CN106760497B - The concrete floor system high form-tie assembly supported using column - Google Patents

The concrete floor system high form-tie assembly supported using column Download PDF

Info

Publication number
CN106760497B
CN106760497B CN201710158233.8A CN201710158233A CN106760497B CN 106760497 B CN106760497 B CN 106760497B CN 201710158233 A CN201710158233 A CN 201710158233A CN 106760497 B CN106760497 B CN 106760497B
Authority
CN
China
Prior art keywords
support
concrete
frame
column
concrete column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710158233.8A
Other languages
Chinese (zh)
Other versions
CN106760497A (en
Inventor
彭宝安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jingmen Chuangjia Machinery Technology Co Ltd
Original Assignee
Jingmen Chuangjia Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jingmen Chuangjia Machinery Technology Co Ltd filed Critical Jingmen Chuangjia Machinery Technology Co Ltd
Priority to CN201710158233.8A priority Critical patent/CN106760497B/en
Publication of CN106760497A publication Critical patent/CN106760497A/en
Application granted granted Critical
Publication of CN106760497B publication Critical patent/CN106760497B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs

Abstract

The concrete floor system high form-tie assembly that the present invention is supported using column is mainly used for the use of building engineering field cast-in-place concrete building roof shuttering supporting, and, using concrete column as support, dismounting is efficient and convenient for it, is not required to consume a large amount of tube materials;The present invention is mainly made of bottom frame, diagonal brace, support frame, strut, coupling beam, by-level support;Support frame mainly by outline border, inside casing, support beam group at;By-level support is mainly made of set frame, horizontal support bar;Its main operational principle is: the concrete column of first construction floor, after whole concrete columns reaches some strength, all parts of the invention are installed on every concrete column, it is finally laid with superstructure template in the coupling beam of longitudinal and transverse direction and pours superstructure concrete, the transfer route of superstructure concrete load is successively are as follows: the multiple strut-support frame-bottom frames of the coupling beam-of longitudinal and transverse direction, by-level support carry out drawknot to diagonal brace.

Description

The concrete floor system high form-tie assembly supported using column
Technical field
Present invention is mainly used for the uses of building engineering field cast-in-place concrete building roof shuttering supporting.
Background technique
It is even using longitudinal steel pipe support and transverse direction in the support system of building engineering field concrete floor system high-supported formwork at present Steel pipe is reinforced, if building superstructure is very high, longitudinal bracing steel pipe is that height is again very intensive, correspondingly increases transversely strengthening again Work consuming is time-consuming again for steel pipe, i.e. waste material, extremely uneconomical.
Summary of the invention
The present invention solves the above problem, and, using concrete column as support, dismounting is efficient and convenient for it, is not required to consume a large amount of Tube material;The present invention is mainly supported by bottom frame (1), diagonal brace (2), support frame (3), strut (4), coupling beam (5), by-level (7) it forms;Support frame (3) is mainly made of outline border (8), inside casing (9), supporting beam (10), hinge joint (11);By-level support (7) it is mainly made of set frame (12), horizontal support bar (13);Bottom frame (1) covers the lower end in concrete column (6) and is fixed temporarily, Four sides of bottom frame (1) and the lower end of diagonal brace (2) are fixed, and the set frame (12) of by-level support (7) covers on concrete column (6) simultaneously It is fixed temporarily, one end of horizontal support bar (13) and set frame (12) are fixed, and the other end of horizontal support bar (13) and diagonal brace (2) are solid Fixed, the outline border (8) of support frame (3) and the upper end of diagonal brace (2) are fixed, the both ends of supporting beam (10) respectively with outline border (8) and inside casing (9) fixed, inside casing (9) covers the top in concrete column (6) and is fixed temporarily, and supporting beam (10) has multiple hinge joints (11), more A hinge joint (11) connect with the lower end of multiple struts (4) respectively, and the upper end of multiple struts (4) is connect with coupling beam (5);The present invention Main operational principle be: the concrete column of first construction floor, it is mixed at every after whole concrete columns reaches some strength All parts of the invention are installed on solidifying earth pillar, superstructure template is finally laid on the coupling beam of longitudinal and transverse direction (5) and pour building Lid concrete, the transfer route of superstructure concrete load is successively are as follows: the coupling beam (5) of longitudinal and transverse direction-multiple struts (4)-support Frame (3)-bottom frame (1), by-level support (7) to carry out drawknot to diagonal brace (2);Need to illustrate, when concrete column (6) intensity and just When spending sufficiently large, bottom frame (1) is mounted on to the top of concrete column (6), cancels by-level support (7).
Detailed description of the invention
Description of symbols: 1- bottom frame, 2- diagonal brace, 3- support frame, 4- strut, 5- coupling beam, 6- concrete column, the centre 7- water Flat support, 8- outline border, 9- inside casing, 10- supporting beam, 11- hinge joint, 12- cover frame, 13- horizontal support bar.
Fig. 1 is elevational schematic view of the invention.
Fig. 2 is A-A sectional view of the invention.
Fig. 3 is B-B sectional view of the invention.
Fig. 4 is C-C sectional view of the invention.
Fig. 5 is the scheme schematic diagram that bottom frame 1 is mounted on to the top of concrete column.
Specific embodiment
Referring to Fig. 1 to Fig. 5, illustrate main operational principle of the invention: the concrete column of first construction floor is mixed to whole After solidifying earth pillar reaches some strength, all parts of the invention are installed on every concrete column, finally in longitudinal and transverse direction It is laid with superstructure template in coupling beam 5 and pours superstructure concrete, the transfer route of superstructure concrete load is successively are as follows: longitudinal and transverse direction The more a strut 4- support frame 3- bottom frames 1 of coupling beam 5-, by-level supports 7 pairs of diagonal braces 2 to carry out drawknots;Referring to Fig. 5, work as concrete When the intensity and rigidity of column are sufficiently large, bottom frame 1 is mounted on to the top of concrete column, cancels by-level support 7, this design Scheme can be further reduced component, but concrete column must have enough bending strengths, resist the eccentric bending moment that top is transmitted, Otherwise concrete column will destroy.

Claims (1)

1. using the concrete floor system high form-tie assembly of column support, it is characterized in that: it is mainly by bottom frame (1), diagonal brace (2), support Frame (3), strut (4), coupling beam (5), by-level support (7) composition;Support frame (3) is mainly by outline border (8), inside casing (9), support Beam (10), hinge joint (11) composition;By-level support (7) is mainly made of set frame (12), horizontal support bar (13);Bottom frame (1) it covers the lower end in concrete column (6) and is fixed temporarily, four sides of bottom frame (1) and the lower end of diagonal brace (2) are fixed, by-level The set frame (12) of support (7) is covered on concrete column (6) and is fixed temporarily, and one end of horizontal support bar (13) and set frame (12) are solid Fixed, the other end of horizontal support bar (13) and diagonal brace (2) are fixed, and the outline border (8) of support frame (3) and the upper end of diagonal brace (2) are fixed, The both ends of supporting beam (10) are fixed with outline border (8) and inside casing (9) respectively, and inside casing (9) covers on the top of concrete column (6) and interim Fixed, supporting beam (10) has multiple hinge joints (11), and multiple hinge joints (11) connect with the lower end of multiple struts (4) respectively, more The upper end of a strut (4) is connect with coupling beam (5);The concrete column of first construction floor reaches certain strong to whole concrete columns After degree, all parts of the invention are installed on every concrete column, are finally laid with superstructure on the coupling beam of longitudinal and transverse direction (5) Template and superstructure concrete is poured, the transfer route of superstructure concrete load is successively are as follows: the coupling beam (5)-of longitudinal and transverse direction is multiple Strut (4)-support frame (3)-bottom frame (1), by-level support (7) to carry out drawknot to diagonal brace (2);It is strong when concrete column (6) When degree is sufficiently large with rigidity, bottom frame (1) is mounted on to the top of concrete column (6), cancels by-level support (7).
CN201710158233.8A 2017-03-16 2017-03-16 The concrete floor system high form-tie assembly supported using column Active CN106760497B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710158233.8A CN106760497B (en) 2017-03-16 2017-03-16 The concrete floor system high form-tie assembly supported using column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710158233.8A CN106760497B (en) 2017-03-16 2017-03-16 The concrete floor system high form-tie assembly supported using column

Publications (2)

Publication Number Publication Date
CN106760497A CN106760497A (en) 2017-05-31
CN106760497B true CN106760497B (en) 2019-01-18

Family

ID=58967925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710158233.8A Active CN106760497B (en) 2017-03-16 2017-03-16 The concrete floor system high form-tie assembly supported using column

Country Status (1)

Country Link
CN (1) CN106760497B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2305453Y (en) * 1996-11-08 1999-01-27 南昌昌梅建筑设备有限公司 In site casting concrete platform device
CN2382784Y (en) * 1999-07-20 2000-06-14 耿道荣 Quick support frame for building
KR20020032487A (en) * 2002-04-08 2002-05-03 안종식 A mold supporting device of slab
CN1352721A (en) * 1999-01-21 2002-06-05 国际筑造公司 Method for forming concrete floors
JP2010053649A (en) * 2008-08-29 2010-03-11 Ohbayashi Corp Construction method for column and beam framework
CN204326570U (en) * 2014-09-30 2015-05-13 中建钢构有限公司 Truss temporary support structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2305453Y (en) * 1996-11-08 1999-01-27 南昌昌梅建筑设备有限公司 In site casting concrete platform device
CN1352721A (en) * 1999-01-21 2002-06-05 国际筑造公司 Method for forming concrete floors
CN2382784Y (en) * 1999-07-20 2000-06-14 耿道荣 Quick support frame for building
KR20020032487A (en) * 2002-04-08 2002-05-03 안종식 A mold supporting device of slab
JP2010053649A (en) * 2008-08-29 2010-03-11 Ohbayashi Corp Construction method for column and beam framework
CN204326570U (en) * 2014-09-30 2015-05-13 中建钢构有限公司 Truss temporary support structure

Also Published As

Publication number Publication date
CN106760497A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN101660296B (en) Method for casting concrete 0# block support by continuous beam cantilever
CN104806011B (en) Raft board post poured band formwork for placing
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN201762663U (en) Reinforced concrete superposed beam wing board support
CN108716283A (en) The construction method of big section cast-in-situ steel reinforced concrete construction of inclined column structure
CN204039927U (en) A kind of bridge emergency first-aid repair connects bracing or strutting arrangement
CN107654021A (en) A kind of assembling prefabricated reinforced concrete column and assembled combination frame building system
CN204676881U (en) Large span intersection truss steel structure supporting system
CN207160221U (en) A kind of light section steel structure assembled-type house frame structure
CN103952979B (en) A kind of steel concrete superposed beam top board erection without scaffolding device and construction method
CN103233426A (en) Bailey beam support free of buttress in soft foundation and supporting method thereof
KR101546827B1 (en) Steel plate girder improved coner fixing capacity and rahmen or box type structure construction method using the same
CN106760497B (en) The concrete floor system high form-tie assembly supported using column
CN211499816U (en) Device for pouring construction of cantilever support of steel-concrete composite beam
CN210658035U (en) Draw to one side and hang knot supporting structure
CN202369931U (en) Arch ring bracket
CN209584813U (en) Frame bridge system
CN208167534U (en) Detachable support for Cast-in-situ Beam steel pipe support
CN207453526U (en) A kind of ruggedized construction of building structure floorboard
CN207314664U (en) A kind of assembling prefabricated reinforced concrete column and assembled combination frame building system
CN206753043U (en) A kind of Structure Beam-column node Hou Jiao areas mould plate supporting device
CN215947924U (en) Support bearing structure for pier stud bent cap
CN214835042U (en) Basement top plate operation reinforcing structure for heavy crawler crane
CN213268892U (en) Post-cast strip connection structure is supported to casing string
CN201924600U (en) Cast-in-place crossbeam construction formwork supporting system with beam type switching layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant