CN106639207A - Complex shared space assembling building decoration construction method based on BIM (building information modeling) - Google Patents
Complex shared space assembling building decoration construction method based on BIM (building information modeling) Download PDFInfo
- Publication number
- CN106639207A CN106639207A CN201610935522.XA CN201610935522A CN106639207A CN 106639207 A CN106639207 A CN 106639207A CN 201610935522 A CN201610935522 A CN 201610935522A CN 106639207 A CN106639207 A CN 106639207A
- Authority
- CN
- China
- Prior art keywords
- model
- decoration
- method based
- construction method
- bim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Instructional Devices (AREA)
Abstract
The invention provides a complex shared space assembling building decoration construction method based on BIM (building information modeling). The method comprises the following steps that (1), three-dimensional scanning is conducted on a construction site, and three-dimensional data of the construction site are collected; (2), a three-dimensional model is obtained according to the three-dimensional data; (3), a decoration model is built according to drawings; (4), the decoration model is matched to the three-dimensional model to conduct simulation installation, a collision test is conducted, discrepant areas and size deviation between the decoration model and the three-dimensional model are found out, and a collision result is obtained; (5), the decoration model is adjusted according to the collision result; and (6), coordinate installation point location information is extracted in a finished decoration model, the point location information is guided into a total station, and a line of a later-installed face is paid off. According to the complex shared space assembling building decoration construction method based on the BIM (building information modeling), the technical problems that in the prior art, building decoration construction deviation is troublesome to be adjusted, and construction efficiency and the construction quality are low are solved.
Description
Technical field
The present invention relates to a kind of building decoration construction method, in particular to a kind of complicated communal space based on BIM
Assembling building decoration construction method.
Background technology
BIM(Building Information Modeling), general abbreviation BIM, it is to build work
Journey item purpose items relevant information data carries out the foundation of BUILDINGS MODELS as the basis of model, and by digital information mould is emulated
Intend the real information that building has.BIM has information completeness, information relevance, consistency on messaging, visualization, coordination
Property, simulation, optimization property and can go out the big feature of figure eight.
As modern architecture is put forward higher requirement to building decoration at aspects such as efficiency, precision, present building dress
Decorations are progressively developed towards digitized direction based on BIM.But, current digital building decoration is only limitted to carry out
The design and foundation of model, and in actual building decoration work progress, the problem of construction error can be run into often, encounter problems
Afterwards, adjustment can only be again re-started after the later stage completes construction, is not only bothered in operation, also comparing affects overall efficiency of construction
And construction quality.
The content of the invention
In consideration of it, the invention provides a kind of complicated communal space assembling building decoration construction method based on BIM, purport
The low technical problem of building decoration construction error adjustment trouble, efficiency of construction and construction quality in prior art is solved.
For this purpose, the invention provides a kind of complicated communal space assembling building decoration construction method based on BIM, its bag
Include following steps:
(1)3-D scanning is carried out to job site, the three-dimensional data of job site is gathered;
(2)Threedimensional model is obtained according to three-dimensional data;
(3)Decoration model is set up according to drawing;
(4)Decoration Model Matching is simulated into installation in threedimensional model, and carries out impact test, find out decoration model
The region not being inconsistent and threedimensional model between and dimensional discrepancy, obtain colliding result;
(5)It is adjusted to decorating model according to collision result;
(6)Coordinate mount point position information is extracted in the decoration model for completing, point position information total powerstation is imported into, after releasing
Phase installation upper thread.
Further, above-mentioned steps(1)In, three-dimensional point cloud scanning is specifically carried out to job site, gather job site
Three dimensional point cloud.
Further, above-mentioned threedimensional model is point cloud model.
Further, above-mentioned steps(2)In, three-dimensional data specifically imports SENS softwares and obtains threedimensional model.
Further, the above-mentioned complicated communal space assembling building decoration construction method based on BIM also includes secondary touching
Hit step(7), it is used to be adjusted live steelframe.
Further, above-mentioned secondary collision step(7)Including:
(71)3-D scanning is carried out to the steel frame construction of job site, steelframe model is obtained;
(72)Steelframe model is imported in decoration model carries out impact test, finds out between decoration model and steelframe model
The region not being inconsistent and dimensional discrepancy, obtain colliding result;
(73)Steelframe model is adjusted according to collision result.
Further, the above-mentioned complicated communal space assembling building decoration construction method based on BIM is also touched including three times
Hit step(8), to complete it is ready-made carry out 3-D scanning, obtain completing model, will complete model with decoration model collided
Check.
Further, the above-mentioned complicated communal space assembling building decoration construction method based on BIM is also swept including material
Retouch step:To marching into the arena, material carries out 3-D scanning, and with drawing data comparison check is carried out, and rejects inept material.
Further, above-mentioned steps(4)In, decoration model and threedimensional model are changed into two-dimentional lines figure, setting lines are long
Degree, by extraction module first framework and the second framework of decoration model and threedimensional model are extracted, and the first framework is to get rid of
The framework of the lines of line length is shorter than, is then contrasted the first framework of decoration model and threedimensional model.
Further, the above-mentioned complicated communal space assembling building decoration construction method based on BIM is additionally provided with lines and adds
Roughcast block, extraction module is extracted after the second framework, and the second framework is carried out plus bulk processing by lines overstriking module, then will dress
Second framework of decorations model and threedimensional model is contrasted.
A kind of complicated communal space assembling building decoration construction method based on BIM provided by the present invention is compared to existing
There is technology that there is advantages below:
1)Digitlization construction simulation:Three-dimensional visualization principle is combined using the precision data of collection in worksite, in computer
Analogue simulation is carried out to work progress, site problems are eliminated in programming phase, realize that the later stage zero does over again;
2)Digitlization unwrapping wire:Scene is carried out to take a little and put a little, the position coordinate in threedimensional model and job site is realized
Position accurate transformation, reach drawing size with scene it is highly consistent, be that the construction that becomes more meticulous in later stage is laid a solid foundation;
3)Digitlization places an order:By digitlization construction planning, generate high-precision electronic document payment producer and place an order, replace
In-site measurement makes the tradition such as template and places an order mode, and realization places an order digitized process, saves a large amount of on the basis of precision is ensured
Manpower and materials;
4)Digitlization construction:Carry out material and place an order by after construction planning terminates, the process that entirely places an order not unwrapping wire and base
Layer construction is synchronous even in advance, and control of material amount and cost provides the sufficient time based on this, while in can greatling save
The construction period at front yard position.
Therefore, the present invention can efficiently solve building decoration construction error adjustment trouble, efficiency of construction in prior art
The technical problem low with construction quality.
Description of the drawings
By the detailed description for reading hereafter preferred embodiment, various other advantages and benefit is common for this area
Technical staff will be clear from understanding.Accompanying drawing is only used for illustrating the purpose of preferred embodiment, and is not considered as to the present invention
Restriction.And in whole accompanying drawing, it is denoted by the same reference numerals identical part.In the accompanying drawings:
Fig. 1 is a kind of complicated communal space assembling building decoration construction party based on BIM provided in an embodiment of the present invention
The schematic flow sheet of method.
Specific embodiment
The exemplary embodiment of the disclosure is more fully described below with reference to accompanying drawings.Although showing the disclosure in accompanying drawing
Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure and should not be by embodiments set forth here
Limited.On the contrary, there is provided these embodiments are able to be best understood from the disclosure, and can be by the scope of the present disclosure
Complete conveys to those skilled in the art.
Referring to Fig. 1, show that a kind of complicated communal space assembling based on BIM provided in an embodiment of the present invention is built in figure
Build decoration construction method.The complicated communal space assembling building decoration construction method that BIM should be based on is comprised the following steps:
S1:3-D scanning is carried out to job site, the three-dimensional data of job site is gathered;
S2:Threedimensional model is obtained according to three-dimensional data;
S3:Decoration model is set up according to drawing;
S4:Decoration Model Matching is simulated into installation in threedimensional model, and carries out impact test, find out decoration model
The region not being inconsistent and threedimensional model between and dimensional discrepancy, obtain colliding result;
S5:It is adjusted to decorating model according to collision result;
S6:Coordinate mount point position information is extracted in the decoration model for completing, point position information total powerstation is imported into, after releasing
Phase installation upper thread.
Wherein, in step S1, three-dimensional point cloud scanning is specifically carried out to job site, gathers the three-dimensional point cloud number of job site
According to.Threedimensional model is specifically as follows point cloud model.In step S2, three-dimensional data specifically imports SENS softwares and obtains threedimensional model.
Referring to Fig. 1, the above-mentioned complicated communal space assembling building decoration construction method based on BIM also includes secondary collision
Step S7, it is used to be adjusted live steelframe.Secondary collision step S7 includes:
S71:3-D scanning is carried out to the steel frame construction of job site, steelframe model is obtained;
S72:Steelframe model is imported in decoration model carries out impact test, finds out between decoration model and steelframe model
The region not being inconsistent and dimensional discrepancy, obtain colliding result;
S73:Steelframe model is adjusted according to collision result.
Referring to Fig. 1, the above-mentioned complicated communal space assembling building decoration construction method based on BIM is also including three collisions
Step S8, to complete it is ready-made carry out 3-D scanning, obtain completing model, will complete model with decoration model carrying out collision inspection
Core.
Referring to Fig. 1, the above-mentioned complicated communal space assembling building decoration construction method based on BIM also includes scanning of materials
Step S0:To marching into the arena, material carries out 3-D scanning, and with drawing data comparison check is carried out, and rejects inept material.
Referring to Fig. 1, in step S4, decoration model and threedimensional model are changed into two-dimentional lines figure, set line length, passed through
Extraction module extracts first framework and the second framework of decoration model and threedimensional model, and the first framework is shorter than lines to get rid of
The framework of the lines of length, is then contrasted the first framework of decoration model and threedimensional model.Due to some portions in model
Dividing not necessarily needs what is adjusted, inside of such as curtain wall etc., if each position scanner uni adjustment will waste a large amount of
Time, and it is very big that the memory space in computer is taken, and extremely wastes efficiency, and utilizes this technological means, just may be used
So that adjustment will not all be implemented the every nook and cranny of model, so that efficiency is increased substantially, the storage of computer is saved
Space.
Referring to Fig. 1, in step S4, lines overstriking module is additionally provided with, extraction module is extracted after the second framework, the second framework
Carried out by lines overstriking module plus bulk processing, then contrasted the second framework of decoration model and threedimensional model.This skill
Art means be in order to prevent some positions to be missed without adjustment, therefore in order to recognize and can will contrast after its overstriking,
Thus the precision of adjustment can also be improved on the basis of the raising of above-mentioned efficiency, it is ensured that construction quality.
Obviously, those skilled in the art can carry out the essence of various changes and modification without deviating from the present invention to the present invention
God and scope.So, if these modifications of the present invention and modification belong to the scope of the claims in the present invention and its equivalent technologies
Within, then the present invention is also intended to comprising these changes and modification.
Claims (10)
1. a kind of complicated communal space assembling building decoration construction method based on BIM, it is characterised in that including following step
Suddenly:
(1) 3-D scanning is carried out to job site, the three-dimensional data of the job site is gathered;
(2) threedimensional model is obtained according to the three-dimensional data;
(3) decoration model is set up according to drawing;
(4) the decoration Model Matching is simulated into installation in the threedimensional model, and carries out impact test, found out described
The region not being inconsistent between decoration model and the threedimensional model and dimensional discrepancy, obtain colliding result;
(5) the decoration model is adjusted according to the collision result;
(6) coordinate mount point position information is extracted in the decoration model for completing, point position information is imported into total powerstation, put
Go out later stage installation upper thread.
2. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 1, it is special
Levy and be, in the step (1), three-dimensional point cloud scanning is specifically carried out to job site, gather the three-dimensional point of the job site
Cloud data.
3. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 1 and 2,
Characterized in that, the threedimensional model is point cloud model.
4. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 1, it is special
Levy and be, in the step (2), the three-dimensional data specifically imports SENS softwares and obtains threedimensional model.
5. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 1, it is special
Levy and be, also including secondary collision step (7), it is used to be adjusted live steelframe.
6. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 5, it is special
Levy and be, the secondary collision step (7) includes:
(71) 3-D scanning is carried out to the steel frame construction of job site, obtains steelframe model;
(72) the steelframe model is imported in the decoration model carries out impact test, finds out the decoration model and described
The region not being inconsistent between steelframe model and dimensional discrepancy, obtain colliding result;
(73) the steelframe model is adjusted according to the collision result.
7. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 5 or 6,
Characterized in that, also include three impacting steps (8), to complete it is ready-made carry out 3-D scanning, obtain completing model, will be described
Complete model carries out collision and checks with the decoration model.
8. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 1, it is special
Levy and be, also including scanning of materials step:To marching into the arena, material carries out 3-D scanning, and with drawing data comparison check is carried out, and rejects
Inept material.
9. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 1, it is special
Levy and be, in the step (4), the decoration model and the threedimensional model are changed into two-dimentional lines figure, set line length,
First framework and the second framework of the decoration model and the threedimensional model, first framework are extracted by extraction module
To get rid of the framework of the lines for being shorter than line length, then by the decoration model and the first frame of the threedimensional model
Frame is contrasted.
10. a kind of complicated communal space assembling building decoration construction method based on BIM according to claim 9, its
It is characterised by, be additionally provided with lines overstriking module, the extraction module is extracted after second framework, and second framework passes through
The lines overstriking module is carried out plus bulk processing, and it is right then to carry out the second framework of the decoration model and the threedimensional model
Than.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610935522.XA CN106639207A (en) | 2016-11-01 | 2016-11-01 | Complex shared space assembling building decoration construction method based on BIM (building information modeling) |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610935522.XA CN106639207A (en) | 2016-11-01 | 2016-11-01 | Complex shared space assembling building decoration construction method based on BIM (building information modeling) |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106639207A true CN106639207A (en) | 2017-05-10 |
Family
ID=58821176
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610935522.XA Pending CN106639207A (en) | 2016-11-01 | 2016-11-01 | Complex shared space assembling building decoration construction method based on BIM (building information modeling) |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106639207A (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107103151A (en) * | 2017-05-15 | 2017-08-29 | 贵州精正检测有限公司 | A kind of method and apparatus of the fabricated construction based on BIM |
CN107423523A (en) * | 2017-08-14 | 2017-12-01 | 郭宇光 | A kind of complicated communal space assembling building decoration construction method based on BIM |
CN107610169A (en) * | 2017-10-06 | 2018-01-19 | 湖北聚注通用技术研究有限公司 | A kind of decoration construction scene 3-D imaging system |
CN107702662A (en) * | 2017-09-27 | 2018-02-16 | 深圳拎得清软件有限公司 | Reverse monitoring method and its system based on laser scanner and BIM |
CN107806176A (en) * | 2017-12-01 | 2018-03-16 | 贵州精正检测有限公司 | Steel construction assembled architecture and its construction method based on BIM |
CN108005409A (en) * | 2017-12-01 | 2018-05-08 | 贵州精正检测有限公司 | It is layered assembled building and its construction method based on BIM |
CN108171786A (en) * | 2017-12-12 | 2018-06-15 | 上海爱优威软件开发有限公司 | A kind of terminal simulation design method and system |
CN108363860A (en) * | 2018-02-07 | 2018-08-03 | 中交公局第二工程有限公司 | A kind of 3-D abnormal bridge formwork assembly setting out method based on BIM technology |
CN108765545A (en) * | 2018-04-18 | 2018-11-06 | 山东聊建集团有限公司 | A kind of kitchen and bath's sun room decorating Deepen Design method based on BIM technology |
CN109858172A (en) * | 2019-02-18 | 2019-06-07 | 中国铁路设计集团有限公司 | Quickly establish the design method of profile steel frame BIM model |
CN110130659A (en) * | 2019-04-18 | 2019-08-16 | 滁州职业技术学院 | A kind of assembled architecture construction method and system based on 3-D scanning |
CN111062069A (en) * | 2019-11-14 | 2020-04-24 | 上海市建筑装饰工程集团有限公司 | Digital construction auxiliary construction method suitable for complex multi-curved member of architectural decoration engineering |
CN111444570A (en) * | 2020-04-16 | 2020-07-24 | 福建汇川物联网技术科技股份有限公司 | Construction error information acquisition method and device |
CN112663885A (en) * | 2020-12-10 | 2021-04-16 | 深圳中安建工程建设有限公司 | Decoration method of interior decoration prefabricated component |
CN113190904A (en) * | 2021-05-08 | 2021-07-30 | 成都亲生命科技有限公司 | Integrated data acquisition and butt-joint order placing system for factory production based on point cloud measurement |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002342386A (en) * | 2001-05-17 | 2002-11-29 | Sumitomo Forestry Co Ltd | Method for calculating the total number of regular- shaped members |
CN103198195A (en) * | 2013-04-16 | 2013-07-10 | 上海上安机电设计事务所有限公司 | BIM-based (building information modeling-based) building engineering model collision detection method |
CN104318610A (en) * | 2014-10-24 | 2015-01-28 | 苏州金螳螂建筑装饰股份有限公司 | Method for large-space three-dimensional entity paying off |
CN104850709A (en) * | 2015-05-25 | 2015-08-19 | 苏州金螳螂建筑装饰股份有限公司 | Three-dimensional simulation method for construction of architectural decoration project |
CN105888248A (en) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology |
CN106055839A (en) * | 2016-06-30 | 2016-10-26 | 上海宝冶集团有限公司 | Application method of three-dimensional scanning technology in building engineering based on BIM |
-
2016
- 2016-11-01 CN CN201610935522.XA patent/CN106639207A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002342386A (en) * | 2001-05-17 | 2002-11-29 | Sumitomo Forestry Co Ltd | Method for calculating the total number of regular- shaped members |
CN103198195A (en) * | 2013-04-16 | 2013-07-10 | 上海上安机电设计事务所有限公司 | BIM-based (building information modeling-based) building engineering model collision detection method |
CN104318610A (en) * | 2014-10-24 | 2015-01-28 | 苏州金螳螂建筑装饰股份有限公司 | Method for large-space three-dimensional entity paying off |
CN104850709A (en) * | 2015-05-25 | 2015-08-19 | 苏州金螳螂建筑装饰股份有限公司 | Three-dimensional simulation method for construction of architectural decoration project |
CN105888248A (en) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology |
CN106055839A (en) * | 2016-06-30 | 2016-10-26 | 上海宝冶集团有限公司 | Application method of three-dimensional scanning technology in building engineering based on BIM |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107103151A (en) * | 2017-05-15 | 2017-08-29 | 贵州精正检测有限公司 | A kind of method and apparatus of the fabricated construction based on BIM |
CN107423523A (en) * | 2017-08-14 | 2017-12-01 | 郭宇光 | A kind of complicated communal space assembling building decoration construction method based on BIM |
CN107423523B (en) * | 2017-08-14 | 2020-11-17 | 郭宇光 | BIM-based complex shared space assembly building decoration construction method |
CN107702662B (en) * | 2017-09-27 | 2020-01-21 | 深圳拎得清软件有限公司 | Reverse monitoring method and system based on laser scanner and BIM |
CN107702662A (en) * | 2017-09-27 | 2018-02-16 | 深圳拎得清软件有限公司 | Reverse monitoring method and its system based on laser scanner and BIM |
CN107610169A (en) * | 2017-10-06 | 2018-01-19 | 湖北聚注通用技术研究有限公司 | A kind of decoration construction scene 3-D imaging system |
CN107806176A (en) * | 2017-12-01 | 2018-03-16 | 贵州精正检测有限公司 | Steel construction assembled architecture and its construction method based on BIM |
CN108005409A (en) * | 2017-12-01 | 2018-05-08 | 贵州精正检测有限公司 | It is layered assembled building and its construction method based on BIM |
CN108171786A (en) * | 2017-12-12 | 2018-06-15 | 上海爱优威软件开发有限公司 | A kind of terminal simulation design method and system |
CN108363860A (en) * | 2018-02-07 | 2018-08-03 | 中交公局第二工程有限公司 | A kind of 3-D abnormal bridge formwork assembly setting out method based on BIM technology |
CN108765545A (en) * | 2018-04-18 | 2018-11-06 | 山东聊建集团有限公司 | A kind of kitchen and bath's sun room decorating Deepen Design method based on BIM technology |
CN108765545B (en) * | 2018-04-18 | 2022-05-03 | 山东聊建集团有限公司 | Kitchen and bathroom sunny room decoration deepening design method based on BIM technology |
CN109858172A (en) * | 2019-02-18 | 2019-06-07 | 中国铁路设计集团有限公司 | Quickly establish the design method of profile steel frame BIM model |
CN110130659A (en) * | 2019-04-18 | 2019-08-16 | 滁州职业技术学院 | A kind of assembled architecture construction method and system based on 3-D scanning |
CN111062069A (en) * | 2019-11-14 | 2020-04-24 | 上海市建筑装饰工程集团有限公司 | Digital construction auxiliary construction method suitable for complex multi-curved member of architectural decoration engineering |
CN111444570A (en) * | 2020-04-16 | 2020-07-24 | 福建汇川物联网技术科技股份有限公司 | Construction error information acquisition method and device |
CN112663885A (en) * | 2020-12-10 | 2021-04-16 | 深圳中安建工程建设有限公司 | Decoration method of interior decoration prefabricated component |
CN113190904A (en) * | 2021-05-08 | 2021-07-30 | 成都亲生命科技有限公司 | Integrated data acquisition and butt-joint order placing system for factory production based on point cloud measurement |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106639207A (en) | Complex shared space assembling building decoration construction method based on BIM (building information modeling) | |
CN106600690B (en) | Complex building three-dimensional modeling method based on point cloud data | |
CN105547151B (en) | Point Cloud Data from Three Dimension Laser Scanning acquires the method and system with processing | |
CN105888248B (en) | A kind of construction method based on BIM technology tutorial message prefabricated components | |
CN105045950B (en) | A kind of bridge security assessment system based on 3 D laser scanning | |
CN109800536A (en) | One kind parameterizing tunnel model fast modeling method based on Revit and Dynamo | |
CN107093206A (en) | The method modeled using 3D laser scanner technique fast Bs IM | |
CN105549548B (en) | Three-dimensional assembly technique generation method and generating means | |
KR101425576B1 (en) | Method for acquiring and processing a three-dimensional data to product a precise wide-area scale model | |
CN104850709B (en) | Building decoration engineering construction three-dimensional simulation method | |
CN107515991A (en) | A kind of house type full trim simulation shows method and display systems based on BIM technology | |
CN108763685A (en) | A kind of construction method of spacial special-shaped curved surface curtain wall system | |
KR100609786B1 (en) | Method of modelling 3-dimensional building using original drawing map | |
CN110633518B (en) | Simple parameterization unit type curtain wall material classification statistical method based on BIM | |
CN108121873A (en) | A kind of application process of buildings model in curtain wall construction | |
CN109583033A (en) | Application method and system of the BIM adaptive model in special-shaped curtain wall construction | |
CN112182718B (en) | Component design method and device based on BIM and 3D technology and storage medium | |
CN106777779B (en) | Railway culvert design method based on BIM | |
CN104077446A (en) | Method and system for extracting two-dimensional electric construction drawing from digitized three-dimensional model | |
CN105550428A (en) | Bridge security evaluation method based on TLS (three-dimensional laser scanning) technique | |
CN113779670B (en) | Method and system for realizing dual-control modeling of Revit pile foundation based on Dynamo | |
Rashidi et al. | Video to BrIM: Automated 3D as-built documentation of bridges | |
CN109903382A (en) | The fusion method and device of point cloud data | |
CN113626911A (en) | Concrete 3D printing path optimization method based on first principal stress vector distribution | |
CN112598786A (en) | Parameterized wall cutting method and device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170510 |
|
RJ01 | Rejection of invention patent application after publication |