CN106836197A - 一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法 - Google Patents
一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法 Download PDFInfo
- Publication number
- CN106836197A CN106836197A CN201710229452.0A CN201710229452A CN106836197A CN 106836197 A CN106836197 A CN 106836197A CN 201710229452 A CN201710229452 A CN 201710229452A CN 106836197 A CN106836197 A CN 106836197A
- Authority
- CN
- China
- Prior art keywords
- deflection
- pile foundation
- lead column
- reinforcement cage
- isolating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 53
- 239000010959 steel Substances 0.000 title claims abstract description 53
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 230000002265 prevention Effects 0.000 title abstract description 9
- 230000002787 reinforcement Effects 0.000 claims abstract description 31
- 238000005266 casting Methods 0.000 claims abstract description 18
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- 238000002512 chemotherapy Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
Abstract
一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法,属建设工程中桥梁建设辅助装置,以及其施工方法。它包括导向柱,在导向柱的顶端设置挂钩。所述挂钩的形状为“n”形。所述预防桩基钢筋笼偏斜的施工方法包括:将导向柱伸入桩孔中;将“n”形挂钩挂于钢护筒上;钢筋笼安装就位;浇筑混凝土。本发明具有的有益效果是:导向柱对钢筋笼起到导向和与孔壁隔离的作用,在浇筑过程中,钢筋笼不易发生偏斜。随着浇筑混凝土量的增加,力矩变大,始终有导向柱在中间隔离导向,保证在力矩变大的情况下仍不发生偏斜,钢筋笼内部弯矩不致积累过大,可有效防止在浇筑混凝土时钢筋笼左右旋转、摆动碰撞孔壁、偏斜及变形,偏斜控制稳定可靠,保证施工质量。
Description
技术领域:
一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法,属建设工程中桥梁建设辅助装置,以及其施工方法。
背景技术:
在铁路建设过程中,要涉及众多的桥梁建设,桥梁基础为钻孔桩基础和扩大基础,钻孔桩数量多,桩基长,扩大基础多。在桩基施工过程中,桩基成孔后将钢筋笼吊装入孔,入孔后往往采用焊接十字钢筋的方法将钢筋笼固定(即在钢筋笼径向方向加焊十字交叉钢筋,然后将十字钢筋焊接在钢护筒上),然后进行浇筑。但是在浇筑过程中由于钢筋笼受力较大,下部力矩远远大于上部焊接十字钢筋力矩,会导致钢筋笼偏斜,不易把控,后期要投入大量的人力、物力加以控制、调整,但是在实际操作中很困难,效果不明显,钢筋笼偏斜程度偏差大,控制不足。
为了解决这个问题,中国专利号201420198462.4公开了一种“钢筋笼入孔定位纠偏装置”,它包括直螺纹顶杆,在直螺纹顶杆顶端设置有顶头弯板,直螺纹顶杆固定在底座上,底座通过固定锚钉固定。顶头弯板横向弧度与钢筋笼相同,弯曲方式与钢筋笼弯曲方向相反。直螺纹顶杆上设置有直螺纹套筒,通过调节微调直螺纹套筒控制钢筋笼下放精度。在钢筋笼底端刚入孔后,四周设置本装置,通过调节直螺纹顶杆对纠正钢筋笼偏斜起到一定作用,但是在混凝土浇筑过程中,因为混凝土对钢筋笼的作用力不仅局限于竖直方向,还有水平方向,钢筋笼受力不确定,所以该装置对钢筋笼偏斜的控制不是十分稳定可靠,而且该装置使用过程麻烦,施工时间延长。
发明内容:
本发明要解决的问题就是针对以上不足而提供一种钢筋笼偏斜控制稳定可靠的保护装置,以及它的施工方法。其技术方案如下:
一种预防桩基钢筋笼偏斜的隔离保护装置,包括导向柱,在导向柱的顶端设置挂钩。
所述挂钩的形状为“n”形。
所述导向柱的形状为圆柱体。
上述预防桩基钢筋笼偏斜的施工方法,其关键技术在于包括以下步骤:
1)混凝土浇筑前,将至少三根导向柱伸入桩孔中,每根导向柱角度等分布置;
2)将“n”形挂钩挂于钢护筒上;
3)钢筋笼安装就位;
4)各点焊接固定;
5)浇筑混凝土。
与现有技术相比,本发明具有的有益效果是:
1、由于导向柱2长达6-8m,在自然重力作用下自然下垂,对钢筋笼起到导向和与孔壁隔离的作用,在浇筑过程中,钢筋笼不易发生偏斜。随着浇筑混凝土量的增加,力矩变大,在上部6-8m范围内,始终有导向柱在中间隔离导向,保证在力矩变大的情况下仍不发生偏斜,钢筋笼内部弯矩不致积累过大,可有效防止在浇筑混凝土时钢筋笼左右旋转、摆动碰撞孔壁、偏斜及变形,偏斜控制稳定可靠,保证施工质量。可以满足桩基础钢筋笼水下施工的需要。
2、本发明装置结构简单,但是能够解决大问题;使用方法也简单,只需使导向柱位于钢筋笼与孔壁之间,将挂钩挂于孔壁上,然后各点焊接固定,就可以浇筑混凝土了。不需再要辅助装置来固定、调整钢筋笼。
附图说明:
图1,是本发明结构示意图;
图2,是本发明使用状态图;
图3,是本发明另一实施例使用状态图。
具体实施方式:
参见图1~图3,一种预防桩基钢筋笼偏斜的隔离保护装置,包括导向柱2,在导向柱2的顶端设置挂钩1。
所述挂钩1的形状为“n”形。
所述导向柱2的长度为6-8m。
所述导向柱2的形状为圆柱体。
所述导向柱2的直径为40~50mm。
上述预防桩基钢筋笼偏斜的施工方法,其关键技术在于包括以下步骤:
1)混凝土浇筑前,将至少三根(如图2或图3所示三根或四根)导向柱2伸入桩孔中,每根导向柱角度等分布置;根据受力情况,导向柱2两端可封口可或不封口;
2)将“n”形挂钩1挂于钢护筒3上,对钢护筒起稳定作用;
3)钢筋笼4安装就位,导向柱2对钢筋笼4有导向作用;
4)各点焊接固定;
5)浇筑混凝土。
Claims (6)
1.一种预防桩基钢筋笼偏斜的隔离保护装置,其特征在于包括导向柱(2),在导向柱(2)的顶端设置挂钩(1)。
2.根据权利要求1所述预防桩基钢筋笼偏斜的隔离保护装置,其特征是挂钩(1)的形状为“n”形。
3.根据权利要求1所述预防桩基钢筋笼偏斜的隔离保护装置,其特征是导向柱(2)的长度为6-8m。
4.根据权利要求1所述预防桩基钢筋笼偏斜的隔离保护装置,其特征是导向柱(2)的形状为圆柱体。
5.根据权利要求1所述预防桩基钢筋笼偏斜的隔离保护装置,其特征是导向柱(2)的直径为40~50mm。
6.一种预防桩基钢筋笼偏斜的施工方法,其特征在于包括以下步骤:
1)混凝土浇筑前,将至少三根导向柱(2)伸入桩孔中,每根导向柱角度等分布置;
2)将“n”形挂钩(1)挂于钢护筒(3)上;
3)钢筋笼(4)安装就位;
4)各点焊接固定;
5)浇筑混凝土。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710229452.0A CN106836197A (zh) | 2017-04-10 | 2017-04-10 | 一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710229452.0A CN106836197A (zh) | 2017-04-10 | 2017-04-10 | 一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106836197A true CN106836197A (zh) | 2017-06-13 |
Family
ID=59148202
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710229452.0A Pending CN106836197A (zh) | 2017-04-10 | 2017-04-10 | 一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106836197A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108797626A (zh) * | 2018-06-29 | 2018-11-13 | 芜湖等莱智能科技有限公司 | 一种建筑桩基防偏装置 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242067A (ja) * | 1996-03-11 | 1997-09-16 | ▲高▼松建設株式会社 | 場所打ちコンクリート杭の構築方法 |
CN1418277A (zh) * | 2000-07-20 | 2003-05-14 | 斯马泰克工程技术株式会社 | 用于结合钢管桩的头部和混凝土基础的结合件和结合结构 |
CN203569558U (zh) * | 2013-10-12 | 2014-04-30 | 中勘冶金勘察设计研究院有限责任公司 | 钻孔灌注桩钢筋笼定位器 |
CN203625894U (zh) * | 2013-12-24 | 2014-06-04 | 中国建筑第四工程局有限公司 | 一种桩孔内钢筋笼安装辅助装置 |
CN203795418U (zh) * | 2014-04-23 | 2014-08-27 | 葛洲坝集团第五工程有限公司 | 钢筋笼入孔定位纠偏装置 |
CN204343343U (zh) * | 2014-12-01 | 2015-05-20 | 中国十七冶集团有限公司 | 桩基质量检测管定位快接装置 |
JP2015134987A (ja) * | 2014-01-16 | 2015-07-27 | 東急建設株式会社 | 場所打ちコンクリート杭の締固め装置と締固め方法 |
CN205276258U (zh) * | 2016-01-06 | 2016-06-01 | 汕头市建筑工程总公司 | 一种防咬合支护桩钢筋笼 |
CN207228104U (zh) * | 2017-04-10 | 2018-04-13 | 中国水利水电第七工程局成都水电建设工程有限公司 | 一种预防桩基钢筋笼偏斜的隔离保护装置 |
-
2017
- 2017-04-10 CN CN201710229452.0A patent/CN106836197A/zh active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242067A (ja) * | 1996-03-11 | 1997-09-16 | ▲高▼松建設株式会社 | 場所打ちコンクリート杭の構築方法 |
CN1418277A (zh) * | 2000-07-20 | 2003-05-14 | 斯马泰克工程技术株式会社 | 用于结合钢管桩的头部和混凝土基础的结合件和结合结构 |
CN203569558U (zh) * | 2013-10-12 | 2014-04-30 | 中勘冶金勘察设计研究院有限责任公司 | 钻孔灌注桩钢筋笼定位器 |
CN203625894U (zh) * | 2013-12-24 | 2014-06-04 | 中国建筑第四工程局有限公司 | 一种桩孔内钢筋笼安装辅助装置 |
JP2015134987A (ja) * | 2014-01-16 | 2015-07-27 | 東急建設株式会社 | 場所打ちコンクリート杭の締固め装置と締固め方法 |
CN203795418U (zh) * | 2014-04-23 | 2014-08-27 | 葛洲坝集团第五工程有限公司 | 钢筋笼入孔定位纠偏装置 |
CN204343343U (zh) * | 2014-12-01 | 2015-05-20 | 中国十七冶集团有限公司 | 桩基质量检测管定位快接装置 |
CN205276258U (zh) * | 2016-01-06 | 2016-06-01 | 汕头市建筑工程总公司 | 一种防咬合支护桩钢筋笼 |
CN207228104U (zh) * | 2017-04-10 | 2018-04-13 | 中国水利水电第七工程局成都水电建设工程有限公司 | 一种预防桩基钢筋笼偏斜的隔离保护装置 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108797626A (zh) * | 2018-06-29 | 2018-11-13 | 芜湖等莱智能科技有限公司 | 一种建筑桩基防偏装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107503353A (zh) | 桩基钢筋笼偏位和倾斜预防装置及方法 | |
CN106087744B (zh) | 斜拉桥混凝土梁索导管支撑定位装置及方法 | |
CN203247603U (zh) | 一种高位地脚螺栓定位装置 | |
CN104947603A (zh) | 一种钢筋混凝土梁桥主梁加固构造及加固方法 | |
CN105569354A (zh) | 一种预制柱的装配方法 | |
CN105696800A (zh) | 防钢结构地脚锚栓施工产生相对位移临时固定套架 | |
CN104264902A (zh) | 钢管柱圆盘定位装置、钢管混凝土柱与桩基连接结构 | |
CN104032969A (zh) | 一种隔震支座预埋板精确定位及过程调控装置 | |
CN107869195A (zh) | 一种型钢钢柱及柱头定型钢模施工方法 | |
CN101864825A (zh) | 一种钢筋混凝土预制柱定位装置及其施工方法 | |
CN105804110A (zh) | 一种铁路接触网地脚螺栓的施工方法以及安装支架 | |
CN108005392A (zh) | 一种装配式混凝土剪力墙精确定位装置及其安装方法 | |
CN107386455A (zh) | 一种隔震支座及其安装施工方法 | |
CN215594016U (zh) | 隔震支座的安装结构 | |
CN106759943A (zh) | 一种预组装钢柱脚锚栓结构 | |
CN207228104U (zh) | 一种预防桩基钢筋笼偏斜的隔离保护装置 | |
CN104196248B (zh) | 逆作法后插钢管柱垂直定位装置及其施工方法 | |
CN106836197A (zh) | 一种预防桩基钢筋笼偏斜的隔离保护装置及其施工方法 | |
CN207092093U (zh) | 一种保障钢立柱垂直度的组合式结构 | |
CN102817482A (zh) | 一种钢柱校正装置及其校正施工方法 | |
CN106368234A (zh) | 一种新型杯口基础箱形钢柱安装施工工艺 | |
CN103334584B (zh) | 一种滑模系统的模板调节系统 | |
CN103031892A (zh) | 钢桁架支柱及钢桁架平台制造方法 | |
CN206600005U (zh) | 剪力墙内预留插筋的定位组件及定位装置 | |
CN109201971A (zh) | 用于制作桩基钢筋笼的定位装置及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170613 |