CN106542249A - A kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system - Google Patents

A kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system Download PDF

Info

Publication number
CN106542249A
CN106542249A CN201610924311.6A CN201610924311A CN106542249A CN 106542249 A CN106542249 A CN 106542249A CN 201610924311 A CN201610924311 A CN 201610924311A CN 106542249 A CN106542249 A CN 106542249A
Authority
CN
China
Prior art keywords
piler
warehouse
steel tower
tower part
task
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610924311.6A
Other languages
Chinese (zh)
Other versions
CN106542249B (en
Inventor
王倩
张国英
运晓飞
张宏伟
郅青
臧梦璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Materials Branch of State Grid Jibei Electric Power Co Ltd
Original Assignee
Materials Branch of State Grid Jibei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Materials Branch of State Grid Jibei Electric Power Co Ltd filed Critical Materials Branch of State Grid Jibei Electric Power Co Ltd
Priority to CN201610924311.6A priority Critical patent/CN106542249B/en
Publication of CN106542249A publication Critical patent/CN106542249A/en
Application granted granted Critical
Publication of CN106542249B publication Critical patent/CN106542249B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G1/00Storing articles, individually or in orderly arrangement, in warehouses or magazines
    • B65G1/02Storage devices
    • B65G1/04Storage devices mechanical
    • B65G1/0407Storage devices mechanical using stacker cranes
    • B65G1/0421Storage devices mechanical using stacker cranes with control for stacker crane operations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G1/00Storing articles, individually or in orderly arrangement, in warehouses or magazines
    • B65G1/02Storage devices
    • B65G1/04Storage devices mechanical
    • B65G1/137Storage devices mechanical with arrangements or automatic control means for selecting which articles are to be removed
    • B65G1/1373Storage devices mechanical with arrangements or automatic control means for selecting which articles are to be removed for fulfilling orders in warehouses
    • B65G1/1375Storage devices mechanical with arrangements or automatic control means for selecting which articles are to be removed for fulfilling orders in warehouses the orders being assembled on a commissioning stacker-crane or truck

Abstract

The invention discloses a kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system, including civil engineering system, mechanical hardware system and electric control system;Wherein civil engineering system includes warehouse main body, fire-fighting system, illuminator, dynamical system, ventilation and heating system;The mechanical hardware system includes shelf, container, pallet, piler and periphery haulage equipment;The electric control system includes detection means, information recognition device, control device, monitoring and controlling equipment, host computer information management system, communication equipment, the specification sorting of steel tower part, warehouse-in, storage, outbound, and production efficiency is significantly improved, reduce error rate.

Description

A kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system
Technical field
The present invention relates to the sorting of large-scale material, warehouse-in, storage, ex-warehouse system, especially a kind of sorting of electric power pylon, Warehouse-in, storage, ex-warehouse system, belong to B65G fields.
Background technology
At present, the tower such as the main subangle head tower of power transmission network steel tower, steel tube tower.In recent years, with extensive extra-high voltage project Construction, and with the steady growth factor of country, electric grid investment scale cumulative year after year, power transmission network steel tower factory production capacity are not enough, the supply of material Progress is delayed, engineering constraint progress.
General steel tower factory honours an agreement ends to contract from acceptance of the bid, need to experience materials procurement, the processing of black part, examination assemble, Pickling, it is zinc-plated, turn warehouse for finished product, sorting, packaging, transport to engineering site, group tower install etc. link.
And at present in sorting, storage, transit link, as finished product reservoir area windrow is more, it is chaotic to stack, in some instances it may even be possible to there is steel Print, label mistake etc., meanwhile, tower factory considers cost factor, and the work such as sorting, packaging, warehouse-in, storage, outbound is more by artificial complete Into, therefore there are problems that inefficiency, error rate are low, the method for needing to study raising efficiency accelerates finishing column material shipping efficiency.
The content of the invention
Prior art is difficult to meet the needs such as the sorting of electric power pylon, warehouse-in, storage, outbound, for the problems referred to above, this It is bright to aim to provide a kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system.
To realize the technical purpose, the technical solution used in the present invention is:A kind of sorting of electric power pylon, warehouse-in, storage, Ex-warehouse system, including civil engineering system, mechanical hardware system and electric control system;Wherein civil engineering system includes warehouse Main body, fire-fighting system, illuminator, dynamical system, ventilation and heating system;The mechanical hardware system include shelf, container, Pallet, piler and periphery haulage equipment;The electric control system include detection means, information recognition device, control device, Monitoring and controlling equipment, host computer information management system, communication equipment, wherein described information identifying device adopt RFID electronics marks Sign, label antenna is the label antenna for adding matching minor matters, the symmetrical arrangement of the label antenna, with label chip Dress axially bored line of feeling at ease is symmetric reference, and the label electric wire is on the right side of symmetric reference successively by the extension of following direction:First level to Right extension then extends straight up, then level extends to the right and then extends straight down, and then level extends to the right again vertical Upwardly extend, then level extends to the right and extends straight up again, then level extends to the right and extends straight down again, Ran Houshui Flat extending in the left extends straight up, and final level extends to the right;The label antenna left part is in mirror with right part As being symmetrical arranged;The matching minor matters are arranged on above label chip center mounting hole;
Further, the overall antennas are shaped like two paperclips and are arranged symmetrically;
Further, the T-shaped shape of the matching minor matters, is arranged on above label chip center mounting hole;
Further, the electric control system adopts industrial computer as host computer, using SIEMENS PLC as bottom control Device processed;It is furnished with 6.0 configuration software of simatic WINCC on the host computer, the piler is furnished with Siemens touch screen OP37, institute State PLC bottom controllers to be made up of Siemens S7-300 PLC and S7-200 PLC;The S7-300 PLC are arranged on for main website Master control room, the S7-200PLC are that slave station is arranged on piler;
Further, the S7-300 PLC also hang an ET200M as long-range slave station, the host computer and the S7- 200PLC systems take wireless ethernet mode to be communicated, and the communication between the S7-300 PLC and the host computer is adopted Wired ethernet mode communicates, and is communicated using PROFIBUS DP between the S7-300 PLC and ET200M;The S7-200 Communicated using MPI modes between PLC and the touch screen.
Further, the invention further relates to a kind of piler operational approach of electric power pylon part, wherein when piler is held During row input work, piler is first checked for whether in initial position, i.e. piler whether in the load bed position for picking and placeing steel tower part Place is put, and piler load bed is detected in lower limit position, otherwise carry out piler and return initial position operation, control piler It is returned to initial position;Piler first determines whether whether overhead baggage rack unit to be gone to has steel tower part after initial position, Warehouse-in task could be performed when overhead baggage rack unit does not have steel tower part;If overhead baggage rack unit to be gone to is without steel tower portion Part, then determine whether whether load bed has steel tower part to be put in storage, and when load bed has steel tower part, piler starts, and performs Warehouse-in task.
Further, in each step that the above is performed, if undesirable situation, then report to the police to host computer;
Further, after piler reaches overhead baggage rack unit to be gone to, piler delivery sub-process, lifting electricity are called Steel tower part is sent into overhead baggage rack unit to be gone to by machine, fork operation, and then piler returns to the load bed for picking and placeing steel tower part Position is initial position;Meanwhile, send the signal that task is completed to host computer, and by piler status indication be without task, this When be subjected to new task;
Further, after piler receives the outbound task that host computer sends, it is have work by piler status indication Make task, carry out steel tower part outbound task;When steel tower part Delivery task is carried out, first check for whether load bed has ferrum Tower part;When load bed does not have steel tower part, then judge whether overhead baggage rack unit to be gone to has steel tower part;Only want When the overhead baggage rack unit for going to has steel tower part, piler outbound task can be just carried out;When piler reaches shelf to be gone to Unit, lifting motor, fork operation carry out taking steel tower operation of components, and steel tower part is taken out from overhead baggage rack unit to be gone to; After the completion of, storehouse operation sub-process is produced, control piler returns to initial position;Then order is performed by the ferrum in piler load bed Tower part is discharged in load bed;Above flow process is completed, that is, represent and complete outbound, send the information of completing to host computer, and by piler Status indication is, without task, to be now subjected to new task.
Compared with prior art, the invention has the beneficial effects as follows:The specification warehouse-in of steel tower part, sorting, outbound flow process, And production efficiency is significantly improved, reduce error rate.
Description of the drawings
Fig. 1 is that the sorting of electric power pylon of the present invention, warehouse-in, storage, ex-warehouse system control the general frame.
Fig. 2 is the piler main flow control figure of the present invention;
Fig. 3 is the piler warehouse-in flow chart of the present invention;
Fig. 4 is the piler outbound flow chart of the present invention;
Fig. 5 is the label antenna of the addition matching minor matters of the present invention;
Fig. 6 be the present invention label antenna L be 14mm when S11 with W variation tendency;
Fig. 7 is the label electric wire after the Optimized Matching minor matters of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than the embodiment of whole.It is based on Embodiment in the present invention, it is all other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
It should be noted that each marque referred in the present invention or communications protocol and each technical term, are all institutes The technical terms for clearly being known in category technical field already, therefore no longer do excessive explanation.
Embodiment one:
A kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system, can be automatically performed transmission of electricity ferrum according to operational order The access of tower, and carry out intelligent management to stock's steel tower, fully achieves automated job, mainly include civil engineering system, Mechanical hardware system and three part of electric control system composition.Wherein civil engineering system is by warehouse main body, fire-fighting system, illumination System, dynamical system, ventilation and heating system and other auxiliary facilities are constituted.Warehouse main body is warehouse capacity and overhead baggage rack unit is The Main Basiss of warehouse body design, in the present embodiment, it is contemplated that go out the frequency of warehouse-in, design scale is floor space 400 Square metre, 3 tunnels, the number of plies 4,100 standard goods yards altogether.Sorting, warehouse-in for electric power pylon, storage, ex-warehouse system For, due to warehouse scale greatly, the steel tower part of storage and equipment are more, and the management in warehouse and operator are few, so Automatic fire protection system is all built typically in warehouse.The difference of goods is stored according to warehouse, also needed to build draining in this enforcement, taken shelter from the thunder The facility such as ground connection and environmental conservation, prevents steel tower part from getting rusty.Mechanical hardware system is mainly by shelf, container and pallet, stacking Machine and periphery haulage equipment composition.The material of shelf typically selects steel or armored concrete, and the advantage of steel shelf is component chi Very little little, firm and durable makes simple, and the installation construction period is short, and can improve the storage capacity in warehouse.Reinforced concrete local products The characteristics of frame is that fire protecting performance is preferable, and resistance to corrosion is stronger, and maintenance is simple.Shelf are typically all separated into goods one by one Frame unit, overhead baggage rack unit can deposit steel tower part with storage trays or directly.The basic function of container and pallet is to carry steel tower Part, the fork in order to piler take and deposit.Depositing for steel tower part can be improved using container and pallet storing steel tower part Take efficiency.Piler is the sorting of electric power pylon, warehouse-in, storage, most important equipment in ex-warehouse system, and it is with logistlcs technology The special equipment for growing up.Back and forth walk between the tunnel that heap behaviour's machine can be between overhead baggage rack unit, its hoistable platform can be past up and down Multiple to move, steel tower part can be stored in from overhead baggage rack unit or be taken out by the storage/access device on hoistable platform.Periphery haulage equipment is main It is driving, can to control manually, it is also possible to automatically control, steel tower part is transported to into another place from one with electric power, it is this kind of Equipment includes conveyer, AVG Guide vehicles etc., and its effect is that tie stacker machine completes the conveying of steel tower part, transfer, sorting etc. and grasps Make.When the main haulage equipment in warehouse breaks down, peripheral equipment can also run, and make operation be unlikely to interrupt.Electrically Control system mainly includes detection means, information recognition device, control device, monitoring and controlling equipment, host computer information management System, communication equipment, wherein detection means are the physical parameters for detecting various operation equipment, are judged by the data to detecting Optimum decision making can be provided foundation for system with analysis, to ensure that system is safely and effectively run.Information recognition device is automatic stored Requisite device in system, it is the essential information for gathering steel tower part.At present this kind equipment generally use magnetic stripe, The technology of identification such as bar code carry out data acquisition.Various accesses that automated storage and retrieval system is equipped with, the equipment such as conveying must be equipped with controlling Device processed, to realize unmanned operation.This kind of control device mainly has chopper, relay, microprocessor, travel switch, biography Sensor and programmable controller etc..Monitoring and controlling equipment are mainly responsible for the coordinated operation of each equipment in system, and it is transmission of electricity The sorting of steel tower, warehouse-in, storage, the hinge of the information management of ex-warehouse system.Host computer information management system is used to carry out warehouse Daily information management and the management of various work flows, and can carry out being connected shared data information with the management system of enterprise.This The sorting of the electric power pylon in bright, warehouse-in, storage, ex-warehouse system are comprehensive complicated integrated systems, and it is by many subsystems Constitute.Need to carry out between each system, each equipment substantial amounts of information exchange and can just complete set task, therefore need substantial amounts of Data communications equipment.
On warehouse design, with outbound in same plane, roadway direction is parallel with warehouse length direction, adopts during warehouse-in for warehouse-in Rail transport cart mode has been accumulated one by one with fork truck, and fork truck is by steel tower component moving and is put on warehouse-in stand, then by rail stacking Machine delivers to steel tower part on the storing goods shelf specified, reverse direction operation during outbound.Steel tower component storage position is according to steel tower The mobility height and warehouse entrance of part is determining:Steel tower part is storage into and out from identical place When department or warehouse, the high steel tower part of mobility is as close possible to porch.Steel tower part passes in and out the entrance in warehouse When different, then number of times is received according to the steel tower part and company send the ratio size of number of times to determine storage location.
Piler is the sorting of electric power pylon, warehouse-in, storage, the nucleus equipment in ex-warehouse system, and power resources are electric power, By being automatically or manually controlled, outbound and the in-stockroom operation of steel tower part are realized.It is mainly used in the tunnel of thing shelf Steel tower part positioned at warehouse mouth is stored in the overhead baggage rack unit specified by inside reciprocal operation back and forth, or on the contrary, taking from shelf The steel tower part for going out is transported to warehouse mouth.In the present invention rail type piler by horizontal running mechanism, vertical lifting mechanism, from It is made up of flexible pallet fork, basic machine, failure protecting device and six part of mechanical electric equipment.According to steel tower part it is heavy, Large-scale the characteristics of, Bian was with double column agency forms.
Piler control using it is emergent, manually, unit automatically, on-line mode.Emergency mode controls stacking using touch screen The actions such as the level run and vertical lift and pallet fork Shen Shrink of machine.Emergency mode is that professional uses, general operation Personnel do not have authority to use, a kind of control mode of professional's operation when being mainly used in debugging, install and breaking down.Now Piler is with the operation of lowest speed.Other with all monitoring devices of host computer and locking device all in disarmed state, but jerk Except protection circuit.The difference of manual mode and emergency mode is that all locking devices, monitoring device and jerk circuit have Effect, that is remains in that contact with host computer.Unit automated manner is to be input into job command on the touchscreen, and piler is The subtask is automatically performed, and waits new task.Task order is performed by piler control system completely, with host computer management is System is without any relation.On-line mode is that piler is communicated by infrared communication sensor and host computer, receive host computer to Various orders that piler sends, and perform corresponding operation, and situation and various shapes that host computer task completes are reported in time State information.
The course of work of electric control system is as follows:(1) assignment instructions of host computer, the piler horizontal line leakage of electricity are received Machine and lifting movable motor are carried out simultaneously, by PC control, are accurate to up to specified location.(2) piler starts, and execution is deposited Enter, take out operation, piler returns to initial position.(3) after stacker fork gets steel tower part, piler level, lifting electricity Machine is run again, and walking is accurately positioned to after destination locations, stops.(4) during stacking machine operation, be according to different mission bit streams Using different control modes.Mission bit stream mainly includes that destination's determination and steel tower part deposit, withdraw the identification of action.Automatically transporting Under line mode, mission bit stream is specified by host computer, and order is issued piler then.
As shown in figure 1, whole monitoring system by industrial computer as host computer, using SIEMENS PLC as bottom controller. It is furnished with 6.0 configuration software of simatic WINCC on host computer, mainly completes the work such as the monitoring of warehousing system, warning, record;Heap Stack machine is furnished with Siemens touch screen OP37, replaces button and switch, can show the real-time status of piler.PLC control system by Siemens S7-300 PLC and S7-200 PLC is constituted.S7-300 PLC are arranged on master control room as main website, mainly complete whole The control in warehouse;S7-200PLC is then arranged on piler as slave station, mainly completes the control of warehousing system piler, is wrapped Include the expanding-contracting action control of traveling, position and speed controlling, pallet fork.S7-300 PLC also hang an ET200M as long-range in addition Slave station, realizes that remote I/O is gathered.The switch board of control piler is arranged on piler, in ceaselessly moving back and forth, no Wire communication is appropriate to, therefore, host computer and S7-200PLC systems take wireless ethernet mode to be communicated.S7-300 Communication between PLC and host computer adopts wired ethernet mode, and PROFIBUS DP are adopted between S7-300 PLC and ET200M Communication;Communicated using MPI modes between S7-200 PLC and touch screen.
The sorting of electric power pylon, warehouse-in, storage, the control of ex-warehouse system essentially consist in the control of piler.Piler Motion includes traveling positioning and traveling speed control, lifting positioning and rising or falling speed control, pallet fork positioning, speed controlling, lifting The actions such as fine setting, WidFin.These actions require at a high speed, it is steady but also want accurate positioning.S7-200PLC passes through frequency conversion Device is realized vertically moving and the control such as the stretching out of pallet fork, retraction movement the walking in a horizontal state of piler, load bed, using frequency conversion Device can also obtain controllable starting-braking process and high gear, medium, three kinds of speeds of service of low speed, so as to realize the flat of action Surely, high-speed cruising.When order piler reaches required position, the target location fed back according to limit switch away from From signal, according to the frequency for changing converter in advance, piler is enable to be close to target location at the appropriate speed, and smoothly The relatively low speed of service is decelerated to, target location is accurately stopped at.Electric power pylon disclosure satisfy that using half-closed loop control mode Sorting, warehouse-in, storage, piler is at a high speed, the control such as steady, accurate positioning requires in ex-warehouse system system.This is Electromechanical Control General technology in technology, does not do excessive elaboration.
When piler runs, carry out first running front detection, then judgement is analyzed according to practical situation, so as to determine Whether piler performs the current command.When piler normal non-fault, and idle condition is in without task, Receive the discrepancy/storehouse job task of host computer.When the input work task of host computer is received, then input work is carried out;Work as receipts To host computer Delivery task when, then perform Delivery;When piler is in the task of execution, it is impossible to receive new task, As shown in Figure 2.
Piler carries out the in-stockroom operation of steel tower part after the warehouse-in task that host computer sends is received.Warehouse-in sub-process As shown in Figure 3.
When piler performs input work, first check for whether whether piler is being picked and placeed in initial position, i.e. piler At the load bed position of steel tower part, and piler load bed is detected in lower limit position, otherwise carry out piler and return initial bit Operation is put, control piler is returned to initial position.Piler first determines whether shelf list to be gone to after initial position Whether unit has steel tower part, and warehouse-in task could be performed when overhead baggage rack unit does not have steel tower part;If to be gone to Overhead baggage rack unit then determines whether the steel tower part whether load bed puts in storage again without steel tower part, when load bed has steel tower part, Piler starts, and performs warehouse-in task.
In each step for performing above, if undesirable situation, then report to the police to host computer.When piler is arrived Up to after overhead baggage rack unit to be gone to, call piler delivery sub-process, lifting motor, fork operation that steel tower part is sent into institute Overhead baggage rack unit to be gone to.Then piler returns to the load bed position i.e. initial position for picking and placeing steel tower part;Meanwhile, to host computer The signal that the task of sending is completed, and be, without task, to be now subjected to new task by piler status indication.
After piler receives the outbound task that host computer sends, by piler status indication to there is task, enter Row steel tower part outbound task.As shown in figure 4, when steel tower part Delivery task is carried out, first checking for whether load bed has Steel tower part;When load bed does not have steel tower part, then judge whether overhead baggage rack unit to be gone to has steel tower part;Only When overhead baggage rack unit to be gone to has steel tower part, piler outbound task can be just carried out;When piler reaches goods to be gone to Frame unit, lifting motor, fork operation carry out taking steel tower operation of components, and steel tower portion is taken out from overhead baggage rack unit to be gone to Part;After the completion of, storehouse operation sub-process is produced, control piler returns to initial position;Then order is performed by piler load bed Steel tower part be discharged in load bed.Above flow process is completed, that is, represent and complete outbound, send the information of completing to host computer, and by heap Stack machine status indication is, without task, to be now subjected to new task.
In being originally embodiment, information recognition device is RFID.Radio RF recognition technology is RFID (Radio FrequencyIdentification) technology, used as the wireless version of bar codes technique, RFID technique has bar shaped Advantage not available for code:Waterproof, antimagnetic, high temperature resistant, read that distance is big, on label data can encrypt, data storage capacity Freely etc., its application will bring revolutionary variation to industries such as retail, logistics to the change of bigger, storage information.Additionally, RFID technique High-speed moving object is can recognize that also, so present invention employs the technology.Wherein at warehouse gateway, read write line is read and write with shelf Device belongs to fixed type reader-writer, keeps being connected with host computer, and structure is similar, differs primarily in that the difference of Antenna Design. Read write line is made up of module for reading and writing, power module, serial line interface and four part of antenna.It is maximum different from portable read-write machine That fixed read write line itself does not have a processing unit directly by host computer PC control, the mode of networking be by multi-serial-port card, this It is because that fixed type reader-writer quantity is more, and each warehouse is typically provided only with a host computer.Host computer is only solid to one every time Fixed pattern read write line sends and reads or write instruction.For the fixed read write line at warehouse gateway, antenna is with module for reading and writing etc. Part set all-in-one-piece, and the part such as antenna and module for reading and writing of shelf read write line is detached, in order to improve shelf read write line Identification ability, can adopt multiple antennas constitute array come from all angles read shelf on steel tower component tag.It is portable Read write line is with 51 single-chip microcomputers as control core.Single-chip microcomputer is realized to radio-frequency (RF) tag data by connecting radio frequency module for reading and writing Read-write.Reading information is storable in extended menory.When needing to communicate with host computer, can be connected to by serial port circuit Position machine is communicated.LAN can be constituted to be ultimately connected to the sorting of electric power pylon, put in storage, deposit between the host computer in each warehouse Storage, the top layer database server of ex-warehouse system management.4 × 4 keyboards coordinate the common finishing man-machine interactions of LCD (LCDs) Function.Power module is using rechargeable battery powered.
Radio frequency module for reading and writing has considerable effect as the ingredient of core in radio-frequency recognition system, is to realize The bridge that processor is communicated with radio-frequency (RF) tag, the design of all read write lines include the content of module for reading and writing.The present invention adopts RI- Key control units of the R6C-001A as module for reading and writing, it is by PHILIPS Co. of Holland of Texas Instruments (TI) (Philips) develop jointly, the agreement of support includes Tag-it agreements, ISO/IEC15693-2, ISO/IEC14443-2 (TYPE A), operating frequency is 13.56MHz, using SSOP20 packing forms.Passive maximum reading/writing distance is read and write up to 1.2 meters Speed is fast, can multi-targets recognition and Motion Recognition, it is per second in theory at most to recognize 50 radio-frequency (RF) tag simultaneously.+ 5V power supplys are supplied The radio-frequency power sent when electric is 80mW up to 200mW, when 3V power supplys are powered, and usual running voltage is+5V.The chip can be with height Communicated by SCLOCK, M_ERR, DIN, DOUT4 data line between fast low-power scm AT90S2313.Chip XTAL_CLK is that crystal oscillator buffers end, and it can export the clock signal of 13.56MHz, is thus supplied to required for single-chip microcomputer work Clock.RI-R6C-001A is arranged by transmitter, receptor, power supply supply, reference clock and internal oscillator, the reset recognized And power management, several parts compositions such as serial communication interface.Radio frequency chip enclosed inside has transmission encoder, manipulator, reception Decoder and demodulator, using Manchester's code mode.The chip has IDLE, tri- kinds of power supplys of POWERDOWN, FULL POWER Management function.
As the design of antenna to be taken into full account the concrete application feelings of the sorting of electric power pylon, warehouse-in, storage, ex-warehouse system Condition, such as in order to increase the reading/writing distance of the read write line at warehouse gateway, is worked using two antennas, in addition it is also necessary to increase day in pairs The size of line simultaneously improves its output.But while the problems such as also must be considered that matching and the safety regulation of system.In addition, needing It should be noted that in general, the 70% of the maximum write distance about reading distance of read write line.In the present invention in order to The various problems for overcoming antenna to exist, devise the label antenna after adding matching minor matters, and matching minor matters can be equivalent to one section Lossy transmission line, the real part of its impedance are mainly determined by its width, and it is exactly partly by the length of matching minor matters that its imaginary part is lost Degree determines that length L and width W of matching minor matters determines the impedance of matching minor matters.L values are 13-15mm, and W values are 0.3- 0.4mm, the structure of antenna is as shown in figure 5, the size of various pieces is as follows:
As shown in figure 5, the symmetrical arrangement of antenna, the center mounting hole axis with label chip as symmetric reference, institute State electric wire to extend by following direction on the right side of symmetric reference successively:First level extends to the right and then extends straight up, then level Extend to the right and then extend straight down, then level extends to the right and extends straight up again, then level extends to the right and erects again Directly upwardly extend, then level extends to the right and extends straight down again, then level is extended in the left and extended straight up, finally Level extends to the right;Antenna left part is arranged in specular with right part.The overall antennas be shaped like two it is back-shaped Pin is arranged.Through test, this structure setting has preferable effect to improving antenna gain, as shown in fig. 6, wherein S11Represent and increase Benefit.
Embodiment two:
Similar with embodiment one, difference is that the antenna in the present embodiment is as shown in Figure 7.Matching minor matters width W pair The input impedance of antenna affects larger, and real part is reduced with the increase of W.In this embodiment, whole label antenna occupies Space is larger, reduces its length in the vertical by bending matching minor matters so as to form a strip.So antenna is still Symmetrical arrangement, the center mounting hole axis with label chip as symmetric reference, the electric wire on the right side of the symmetric reference according to It is secondary to extend by following direction:First level extends to the right and then extends straight up, then level extends to the right and then prolongs straight down Stretch, then level extends to the right and extends straight up again, then level extends to the right and extends straight up again, then level is to the right Extension extends again straight down, and then level is extended in the left and extended straight up, and final level extends to the right;Antenna left side Divide and arrange in specular with right part.The overall antennas are shaped like two paperclip arrangements.Minor matters are matched wherein T-shaped Shape, above centrally disposed installing hole.
Using the embodiment in embodiment one and embodiment two, can greatly improve electric power pylon part warehouse-in, sorting, The efficiency of outbound, accelerates the transmission of tower material.
To those skilled in the art, the invention is not restricted to the details of above-mentioned one exemplary embodiment, and do not carrying on the back In the case of the spirit or essential attributes of the present invention, the present invention can be realized in other specific forms.Therefore, no matter from which From the point of view of a bit, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention will by appended right Ask rather than described above is limited, it is intended that all changes that will fall in the implication and scope of the equivalency of claim Include in the present invention.Any reference in claim should not be considered as and limit involved claim.
The above, only presently preferred embodiments of the present invention, not to limit the present invention, every skill according to the present invention Any trickle amendment, equivalent and improvement that art is substantially made to above example, should be included in technical solution of the present invention Protection domain within.

Claims (9)

1. a kind of sorting of electric power pylon, warehouse-in, storage, ex-warehouse system, including civil engineering system, mechanical hardware system and electricity Gas control system;Wherein civil engineering system includes warehouse main body, fire-fighting system, illuminator, dynamical system, ventilation and heating System;The mechanical hardware system includes shelf, container, pallet, piler and periphery haulage equipment;The electric control system Set including detection means, information recognition device, control device, monitoring and controlling equipment, host computer information management system, communication Standby, it is characterised in that described information identifying device adopts RFID, label antenna is the label day for adding matching minor matters Line, the symmetrical arrangement of the label antenna, the center mounting hole axis with label chip as symmetric reference, the label electricity Line is extended by following direction on the right side of symmetric reference successively:First level extends to the right and then extends straight up, then level is to the right Extension then extend straight down, then level extends to the right and extends straight up again, then level extend to the right again vertically to Upper extension, then level extend to the right and extend straight down again, then level extends to the left and extends straight up again, final level Extend to the right;The label antenna left part is arranged in specular with right part;The matching minor matters are arranged on label Above chip center's installing hole.
2. a kind of sorting of electric power pylon according to claim 1, warehouse-in, storage, ex-warehouse system, it is characterised in that:Institute State similar two paperclips of label antenna overall shape to be arranged symmetrically.
3. a kind of sorting of electric power pylon according to claim 1, warehouse-in, storage, ex-warehouse system, it is characterised in that:Institute The T-shaped shape of matching minor matters is stated, is arranged on above label chip center mounting hole.
4. a kind of sorting of electric power pylon according to claim 1, warehouse-in, storage, ex-warehouse system, it is characterised in that:Institute Electric control system is stated using industrial computer as host computer, using SIEMENS PLC as bottom controller;Match somebody with somebody on the host computer There is 6.0 configuration software of simatic WINCC, the piler is furnished with Siemens touch screen OP37, and the PLC bottom controllers are by west MENZI S7-300PLC and S7-200PLC are constituted;The S7-300PLC is that main website is arranged on master control room, and the S7-200PLC is Slave station is arranged on piler.
5. a kind of sorting of electric power pylon according to claim 4, warehouse-in, storage, ex-warehouse system, it is characterised in that:Institute State S7-300PLC and also hang an ET200M as long-range slave station, the host computer and the S7-200PLC systems take wirelessly with Too net mode is communicated, and the communication between the S7-300PLC and the host computer is communicated using wired ethernet mode, institute State;Adopt between the S7-200PLC and the touch screen MPI modes communicate.
6. electric power pylon is carried out using a kind of sorting of electric power pylon as claimed in claim 4, warehouse-in, storage, ex-warehouse system The piler operational approach of part, it is characterised in that:When piler performs input work, whether piler is first checked for first Whether whether beginning position, i.e. piler are at the load bed position for picking and placeing steel tower part, and detect piler load bed in lower limit Position position, otherwise carries out piler and returns initial position operation, and control piler is returned to initial position;Piler is in initial bit Postpone, first determine whether whether overhead baggage rack unit to be gone to has steel tower part, when overhead baggage rack unit does not have steel tower part Perform warehouse-in task;If overhead baggage rack unit to be gone to is without steel tower part, determine whether whether load bed has to be put in storage Steel tower part, when load bed has steel tower part, piler starts, and performs warehouse-in task.
7. a kind of piler operational approach as claimed in claim 6, it is characterised in that:In each step for performing above, such as Fruit has undesirable situation, then report to the police to host computer.
8. a kind of piler operational approach as claimed in claim 7, it is characterised in that:When piler reaches goods to be gone to After frame unit, call piler delivery sub-process, lifting motor, fork operation that steel tower part is sent into shelf list to be gone to Unit, then piler return to the load bed position i.e. initial position for picking and placeing steel tower part;Meanwhile, send what task was completed to host computer Signal, and be, without task, to be now subjected to new task by piler status indication.
9. electric power pylon is carried out using a kind of sorting of electric power pylon as claimed in claim 4, warehouse-in, storage, ex-warehouse system The piler operational approach of part, it is characterised in that:After piler receives the outbound task that host computer sends, by piler Status indication carries out steel tower part outbound task to there is task;When steel tower part Delivery task is carried out, examine first Look into whether load bed has steel tower part;When load bed does not have steel tower part, then judge whether overhead baggage rack unit to be gone to has ferrum Tower part;When only overhead baggage rack unit to be gone to has steel tower part, piler outbound task can be just carried out;When piler is reached Overhead baggage rack unit to be gone to, lifting motor, fork operation carry out taking steel tower operation of components, from overhead baggage rack unit to be gone to Take out steel tower part;After the completion of, storehouse operation sub-process is produced, control piler returns to initial position;Then order is performed by heap Steel tower part in stack machine load bed is discharged in load bed;Above flow process is completed, that is, represent and complete outbound, send to host computer and complete letter Breath, and be, without task, to be now subjected to new task by piler status indication.
CN201610924311.6A 2016-10-24 2016-10-24 A kind of sorting of electric power pylon, storage, storage, ex-warehouse system Active CN106542249B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610924311.6A CN106542249B (en) 2016-10-24 2016-10-24 A kind of sorting of electric power pylon, storage, storage, ex-warehouse system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610924311.6A CN106542249B (en) 2016-10-24 2016-10-24 A kind of sorting of electric power pylon, storage, storage, ex-warehouse system

Publications (2)

Publication Number Publication Date
CN106542249A true CN106542249A (en) 2017-03-29
CN106542249B CN106542249B (en) 2017-10-03

Family

ID=58392277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610924311.6A Active CN106542249B (en) 2016-10-24 2016-10-24 A kind of sorting of electric power pylon, storage, storage, ex-warehouse system

Country Status (1)

Country Link
CN (1) CN106542249B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108876083A (en) * 2017-11-06 2018-11-23 武汉燎原模塑有限公司 A kind of storage scheduling system and the production line using the system
CN109383963A (en) * 2017-08-08 2019-02-26 司米厨柜有限公司 A kind of single sorting system of spelling
CN110533371A (en) * 2019-08-26 2019-12-03 国网山西省电力公司计量中心 A kind of Intelligent logistics warehousing system and method having fool proof electric power internet of things equipment
CN111582781A (en) * 2020-04-24 2020-08-25 清华大学深圳国际研究生院 Method for distributing goods shelves according to replenishment orders and computer-readable storage medium
CN115027856A (en) * 2022-05-19 2022-09-09 北京旷视机器人技术有限公司 Material sorting system and material sorting method
CN116198898A (en) * 2023-04-20 2023-06-02 巴斯夫一体化基地(广东)有限公司 Warehouse for storing goods

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0218059A1 (en) * 1985-09-10 1987-04-15 Untertage Maschinenfabrik Dudweiler GmbH Installation for storing pallets or the like
JPH08119419A (en) * 1994-10-27 1996-05-14 Hitachi Transport Syst Ltd Intelligent picking dolly, its maneuvering method, and intelligent picking system
CN1184070A (en) * 1997-12-30 1998-06-10 北京矿冶研究总院 Belt cableway conveyer
CN202625340U (en) * 2012-06-14 2012-12-26 云南电力线路器材厂 Production line discharge device for transmission line towers
CN202754442U (en) * 2012-06-27 2013-02-27 温州泰昌铁塔制造有限公司 Conveyor device for 110-500KV steel pylon
CN203222287U (en) * 2013-03-12 2013-10-02 吴敏郎 Tower type classification collection and feeding mechanism

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0218059A1 (en) * 1985-09-10 1987-04-15 Untertage Maschinenfabrik Dudweiler GmbH Installation for storing pallets or the like
JPH08119419A (en) * 1994-10-27 1996-05-14 Hitachi Transport Syst Ltd Intelligent picking dolly, its maneuvering method, and intelligent picking system
CN1184070A (en) * 1997-12-30 1998-06-10 北京矿冶研究总院 Belt cableway conveyer
CN202625340U (en) * 2012-06-14 2012-12-26 云南电力线路器材厂 Production line discharge device for transmission line towers
CN202754442U (en) * 2012-06-27 2013-02-27 温州泰昌铁塔制造有限公司 Conveyor device for 110-500KV steel pylon
CN203222287U (en) * 2013-03-12 2013-10-02 吴敏郎 Tower type classification collection and feeding mechanism

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109383963A (en) * 2017-08-08 2019-02-26 司米厨柜有限公司 A kind of single sorting system of spelling
CN108876083A (en) * 2017-11-06 2018-11-23 武汉燎原模塑有限公司 A kind of storage scheduling system and the production line using the system
CN108876083B (en) * 2017-11-06 2024-03-22 武汉燎原模塑有限公司 Warehouse dispatching system and production line applying same
CN110533371A (en) * 2019-08-26 2019-12-03 国网山西省电力公司计量中心 A kind of Intelligent logistics warehousing system and method having fool proof electric power internet of things equipment
CN111582781A (en) * 2020-04-24 2020-08-25 清华大学深圳国际研究生院 Method for distributing goods shelves according to replenishment orders and computer-readable storage medium
CN115027856A (en) * 2022-05-19 2022-09-09 北京旷视机器人技术有限公司 Material sorting system and material sorting method
CN116198898A (en) * 2023-04-20 2023-06-02 巴斯夫一体化基地(广东)有限公司 Warehouse for storing goods
CN116198898B (en) * 2023-04-20 2023-07-25 巴斯夫一体化基地(广东)有限公司 Warehouse for storing goods

Also Published As

Publication number Publication date
CN106542249B (en) 2017-10-03

Similar Documents

Publication Publication Date Title
CN106542249B (en) A kind of sorting of electric power pylon, storage, storage, ex-warehouse system
CN205230118U (en) Intelligence warehouse system based on multirobot
CN107032033B (en) The intensive storage method of cargo smart three-dimensional and intelligent intensive stereo garage system
CN109359919A (en) A kind of Warehouse Management System and management method for logistics storage
CN105775549B (en) A kind of auxiliary material empty pallet recovery method of ultrahigh speed cigarette machine
CN102663576A (en) Steel product intelligent warehousing system based on radio frequency identification technology
CN105923334B (en) A kind of auxiliary material automatic delivery of ultrahigh speed cigarette machine
CN109508926A (en) A kind of logistics system and working method of dangerous material transfer house
CN103955812A (en) Key-point product monitoring equipment storage management system based on RFID
CN109353732A (en) A kind of large size material automated warehousing system and method
CN206627997U (en) A kind of article based on RFID technique goes out Input System automatically
CN107380990B (en) A kind of intelligent storage sorting station and its method for sorting
CN205345971U (en) Intelligent intensive three -dimensional storehouse
CN109911499A (en) Unmanned intelligence Workshop control system
CN105005887A (en) Intelligent electricity metering warehouse management system
CN108182373A (en) A kind of RFID intelligent environment protections express delivery collection packet sorting management system
CN101887550A (en) Large warehoused cargo triggered fault-tolerant addressing method based on wireless radio-frequency identification
CN115759892A (en) Unmanned intelligent checking system and method for electric power material storage
CN207957139U (en) A kind of robot for carrying and piling trolley based on laser navigation
EP4226303A1 (en) Method for the computer-aided processing of a status change of a goods carrier in a storage and picking system, and storage and picking system
CN107194633A (en) Product transport system
CN111891611B (en) Intelligent warehousing distribution system, method and device and readable storage medium
CN113050563A (en) Material management system based on RFID and operation method thereof
CN202171826U (en) International express mail custom clearance and warehouse management system based on ultrahigh frequency RFID
CN114044295B (en) Auxiliary material library information checking method based on cooperation of stacker and conveyor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170815

Address after: 100075 Beijing, Fengtai District Lin Lin Road, No. 15

Applicant after: MATERIALS BRANCH, STATE GRID JIBEI ELECTRIC POWER CO., LTD.

Applicant after: State Grid Corporation of China

Address before: 100075 Beijing, Fengtai District, Lin Wai Road, No. 15

Applicant before: MATERIALS BRANCH, STATE GRID JIBEI ELECTRIC POWER CO., LTD.

GR01 Patent grant
GR01 Patent grant