CN106320681A - Elevator shaft standard operation platform and implementation platform - Google Patents
Elevator shaft standard operation platform and implementation platform Download PDFInfo
- Publication number
- CN106320681A CN106320681A CN201510380240.3A CN201510380240A CN106320681A CN 106320681 A CN106320681 A CN 106320681A CN 201510380240 A CN201510380240 A CN 201510380240A CN 106320681 A CN106320681 A CN 106320681A
- Authority
- CN
- China
- Prior art keywords
- girder
- operating platform
- elevator
- supporting leg
- supporting legs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 19
- 239000010959 steel Substances 0.000 claims abstract description 19
- 238000010276 construction Methods 0.000 claims abstract description 18
- 238000000034 method Methods 0.000 claims abstract description 7
- 238000003466 welding Methods 0.000 claims abstract description 7
- 238000009415 formwork Methods 0.000 claims abstract description 6
- 238000005452 bending Methods 0.000 claims abstract description 4
- 238000004519 manufacturing process Methods 0.000 claims abstract description 4
- 239000000725 suspension Substances 0.000 claims description 13
- 238000005520 cutting process Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 abstract description 5
- 239000000463 material Substances 0.000 abstract description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract 4
- 229910052742 iron Inorganic materials 0.000 abstract 2
- 230000007306 turnover Effects 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses an elevator shaft standard operation platform and an implementation method. The operation platform comprises a supporting frame, supporting legs, hanging rings and a formwork. The supporting frame is formed by welding box iron girders and box iron secondary beams. The supporting legs are composed of the rotary supporting legs and the fixed supporting legs. The rotary supporting legs are mechanically connected with the girders through rotary shafts, when the operation platform is lifted, the rotary supporting legs can rotate freely by 90 degrees, and an operator just needs to place the rotary supporting legs into reserved holes during installation. One end of each fixed supporting leg is welded and fixed to the corresponding girder, the other end of each fixed supporting leg is connected with a reserved steel bar, and in the lifting process, the fixed supporting legs are cut off the reserved steel bars. The hanging rings are formed by bending steel bars and welded to the girders. The formwork is laid on the girders. According to the elevator shaft standard operation platform and the implementation method, standard manufacturing of the elevator shaft operation platform is achieved, overall installation is convenient and fast, the problems that the erection efficiency of a scaffold in an elevator liftway is low, the material turnover cycle is long can be effectively solved, the construction cost is reduced, and construction safety is guaranteed.
Description
Technical field
The invention belongs to building structure construction field, concretely relate to elevator canalization operating platform and implementation.
Background technology
During building structure construction of lift well, in elevator hoistways, typically set up steel pipe scaffold, then carry out the reinforcing bar binding in elevator hoistways, formwork erection.For building height higher time, to successively set up scaffold, owing to ele-vator shaft spaces is narrow and small, operative's inconvenience, the material turn around times such as efficiency of construction is low, the steel pipe used by scaffold are long, it is unfavorable for saving construction cost, simultaneously when building height is too high, there is also general safety hidden danger.
Application publication number is that the patent of invention of CN 104453199 A discloses a kind of construction of lift well operating platform, including work platforms and supported underneath system, its work platforms is made up of steel plate and four fixing steel pipes, support system is made up of steel channel beam and the L-type Steel bar rack that welds below, this hoistway operation platform uses tool-type platform, and solution high-rise building elevator shaft operating platform takies a large amount of scaffold, material has enough to meet the need the problems such as slow.But, the installation each time of this operating platform is required for lower support and Main Girder Welding, and work progress welding job amount is big, relatively complicated and dangerous.
Summary of the invention
The technical problem to be solved is just to provide elevator canalization operating platform and implementation, can make with canalization, it is achieved repeatedly having enough to meet the need, reuse, construction cost is low, and implementation process is simple, operates safe and reliable.
For solving above-mentioned technical problem, the present invention adopts the following technical scheme that elevator canalization operating platform, including the bracing frame being made up of girder and secondary beam, the supporting leg being connected with girder respectively and suspension ring, the template being held on bracing frame, the girder that described bracing frame is made by channel-section steel is welded to connect with secondary beam, described supporting leg includes swing leg and fixed supporting leg, described swing leg is mechanically connected by one end of rotary shaft with girder, described fixed supporting leg is welded to connect with the other end of girder, described suspension ring by bar bending and and Main Girder Welding, described template is held on girder.
Preferably, described girder is provided with breach at the lower notch being connected with swing leg.
Preferably, described swing leg is made by channel-section steel, and rotary shaft is mechanically connected with girder, can do 90 ° and rotate freely.
The present invention also provides for the implementation of above-mentioned elevator canalization operating platform, mainly comprises the steps that
Step one: process girder, secondary beam, swing leg, fixed supporting leg, suspension ring, welding production operating platform according to the design size of elevator;
Step 2: during construction of lift well, at inner structural wall reserved opening, if any shear wall structure, the operating platform lay down location embedded bar on shear wall;
Step 3: tied up by lifting rope on suspension ring, utilizes crane gear lifting operation platform, is first connected with reserved steel bar by fixed supporting leg, be then stretched flat by swing leg, is positioned in pre-buried hole;
Step 4: template be held on girder, template requires to exceed bracing frame outward flange.
Step 5: treat that This floor complete, the hoistway formwork of construction is removed, and relevant work completes, cutting fixed supporting leg and embedded bar, by crane gear, operating platform is promoted to last layer again, then install, so circulate, until this canalization operating platform is hung away before binding by floor.
The present invention is elevator canalization operating platform and implementation, achieving hoistway operation platform canalization to make, integral installation is convenient and swift, can effectively solve in elevator hoistways the problems such as low, the material turn around time length of scaffold building efficiency, save construction cost, and ensure construction safety.
The invention will be further described with detailed description of the invention below in conjunction with the accompanying drawings.
Accompanying drawing explanation
Fig. 1 is the elevator canalization operating platform site plan of the present invention.
Fig. 2 is the elevator canalization operating platform side view of the present invention.
Detailed description of the invention
If Fig. 1 is to shown in 2, elevator canalization operating platform, mainly include bracing frame 1, supporting leg 2, suspension ring 3 and template 4.Described bracing frame 1 is welded by 2 girders 11 and 7 secondary beams 12, and its middle girder 11 and secondary beam 12 are welded by the channel-section steel not less than 16#, 14# respectively;Described supporting leg 2 is by swing leg 21 and fixes 22 and forms, wherein swing leg 21 is connected with girder 11 by rotary shaft 211, it is provided with breach at 11 times notches of the girder being connected with swing leg 21, swing leg rotates in the range of can realizing 90 °, fixed supporting leg 22 is welded with girder 11 by steel plate, and its other end is held in elevator shaft structure on reserved opening;Described suspension ring 3 weld by Φ 16 bar bending and with girder 11, and every girder 11 is provided with 2 suspension ring;Described template 4 is held on girder 11, and back gauge outer with bracing frame 1 is not less than 100mm.
The implementation of above-mentioned elevator canalization operating platform, mainly comprises the steps that
Step one: process channel-section steel girder 11, secondary beam 12, swing leg 21, fixed supporting leg 22, suspension ring 3, welding production operating platform according to the design size of elevator;
Step 2: during construction of lift well, at inner structural wall reserved opening 5, if any shear wall structure, the operating platform lay down location embedded bar 6 on shear wall;
Step 3: tied up on suspension ring 3 by lifting rope, utilizes crane gear lifting operation platform, is first connected with reserved steel bar 6 by fixed supporting leg 22, be then stretched flat by swing leg 21, is positioned in pre-buried hole 5;
Step 4: template 4 be held on girder 11, template 4 requires to exceed bracing frame 1 outward flange.
Step 5: treat that This floor complete, the hoistway formwork of construction is removed, and relevant work completes, cutting fixed supporting leg 22 and embedded bar 6, by crane gear, operating platform is promoted to last layer again, then install, so circulate, until this canalization operating platform is hung away before binding by floor.
The present invention compares more common hoistway operation platform and implementation compares, achieve hoistway operation platform canalization to make, integral installation, promote convenient and swift, can effectively solve the problem such as low, material turn around time length of scaffold building efficiency in elevator hoistways, save construction cost, and ensure construction safety.
The foregoing is only the specific embodiment of the present invention, but the technical characteristic of the present invention is not limited thereto, any those skilled in the art is in the field of the invention, and change or the modification made all are contained among the scope of the claims of the present invention.
Claims (5)
1. elevator canalization operating platform, it is characterized in that: include the bracing frame (1) being made up of girder (11) and secondary beam (12), the supporting leg (2) being connected with girder (11) respectively and suspension ring (3), the template (4) being held on bracing frame (1), the girder (11) that described bracing frame (1) is made by channel-section steel is welded to connect with secondary beam (12), described supporting leg (2) includes swing leg (21) and fixed supporting leg (22), described swing leg (21) is mechanically connected by one end of rotary shaft (211) with girder (11), described fixed supporting leg (22) is welded to connect with the other end of girder (11), described suspension ring (3) weld by bar bending and with girder (11), described template (4) is held on girder (11).
Elevator canalization operating platform the most according to claim 1, it is characterised in that: described girder (11) is provided with breach at the lower notch being connected with swing leg (21).
3. according to the elevator canalization operating platform described in claim 1 and 2, it is characterised in that: described swing leg (21) is made by channel-section steel, is mechanically connected with girder (11) by rotary shaft (211), can do 90 ° and rotate freely.
4. the implementation of elevator canalization operating platform as claimed in claim 1, it is characterised in that: mainly comprise the steps that
Step one: process girder (11), secondary beam (12), swing leg (21), fixed supporting leg (22), suspension ring (3), welding production operating platform according to the design size of elevator;
Step 2: during construction of lift well, in inner structural wall reserved opening (5), if any shear wall structure, operating platform lay down location embedded bar (6) on shear wall;
Step 3: tied up by lifting rope on suspension ring (3), utilizes crane gear lifting operation platform, is first connected with reserved steel bar (6) by fixed supporting leg (22), be then stretched flat by swing leg (21), be positioned over pre-buried hole (5) inner;
Step 4: template (4) be held on girder (11), template (4) requires to exceed bracing frame (1) outward flange.
5. step 5: treat that This floor complete, the hoistway formwork of construction is removed, and relevant work completes, cutting fixed supporting leg (22) and embedded bar (6), by crane gear, operating platform is promoted to last layer, then install, so circulation, until this canalization operating platform is hung away before binding by floor.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510380240.3A CN106320681A (en) | 2015-07-02 | 2015-07-02 | Elevator shaft standard operation platform and implementation platform |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510380240.3A CN106320681A (en) | 2015-07-02 | 2015-07-02 | Elevator shaft standard operation platform and implementation platform |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN106320681A true CN106320681A (en) | 2017-01-11 |
Family
ID=57726726
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510380240.3A Pending CN106320681A (en) | 2015-07-02 | 2015-07-02 | Elevator shaft standard operation platform and implementation platform |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106320681A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111472534A (en) * | 2020-04-30 | 2020-07-31 | 中建四局第六建设有限公司 | Steel operation platform for assisting hoisting of super high-rise steel bar |
| CN112627489A (en) * | 2020-12-07 | 2021-04-09 | 浙江二十冶建设有限公司 | Elevator shaft lifting operation platform |
| CN113387138A (en) * | 2021-06-30 | 2021-09-14 | 北京国际建设集团有限公司 | A conveyor for elevator reservation hole |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6311800B1 (en) * | 1999-06-28 | 2001-11-06 | ST-GERMAIN ANDRé | Raising system for scaffolding and the like |
| JP3699270B2 (en) * | 1998-03-03 | 2005-09-28 | 米山工業株式会社 | Mobile scaffold equipment |
| CN101387152A (en) * | 2008-10-20 | 2009-03-18 | 中建三局第一建设工程有限责任公司 | Tool-type scaffolding for an elevator shaft |
| CN201695681U (en) * | 2010-07-01 | 2011-01-05 | 中建三局建设工程股份有限公司 | Integral self-elevating type elevator hoistway tube mold |
| CN202745355U (en) * | 2012-08-06 | 2013-02-20 | 中建三局建设工程股份有限公司 | Lifting type elevator shaft operating platform |
-
2015
- 2015-07-02 CN CN201510380240.3A patent/CN106320681A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3699270B2 (en) * | 1998-03-03 | 2005-09-28 | 米山工業株式会社 | Mobile scaffold equipment |
| US6311800B1 (en) * | 1999-06-28 | 2001-11-06 | ST-GERMAIN ANDRé | Raising system for scaffolding and the like |
| CN101387152A (en) * | 2008-10-20 | 2009-03-18 | 中建三局第一建设工程有限责任公司 | Tool-type scaffolding for an elevator shaft |
| CN201695681U (en) * | 2010-07-01 | 2011-01-05 | 中建三局建设工程股份有限公司 | Integral self-elevating type elevator hoistway tube mold |
| CN202745355U (en) * | 2012-08-06 | 2013-02-20 | 中建三局建设工程股份有限公司 | Lifting type elevator shaft operating platform |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111472534A (en) * | 2020-04-30 | 2020-07-31 | 中建四局第六建设有限公司 | Steel operation platform for assisting hoisting of super high-rise steel bar |
| CN111472534B (en) * | 2020-04-30 | 2025-04-01 | 中国建筑第四工程局有限公司 | A steel operating platform for assisting the lifting of super-high-rise steel bars |
| CN112627489A (en) * | 2020-12-07 | 2021-04-09 | 浙江二十冶建设有限公司 | Elevator shaft lifting operation platform |
| CN113387138A (en) * | 2021-06-30 | 2021-09-14 | 北京国际建设集团有限公司 | A conveyor for elevator reservation hole |
| CN113387138B (en) * | 2021-06-30 | 2022-05-20 | 北京国际建设集团有限公司 | A conveyor for elevator reservation hole |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
| CN204899180U (en) | Steel construction jar body aerial working platform simply sets up device | |
| CN106006425A (en) | Method of hoisting and transporting large-sized equipment arranged in underground machine rooms of super high-rise buildings | |
| CN108979131B (en) | Integral lifting platform device for high-rise building construction steel formwork and operation frame | |
| CN102777030A (en) | Method for building up formwork construction platform of lift shaft | |
| CN202831601U (en) | Lifting type structural construction operation platform for elevator shaft | |
| CN106320681A (en) | Elevator shaft standard operation platform and implementation platform | |
| CN103375022B (en) | Multi-functional dynamic rail attached lifting scaffold | |
| CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
| CN210084736U (en) | A portable lifting hook for installation of people's air defense door | |
| CN100504031C (en) | Steel cage hoisting structure in tank wall construction | |
| CN110577162A (en) | A method and device for flipping a climbing beam of an internal climbing tower crane | |
| JP2010242308A (en) | Method for demolishing high-rise building of concrete slab structure, and concrete slab demolition equipment | |
| CN203475801U (en) | Telescopic steel platform for elevator shaft | |
| CN204876526U (en) | Instrument formula girder steel of encorbelmenting | |
| CN204850048U (en) | Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel | |
| CN205296802U (en) | Well steel platform | |
| CN218264865U (en) | A triangular hanging basket support structure | |
| CN204001751U (en) | Super high steel structure construction overhanging unloading platform | |
| CN105731271A (en) | Combined tower crane for roof construction and construction method thereof | |
| CN211899584U (en) | A super high-rise hanging operation platform | |
| CN203320922U (en) | Supporting device for forming of elevator shaft template | |
| CN204873403U (en) | A supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin | |
| CN204728675U (en) | A kind of high rise elevator well is with layer activity operations frame | |
| CN203222981U (en) | Suspended platform for steel reinforced concrete cantilever structure construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170111 |