CN105731271A - Combined tower crane for roof construction and construction method thereof - Google Patents

Combined tower crane for roof construction and construction method thereof Download PDF

Info

Publication number
CN105731271A
CN105731271A CN201610212542.4A CN201610212542A CN105731271A CN 105731271 A CN105731271 A CN 105731271A CN 201610212542 A CN201610212542 A CN 201610212542A CN 105731271 A CN105731271 A CN 105731271A
Authority
CN
China
Prior art keywords
roof
roofing
tower crane
tower
tower body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610212542.4A
Other languages
Chinese (zh)
Inventor
严凤英
陈晓明
冯振源
张宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201610212542.4A priority Critical patent/CN105731271A/en
Publication of CN105731271A publication Critical patent/CN105731271A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/20Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes with supporting couples provided by walls of buildings or like structures
    • B66C23/205Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes with supporting couples provided by walls of buildings or like structures for use on top of roofs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a combined tower crane for roof construction and a construction method thereof and belongs to the technical field of architectural engineering. The combined tower crane for roof construction and the construction method thereof are used for solving the technical problem that a conventional tower crane and other mechanical equipment cannot be used for hoisting construction normally under the condition that the structure of a roof is complex. The combined tower crane comprises a first roof surface crane body and a second roof surface crane body which are arranged in parallel. The first roof surface crane body is installed on a roof through a supporting frame. The second roof surface crane body is connected with the roof through a tower crane foundation. The tower crane foundation comprises a tower body and foundation steel beams. The upper end of the tower body is in rotary connection with the second roof surface crane body. The lower end of the tower body is in fixed connection with the foundation steel beams. The foundation steel beams are fixedly connection with the roof. The construction method comprises the steps that 1, the first roof surface crane body is fixedly installed in the position, above a core barrel, of the roof through the supporting frame; 2, the foundation steel beams are fixedly installed on the roof, and the tower body is fixedly installed over the foundation steel beams; and 3, the second roof surface crane body is lifted through the first roof surface crane body, so that a lower rotation body at the bottom of the second roof surface crane body is in rotary connection with an upper rotation body of the tower body.

Description

A kind of combination tower crane for roof construction and construction method thereof
Technical field
The present invention relates to construction engineering technical field, particularly to a kind of combination tower crane for roof construction and construction method thereof.
Background technology
Along with the building that the development of urban construction, outdated building or construction time are more of a specified duration all needs to transform, especially increasing FRAME ON THE ROOF OF HIGH-RISE BUILDING needs to transform.When the roof modified construction carrying out skyscraper, often adopting tower crane to carry out the lifting of component, the more commonly used tower crane is that roofing hangs, and roofing hangs the tower body not having supporting setting, thus requires higher to installation site.When carrying out roof modified construction, when roof structure is complicated, especially each position end face absolute altitude straggly bigger time, roofing hangs the construction requirement that can not meet lifting.Therefore, how providing low, the safe and reliable tower crane for roof construction of a kind of easy to operate, cost and construction method thereof is that those skilled in the art need badly and solve the technical problem that.
Summary of the invention
It is an object of the invention to provide a kind of combination tower crane for roof construction and construction method thereof, be used for solving under roof structure complex situations, it is impossible to use the plant equipment such as conventional tower crane to carry out the technical barrier of lifting construction.
For solving above-mentioned technical problem, technical scheme is as follows:
A kind of combination tower crane for roof construction, including the roofing being set up in parallel hang one and roofing hang two, described roofing hangs one and is installed on described roof by bracing frame, described roofing is hung two and is connected with described roof by tower crane, described tower crane includes tower body and basis girder steel, the upper end of described tower body is hung two-revolution with described roofing and is connected, and the lower end of described tower body is fixing with described basis girder steel to be connected, and described basis girder steel is fixing with described roof to be connected.
Further, also including sustaining wall bar, one end of described sustaining wall bar is fixing with described roof to be connected, and the other end of described sustaining wall bar is fixing with described tower body to be connected.
Further, described sustaining wall bar is Two bors d's oeuveres channel-section steel.
Further, described tower body welds or riveting with described basis girder steel.
The invention also discloses the construction method of combination tower crane, comprise the steps:
Step one, by support frame as described above, described roofing is hung on a described roof being fixedly installed in above Core Walls Structure;
Step 2, fixedly mount on described roof described basis girder steel, and described tower body is fixedly installed in described basis girder steel above;
Step 3, hung a described roofing of lifting by described roofing and hang two so that described roofing hangs the lower revolution bottom two and turns round with the upper rotary of described tower body and be connected.
Further, described step 2 also includes: the first step, pre-buried embedded part on described roof;Second step, welds described basis girder steel on described embedded part;3rd step, welds described tower body above the girder steel of described basis.
Compared with prior art, useful the having the technical effect that of the present invention
1, the combination tower crane for roof construction that the embodiment of the present invention provides, including the roofing being set up in parallel hang one and roofing hang two, roofing hangs one and is installed on roof by bracing frame, roofing is hung two and is connected with roof by tower crane, tower crane includes tower body and basis girder steel, the upper end of tower body is hung two-revolution with roofing and is connected, and the lower end of tower body is fixing with basis girder steel to be connected, and basis girder steel is fixing with roof to be connected.The installation hung due to roofing is high to status requirement, therefore, the difficult problem of two is hung for can not install roofing by conventional methods because installation site is special, a matched tower body is set up, thus solving roofing to hang the installation difficult problem of two by when mounted the roofing originally not having supporting tower body being hung two.It is to say, by hanging one tower body of corresponding increase below two at roofing, solve under roof structure complex situations, it is impossible to use the plant equipment such as conventional tower crane to carry out the technical barrier of lifting construction.
The construction method of the combination tower crane that 2, the embodiment of the present invention provides, it is first according to the usual manner good roofing of installation installation site and hangs one, then utilize the roofing installed to hang a lifting roofing and hang two, and roofing is hung the lower revolution of two turn round with the upper rotary of tower body and be connected, make roofing hang the installation of two by the restriction of installation site, thus ensure to be hung by roofing one and roofing hang the lifting work that the combination tower crane that two combinations constitute normally completes in roof modified construction.
Accompanying drawing explanation
Fig. 1 is the elevation of the combination tower crane for roof construction of one embodiment of the invention;
Fig. 2 is the tower crane schematic diagram of the tower crane two of the combination tower crane for roof construction of one embodiment of the invention;
Fig. 3 is the tower crane two connection diagram with tower body of the combination tower crane for roof construction of one embodiment of the invention;
Fig. 4 is the basic girder steel connection diagram with embedded part of one embodiment of the invention.
In figure:
10-roofing hangs one;20-roofing hangs two;21-tower body;22-basis girder steel;23-sustaining wall bar;25-upper rotary;Turn round under 26-;30-bracing frame;40-roof.
Detailed description of the invention
The combination tower crane for roof construction and the construction method thereof that the present invention are proposed below in conjunction with the drawings and specific embodiments are described in further detail.According to the following describes and claims, advantages and features of the invention will be apparent from.It should be noted that, accompanying drawing all adopts the form simplified very much and all uses non-ratio accurately, only in order to convenience, the purpose aiding in illustrating the embodiment of the present invention lucidly.For sake of convenience, described below " on ", the upper and lower direction of D score and accompanying drawing consistent, but this can not become the restriction of technical solution of the present invention.
The invention provides a kind of combination tower crane for roof construction and construction method thereof, be used for solving under roof structure complex situations, it is impossible to use the plant equipment such as conventional tower crane to carry out the technical barrier of lifting construction.
Combination tower crane and the construction method thereof that the present invention constructs for roof is described in detail below in conjunction with Fig. 1 to Fig. 4.
Embodiment one
The present embodiment is for certain technological transformation project, this project high building original structure Bock Altitude is to 115.75m, owing to being subject to place and original structure restriction, outer attached tower crane and interior (outward) climbing tower crane cannot be installed, the peripheral combination tower crane installation in position using the present embodiment with the newly-increased steel construction in roof of final high building.As shown in Figures 1 to 4, a kind of combination tower crane for roof construction, including the roofing being set up in parallel hang 1 and roofing hang 2 20, roofing hangs 1 and is installed on roof 40 by bracing frame 30, roofing is hung 2 20 and is connected with roof 40 by tower crane, and tower crane includes tower body 21 and basis girder steel 22, and the upper end of tower body 21 is hung 2 20 revolutions and is connected with roofing, the lower end of tower body 21 is fixing with basis girder steel 22 to be connected, and basis girder steel 22 is fixing with roof 40 to be connected.
Specifically, for the complex working condition that each position, roof 40 end face absolute altitude of original structure is different, select two tower cranes (roofing hang 1 and roofing hang 2 20) combination use, wherein roofing hangs on one 10 roofs 40 being arranged at above the Core Walls Structure that end face absolute altitude is higher, and roofing hangs 1 and is connected by bracing frame 30 is fixing with the roof 40 above Core Walls Structure.Roofing hangs 2 20 and is positioned on the relatively low roof of end face absolute altitude 40.In order to ensure roofing hang 1 and roofing hang 2 20 combination use, roofing hangs and arranges tower body 21 between 2 20 and roof 40, thus solving the installation that under roof 40 end face Altitude difference situation, roofing hangs so that be not subject to the restriction of installation site when roofing hangs 2 10 installation.Certainly, before tower body 21 is installed, it is necessary to a load transfer device is set between tower body 21 and roof 40, in the present embodiment, girder steel 22 based on load transfer device, by the effect of basis girder steel 22, by in the power smooth transfer of tower body 21 to roof 40, thus ensureing that roofing hangs 2 20 safty hoisting constructions.This combination tower crane uses QD10 roofing to hang and hangs 2 20 as roofing and be combined into roofing with ST6015 tower body 21 and hang 2 20 and be installed on 103.8m absolute altitude place, roof, the brachium that wherein QD10 roofing hangs is 24 meters, the height of ST6015 tower body 21 is 12 meters, the lower end of 2 20 is hung by tower body 21 is installed on roofing, hang so that the roofing after improving hangs the serviceability of 2 20 more than QD10 roofing, it is possible to meet QD10 roofing and hang the construction operating mode load requirement to tower body.That is select QD10 roofing to hang and hang 2 20 as roofing, and select tower body 21 to hang the basis of 2 20 as roofing, thus meeting roofing to hang the installation requirement of 2 20 so that roofing hangs the installation of 2 20 not by the restriction of installation site.
Further, also including sustaining wall bar 23, one end of sustaining wall bar 23 is fixing with roof 40 to be connected, and the other end of sustaining wall bar 23 is fixing with tower body 21 to be connected.By arranging sustaining wall bar 23, it is possible to prevent tower body 21 from occurring to roll phenomenon, thus ensureing the safe and stable operation of tower body 21.Certainly, the position of sustaining wall bar 23 is be more than or equal to the position of centre of gravity of tower body 21, to ensure the positioning action of sustaining wall bar 23.Sustaining wall bar 23 is connected by embedded part is fixing with roof 40.Certainly, it is contemplated that the convenience drawn materials and saving cost, sustaining wall bar 23 is Two bors d's oeuveres channel-section steel.
With continued reference to Fig. 4 especially, tower body 21 welds or riveting with basis girder steel 22.QD10 tower crane hangs 2 20 as roofing, and the angle welding of its basis girder steel 22 and embedded part should be greater than being equal to 20mm, it is possible to selecting chemical anchor bolts, wherein 6M12 chemical anchor bolts are for inner side metope, and 6M20 chemical anchor bolts are for outside metope.
Accordingly, the present embodiment additionally provides a kind of construction method combining tower crane.Incorporated by reference to referring to figs. 1 to Fig. 4, the construction method of combination tower crane, comprising the following steps:
S001: roofing is hung on one 10 roofs 40 being fixedly installed in above Core Walls Structure by bracing frame 30;
S002: fixed installation basis girder steel 22 on roof 40, and tower body 21 is fixedly installed in above the girder steel 22 of basis;
S003: hang one 10 lifting roofings by roofing and hang 2 20 so that the lower revolution 26 that roofing hangs bottom 2 20 is connected with upper rotary 25 revolution of tower body 21.
Preferably, S002 also comprises the steps:
The first step, pre-buried embedded part on roof 40;
Second step, welding basis girder steel 22 on embedded part;
3rd step, welding tower body 21 above the girder steel of basis.
In sum, the combination tower crane for roof construction of the present invention, including the roofing being set up in parallel hang one and roofing hang two, roofing hangs one and is installed on roof by bracing frame, roofing is hung two and is connected with roof by tower crane, and tower crane includes tower body and basis girder steel, and the upper end of tower body is hung two-revolution with roofing and is connected, the lower end of tower body is fixing with basis girder steel to be connected, and basis girder steel is fixing with roof to be connected.The installation hung due to roofing is high to status requirement, therefore, the difficult problem of two is hung for can not install roofing by conventional methods because installation site is special, a matched tower body is set up, thus solving roofing to hang the installation difficult problem of two by when mounted the roofing originally not having supporting tower body being hung two.It is to say, by hanging one tower body of corresponding increase below two at roofing, solve under roof structure complex situations, it is impossible to use the plant equipment such as conventional tower crane to carry out the technical barrier of lifting construction.The construction method of this combination tower crane, it is first according to the usual manner good roofing of installation installation site and hangs one, then utilize the roofing installed to hang a lifting roofing and hang two, and roofing is hung the lower revolution of two turn round with the upper rotary of tower body and be connected, make roofing hang the installation of two by the restriction of installation site, thus ensure to be hung by roofing one and roofing hang the lifting work that the combination tower crane that two combinations constitute normally completes in roof modified construction.
Foregoing description is only the description to present pre-ferred embodiments, not any restriction to the scope of the invention, any change that the those of ordinary skill in field of the present invention does according to the disclosure above content, modification, belongs to the protection domain of claims.

Claims (6)

1. the combination tower crane for roof construction, it is characterized in that, including the roofing being set up in parallel hang one and roofing hang two, described roofing hangs one and is installed on described roof by bracing frame, described roofing is hung two and is connected with described roof by tower crane, and described tower crane includes tower body and basis girder steel, and the upper end of described tower body is hung two-revolution with described roofing and is connected, the lower end of described tower body is fixing with described basis girder steel to be connected, and described basis girder steel is fixing with described roof to be connected.
2. the combination tower crane for roof construction as claimed in claim 1, it is characterised in that also include sustaining wall bar, one end of described sustaining wall bar is fixing with described roof to be connected, and the other end of described sustaining wall bar is fixing with described tower body to be connected.
3. the combination tower crane for roof construction as claimed in claim 2, it is characterised in that described sustaining wall bar is Two bors d's oeuveres channel-section steel.
4. the combination tower crane for roof construction as claimed in claim 3, it is characterised in that described tower body welds or riveting with described basis girder steel.
5. the construction method of the combination tower crane as described in any one of Claims 1-4, it is characterised in that comprise the steps:
Step one, by support frame as described above, described roofing is hung on a described roof being fixedly installed in above Core Walls Structure;
Step 2, fixedly mount on described roof described basis girder steel, and described tower body is fixedly installed in described basis girder steel above;
Step 3, hung a described roofing of lifting by described roofing and hang two so that described roofing hangs the lower revolution bottom two and turns round with the upper rotary of described tower body and be connected.
6. the construction method combining tower crane as claimed in claim 5, it is characterised in that described step 2 also includes: the first step, pre-buried embedded part on described roof;
Second step, welds described basis girder steel on described embedded part;
3rd step, welds described tower body above the girder steel of described basis.
CN201610212542.4A 2016-04-07 2016-04-07 Combined tower crane for roof construction and construction method thereof Pending CN105731271A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610212542.4A CN105731271A (en) 2016-04-07 2016-04-07 Combined tower crane for roof construction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610212542.4A CN105731271A (en) 2016-04-07 2016-04-07 Combined tower crane for roof construction and construction method thereof

Publications (1)

Publication Number Publication Date
CN105731271A true CN105731271A (en) 2016-07-06

Family

ID=56252933

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610212542.4A Pending CN105731271A (en) 2016-04-07 2016-04-07 Combined tower crane for roof construction and construction method thereof

Country Status (1)

Country Link
CN (1) CN105731271A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106365054A (en) * 2016-10-31 2017-02-01 林少明 Material elevator for construction
CN107055347A (en) * 2017-05-22 2017-08-18 庄爱军 A kind of high-rise Tower crane disassembly structures and methods installed
CN108792963A (en) * 2017-05-04 2018-11-13 黄明 A kind of Steel Space Truss formula tower crane wall-attached supporting seat method for high-rise roof framework

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2266511A (en) * 1992-04-30 1993-11-03 Lin Huang Chuan Mobile construction crane
CN201228206Y (en) * 2008-04-30 2009-04-29 中建三局建设工程股份有限公司 Self-made small-sized hoisting machine
CN202530775U (en) * 2012-02-03 2012-11-14 上海庞源机械租赁股份有限公司 Structure for dismounting inner climbing tower crane by using roof crane
CN103979437A (en) * 2014-05-26 2014-08-13 上海市机械施工集团有限公司 Tower crane wall attached member bar device
CN203795459U (en) * 2014-03-31 2014-08-27 广东庞源工程机械有限公司 Foundation structure of tower crane for high-altitude roofs

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2266511A (en) * 1992-04-30 1993-11-03 Lin Huang Chuan Mobile construction crane
CN201228206Y (en) * 2008-04-30 2009-04-29 中建三局建设工程股份有限公司 Self-made small-sized hoisting machine
CN202530775U (en) * 2012-02-03 2012-11-14 上海庞源机械租赁股份有限公司 Structure for dismounting inner climbing tower crane by using roof crane
CN203795459U (en) * 2014-03-31 2014-08-27 广东庞源工程机械有限公司 Foundation structure of tower crane for high-altitude roofs
CN103979437A (en) * 2014-05-26 2014-08-13 上海市机械施工集团有限公司 Tower crane wall attached member bar device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
朱武军: "高层建筑改造中新增屋面钢结构吊装方案选择与优化", 《建筑施工》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106365054A (en) * 2016-10-31 2017-02-01 林少明 Material elevator for construction
CN108792963A (en) * 2017-05-04 2018-11-13 黄明 A kind of Steel Space Truss formula tower crane wall-attached supporting seat method for high-rise roof framework
CN107055347A (en) * 2017-05-22 2017-08-18 庄爱军 A kind of high-rise Tower crane disassembly structures and methods installed
CN107055347B (en) * 2017-05-22 2018-03-27 庄爱军 A kind of Tower crane disassembly structures and methods of high-rise installation

Similar Documents

Publication Publication Date Title
CN105692470B (en) Inner climbing crane tower and its operating method
CN104234200B (en) A kind of suspen-shell structure rope leverage is by ring lifting installation method
CN102733615B (en) Unsymmetrical integral lifting construction method
CN106219419A (en) High-rise building large-scale swing arm tower crane is converted to plug-in construction method by interior climbing in situ
CN102953553B (en) Method for installing large-span pipe truss by utilizing boom luffing mechanism
CN103195256A (en) Hanging column type steel structure jig frame construction method
CN105731271A (en) Combined tower crane for roof construction and construction method thereof
CN103352576A (en) Externally expanding, assembling, converting and lifting method for medium/small span steel structure roof net rack
CN207268073U (en) Novel flexible formwork bearing frame
CN207879008U (en) Diameter Silo structure roof support system
CN201567163U (en) Tower crane
CN203441069U (en) Outer wall dangling working platform capable of overturning
CN103276722B (en) A kind of low clearance pile frame and using method thereof
CN101906870A (en) Suspended scaffolding
CN201687218U (en) Installation device of steel shaft well
CN203794505U (en) Internal climbing steel beam conveying device of internal climbing movable arm tower crane
CN103482493A (en) Internal climbing tower crane
CN107130786B (en) Construction lifting platform
CN104591006A (en) Single-edge extended truss mechanism of tower crane and construction method thereof
CN203320922U (en) Supporting device for forming of elevator shaft template
CN209194970U (en) A kind of detachable vertical hoistway promotion platform of Super High
CN105781610A (en) Safety cabin for manual hole digging operation
CN106869508B (en) A kind of rotation lifting of assembled architecture steel box column is welded and fixed mounting process in place
CN206987720U (en) A kind of double shield cage cat ladders
CN106320681A (en) Elevator shaft standard operation platform and implementation platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160706