CN106812301A - A kind of mounting structure and installation method of built on stilts hanging basket - Google Patents
A kind of mounting structure and installation method of built on stilts hanging basket Download PDFInfo
- Publication number
- CN106812301A CN106812301A CN201710103617.XA CN201710103617A CN106812301A CN 106812301 A CN106812301 A CN 106812301A CN 201710103617 A CN201710103617 A CN 201710103617A CN 106812301 A CN106812301 A CN 106812301A
- Authority
- CN
- China
- Prior art keywords
- support
- hanging basket
- lifting rope
- rope
- stilts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 241000272165 Charadriidae Species 0.000 title claims abstract description 29
- 238000009434 installation Methods 0.000 title claims abstract description 16
- 238000000034 method Methods 0.000 title claims abstract description 15
- 238000010276 construction Methods 0.000 claims abstract description 65
- 238000005096 rolling process Methods 0.000 claims abstract description 31
- 239000000126 substance Substances 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 description 9
- 239000010959 steel Substances 0.000 description 9
- 238000004873 anchoring Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 3
- 238000005299 abrasion Methods 0.000 description 2
- 238000005266 casting Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G3/34—Mobile scaffolds; Scaffolds with mobile platforms characterised by supporting structures provided on the roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/041—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffolds on roof frameworks or on roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/045—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on profiles, e.g. I or H profiles
Abstract
The invention provides a kind of mounting structure and installation method of built on stilts hanging basket, wherein mounting structure includes:It is installed on the first support on the first aerial construction beam;Second support, the second support includes the hoop anchor ear being located on the second aerial construction beam and the linking arm for being connected to anchor ear and first support;Lifting rope, the first end of the lifting rope bypasses first support and is connected to second support;Hanging basket, the hanging basket is connected to the second end of lifting rope;And rope rolling, the rope rolling is installed on lifting rope.The present invention is by setting first support and second support, with second support come instead of traditional hanging basket counterweight, the hanging basket of " with support for counterweight " installs system, eliminate the ideas of hanging basket counterweight, and then hanging basket is arranged in structural beams, change construction method, solve roofing overhead depth of beam it is high cannot installation hanging basket problem.
Description
Technical field
The present invention relates to the realm of building construction, more particularly to a kind of mounting structure and installation method of built on stilts hanging basket.
Background technology
At present, with high-rise building increase and people are to the esthetic requirement of architectural appearance, curtain wall is more and more
Application and Civil structure in, its construction is permitted to be carried out using construction hanging basket, and major part building roof is consideration at present
Space availability ratio and attractive in appearance and make roof structure roof beam structure sky form, and overhead height is higher, causes curtain wall construction in construction
Hanging basket installation difficulty cannot even be installed, and for this construction difficult problem, the present invention arises at the historic moment.
The content of the invention
In view of the foregoing, present invention offer one kind can solve high-altitude hanging basket present in prior art and be difficult to installation question
Overhead type hanging basket.
To achieve the above object, the invention provides a kind of mounting structure of built on stilts hanging basket, including:
First support, is installed on the first aerial construction beam;
Second support, including bind round the anchor ear on the second aerial construction beam and be connected to the anchor ear with described first
The linking arm of frame;And
Lifting rope, the first end of the lifting rope is connected to the second support, and the second end of the lifting rope bypasses described first
Support is simultaneously connected with hanging basket.
The beneficial effects of the present invention are, it is of the invention by setting first support and second support, with second support come generation
For traditional hanging basket counterweight, the hanging basket of " with support for counterweight " installs system, eliminates the ideas of hanging basket counterweight, and then will
Hanging basket be arranged on structural beams on, change construction method, solve roofing overhead depth of beam it is high cannot installation hanging basket difficulty
Topic.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, be formed with the top of the first support and supply institute
The first lifting rope fulcrum that lifting rope is bypassed is stated, the side in the first support away from the second support is provided with for by described in
Encorbelment support arm of the lifting rope with the first aerial construction beam from a distance, is formed with for the lifting rope on the support arm of encorbelmenting
The the second lifting rope fulcrum for bypassing.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, the first support is connected to institute by bearing
The first aerial construction beam is stated, the bearing includes backing plate and chemical anchor bolts, perforation, the chemical anchor bolts are offered on the backing plate
It is arranged in the perforation and plugs and is fixed on the first aerial construction beam.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, the second support also includes second support arm;
The second support arm is connected to the anchor ear with the linking arm.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, connect between the anchor ear and the second support arm
It is connected to bearing diagonal.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, the anchor ear is a closed-loop, described second
The cross-sections match of aerial construction beam is in the internal diameter of the closed-loop.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, also including rope rolling, the rope rolling is fixed
In the linking arm away from the first support one end, the first end of the lifting rope is connected to the rope rolling.
The built on stilts hanging basket of the present invention mounting structure further improvement is that, also including rope rolling, the rope rolling is fixed
In the hanging basket, the second end of the lifting rope is connected to the rope rolling.
A kind of installation method of built on stilts hanging basket, it is characterised in that comprise the following steps:
First support is installed on the first aerial construction beam;
Second support is installed on the second aerial construction beam, the second support includes hoop on the second aerial construction beam
Anchor ear and be connected to the linking arm of the anchor ear and the first support;And
Lifting rope is installed in the first support with the second support, the first end of the lifting rope is connected to described second
Support, the second end of the lifting rope bypasses the first support and is connected with hanging basket.
The built on stilts hanging basket of the present invention installation method further improvement is that, the rope rolling is fixedly arranged on the hanging basket,
Second end of the lifting rope is connected to the rope rolling.
The beneficial effect of this method is that the present invention sets first support and second support by built on stilts beam, to embrace
The mode that hoop hoop sets instead of traditional Balance weight end so that the installation of hanging basket is simple and convenient, it is easy to dismantle, and can reuse.
Brief description of the drawings
Fig. 1 is the structural representation of the mounting structure first embodiment of the built on stilts hanging basket of the present invention.
Fig. 2 is the enlarged drawing at A in Fig. 1.
Fig. 3 is the structural representation of the mounting structure second embodiment of the built on stilts hanging basket of the present invention.
Specific embodiment
Fig. 1 and Fig. 2 is refer to, traditional hanging basket system is all to hang a liter end cooperation Balance weight end to carry out hanging liter, it is contemplated that
Replace the mounting structure of the built on stilts hanging basket of Balance weight end in a kind of support with detachable installation is provided.Therefore, frame of the present invention
Empty formula hanging basket system includes:It is installed on the first support 11 on the first aerial construction beam 7;Second support, the second support includes
Bind round the anchor ear 21 on the second aerial construction beam 8 and be connected to the linking arm 24 of anchor ear 21 and first support 11;Lifting rope 4, should
The first end of lifting rope 4 is connected to second support, and the second end of the lifting rope 4 bypasses the first support 11 and is connected with hanging basket 5.This
Invention replaces traditional hanging basket counterweight, " with support for counterweight " by setting first support and second support with second support
Hanging basket system is installed, eliminate the ideas of hanging basket counterweight, and then hanging basket is arranged in structural beams, change construction party
Method, solve roofing overhead depth of beam it is high cannot installation hanging basket problem.
For the benefit of to the understanding of structure of the invention, illustrated below in conjunction with drawings and Examples.
As the better embodiment of the present embodiment one, in order to prevent between the aerial construction beam 7 of hanging basket 5 and first because of distance too
Closely collide, rub, further also for protection hanging basket 5, the top of first support 11 is formed with what is bypassed for lifting rope 4
First lifting rope fulcrum, first support 11 away from the side of second support be provided with for by the aerial construction beam 7 of lifting rope 4 and first every
The support arm 241 of encorbelmenting of a segment distance is opened, the second lifting rope fulcrum bypassed for lifting rope 4 is formed with support arm 241 of encorbelmenting.Preferably,
Support arm 241 of encorbelmenting can be structure as a whole with linking arm 24, preferably square steel tube or shaped steel.
As the better embodiment of the present embodiment one, when liter object is hung, the bonding strength of hanging basket 5 and structural beams,
Directly determine construction, security, the efficiency of operation etc..In order to lifted overhead type hanging basket mounting stability and with structural beams
Bonding strength, first support 11 is connected to the first aerial construction beam 7 by bearing, and bearing includes backing plate 12 and chemical anchor bolts 13,
Perforation is offered on backing plate 12, chemical anchor bolts 13 are arranged in perforate and plug and are fixed on the first aerial construction beam 7.
Used as the better embodiment of the present embodiment one, first support 11 is made up of vertical rod, and vertical rod uses 100 × 100 × 5 sides
Steel pipe, length is not less than 600mm, and backing plate 12 is billet, and billet is fixed on the first aerial construction beam 7 by chemical bolt 13
Place, on curtain wall roofing, the first aerial construction beam 7 is outside aerial construction beam, the second frame to the present invention in the present embodiment
Hollow structure beam 8 is inner side aerial construction beam.Billet is advised using 10mm steel plates, chemical anchor bolts are not less than using M14 is not less than
Lattice.
As the better embodiment of the present embodiment one, when hanging basket 5 are installed in the structures such as roofing, the first aerial construction
Beam 7 and the second aerial construction beam 8 spatially and it is highly inconsistent.Therefore, second support also includes second support arm 22;Second
Support arm 22 is connected to anchor ear 21 and linking arm 24.
Used as the better embodiment of the present embodiment one, traditional hanging basket needs the Balance weight end could to complete to hang liter, and general matches somebody with somebody
The weight member to be placed in foundation structure, or the anchoring piece of anchoring or formed by integrally casting in foundation structure are held again.This two
Plant mode one side waste of materials, install more heaviness;On the other hand install.Dismounting is all cumbersome, influence construction effect
Rate and process.And second support is removably bound round on the second aerial construction beam 8 by anchor ear 21 in the present invention, so as to solve
Above-mentioned drawback, at the same time, in order to strengthen the bonding strength between anchor ear 21 and second support arm 22, in anchor ear 21 and second
Bearing diagonal 23 is connected between arm 22.Preferably, bearing diagonal 23 is shaped steel.
Used as the better embodiment of the present embodiment one, the second support is detachable connection with the second aerial construction beam 8,
Specifically, the hoop of anchor ear 21 of second support is located at structural beams 8, there is provided impetus of the invention, as " Balance weight end " of the invention.
Further, anchor ear 21 is a closed-loop, and the cross-sections match of the second aerial construction beam 8 is in the internal diameter of closed-loop, present embodiment
It is only a better embodiment of the present embodiment, anchor ear 21 is intended to card and sets be fixed in structural beams 8, in the presence of external force not
Separated with structural beams 8.Specifically, anchor ear 21 can be non-close ring etc..
Used as the better embodiment of the present embodiment one, rope rolling 6 has two kinds of set-up modes:
The first, refers to Fig. 1, and rope rolling 6 is fixedly arranged on hanging basket, and the second end of lifting rope 5 is connected to rope rolling 6.By volume
With lifting rope 4 be connected hanging basket 5 by rope machine 6, when the serving of rope rolling 6, rope closing, drives hanging basket 5 to be lifted, so as to complete object
Hang liter;
Second, Fig. 2 is referred to, rope rolling 6a is fixedly arranged on the one end of linking arm 24 away from first support 11, the of lifting rope 4
One end is connected to rope rolling 6a.Rope rolling 6a is arranged on rope closing, serving on linking arm 24, so as to drive the second end of lifting rope 4
Hanging basket 5 lifting., can there is friction in this kind of set-up mode, be between the lifting rope fulcrum of lifting rope 4 and first, the second lifting rope fulcrum
This is respectively provided with the first antifriction pulley 91 and the second antifriction pulley 92 on the first lifting rope fulcrum and the second lifting rope fulcrum.Subtracted with this
The abrasion of small lifting rope 4.
Above-mentioned technical proposal is taken, following technique effect is obtained:
First, the first support in the present invention is fixed on concrete structure by chemical anchor bolts and billet, and stability is high,
Hanging basket is difficult displacement.
2nd, second support height can determine that adjustable is high, and practicality is wide according to the height of aerial construction beam 8 in the present invention.
3rd, the present invention uses 100 × 100 × 5 square steel tubes, and type of attachment is welding and anchor bolts, repeats and utilizes, section
Material saving.
Present invention also offers a kind of installation method of the mounting structure of built on stilts hanging basket, comprise the following steps:
Step S1:First support is installed on the first aerial construction beam.
Specifically, when liter object is hung, hanging basket and the bonding strength of agent structure directly determine construction, operate
Security, efficiency etc..In order to lift the mounting stability and bonding strength with agent structure of overhead type hanging basket, first support
11 are connected to the first aerial construction beam 7 by bearing, and bearing includes backing plate 12 and chemical anchor bolts 13, offered on backing plate 12 and worn
Hole, chemical anchor bolts 13 are arranged in perforate and plug and are fixed on the first aerial construction beam 7.
Preferably, first support is made up of vertical rod, vertical rod uses 100 × 100 × 5 square steel tubes, and length is not less than 600mm,
Backing plate 12 is billet, and billet hangs liter place by what chemical bolt 13 was fixed on agent structure, of the invention in the present embodiment
On curtain wall roofing, the first aerial construction beam 7 is outside aerial construction beam, and the second aerial construction beam 8 is the built on stilts knot in inner side
Structure beam.Billet is used and is not less than M14 specifications using 10mm steel plates, chemical anchor bolts are not less than.
Preferably, in order to prevent from being collided because distance is too near between the aerial construction beam 7 of hanging basket 5 and first, rub, entering
One step also for protection hanging basket 5, the top of first support 11 is formed with the first lifting rope fulcrum bypassed for lifting rope 4, first
Side in frame 11 away from the second aerial construction beam 8 be provided with for by the aerial construction beam 7 of lifting rope 4 and first from a distance
Support arm 241 of encorbelmenting, the second lifting rope fulcrum bypassed for lifting rope 4 is formed with support arm 241 of encorbelmenting.
Step S2:Second support is installed on the second aerial construction beam.
Specifically, second support includes anchor ear 21 of the hoop on the second aerial construction beam 8 and is connected to anchor ear 21 and the
The linking arm 24 of one support.
Preferably, when hanging basket is installed in the structures such as roofing, the first aerial construction beam 7 and the second aerial construction beam 8
Spatially and it is highly inconsistent.Therefore, second support also includes second support arm 22;Second support arm 22 be connected to anchor ear 21 with
Linking arm 24.
Preferably, traditional hanging basket needs the Balance weight end could to complete to hang liter, general Balance weight end is to be placed in foundation structure
Weight member, or anchoring piece in foundation structure of anchoring or formed by integrally casting.This two kinds of mode one side waste of materials,
Install more heavy;On the other hand install.Dismounting is all cumbersome, influences efficiency of construction and process.And in the present invention
Two supports are removably bound round on the second aerial construction beam 8 by anchor ear 21, so as to solve above-mentioned drawback, at the same time,
In order to strengthen the bonding strength between anchor ear 21 and second support arm 22, bearing diagonal is connected between anchor ear 21 and second support arm 22
23.Preferably, bearing diagonal 23 is shaped steel.
Preferably, the second support is detachable connection with structural beams 8, specifically, the hoop of anchor ear 21 of first support sets
In the first aerial construction beam 8, there is provided impetus of the invention.Further, anchor ear 21 is a closed-loop, the second aerial construction beam
In the internal diameter of closed-loop, present embodiment is only a better embodiment of the present embodiment to 8 cross-sections match, and anchor ear 21 is intended to
Card sets and is fixed in structural beams 8, when hanging liter, is not separated with structural beams 8 in the presence of external force.Specifically, anchor ear
21 can be non-close ring etc..
Step S3:Lifting rope 4 is installed in first support 11 with the second support.Specifically, the first end of lifting rope 4 is connected
Second support is connected to, the second end bypasses first support 11 and is connected to hanging basket 5.
Step S4:Rope rolling 6 is installed on lifting rope 4.
Specifically, rope rolling 6 has two kinds of set-up modes:
The first, refers to Fig. 1, and rope rolling 6 is fixedly arranged on hanging basket 5, and the second end of lifting rope 4 is connected to rope rolling 6.By volume
With lifting rope 4 be connected hanging basket 5 by rope machine 6, when the serving of rope rolling 6, rope closing, drives hanging basket 5 to be lifted, so as to complete object
Hang liter;
Second, Fig. 3 is referred to, rope rolling 6a is fixedly arranged on the one end of linking arm 24 away from first support, the first of lifting rope
End is connected to rope rolling.Rope rolling is arranged on rope closing on linking arm, serving, so as to drive the hanging basket 5 at the second end of lifting rope 4
Lifting., can there is friction in this kind of set-up mode, be that this hangs first between the lifting rope fulcrum of lifting rope 4 and first, the second lifting rope fulcrum
The first antifriction pulley 91 and the second antifriction pulley 92 are respectively provided with rope fulcrum and the second lifting rope fulcrum.Lifting rope 4 is reduced with this
Abrasion.
Using above method so that the present invention specific following beneficial effect when liter object is hung:
First, convenient to assemble and disassemble, materials are simple, and cost control is relatively low;
2nd, second support height can determine that adjustable is high, and practicality is wide according to aerial construction depth of beam in the present invention.
3rd, it is reusable, and itself will not be damaged during reuse, meet environmental protection theory.
The present invention is described in detail above in association with accompanying drawing embodiment, those skilled in the art can be according to upper
State and bright various changes are made to the present invention.Thus, on the premise of claim objective of the invention is not violated, in embodiment
Some details should not constitute limitation of the invention, the scope that the present invention will be defined using appended claims is used as protection model
Enclose.
Claims (10)
1. a kind of mounting structure of built on stilts hanging basket, it is characterised in that including:
First support, is installed on the first aerial construction beam;
Second support, including bind round the anchor ear on the second aerial construction beam and be connected to the anchor ear with the first support
Linking arm;And
Lifting rope, the first end of the lifting rope is connected to the second support, and the second end of the lifting rope bypasses the first support
And it is connected with hanging basket.
2. the mounting structure of built on stilts hanging basket according to claim 1, it is characterised in that the top of the first support is formed
Have a first lifting rope fulcrum bypassed for the lifting rope, the side in the first support away from the second support be provided with for
Support arm of encorbelmenting by the lifting rope with the first aerial construction beam from a distance, is formed with the support arm of encorbelmenting and supplies institute
State the second lifting rope fulcrum that lifting rope is bypassed.
3. the mounting structure of built on stilts hanging basket according to claim 1, it is characterised in that the first support is connected by bearing
The first aerial construction beam is connected to, the bearing includes backing plate and chemical anchor bolts, perforation, describedization are offered on the backing plate
Learn crab-bolt and be arranged in the perforation and plug and be fixed on the first aerial construction beam.
4. the mounting structure of built on stilts hanging basket according to claim 1, it is characterised in that the second support also includes second
Support arm;The second support arm is connected to the anchor ear with the linking arm.
5. the mounting structure of built on stilts hanging basket according to claim 4, it is characterised in that the anchor ear and the second support arm
Between be connected with bearing diagonal.
6. the mounting structure of built on stilts hanging basket according to claim 1, it is characterised in that the anchor ear is a closed-loop, institute
The cross-sections match of the second aerial construction beam is stated in the internal diameter of the closed-loop.
7. the mounting structure of built on stilts hanging basket according to claim 1, it is characterised in that also including rope rolling, the serving
Machine is fixedly arranged on the one end of the linking arm away from the first support, and the first end of the lifting rope is connected to the rope rolling.
8. the mounting structure of built on stilts hanging basket according to claim 1, it is characterised in that also including rope rolling, the serving
Machine is fixedly arranged on the hanging basket, and the second end of the lifting rope is connected to the rope rolling.
9. a kind of installation method of air-spaced roof hanging basket, it is characterised in that comprise the following steps:
First support is installed on the first aerial construction beam;
Second support is installed on the second aerial construction beam, the second support includes hoop embracing on the second aerial construction beam
Bind round and be connected to the linking arm of the anchor ear and the first support;And
Lifting rope is installed in the first support with the second support, the first end of the lifting rope is connected to described second
Frame, the second end of the lifting rope bypasses the first support and is connected with hanging basket.
10. the installation method of the mounting structure of built on stilts hanging basket according to claim 9, it is characterised in that be also equipped with volume
Rope machine, the hanging basket is fixedly arranged on by the rope rolling, and the second end of the lifting rope is connected into the rope rolling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710103617.XA CN106812301A (en) | 2017-02-24 | 2017-02-24 | A kind of mounting structure and installation method of built on stilts hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710103617.XA CN106812301A (en) | 2017-02-24 | 2017-02-24 | A kind of mounting structure and installation method of built on stilts hanging basket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106812301A true CN106812301A (en) | 2017-06-09 |
Family
ID=59111891
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710103617.XA Pending CN106812301A (en) | 2017-02-24 | 2017-02-24 | A kind of mounting structure and installation method of built on stilts hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106812301A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110185250A (en) * | 2019-06-13 | 2019-08-30 | 中建八局第四建设有限公司 | A kind of nacelle construction device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103058090A (en) * | 2013-01-11 | 2013-04-24 | 江苏申锡建筑机械有限公司 | Multifunctional lifting device |
CN204571264U (en) * | 2015-03-24 | 2015-08-19 | 中建八局第一建设有限公司 | A kind of fastening devices without counterweight hanging basket |
CN204983613U (en) * | 2015-08-05 | 2016-01-20 | 中建一局集团第二建筑有限公司 | Hoist and mount system of cell board curtain installation |
CN105776092A (en) * | 2016-04-21 | 2016-07-20 | 江河创建集团股份有限公司 | Stretching type basket device and construction method thereof |
CN205777425U (en) * | 2016-07-07 | 2016-12-07 | 中建三局集团有限公司 | A kind of scalable hanging basket support means |
-
2017
- 2017-02-24 CN CN201710103617.XA patent/CN106812301A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103058090A (en) * | 2013-01-11 | 2013-04-24 | 江苏申锡建筑机械有限公司 | Multifunctional lifting device |
CN204571264U (en) * | 2015-03-24 | 2015-08-19 | 中建八局第一建设有限公司 | A kind of fastening devices without counterweight hanging basket |
CN204983613U (en) * | 2015-08-05 | 2016-01-20 | 中建一局集团第二建筑有限公司 | Hoist and mount system of cell board curtain installation |
CN105776092A (en) * | 2016-04-21 | 2016-07-20 | 江河创建集团股份有限公司 | Stretching type basket device and construction method thereof |
CN205777425U (en) * | 2016-07-07 | 2016-12-07 | 中建三局集团有限公司 | A kind of scalable hanging basket support means |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110185250A (en) * | 2019-06-13 | 2019-08-30 | 中建八局第四建设有限公司 | A kind of nacelle construction device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206016225U (en) | One kind is without counterweight fixture type gondola-hanging mechanism | |
CN104310165A (en) | Guide rail type adhesion construction lifter and construction method thereof | |
CN207268073U (en) | Novel flexible formwork bearing frame | |
CN102777037B (en) | Simple and practical hoisting construction method of long-span steel girder | |
CN202577925U (en) | Lifting type platform in elevator shaft | |
CN106812301A (en) | A kind of mounting structure and installation method of built on stilts hanging basket | |
CN105776092B (en) | A kind of extended position nacelle device | |
CN205953378U (en) | Tower crane counter weight is put from dismouting | |
CN206599984U (en) | A kind of mounting structure of built on stilts hanging basket | |
CN105731271A (en) | Combined tower crane for roof construction and construction method thereof | |
CN204252083U (en) | Arch dam bracket hangs plate device by the feet entirely | |
CN206646836U (en) | A kind of exterior wall, inner partition plate movement lifting frame | |
CN206158146U (en) | Novel building section of thick bamboo well construction operation platform | |
CN202000647U (en) | Base device for lifting scaffold in elevator shaft | |
CN201502170U (en) | Horizontal supporting device of building external frame | |
CN209567730U (en) | A kind of small-sized lattice dead man steel construction | |
CN204096948U (en) | Annular double track sliding rail Special hoisting mechanism | |
CN207436058U (en) | A kind of clump weight of hydraulic static pile pressing machine | |
CN203320922U (en) | Supporting device for forming of elevator shaft template | |
CN101845914B (en) | Installation method of three-tube steel chimney | |
CN206328867U (en) | A kind of post bottom steel structure member | |
CN206376578U (en) | A kind of monoblock type fire water pump house | |
CN205932940U (en) | Hang various steel sheet tripod | |
CN205875410U (en) | A hang module system all for tube structure room panel construction | |
CN201485204U (en) | Gas tank hanging device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170609 |
|
RJ01 | Rejection of invention patent application after publication |