection video module 400 is provided with UHF reading circuits on logging, utilizes UHF reading circuit rapid batch The information read in UHF labels is sent to management computer, to which when employee's intelligent terminal breaks down or is disturbed, energy is true The accuracy of guarantor's work cloth bitmap, the camera on logging worn by inspector, whole process records its inspection process, and leads to It crosses image automatic identification and shows that it does not conform to rule, unsafe action or arranges in simultaneously its patrol record of the typing of automatic selectivity And it is transferred to management computer, determine employee work performance and labo attendant;
The progress control module 500, by manage computer according to work schedule generate the same day worker go to work quantity, Working region, task amount are accomplished existing in the real-time reminding employees job schedule of employee's intelligent terminal and further work content The inventory of field management and visualization.
The construction visual management method of this band feedback, includes the following steps:
A, the method for establishing artificial cloth bitmap, the method for establishing artificial cloth bitmap include the following steps,
A. employee information is identified by human bioequivalence device and transmits information to management computer;
B. employee's real-time position information is acquired by employee's intelligent terminal and is sent to management computer, management computer is established Artificial cloth bitmap is simultaneously compared and adjusts with work person's demand of progress control module, in real time clearly reflection person people work hours Cloth position section;
C. inspection monitors, and the camera on logging worn by inspector, whole process records its inspection process, and passes through Image automatic identification shows that it does not conform to rule, unsafe action or arranges in simultaneously its patrol record of the typing of automatic selectivity simultaneously It is transferred to management computer, compares headcount and position and goes out number with worker on the day of being generated in the job schedule of management computer Whether amount, working region and task amount manually coincide, and are sent out to employee's intelligent terminal if misfitting by managing computer Send deployment information;
D. by the UHF reading circuits of setting, the rapid batch in inspection reads UHF on each employee's intelligent terminal to logging Information in label is simultaneously sent to management computer, artificial to can ensure that when employee's intelligent terminal breaks down or is disturbed The accuracy of cloth bitmap;
E. it when work at present is completed, is inputted by employee's intelligent terminal and completes information, employee's intelligent terminal generates in real time The prompting message of job schedule and further work content accomplishes the inventory of field management to establish new artificial cloth bitmap Change and visualized management;
B, progress control method, the progress control method include the following steps,
A. it is drawn according to work schedule input service gauge by managing computer, which at least generates the same day Worker goes to work quantity, working region and task amount;
B. work schedule is associated with live artificial cloth bitmap, and management computer judges the artificial cloth bitmap in scene and pipe It manages and generates whether the same day go to work quantity, working region and task amount of worker manually coincide in the job schedule of computer, such as It misfits and then sends deployment information to employee's intelligent terminal by managing computer.
The system and method for the present invention form a closed logic checking chain, both really by being mutually authenticated in many ways The accuracy for having protected data, in turn avoids artificially playing tricks and non-standard operation;Occur the case where not being consistent, meeting during verification It is reminded in time, ensure that administrative staff can rectify a deviation in time, the improvement of management is forced with machine and equipment;Various video monitors The use in conjunction of equipment, it is ensured that monitoring is without dead angle.Logging is worn when building site carries out inspection by logging in inspector UHF reading circuit rapid batch in setting reads the information on each employee's intelligent terminal in UHF labels and is sent to management meter Calculation machine can be read to can ensure that the accuracy of artificial cloth bitmap when employee's intelligent terminal breaks down or is disturbed by UHF Breath of winning the confidence feeds back to management computer, carries out the amendment of artificial cloth bitmap, it is ensured that its accuracy.
The construction Visualized management system of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is that employee's intelligent terminal is smartwatch.
The construction Visualized management system of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is that the human bioequivalence device is the combination of fingerprint identification device, face identification device or the two.
The construction visual management method of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is that the logging is with camera and is equipped with open and close secret code.
The construction visual management method of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is that, when the data that human bioequivalence device uploads are not consistent with monitor video system catcher's face data, management computer generates Prompting message.
The construction visual management method of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is that, when employee's cloth bitmap is not consistent with the data that human bioequivalence device uploads, management computer generates prompting message.
The construction visual management method of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is when the data that human bioequivalence device uploads incremental data of going to work with the same day worker generated in job schedule is not consistent, to manage Computer generates prompting message.
The construction visual management method of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is that, when the data that human bioequivalence device uploads are not consistent with the camera catcher face on logging, management computer generates Prompting message.
The construction visual management method of the band feedback of the present invention, it is specific on the basis of technical solution in front with reference to figure 1 It is, when the same day worker generated in labo attendant, process of work and the job schedule that the camera on logging captures goes out Number amount, process of work data are not consistent, and management computer generates prompting message.
It is to be expounded to construction visual management method of the present invention with feedback above, is used to help understand this hair It is bright, but embodiment of the present invention are not limited by the above embodiments, it is any without departing from change made by under the principle of the invention, Modification substitutes, combination, simplifies, and should be equivalent substitute mode, is included within the scope of the present invention.

Claims (10)

1. a kind of construction Visualized management system of band feedback, it is characterised in that:Including attendance module, video monitoring module, member Work cloth bitmap module, inspection video module and progress control module;
The attendance module identifies that employee check card by human bioequivalence device and turns out for work and transmit information to management calculating Machine generates person chart of turning out for work;
The video monitoring module confirms the labo attendant that turns out for work by the camera real-time capture difference face of laying, to generate Employee's cloth bitmap horizontal coordinate;
Employee's cloth bitmap module acquires real-time position information by employee's intelligent terminal and is sent to management computer, manages Computer establishes artificial cloth bitmap, in real time clearly reflection person people work hours cloth position section, is provided on employee's intelligent terminal UHF labels;
The inspection video module is provided with UHF reading circuits on logging, and UHF reading circuit rapid batch is utilized to read UHF Information in label is sent to management computer, to can ensure that artificial cloth when employee's intelligent terminal breaks down or is disturbed The accuracy of bitmap, the camera on logging worn by inspector, whole process record its inspection process, and certainly by image Dynamic identification shows that it does not conform to rule, unsafe action or arranges and in the typing of automatic selectivity its patrol record and be transferred to Computer is managed, determines employee work performance and labo attendant;
The progress control module generates same day worker according to work schedule by managing computer and goes to work quantity, workspace Domain, task amount accomplish field management in the real-time reminding employees job schedule of employee's intelligent terminal and further work content Inventory and visualization.
2. the construction Visualized management system according to claim 1 with feedback, it is characterised in that:Employee's intelligent terminal For smartwatch.
3. the construction Visualized management system according to claim 1 with feedback, it is characterised in that:The human bioequivalence device For the combination of fingerprint identification device, face identification device or the two.
4. the construction Visualized management system according to claim 1 with feedback, it is characterised in that:The logging is carried and is taken the photograph As head and it is equipped with open and close secret code.
5. a kind of construction visual management method of band feedback, it is characterised in that include the following steps:
A, the method for establishing artificial cloth bitmap, the method for establishing artificial cloth bitmap include the following steps,
A. employee information is identified by human bioequivalence device and transmits information to management computer;
B. employee's real-time position information is acquired by employee's intelligent terminal and is sent to management computer, management computer is established artificial Cloth bitmap is simultaneously compared and adjusts with work person's demand of progress control module, in real time clearly reflection person people work hours cloth position Section;
C. inspection monitors, and the camera on logging worn by inspector, whole process records its inspection process, and passes through image Automatic identification shows that it does not conform in rule, unsafe action or arrangement and the typing of automatic selectivity its patrol record and transmits Give management computer, compare headcount and position with generated in the job schedule of management computer same day worker go to work quantity, Whether working region and task amount manually coincide, and tune is sent to employee's intelligent terminal by managing computer if misfitting With information;
D. by the UHF reading circuits of setting, the rapid batch in inspection reads UHF labels on each employee's intelligent terminal to logging In information and be sent to management computer, to can ensure that artificial cloth position when employee's intelligent terminal breaks down or is disturbed The accuracy of figure;
E. it when work at present is completed, is inputted by employee's intelligent terminal and completes information, employee's intelligent terminal generates work in real time The prompting message of progress and further work content, to establish new artificial cloth bitmap, accomplish field management inventoryization and Visualized management;
B, progress control method, the progress control method include the following steps,
A. it is drawn according to work schedule input service gauge by managing computer, which at least generates same day worker It goes to work quantity, working region and task amount;
B. work schedule is associated with live artificial cloth bitmap, and management computer judges that the artificial cloth bitmap in scene is counted with management Generate whether the same day go to work quantity, working region and task amount of worker manually coincide in the job schedule of calculation machine, if do not kissed It closes and then sends deployment information to employee's intelligent terminal by managing computer.
6. the construction visual management method according to claim 5 with feedback, it is characterised in that:When on human bioequivalence device The data of biography are not consistent with monitor video system catcher's face data, and management computer generates prompting message.
7. the construction visual management method according to claim 5 with feedback, it is characterised in that:As employee's cloth bitmap and people The data that body identification device uploads are not consistent, and management computer generates prompting message.
8. the construction visual management method according to claim 5 with feedback, it is characterised in that:When on human bioequivalence device The data of biography incremental data of going to work with the same day worker generated in job schedule is not consistent, and management computer generates prompting message.
9. the construction visual management method according to claim 5 with feedback, it is characterised in that:When on human bioequivalence device The data of biography are not consistent with the camera catcher face on logging, and management computer generates prompting message.
10. the construction visual management method according to claim 5 with feedback, it is characterised in that:When taking the photograph on logging As feelings are completed in go to work quantity, work of the same day worker generated in labo attendant that head captures, process of work and job schedule Condition data are not consistent, and management computer generates prompting message.
CN201810254208.4A 2018-03-26 2018-03-26 Construction Visualized management system with feedback and method Pending CN108647929A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810254208.4A CN108647929A (en) 2018-03-26 2018-03-26 Construction Visualized management system with feedback and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810254208.4A CN108647929A (en) 2018-03-26 2018-03-26 Construction Visualized management system with feedback and method

Publications (1)

Publication Number Publication Date
CN108647929A true CN108647929A (en) 2018-10-12

Family

ID=63744614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810254208.4A Pending CN108647929A (en) 2018-03-26 2018-03-26 Construction Visualized management system with feedback and method

Country Status (1)

Country Link
CN (1) CN108647929A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103390255A (en) * 2013-07-30 2013-11-13 上海城建市政工程(集团)有限公司 Construction site digital management system and application method thereof
CN105847769A (en) * 2016-06-16 2016-08-10 苏州安控物联网科技有限公司 Construction site behavior analysis system and analysis method
CN106056347A (en) * 2016-05-16 2016-10-26 北京诺士诚国际工程项目管理有限公司 Engineering project management cloud platform system based on video monitoring
CN106204784A (en) * 2016-06-30 2016-12-07 北京海顿中科技术有限公司 Safety guides intelligence and patrols point detection system
CN106384190A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway roadbed construction progress management system and method based on 3DGIS and engineering 3D model
CN106529901A (en) * 2016-10-13 2017-03-22 广西大学 Integrated management system for construction engineering
CN106570642A (en) * 2016-11-07 2017-04-19 成都科曦科技有限公司 Task distribution system and method based on personnel location and automatic work identification
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality
CN107610266A (en) * 2017-07-06 2018-01-19 北京万相融通科技股份有限公司 A kind of station cruising inspection system
CN107742330A (en) * 2017-09-30 2018-02-27 四川民工加网络科技有限公司 A kind of worker's attendance checking system suitable for construction site

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103390255A (en) * 2013-07-30 2013-11-13 上海城建市政工程(集团)有限公司 Construction site digital management system and application method thereof
CN106056347A (en) * 2016-05-16 2016-10-26 北京诺士诚国际工程项目管理有限公司 Engineering project management cloud platform system based on video monitoring
CN105847769A (en) * 2016-06-16 2016-08-10 苏州安控物联网科技有限公司 Construction site behavior analysis system and analysis method
CN106204784A (en) * 2016-06-30 2016-12-07 北京海顿中科技术有限公司 Safety guides intelligence and patrols point detection system
CN106384190A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway roadbed construction progress management system and method based on 3DGIS and engineering 3D model
CN106529901A (en) * 2016-10-13 2017-03-22 广西大学 Integrated management system for construction engineering
CN106570642A (en) * 2016-11-07 2017-04-19 成都科曦科技有限公司 Task distribution system and method based on personnel location and automatic work identification
CN106897817A (en) * 2017-01-22 2017-06-27 朗坤智慧科技股份有限公司 A kind of construction speed Visualized management system and method based on augmented reality
CN107610266A (en) * 2017-07-06 2018-01-19 北京万相融通科技股份有限公司 A kind of station cruising inspection system
CN107742330A (en) * 2017-09-30 2018-02-27 四川民工加网络科技有限公司 A kind of worker's attendance checking system suitable for construction site

Similar Documents

Publication Publication Date Title
CN110971878B (en) Engineering field management system
CN105303632B (en) A kind of mobile monitor is registered system and method for work
CN201251796Y (en) Signing system based on face recognition
CN107665419A (en) The labor service real-name management system of national grid wisdom building site control platform
CN111126219A (en) Transformer substation personnel identity recognition system and method based on artificial intelligence
US20210349476A1 (en) Method and apparatus for controlling cruise of unmanned air vehicle based on prefabricated construction platform
CN112396658B (en) Indoor personnel positioning method and system based on video
CN110287859A (en) A kind of personnel's material dispatching system based on artificial intelligence technology
CN103208212A (en) Anti-cheating remote online examination method and system
CN110991979B (en) Attendance management method, device and equipment for intelligent building site and computer storage medium
CN108665231A (en) Construction Visualized management system and method
CN103295297A (en) Kindergarten safety management system based on face recognition
CN109829693A (en) One kind being used for Construction Schedule management system and management method
CN103559751A (en) Auxiliary device and method for confirming cheating attendance behavior
CN211509189U (en) Electric power operation field supervision equipment and system
CN113705372A (en) AI identification system for join in marriage net job site violating regulations
CN112149551A (en) Safety helmet identification method based on embedded equipment and deep learning
CN113780823A (en) Intelligent project supervision system and supervision method based on image acquisition system
CN205751110U (en) Classroom based on image procossing intelligent management system
CN207319279U (en) The labor service real-name management system of national grid wisdom building site control platform
CN113191591A (en) On-site monitoring method for electric power operating personnel
CN112528860A (en) Safety tool management method and system based on image recognition
CN113010987B (en) Real-time judgment method for construction progress of overhead line based on Internet of things
CN107693997A (en) A kind of fire-fighting equipment detection and maintaining management system and management method
CN109636940A (en) A kind of building-site attendance checking system and Work attendance method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181012