CN106741607A - 一种船舶分段安装集装箱埋入式底座的方法 - Google Patents
一种船舶分段安装集装箱埋入式底座的方法 Download PDFInfo
- Publication number
- CN106741607A CN106741607A CN201611159754.7A CN201611159754A CN106741607A CN 106741607 A CN106741607 A CN 106741607A CN 201611159754 A CN201611159754 A CN 201611159754A CN 106741607 A CN106741607 A CN 106741607A
- Authority
- CN
- China
- Prior art keywords
- base frame
- buried base
- container buried
- container
- installs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B71/00—Designing vessels; Predicting their performance
Abstract
本发明涉及一种船舶分段安装集装箱埋入式底座的方法,该方法包括以下步骤:设计集装箱埋入式底座布置图;制作分段胎架并装焊分段;调整分段整体水平度;设测量标杆并划基准平面;划长、宽位置线;划开孔位置;切割开孔并安装集装箱埋入式底座;焊接固定集装箱埋入式底座。本发明船舶分段安装集装箱埋入式底座的方法具有适用范围广、安装精度高、提高效率和节约成本的优点。
Description
技术领域
本发明涉及船舶建造领域,尤其是涉及一种船舶分段安装集装箱埋入式底座的方法。
背景技术
随着现代造船模式的不断进步和PSPC要求,对船舶分段的建造完整性要求也越来越高,为了尽可能减少在总组施工过程中对船体油漆破坏,集装箱埋入式底座就势必要求在分段阶段安装。由于集装箱本体精度比较高,分段阶段安装集装箱埋入式底座的精度要求更高,水平要求在±3mm内,主尺寸要求在2mm内。由于箱脚形式为埋入式,错误后返工将及其困难,损失较大。
发明内容
为了解决上述现有技术中存在的不足,本发明提供一种船舶分段安装集装箱埋入式底座的方法,不仅能广泛地应用于集装箱船和集装箱滚装船等船型在分段阶段安装集装箱埋入式底座的情况,确保安装精度要求,减少在总组施工过程中的油漆破坏,满足现代造船PSPC要求,同时能够提高船舶建造质量和生产效率,并在一定程度上节约造船成本。
为了实现上述发明目的,本发明提供以下技术方案:
一种船舶分段安装集装箱埋入式底座的方法,该方法包括以下步骤:
一、设计集装箱埋入式底座布置图,以每个分段的基准肋位线和基准纵剖线为基准标注集装箱埋入式底座的尺寸,标注在集装箱埋入式底座布置图中的纵横十字线处;
二、制作分段胎架,然后在分段胎架上进行分段的装配及焊接作业,分段在装配及焊接时为反态;
三、分段装配焊接完毕后,将分段翻转为正态,调整分段整体水平度;
四、在每个集装箱埋入式底座的一端竖一根测量标杆,用激光水平仪在测量标杆上划出基准平面,并作样冲标记;
五、以分段的基准肋位线和基准纵剖线为基准,依据每个集装箱埋入式底座对应的基准肋位线和基准纵剖线的数据,划出集装箱埋入式底座十字中心的长、宽位置线;
六、依据开孔样板划出集装箱埋入式底座的开孔位置,将中心线延长至开孔外侧,并作样冲标记;
七、根据步骤六中划出的开孔位置进行切割开孔作业,并依据开孔安装集装箱埋入式底座;
八、将安装完毕的集装箱埋入式底座进行焊接固定。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤二中,在进行制作分段胎架操作时加放垫块,所述垫块为一块铁板。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤三中,所述调整分段整体水平度包括矫正局部较大变形及调整分段内底板和平台板的水平度,所述水平度误差不超过5mm。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,所述测量标杆包括扁钢和角钢,所述测量标杆的高度为400mm。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤六中,开孔位置与集装箱埋入式底座的型号及船体的艏艉方向相对应。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤六中,开孔位置划线完毕后,检验确认开孔位置线及每个集装箱所对应四个集装箱埋入式底座的长、宽、对角线尺寸的准确无误。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤七中,所述切割开孔作业使用半自动火焰切割机进行切割开孔。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤七中,集装箱埋入式底座安装完毕后,检验每个集装箱所对应四个集装箱埋入式底座的长、宽、对角线尺寸,并依据测量标杆的基准平面调整每个集装箱埋入式底座的高度,报验尺寸精度。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤八中,集装箱埋入式底座进行焊接固定时,所述集装箱埋入式底座分成两部分进行对称焊接,且焊接接头位于集装箱埋入式底座的非圆角处。
在上述的本发明一种船舶分段安装集装箱埋入式底座的方法中,在步骤八中,集装箱埋入式底座焊接完毕后,报验尺寸精度。
基于上述技术方案,相比于现有技术本发明具有以下优点:
1、通过通过采用本发明方法进行集装箱埋入式底座的安装,能广泛地应用于集装箱船和集装箱滚装船等船型在分段阶段安装集装箱埋入式底座的情况,确保安装精度要求,减少在总组施工过程中的油漆破坏,满足现代造船PSPC要求,同时能够提高船舶建造质量和生产效率,并在一定程度上节约造船成本。
2、本发明在进行制作分段胎架时加放垫块,有效地防止分段装配及焊接时引起内底板和平台板的变形,确保分段内底板和平台板的水平度符合精度要求。
3、本发明在进行切割开孔作业时使用半自动火焰切割机进行切割开孔,保证开孔的切割质量。
附图说明
图1是本发明中集装箱埋入式底座的第一种结构形式的俯视图。
图2是本发明中集装箱埋入式底座的第一种结构形式的剖视图。
图3是本发明中集装箱埋入式底座的第二种结构形式的俯视图。
图4是本发明中集装箱埋入式底座的第二种结构形式的剖视图。
图5是本发明中集装箱埋入式底座的布置图。
具体实施方式
下面结合附图和具体的实施例来对本发明一种船舶分段安装集装箱埋入式底座的方法做进一步地详细阐述,以求更为清楚明了地理解其工作过程和使用方式,但不能以此来限定本发明专利的保护范围。
集装箱埋入式底座包括两种结构形式,所述集装箱埋入式底座的焊接坡口的角度为40度,如图1和图2所示,第一种结构形式包括单个支撑脚;如图3和图4所示,第二种结构形式包括两个并排的支撑脚。
一种船舶分段安装集装箱埋入式底座的方法,该方法包括以下步骤:
一、如图5所示,设计集装箱埋入式底座布置图,以每个分段的基准肋位线和基准纵剖线为基准标注集装箱埋入式底座的尺寸,标注在集装箱埋入式底座布置图中的纵横十字线处;
二、制作分段胎架,并在制作分段胎架时加放垫块,所述垫块为一块铁板,然后在分段胎架上进行分段的装配及焊接作业,分段在装配及焊接时为反态;
三、分段装配焊接完毕后,将分段翻转为正态,调整分段整体水平度,所述调整分段整体水平度包括矫正局部较大变形及调整分段内底板和平台板的水平度,所述水平度误差不超过5mm;
四、在每个集装箱埋入式底座的一端竖一根测量标杆,所述测量标杆包括扁钢和角钢,所述测量标杆的高度为400mm,用激光水平仪在测量标杆上划出基准平面,并作样冲标记;
五、以分段的基准肋位线和基准纵剖线为基准,依据每个集装箱埋入式底座对应的基准肋位线和基准纵剖线的数据,划出集装箱埋入式底座十字中心的长、宽位置线;
六、依据开孔样板划出集装箱埋入式底座的开孔位置,开孔位置划线完毕后,检验确认开孔位置线及每个集装箱所对应四个集装箱埋入式底座的长、宽、对角线尺寸的准确无误,开孔位置与集装箱埋入式底座的型号及船体的艏艉方向相对应,将中心线延长至开孔外侧,并作样冲标记;
七、根据步骤六中划出的开孔位置进行切割开孔作业,所述切割开孔作业使用半自动火焰切割机进行切割开孔,并依据开孔安装集装箱埋入式底座,集装箱埋入式底座安装完毕后,检验每个集装箱所对应四个集装箱埋入式底座的长、宽、对角线尺寸,并依据测量标杆的基准平面调整每个集装箱埋入式底座的高度,报验尺寸精度;
八、将安装完毕的集装箱埋入式底座进行焊接固定,集装箱埋入式底座进行焊接固定时,所述集装箱埋入式底座分成两部分进行对称焊接,且焊接接头位于集装箱埋入式底座的非圆角处,集装箱埋入式底座焊接完毕后,报验尺寸精度。
毫无疑问,本发明一种船舶分段安装集装箱埋入式底座的方法除了上述实例中讲述的类型和方式以外,还包括其他类似的结构组成方式和固定连接方式。总而言之,本发明还包括其他对于本领域技术人员显而易见的变换和替代。
Claims (10)
1.一种船舶分段安装集装箱埋入式底座的方法,其特征在于,该方法包括以下步骤:
一、设计集装箱埋入式底座布置图,以每个分段的基准肋位线和基准纵剖线为基准标注集装箱埋入式底座的尺寸,标注在集装箱埋入式底座布置图中的纵横十字线处;
二、制作分段胎架,然后在分段胎架上进行分段的装配及焊接作业,分段在装配及焊接时为反态;
三、分段装配焊接完毕后,将分段翻转为正态,调整分段整体水平度;
四、在每个集装箱埋入式底座的一端竖一根测量标杆,用激光水平仪在测量标杆上划出基准平面,并作样冲标记;
五、以分段的基准肋位线和基准纵剖线为基准,依据每个集装箱埋入式底座对应的基准肋位线和基准纵剖线的数据,划出集装箱埋入式底座十字中心的长、宽位置线;
六、依据开孔样板划出集装箱埋入式底座的开孔位置,将中心线延长至开孔外侧,并作样冲标记;
七、根据步骤六中划出的开孔位置进行切割开孔作业,并依据开孔安装集装箱埋入式底座;
八、将安装完毕的集装箱埋入式底座进行焊接固定。
2.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤二中,在进行制作分段胎架操作时加放垫块,所述垫块为一块铁板。
3.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤三中,所述调整分段整体水平度包括矫正局部较大变形及调整分段内底板和平台板的水平度,所述水平度误差不超过5mm。
4.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,所述测量标杆包括扁钢和角钢,所述测量标杆的高度为400mm。
5.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤六中,开孔位置与集装箱埋入式底座的型号及船体的艏艉方向相对应。
6.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤六中,开孔位置划线完毕后,检验确认开孔位置线及每个集装箱所对应四个集装箱埋入式底座的长、宽、对角线尺寸的准确无误。
7.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤七中,所述切割开孔作业使用半自动火焰切割机进行切割开孔。
8.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤七中,集装箱埋入式底座安装完毕后,检验每个集装箱所对应四个集装箱埋入式底座的长、宽、对角线尺寸,并依据测量标杆的基准平面调整每个集装箱埋入式底座的高度,报验尺寸精度。
9.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤八中,集装箱埋入式底座进行焊接固定时,所述集装箱埋入式底座分成两部分进行对称焊接,且焊接接头位于集装箱埋入式底座的非圆角处。
10.根据权利要求1所述的一种船舶分段安装集装箱埋入式底座的方法,其特征在于,在步骤八中,集装箱埋入式底座焊接完毕后,报验尺寸精度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611159754.7A CN106741607B (zh) | 2016-12-15 | 2016-12-15 | 一种船舶分段安装集装箱埋入式底座的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611159754.7A CN106741607B (zh) | 2016-12-15 | 2016-12-15 | 一种船舶分段安装集装箱埋入式底座的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106741607A true CN106741607A (zh) | 2017-05-31 |
CN106741607B CN106741607B (zh) | 2019-02-05 |
Family
ID=58889270
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611159754.7A Active CN106741607B (zh) | 2016-12-15 | 2016-12-15 | 一种船舶分段安装集装箱埋入式底座的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106741607B (zh) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108327846A (zh) * | 2017-10-30 | 2018-07-27 | 上海振华重工启东海洋工程股份有限公司 | 一种整体上建气动减振系统安装技术 |
CN109883283A (zh) * | 2019-03-29 | 2019-06-14 | 无锡海核装备科技有限公司 | 罐式集装箱用对角线尺寸测量装置 |
CN110937079A (zh) * | 2019-10-24 | 2020-03-31 | 上海江南长兴造船有限责任公司 | 一种大型集装箱船双层底箱位精度控制方法 |
CN113148020A (zh) * | 2021-05-28 | 2021-07-23 | 广船国际有限公司 | 一种集装箱船埋入式绑扎件的安装布置方法及船舶 |
CN113247205A (zh) * | 2021-06-30 | 2021-08-13 | 广船国际有限公司 | 一种船舶甲板埋入式集装箱固定座的安装方法 |
CN113697079A (zh) * | 2021-09-02 | 2021-11-26 | 陈丁 | 一种混合动力船 |
CN114148474A (zh) * | 2021-11-03 | 2022-03-08 | 中船澄西船舶修造有限公司 | 一种集装箱垫脚安装工艺及垫脚 |
CN114589547A (zh) * | 2022-04-06 | 2022-06-07 | 广船国际有限公司 | 一种集装箱箱脚开孔的画线方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102795316A (zh) * | 2012-08-03 | 2012-11-28 | 扬帆集团股份有限公司 | 一种集装箱底座安装方法 |
CN104029793A (zh) * | 2014-06-04 | 2014-09-10 | 浙江省海洋开发研究院 | 集装箱箱脚的安装方法 |
CN104058064A (zh) * | 2013-03-21 | 2014-09-24 | 上海江南长兴重工有限责任公司 | 集装箱船箱脚底锥安装方法 |
CN104210619A (zh) * | 2014-09-04 | 2014-12-17 | 广州文冲船厂有限责任公司 | 集装箱船埋入式箱座安装方法 |
-
2016
- 2016-12-15 CN CN201611159754.7A patent/CN106741607B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102795316A (zh) * | 2012-08-03 | 2012-11-28 | 扬帆集团股份有限公司 | 一种集装箱底座安装方法 |
CN104058064A (zh) * | 2013-03-21 | 2014-09-24 | 上海江南长兴重工有限责任公司 | 集装箱船箱脚底锥安装方法 |
CN104029793A (zh) * | 2014-06-04 | 2014-09-10 | 浙江省海洋开发研究院 | 集装箱箱脚的安装方法 |
CN104210619A (zh) * | 2014-09-04 | 2014-12-17 | 广州文冲船厂有限责任公司 | 集装箱船埋入式箱座安装方法 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108327846A (zh) * | 2017-10-30 | 2018-07-27 | 上海振华重工启东海洋工程股份有限公司 | 一种整体上建气动减振系统安装技术 |
CN109883283A (zh) * | 2019-03-29 | 2019-06-14 | 无锡海核装备科技有限公司 | 罐式集装箱用对角线尺寸测量装置 |
CN110937079A (zh) * | 2019-10-24 | 2020-03-31 | 上海江南长兴造船有限责任公司 | 一种大型集装箱船双层底箱位精度控制方法 |
CN113148020A (zh) * | 2021-05-28 | 2021-07-23 | 广船国际有限公司 | 一种集装箱船埋入式绑扎件的安装布置方法及船舶 |
CN113148020B (zh) * | 2021-05-28 | 2023-09-22 | 广船国际有限公司 | 一种集装箱船埋入式绑扎件的安装布置方法及船舶 |
CN113247205A (zh) * | 2021-06-30 | 2021-08-13 | 广船国际有限公司 | 一种船舶甲板埋入式集装箱固定座的安装方法 |
CN113697079A (zh) * | 2021-09-02 | 2021-11-26 | 陈丁 | 一种混合动力船 |
CN114148474A (zh) * | 2021-11-03 | 2022-03-08 | 中船澄西船舶修造有限公司 | 一种集装箱垫脚安装工艺及垫脚 |
CN114589547A (zh) * | 2022-04-06 | 2022-06-07 | 广船国际有限公司 | 一种集装箱箱脚开孔的画线方法 |
CN114589547B (zh) * | 2022-04-06 | 2022-11-22 | 广船国际有限公司 | 一种集装箱箱脚开孔的画线方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106741607B (zh) | 2019-02-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106741607A (zh) | 一种船舶分段安装集装箱埋入式底座的方法 | |
CN101811553B (zh) | 绞吸式挖泥船桥架制作、船上安装工艺 | |
CN101885368B (zh) | 集装箱船货舱内导轨的制造安装方法 | |
CN105383642B (zh) | 一种垂直导轨安装焊接方法 | |
CN101323351B (zh) | 一种船舶舵系照光及安装的方法 | |
CN109895945A (zh) | 一种矿砂船舷侧总段的纵横舱壁预组装方法 | |
CN106080964A (zh) | 一种用于超大型集装箱船横隔舱总段双面导轨的安装方法 | |
CN103523168B (zh) | Css平台连接桥区域分段制造工艺及专用斜切胎架 | |
CN108457262B (zh) | 一种自升式钻井平台钻台建造工艺 | |
CN110696993B (zh) | 一种船舶分段外板及骨材定位方法 | |
CN108189964B (zh) | 在船舶建造中轴系对中时确定船舶艉部基线的方法 | |
CN105155497A (zh) | 一种自升式起重平台升降装置及其制造工艺 | |
CN101745748B (zh) | 钻井平台的桩腿与桩靴的焊接方法 | |
CN108995764B (zh) | 一种lng运输船舵套筒安装方法 | |
CN104210619A (zh) | 集装箱船埋入式箱座安装方法 | |
CN103481022B (zh) | 一种墩柱模板制造方法 | |
CN110789684A (zh) | 一种大型甲板机械本体基座的装配方法 | |
CN107877093B (zh) | 一种曲面板加工工装及加工方法 | |
CN110282078B (zh) | 一种自卸船货舱底部w型分段的精度控制方法 | |
CN113998072B (zh) | 一种标准锚台的制造与安装方法 | |
CN106112219A (zh) | 一种建筑装配式薄壁非标箱式钢构件加工方法 | |
CN107795283B (zh) | 钻井架安装方法 | |
CN101811555A (zh) | 浮船坞内散货船船体分段合拢控制方法 | |
CN111252208B (zh) | 一种艉部分段节能装置的安装方法 | |
CN202292747U (zh) | 高度可调节的划线装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |