CN106463938B - Controller switching equipment livewire work method - Google Patents
Controller switching equipment livewire work method Download PDFInfo
- Publication number
- CN106463938B CN106463938B CN201580030633.XA CN201580030633A CN106463938B CN 106463938 B CN106463938 B CN 106463938B CN 201580030633 A CN201580030633 A CN 201580030633A CN 106463938 B CN106463938 B CN 106463938B
- Authority
- CN
- China
- Prior art keywords
- cross arm
- mentioned
- interim wooden
- stage
- wooden cross
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/24—Cross arms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01B—CABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
- H01B17/00—Insulators or insulating bodies characterised by their form
- H01B17/14—Supporting insulators
- H01B17/16—Fastening of insulators to support, to conductor, or to adjoining insulator
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/02—Devices for adjusting or maintaining mechanical tension, e.g. take-up device
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/05—Suspension arrangements or devices for electric cables or lines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/20—Spatial arrangements or dispositions of lines or cables on poles, posts or towers
- H02G7/205—Installation of electric cables, extending along a pole
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Electric Cable Installation (AREA)
Abstract
Illustrate the invention in relation to controller switching equipment livewire work method.The controller switching equipment livewire work method of the present invention:Include to install newly set the stage of electric pole, interim wooden cross arm is fixed on the new stage set on electric pole, electric wire is fixed to the stage for the wire rack being mounted on interim wooden cross arm, moves up interim wooden cross arm or wire rack on the electrical wiring between having set electric pole, stage for placing the wires on the predetermined mounting height of PIN cross-arms, the stage that PIN cross-arms are installed to the new stage for setting electric pole, are moved to PIN cross-arms by stage that interim wooden cross arm or wire rack are moved down to PIN cross-arms direction, by the electric wire for being connected to wire rack.
Description
Technical field
The present invention is the related content of controller switching equipment livewire work method, be about using controller switching equipment livewire work with auxiliary
Device is helped newly to set the content of electric pole.
Background technology
The top of electric pole can generally install cross-arm, and cross-arm is insulated by horizontal iron cross arm and 3 on iron cross arm
Son composition.3 phase electric wires are connected respectively to 3 insulators by binder.
When safeguarding mounted electric pole, cross-arm, insulator, old insulator is replaced with new insulator, is replaced with new cross-arm
Old cross-arm is replaced with new electric pole with regard to originals such as the extension angle increases of electric wire caused by the change in location of electric pole or electric pole
Cause has PIN cross-arms replacing with the operations such as interior cross-arm.Also have and set newly setting for electric pole etc. because the extended position change of electric wire etc. is new
The operation of controller switching equipment.
These work are the security risks that the electric wire of electriferous state moves up and down, therefore has certain.So in order to
Security risk is reduced, livewire work is preferably carried out, is just developing various devices and technology.
Related online technique Korean published Patent announce No. 2006-0082713 (2006.7.19. is disclosed,
Denomination of invention:Have the distribution line operation multi-axis robot of 2 dimensions and the comprehensive driving method of 3 dimensions) it is illustrated.
Invention content
It solves the problems, such as
The object of the present invention is to provide staff to automatically move electric wire simultaneously in the position far from electric wire using electric power remote
The method of the new controller switching equipment livewire work for setting electric pole, to make, controller switching equipment livewire work is safer, successfully carries out.
Solution to the problem
The controller switching equipment livewire work method of the present invention:Include newly to set electric wire on the electrical wiring between having set electric pole
Interim wooden cross arm is fixed to the above-mentioned new stage set on electric pole, said wires is connected to mounted on upper by the stage of bar
It states the stage on the wire rack on interim wooden cross arm, move up above-mentioned interim wooden cross arm or said wires holder, it will be above-mentioned
Above-mentioned PIN cross-arms are installed to the above-mentioned new rank set on electric pole by stage that electric wire is placed on the predetermined installation site of PIN cross-arms
Section, by stage that above-mentioned interim wooden cross arm or said wires holder are moved down to above-mentioned PIN cross-arms direction, will be connected to it is above-mentioned
The stage that the said wires of wire rack are moved to above-mentioned PIN cross-arms.
It is that the 1st lifting moving portion receives the 1st driver by the ideal method that above-mentioned interim wooden cross arm moves up or down
Power after, move up and down above-mentioned interim wooden cross arm.
It is that the 2nd lifting moving portion receives the 2nd driver by the best approach that said wires holder moves up or down
After power, said wires holder is moved up and down.
Said wires are connected to the stage on said wires holder, said wires is preferably included and is inserted into said wires branch
In the state of internal stent on frame, the process of carrier openings is closed with sticking department;Said wires are moved to above-mentioned PIN cross-arms
Stage, preferably include the process for the outside that said wires are pulled out to above-mentioned holder by above-mentioned opening.
Above-mentioned PIN cross-arms, preferably take the horizontally arranged of common cross-arm.
Invention effect
Controller switching equipment livewire work auxiliary device according to the present invention utilizes the electronic of the 1st driver or the 2nd driver
Power automatically adjusts the height of interim wooden cross arm, the height of each wire rack, the electric wire height being fixed on wire rack, can be light
Pine carries out newly setting electric pole.
According to the present invention, the 1st driver or the 2nd driver can use electric drill, the electricity for being generally used for replacing controller switching equipment
The electric tools such as dynamic screwdriver, staff can be easily real without the electric device needed for the mobile wire rack of specially preparation
It is existing.
According to the present invention, the height of interim wooden cross arm and wire rack entirety can be not only adjusted with multistage, by only up and down
The sub- extension that electric wire fixing segments are formed in mobile wire rack, you can 3 sections adjust electric wire fixing segments or electric wire height.
According to the present invention, can automatic or manual adjust electric wire fixing segments or electric wire height, adjustment length is up to vertical extension
The length in portion, the length of main extension, the sum of the length of sub- extension adjust interim wooden cross arm and wire rack by multistage
Highly, close to after target fulcrum, by finely tuning sub- extension, electric wire fixing segments are more accurately placed in object height.
According to the present invention, staff selectively adjusts interim wooden cross arm on one side according to operating environment or convenience
Highly, the height of wire rack whole height, sub- extension can be stablized, easily be temporarily placed within electric wire into being about to electric wire on one side
Operation on holder ensures PIN cross-arms being installed to the new operation for setting space needed for electric pole.
According to the present invention, using the 1st driver or the 2nd driver, staff can be long-range with electric wire remote position
Electric wire is moved to the top of PIN cross-arms, can more easily control ensure newly to set the livewire work space needed for electric pole, can be reduced new
If staff leads to the danger of safety accident with line contacts when electric pole.
According to the present invention, when the different LP insulators of multiple height are installed, using the 2nd lifting moving portion, insulated according to LP
The height of son, individually lifts wire rack, can easily carry out operation, when using live-wire work tool and utensil difficulty, also may be used
The above lower adjustment uses position, and operation is made to be more prone to.
According to the present invention, multiple wire racks are mounted in the state of interim wooden cross arm, move up interim wooden cross arm, can
The trouble that wire rack moves up one by one is avoided, all wire racks can be moved up simultaneously with identical displacement.
Description of the drawings
Fig. 1 is the perspective sketch map of the controller switching equipment livewire work auxiliary device of one embodiment of the invention.
Fig. 2 is the interim wooden cross arm fixed part of one embodiment of the invention and the perspective sketch map in the 1st lifting moving portion.
Fig. 3 is the lateral concept map of the 1st lifting moving portion internal structure of one embodiment of the invention.
Fig. 4 to illustrate the invention one embodiment the 1st driving portion operation concept map.
Fig. 5 is the wire rack of one embodiment of the invention and the perspective sketch map in the 2nd lifting moving portion.
Fig. 6 to illustrate the invention one embodiment the 2nd lifting moving portion operation concept map.
Fig. 7 to illustrate the invention one embodiment into electric wire fixing segments be inserted into electric wire process concept map.
The flow chart of Fig. 8 controller switching equipment livewire work methods of one embodiment to illustrate the invention.
Fig. 9 is to illustrate electric between having set electric pole in the controller switching equipment livewire work method of one embodiment of the invention
The concept map of electric pole process is newly set on line circuit.
Figure 10 is to illustrate interim wooden cross arm being fixed in the controller switching equipment livewire work method of one embodiment of the invention
The new concept map for setting electric pole process.
Figure 11 is to illustrate wire rack to electric wire side in the controller switching equipment livewire work method of one embodiment of the invention
To the concept map for the process of moving up.
Figure 12 is in the controller switching equipment livewire work method of one embodiment of the invention, and explanation will be wired to and be mounted on
The concept map of the wire rack process of interim wooden cross arm.
Figure 13 is to illustrate wire rack to moving up in the controller switching equipment livewire work method of one embodiment of the invention
It is dynamic, make the concept map for the process that electric wire is placed on the predetermined mounting height of PIN cross-arms.
Figure 14 is to illustrate PIN cross-arms being fixed on newly in the controller switching equipment livewire work method of one embodiment of the invention
If the concept map of electric pole process.
Figure 15 is to illustrate wire rack is horizontal to PIN in the controller switching equipment livewire work method of one embodiment of the invention
The LP insulators direction of load moves down the concept map of process.
Figure 16 is to illustrate to move electric wire to LP insulators in the controller switching equipment livewire work method of one embodiment of the invention
The concept map of dynamic process.
Figure 17 is to illustrate to set interim wooden cross arm from newly in the controller switching equipment livewire work method of one embodiment of the invention
The concept map of electric pole disassembly process.
Specific implementation mode
The particular content to carry out an invention
With reference to the drawing in attachment, illustrate the embodiment of the controller switching equipment livewire work method of the present invention.During this, it is
It conveniently clearly demonstrates, the thickness of the line in drawing or the size of component etc. may compare exaggeration.
Aftermentioned term is to consider the function in the present invention and the term that defines, according to user, operating personnel purpose or
Convention may be different.Therefore, these terms should be defined based on this detail entire content.
First, illustrate the controller switching equipment livewire work auxiliary device 500 of the present invention.
Fig. 1 is the perspective sketch map of the controller switching equipment livewire work auxiliary device of one embodiment of the invention.
With reference to figure 1, controller switching equipment livewire work of the invention is horizontal by interim wooden cross arm 510, interim wood with auxiliary device 500
Carry on a shoulder pole fixed part 520, the 1st lifting moving portion 530, wire rack 540, the 2nd lifting moving portion 550 composition.
Interim wooden cross arm 510, which is fixed on, newly to be set on electric pole 13, and wire rack 540 and is connected on wire rack 540
Electric wire 30 formed support bear a heavy burden frame.The interim wooden cross arm 510 of one embodiment of the invention by horizontal extension portion 511, hang down
Straight extension 513, holder 515 form.
Horizontal extension portion 511 is that horizontal direction extends.Therefore, vertical extensions 513 are fixed on and newly set electric pole
In the state of 13, horizontal extension portion 511 newly sets the PIN iron cross arms on electric pole 13 and is arranged side by side with will be mounted on.Horizontal water
One or more wire racks 540 are installed on flat extension 511.
Vertical extensions 513 are connected to the bottom in horizontal extension portion 511.Vertical extensions 513 along it is new set electric pole 13 with
Vertical direction extends, and is fixed on by interim wooden cross arm 520 and is newly set on electric pole 13.
Holder 515 is rod shape, and inclination is installed between horizontal extension portion 511 and vertical extensions 513, and connects level
Extension 511 and vertical extensions 513.The top of holder 515 connects with the chaining part 516 mounted on 511 end of horizontal extension portion
It connects, keeps its rotatable, the lower part of holder 515 is connect with vertical extensions 513.By above-mentioned connection structure, holder 515 with
On the basis of the interconnecting piece of vertical extensions 513, support level extension 511.
The method that chaining part 516 is installed to horizontal extension portion 511:Chaining part 516 is inserted into level frame interconnecting piece 521
After end, the bolts fitting such as lifting bolt is run through to the side of chaining part 516, chaining part 516 and horizontal extension portion 511 is tight
It is close to and is connected together.
Fig. 2 is the interim wooden cross arm fixed part of one embodiment of the invention and the perspective sketch map in the 1st lifting moving portion;Fig. 3
For the lateral concept map of the 1st lifting moving portion internal structure of one embodiment of the invention;Fig. 4 implementations to illustrate the invention
The concept map of the 1st driving portion operation of example.
Interim wooden cross arm 510 or the 1st lifting moving portion 530 are fixed on by interim wooden cross arm fixed part 520 newly sets electric pole
13.With reference to figure 2, the interim wooden cross arm fixed part 520 of one embodiment of the invention is by interim wooden cross arm interconnecting piece 521 and electric pole
Interconnecting piece 523 forms.
Interim wooden cross arm interconnecting piece 521 is the part being connect with interim wooden cross arm 510 or the 1st lifting moving portion 530.Temporarily
Wooden cross arm interconnecting piece 521, which possesses, can load and unload interim wooden cross arm 510 or the 1st interconnecting piece 531a in the 1st lifting moving portion 530
2nd interconnecting piece, 522 structure.
In one embodiment of the invention, the 1st interconnecting piece 531a longitudinally (upper and lower) can extend, and lower part is in the opening wider than top
Shape, the 2nd interconnecting piece 522 are the appearance to 530 side of the 1st lifting moving portion outer interconnecting piece outstanding, and the width of end can pass through
The lower part of 1st interconnecting piece 531a, but top can not be passed through.
The 2nd interconnecting piece 522 is inserted into the lower part of 1st interconnecting piece 531a, the lifting of interim wooden cross arm 510 or the 1st is lifted in releasing
The external force of moving portion 530, because of interim wooden cross arm 510 or the weight in the 1st lifting moving portion 530, the 1st interconnecting piece 531a is to moving down
It is dynamic, so that the 2nd interconnecting piece 522 is located at the top of the 1st interconnecting piece 531a.At this point, the end of the 2nd interconnecting piece 522 hangs over the 1st interconnecting piece
The top of 531a.By above-mentioned assembling, interim wooden cross arm 510 or the 1st lifting moving portion 530 can be connected mounted in interim wooden cross arm
On portion 521.
Electric pole interconnecting piece 523 is secured to the new part for setting electric pole 13.Electric pole interconnecting piece 523 and interim wooden cross arm
Interconnecting piece 521 connects, and possesses and may be mounted to new set on electric pole 13 or from the clip structure dismantled thereon.
General clip is the accessory that the 1st accessory is connected to the 2nd accessory, can encase the 2nd accessory " ㄈ " shape or " C "
Shape or band-like, there are the connectors such as bolt or nut in end.Although the electric pole interconnecting piece of one embodiment of the invention
523 be clip structure, newly sets electric pole 13 but if can be fixed to interim wooden cross arm 510, not limit structure and appearance.
It, will be on interim wooden cross arm 510 in the state that 1st lifting moving portion 530 is to be fixed on interim wooden cross arm fixed part 520
Lower movement.With reference to 2~Fig. 4 of figure, the 1st lifting moving portion 530 of one embodiment of the invention is by electric pole mounting portion 531 and the 1st
Driving portion 533 forms.
In the state that electric pole mounting portion 531 is to be mounted on interim wooden cross arm fixed part 520, formation can be supported including hanging down
The frame of interim wooden cross arm 510 and 30 weight of electric wire including straight extension 513.531 side of electric pole mounting portion has and can face
When wooden cross arm fixed part 520 on the 1st interconnecting piece 531a that loads and unloads.Have and the 1st interconnecting piece 531a on interim wooden cross arm fixed part 520
The 2nd interconnecting piece 522 being spirally connected.It, can be by the 1st lifting moving by being spirally connected for the 1st interconnecting piece 531a and the 2nd interconnecting piece 522
Portion 530 is installed on interim wooden cross arm fixed part 520.By releasing being spirally connected for the 1st interconnecting piece 531a and the 2nd interconnecting piece 522,
1st lifting moving portion 530 and interim wooden cross arm fixed part 520 can be separated.
Vertical extensions 513 are installed so that it can move up and down in the offside of electric pole mounting portion 531.Installation is vertically prolonged
When long portion 513, electric pole mounting portion 531 is run through up and down, so that it is coordinated the movement of the 1st driving portion 533, move up and down.
To prevent from hindering the movement of vertical extensions 513, the electricity connecting with vertical extensions 513 with the friction of electric pole mounting portion 531
Line bar mounting portion 531 is mounted with multiple rollers 532 in a manner of being arranged above and below.When vertical extensions 513 are upward/lower mobile, rolling
Son 532 keeps the state contacted with vertical extensions 513, coordinates the movement of vertical extensions 513, to side or reverse rotation.
1st driving portion 533 is mounted on electric pole mounting portion 531, will interim wood after the power for receiving the 1st driver 41
Cross-arm 510 moves up and down.1st driver 41 can be applicable in electric drill, the electric screw driver etc. replaced and generally used when controller switching equipment
The driving devices such as electric tool or motor.1st driving portion 533 of one embodiment of the invention is by the 1st driving section 534, the 1st beam barrel
537, the 1st transmission belt 538 forms.
1st driving section 534 is to be rotated to drive by the 1st driver 41.In one embodiment of the invention, the 1st driving section 534
It is made of the 1st worm screw 535 and the 1st worm gear 536.
There is the 1st power receiving portion 535a being connect with the 1st driver 41 in the end of 1st worm screw 535, receives the 1st driver
41 rotary powers transmitted.1st worm gear 536 is engaged with the 1st worm screw 535, is separately mounted on the 1st beam barrel 537 and transmission shaft, with
The linkage of 1st worm screw 535 is rotated.Using electric tool as the 1st driver 41 in use, the 1st worm screw 535 with the 1st by swashing
The rotation linkage for encouraging device 41 is rotated, and the 1st worm gear 536 is then rotated in deceleration by the rotation linkage with the 1st worm screw 535,
Increase rotary force simultaneously.
As described above, according to the turbine structure for having the 1st worm screw 535 and the 1st worm gear 536, power can only be from the 1st worm screw
535 transmit to the 1st worm gear 536, can not be transmitted from the 1st worm gear 536 to the 1st worm screw 535.That is, imposing rotation to the 1st worm gear 536
Power, can not be such that the 1st worm screw 535 rotates, and the 1st worm gear 536 will not rotate.
1st worm gear 536 is connect by the 1st beam barrel 537 and the 1st transmission belt 538 with interim wooden cross arm 510, according to above-mentioned
Worm gear arrangement can prevent from making interim wooden cross arm 510 move down because of the weight such as interim wooden cross arm 510 and electric wire 30.
The 1st transmission belt 538 is rolled or unlocked to 1st beam barrel 537, to side or reverse rotation, by the 1st driving section 534.1st
Beam barrel 537 is the cylindrical structure that can batch the 1st transmission belt 538, is connected on transmission shaft with the 1st worm gear 536.
1st transmission belt 538 will be rolled to the 1st beam barrel 537, and end is connected to interim wooden cross arm 510.1st transmission belt 538 can
To be the general transmission belt of flat rectangle or linear section, the linear accessories such as cable, cable wire can also be used.1st transmission belt, 538 end
The connector and interim wooden cross arm 510 that end can be connected and be detached by hook, connector (fitt ing), buckle, spiro connecting piece etc. into
Row connection.
1st driver 41 is rotated with the state that its end is connect with the 1st power receiving portion 535a to side, rotary power
It is transferred to the 1st beam barrel 537 by the 1st driving section 534, the 1st beam barrel 537 will while rolling the 1st transmission belt 538 to side rotation
The interim wooden cross arm 510 being connect with 538 end of the 1st transmission belt is pulled upwardly.If making the 1st driver 41 reversely rotate, the 1st axis
Cylinder 537 also reversely rotates, and unlocks interim wooden cross arm 510 while the 1st transmission belt 538 and declines.
The safety position limiter 539 for limiting interim wooden cross arm 510 and moving down can be added in 510 bottom of interim wooden cross arm.This
In invention one embodiment, safety position limiter 539 is the banded structure with certain length, end and interim wooden cross arm 510
Connection.Safety position limiter 539 can be connected with as the 1st transmission belt 538 by hook, connector (fitting), buckle, spiro connecting piece etc.
The connector for connecing and detaching is attached with interim wooden cross arm 510.
With reference to 1~Fig. 4 of figure, the controller switching equipment livewire work of one embodiment of the invention is in auxiliary device 500, interim wood
Cross-arm 510 is attached by the 1st lifting moving portion 530 and interim wooden cross arm fixed part 520.That is, interim wooden cross arm fixed part
520 are fixed to by the 1st lifting moving portion 530 and interim wooden cross arm fixed part 520 and newly set electric pole 13.
But controller switching equipment livewire work of the invention is in auxiliary device 500, if the 1st lifting moving portion 530 can only
Interim wooden cross arm 510 is lifted, is not necessarily intended to be mounted between interim wooden cross arm 510 and interim wooden cross arm fixed part 520.That is, facing
When wooden cross arm 510 not by the 1st lifting moving portion 530, but be directly installed to by interim wooden cross arm fixed part 520 and newly set electricity
In line bar 13;It is installed not between interim wooden cross arm 510 and interim wooden cross arm fixed part 520 in 1st lifting moving portion 530
To the other positions for newly setting electric pole 13, the lifting of interim wooden cross arm 510 is controlled.
Fig. 5 is the wire rack of one embodiment of the invention and the perspective sketch map in the 1st lifting moving portion;Fig. 6 is to illustrate this
The concept map of the 1st lifting moving portion operation of invention one embodiment;Fig. 7 one embodiment to illustrate the invention it is solid to electric wire
Determine the concept map that electric wire process is inserted into portion.
Wire rack 540 mounted on the support of the state of interim wooden cross arm 510 to be connected to the new electric wire set on electric pole 13
30.With reference to figure 5, the wire rack 540 of one embodiment of the invention is made of extension 541 and electric wire fixing segments 545.
Extension 541 is extended structure to pass through the 2nd lifting moving portion 550 mounted on horizontal extension portion 511 up and down
It moves up and down.The extension 541 of one embodiment of the invention is by main extension 542, sub- extension 543,544 groups of fixed part
At.
Main extension 542 is connect with lifting moving portion 550, after the power for receiving the 2nd driver 42, is moved by the 2nd lifting
Dynamic portion 550 moves up and down.Sub- extension 543 includes isolation material, is mounted on the main extension of cylindrical shape in the way to insert
Bottom inside 542 makes it that can be moved to the top of main extension 542.
The sub- extension 543 moved up is fixed on main extension 542 by fixed part 544 and extension 541.It is fixed
Portion 544 can be used rotary fixing device, run through device through sub- extension 543 and main extension 542.
When fixed part 544 is using rotary fixing device, son is prolonged by way of rotating fixed part 544 to side
Long portion 543 is fixed on main extension 542, and the connection of sub- extension 543 and main extension 542 can be released by reversely rotating.Such as
Fruit has fixed part 544, after sub- extension 543 is moved to object height, by with 544 stator extension 543 of fixed part
Process adjust the length of extension 541 manually.
If without fixed part 544, screw bolt and nut is set in the interconnecting piece of sub- extension 543 and main extension 542, is led to
Cross the mode for rotating sub- extension 543 to side, sub- extension 543 be fixed on main extension 542, make its can not on move down
It is dynamic;The connection of sub- extension 543 and main extension 542 can be released by reversely rotating sub- extension 543.
Electric wire fixing segments 545 be install electricity lines 30 part, be mounted on sub- extension 543 top.Electric wire fixing segments 545 will
Electric wire 30 is tightly attached on wire rack 540.With reference to figure 7, the electric wire fixing segments 545 of one embodiment of the invention are by holder
546 and sticking department 548 form.
Holder 546 is attached with extension 541, and have can supply lines 30 by opening 546a.Sticking department 548 with
Holder 546 is attached, switch opening 546a.In one embodiment of the invention, 546a is in 546 top of holder, sticking department for opening
548 are mounted on one end of holder 546, rotatable.
When sticking department 548 is rotated to side, the other end that sticking department 548 hangs over holder 546 simultaneously closes off opening 546a.
When (with reference to figure 5) reversely rotates sticking department 548, the other end of the sticking department 548 far from holder 546 opens simultaneously opening 546a.
Electric wire 30 is inserted into electric wire fixing segments by (with reference to figure 7) as described above, while by operating the switch opening 546a of sticking department 546
545 are fixed, or electric wire 30 is removed from electric wire fixing segments 545.
It is mounted with lower roller 547 on holder 546, it can be made to be rotated in specified position, is mounted on sticking department 548
Top roller 549 can be such that it is rotated in specified position.The insertion 546 inside sticking department 548 of holder of electric wire 30 is locked
Under state, the outside of electric wire 30 is contacted with lower roller 547 and top roller 549.That is, electric wire 30 is being inserted into electric wire fixing segments
In the state of 545, electric wire 30 is in rolling contact with electric wire fixing segments 545.
It therefore, can when relative displacement occurring during replacing controller switching equipment, between electric wire fixing segments 545 and electric wire 30
It prevents electric wire 30 from being injured by electric wire fixing segments 545, the connection status for keeping electric wire fixing segments 545 and electric wire 30 can be stablized, simultaneously
It can ensure the smooth movement of electric wire fixing segments 545 or electric wire 30.
2nd lifting moving portion 550 moves up and down wire rack 540.2nd lifting moving portion 550 can individually lift each electric wire
Holder 540.Therefore, the quantity in the 2nd lifting moving portion 550 is determined by the quantity of wire rack 540.With reference to figure 6, the present invention the 2nd
2nd lifting moving portion 550 of embodiment is made of 551 and the 1st driving portion 553 of interim wooden cross arm mounting portion.
Interim wooden cross arm mounting portion 551 is mounted on horizontal extension portion 511.There is folder on interim wooden cross arm mounting portion 551
Minor structure is connected in horizontal extension portion 511, and can be loaded and unloaded.Clip structure in relation to interim wooden cross arm mounting portion 551 can refer to
523 related description of electric pole interconnecting piece, is not repeated herein.
There is guide wire rack 540 to move up and down to lead on the interim wooden cross arm mounting portion 551 of one embodiment of the invention
Rail 552.It is lifted, is had on guide rail 552 extended hollow up and down with being inserted into the state inside guide rail 552 in order to make wire rack 540
Guide-track groove 552a.
If lifting moving portion 550 can be fixed in horizontal extension portion 511, interim wooden cross arm mounting portion 551 includes suitable
Clip structure on interim wooden cross arm fixed part 520 or the structure different from interim wooden cross arm fixed part 520, are not limited to spy
Fixed structure and shape.
2nd driving portion 553 is mounted on interim wooden cross arm mounting portion 551, will be electric after the power for receiving the 2nd driver 42
Line bracket 540 moves up and down.2nd driver 42 is identical as the 1st driver 41, can use general when replacing controller switching equipment operation
The driving devices such as the electric tools such as the electric screw driver used or motor.2nd driving portion 553 of the 2nd embodiment of the invention is by the 2nd
Driving section 554, the 2nd beam barrel 557, the 1st transmission belt 558 composition.
2nd driving section 554 is to be rotated to drive by the 2nd driver 42.In one embodiment of the invention, the 2nd driving section 554
It is made of the 2nd worm screw 555 and the 2nd worm gear 556, there is the 2nd power receiving portion being connect with the 2nd driver 42 in 555 end of the 2nd worm screw
555a。
1st biography of the 2nd driving section 554, the 2nd beam barrel 557, the 2nd band 558 and the 1st driving portion 533 on the 2nd driving portion 553
Dynamic portion 534, the 1st beam barrel 537, the structure of the 1st transmission belt 538 are identical, omit related description herein.
According to the worm gear arrangement that the 2nd worm screw 555 and the 2nd worm gear 556 form, it can prevent the weight because of electric wire 30 etc. from causing
Wire rack 540 moves down.In the state that the end of 2nd driver 42 is connect with the 2nd power receiving portion 555a, by by
2 drivers 42 pull up or move down wire rack 540 to side or reverse rotation.
Controller switching equipment livewire work auxiliary device 500 according to the present invention is swashed using above-mentioned 1st driver 41 or the 2nd
The power of device 42 is encouraged, the height of interim wooden cross arm 510, the height of wire rack 540, frame can be automatically adjusted in wire rack 540
On electric wire 30 height.
It illustrates further:Using the 1st driver 41, the 1st movement is carried out, makes interim wooden cross arm 510 and mounted on facing
When wooden cross arm 510 on wire rack 540 closer to or far from electric wire 30;Using the 2nd driver 42, the 2nd movement is carried out,
Make wire rack 540 closer to or far from electric wire 30.By adjusting the height of sub- extension 543, fine tuning is connected to sub- extension
The overall length of the height of electric wire fixing segments 545 in portion 543 or scalable adjustment wire rack 540.
According to the present invention, the 1st driver 41 or the 2nd driver 42 can use the electricity for being generally used for replacing controller switching equipment
The electric tools such as brill, electric screw driver, staff is without specially preparing the electric device needed for mobile wire rack 540
Easily realize.
According to the present invention supporting electric wire 30 can be moved up and down using the electric power of the 1st driver 41 or the 2nd driver 42
The wire rack 540 of weight moves up and down electric wire 30 without using pulley etc. by tractive force, and livewire work is made to become more light
Pine.
According to the present invention, the 1st driver 41 and the 1st lifting moving portion 530, the 2nd driver 42 and the 2nd lifting moving are utilized
Portion 550 is accurately put into object height with certain speed movement wire rack 540 or electric wire 30.
The controller switching equipment livewire work of the present invention of following explanation above structure newly sets electric pole with auxiliary device 500 ---
The controller switching equipment livewire work method of the present invention.
It in the present invention, newly sets and PIN cross-arms 23 is installed on electric pole 13, PIN cross-arms 23, which are that common cross-arm is horizontally arranged, to be formed.
Common cross-arm is different from multiple insulators and is all installed to the new extended arm for setting 13 side of electric pole, it is insulator newly to set electricity
Centered on line bar 13, it is evenly distributed on the cross-arm of the new both sides for setting electric pole.If PIN cross-arms 23 are the structure of common cross-arm,
Staff can be uniformly distributed in the space between the LP insulators 25 of its both sides centered on newly to set electric pole 13 and carry out
The livewire work of PIN cross-arms 23 is installed.
The flow chart of Fig. 8 controller switching equipment livewire work methods of one embodiment to illustrate the invention.
With reference to figure 8, the controller switching equipment livewire work method of one embodiment of the invention includes between having set electric pole 10
30 circuit of electric wire on set up and newly set the stage S1 of electric pole 13, interim wooden cross arm 510 is fixed to newly sets the rank of electric pole 13
Section S2, the stage S3 that the wire rack 540 on interim wooden cross arm 510 is moved up to 30 direction of electric wire, by electric wire
30 are fixed on stage S4 on the wire rack 540 on interim wooden cross arm 510, by interim wooden cross arm 510 or electric wire branch
Frame 540 is moved further up, and electric wire 30 is placed in stage S5 on 23 predetermined mounting height of PIN cross-arms, by PIN cross-arms 23
It is installed to the new stage S6 set on electric pole 13, interim wooden cross arm 510 or wire rack 540 is downward to 23 direction of PIN cross-arms
Mobile stage S7, the stage S8 that the electric wire 30 being connect with wire rack 540 is moved to PIN cross-arms 23 and by interim wooden cross arm
510 from the stage S9 for newly setting electric pole 13 and removing.
Fig. 9 is to illustrate electric between having set electric pole in the controller switching equipment livewire work method of one embodiment of the invention
The concept map of electric pole process is newly set on line circuit;Figure 10 is the controller switching equipment livewire work method of one embodiment of the invention
In, illustrate interim wooden cross arm being fixed on the new concept map for setting electric pole process;Figure 11 is the distribution of one embodiment of the invention
In equipment live operational method, illustrate the concept map that wire rack is moved up to process to electric wire direction.
Figure 12 is in the controller switching equipment livewire work method of one embodiment of the invention, and explanation will be wired to and be mounted on
The concept map of the wire rack process of interim wooden cross arm;Figure 13 is the controller switching equipment livewire work method of one embodiment of the invention
In, illustrate to move up wire rack, makes the concept map for the process that electric wire is placed on the predetermined mounting height of PIN cross-arms;Figure
14 newly set electric pole mistake in the controller switching equipment livewire work method of one embodiment of the invention, to illustrate PIN cross-arms being fixed on
The concept map of journey.
Figure 15 is to illustrate wire rack is horizontal to PIN in the controller switching equipment livewire work method of one embodiment of the invention
The LP insulators direction of load moves down the concept map of process;Figure 16 is the controller switching equipment livewire work of one embodiment of the invention
In method, illustrate the concept map to LP insulator moving process by electric wire;Figure 17 is the controller switching equipment of one embodiment of the invention
In livewire work method, illustrate interim wooden cross arm from the concept map for newly setting electric pole disassembly process.
With reference to figure 9, the side for the stage S1 that electric pole 13 is newly set on 30 circuit of electric wire between having set electric pole 10 is realized
Method:It has set to organize to stand on 30 circuit of electric wire between electric pole 13 in a pair and has newly set electric pole 13.
With reference to figure 10, the method that interim wooden cross arm 510 is fixed on the new stage S2 for setting electric pole 13 is realized:It will interim wood
Cross-arm fixed part 520, which is fixed on, newly to be set on electric pole 13, and the 1st lifting moving portion 530 is fixed on interim wooden cross arm fixed part
520, the 1st lifting moving portion 530 and interim wooden cross arm 510 are connected, the 2nd lifting moving portion 550 and wire rack 540 are fixed on
On interim wooden cross arm 510, keep its position corresponding with mounted LP insulators 22.
A pair of adjacent electric wire 30 set between electric pole 10 such as Fig. 9 is bent downwardly, therefore electric wire 30 sets electric pole newly
Under PIN cross-arms 23 on 13.And interim wooden cross arm 510 is further below, i.e., below electric wire 30.That is, by interim wooden cross arm 510
Mounted on when newly setting on electric pole 13, wire rack 540 will be under electric wire 30.
Sequence when connecting interim wooden cross arm 510 and the 1st lifting moving portion 530 is first to be mounted on vertical extensions 513
1st lifting moving portion 530, behind 513 top of vertical extensions connection horizontal extension portion 511, in horizontal extension portion 511 and vertically
Mounting bracket 515 between extension 513.
The sequence of mounting bracket 515 between horizontal extension portion 511 and vertical extensions 513:Chaining part 516 is mounted on water
After on flat extension, the top of holder 515 is mounted on chaining part 516 so that it can rotate, the lower part peace of holder 515
So that it can by loading and unloading on the fasteners such as the lifting bolt mounted in 513 lower part of vertical extensions.
The sequence 2nd lifting moving portion 550 and wire rack 540 being fixed on interim wooden cross arm 510:First by the 2nd liter
Drop moving portion 550 is fixed on interim wooden cross arm 510, then wire rack 540 is connected in the 2nd lifting moving portion 550.Also may be used
After first wire rack 540 to be connected in the 2nd lifting moving portion 550, then the 2nd lifting moving portion 550 is fixed on temporarily
On wooden cross arm 510.
Also it can realize and interim wooden cross arm 510 is fixed on the new method for setting the stage S2 on electric pole 13:The 2nd liter will be equipped with
The interim wooden cross arm 510 of drop moving portion 550 and wire rack 540 is connected to the 1st lifting moving portion 530 or interim wooden cross arm is fixed
Portion 520.
With reference to figure 11, the stage S3 for moving up interim wooden cross arm 510 or the 3rd wire rack 540 to electric wire 30 is realized
Method:Staff is moved up sub- extension 543 to electric wire 30 by way of manual operation.
Also the method that can realize the stage S3 for moving up interim wooden cross arm 510 or wire rack 540 to electric wire 30:Root
According to operating condition or the convenience of staff, by the 1st driver 41 and the 1st lifting moving portion 530, only by interim wooden cross arm
510 move up;It, only will be on interim wooden cross arm 510 or by the 2nd driver 42 and the 2nd lifting moving portion 550
Wire rack 540 moves up.
Also the method that can realize the stage S3 for moving up interim wooden cross arm 510 or wire rack 540 to electric wire 30:Root
, can be by the 1st driver 41 and the 1st lifting moving portion 530 according to operating condition or the convenience of staff, it only will interim wood cross
Load 510 moves up, and by the 2nd driver 42 and the 2nd lifting moving portion 550, will only be mounted on interim wooden cross arm 510
Wire rack 540 move up.
Also the method that can realize the stage S3 for moving up interim wooden cross arm 510 or wire rack 540 to electric wire 30:Root
It, can be by the 1st driver 41 and the 1st lifting moving portion 530, by interim wooden cross arm according to operating condition or the convenience of staff
510 move up with staff through manual operation, and sub- extension 543 is moved up to 30 direction of electric wire.
Also the method that can realize the stage S3 for moving up interim wooden cross arm 510 or wire rack 540 to electric wire 30:Root
According to operating condition or the convenience of staff, can will be mounted on interim by the 2nd driver 42 and the 2nd lifting moving portion 550
The wire rack 540 of wooden cross arm 510 is moved up with staff by manual operation, by sub- extension 543 to 30 side of electric wire
To movement.
Also the method that can realize the stage S3 for moving up interim wooden cross arm 510 or wire rack 540 to electric wire 30:Root
It, can be by the 1st driver 41 and the 1st lifting moving portion 530, by interim wooden cross arm according to operating condition or the convenience of staff
510 move up, by the 2nd driver 42 and the 2nd lifting moving portion 550, by the electric wire branch on interim wooden cross arm 510
Frame 540 moves up and staff is by manual operation, and sub- extension 543 is moved to 30 direction of electric wire.
The present invention explanation in, wire rack 540 is moved up or down, include by the main extension 542 of movement,
The mobile wire rack 540 including main extension 542 and sub- extension 543 is whole, or only moves on wire rack 540
The embodiment of the sub- extension in portion 543, the part for the electric wire fixing segments 545 being connect with electric wire 30 in wire rack 540 include
The process of 540 upper height of wire rack is adjusted upward or downward.
That is, in the explanation of the present invention, mobile wire rack 540 includes by the 2nd driver 42 and the 2nd lifting moving portion
Only the embodiment, synthesis of mobile sub- extension 543 are moved in 550 movement wire rack, 540 whole embodiment, wire rack 540
The embodiment of dynamic wire rack 540 and mobile sub- 543 process of extension.
Therefore, even if the whole and mobile sub- extension 543 of not specified mobile wire rack 540, explanation of the invention
In to mention mobile wire rack 540 just refer to one of above three embodiments.
In the state of the opening 546a for opening holder 546 top, into be about to interim wooden cross arm 510 or wire rack 540 to
When the stage S3 that 30 direction of electric wire moves up, after completing the stage S3 for moving up wire rack 540 to 30 direction of electric wire,
Electric wire 30 is entered by the 546a that is open inside holder 546.
With reference to figure 12, realize stage electric wire 30 being fixed on the wire rack 540 on interim wooden cross arm 510
The method of S4:Locking electric wire 30 enters internal 546 sticking department 548 of holder through the 546a that is open, that is, is opened with the block of sticking department 548
Mouth 546a.
Interim wooden cross arm 510 or wire rack 540 are moved up, it is high that electric wire 30 is placed in the predetermined installation of PIN cross-arms 23
Stage S5 on degree is to ensure that the new process for setting and installing space needed for PIN cross-arms 23 on electric pole 13.
With reference to figure 13, interim wooden cross arm 510 or wire rack 540 are moved further up, electric wire 30 are placed in by realization
The method of stage S5 on 23 predetermined mounting height of PIN cross-arms:Upwards by the 1st driver 41 and the 1st lifting moving portion 530
Mobile interim wooden cross arm 510, and wire rack 540 is moved up by the 2nd driver 42 and the 2nd lifting moving portion 550.
Also the method that can realize the stage S5 being placed in electric wire 30 on 23 predetermined mounting height of PIN cross-arms:According to operation
The convenience of condition and staff, can be only by moving interim wooden cross arm by the 1st driver 41 and the 1st lifting moving portion 530
510, or wire rack 540 is moved by the 2nd driver 42 and the 2nd lifting moving portion 550, or be manually operated by staff
Sub- extension 543 is moved up to 30 direction of electric wire.
Also the method that can realize the stage S5 being placed in electric wire 30 on 23 predetermined mounting height of PIN cross-arms:According to operation
The convenience of condition or staff, it is by the 1st driver 41 and the 1st lifting moving portion 530, interim wooden cross arm 510 is upward
It is mobile;And staff is moved sub- extension 543 to 30 direction of electric wire by manual operation.
Also the method that can realize the stage S5 being placed in electric wire 30 on 23 predetermined mounting height of PIN cross-arms:According to operation
The convenience of condition or staff can will be mounted on interim wooden cross arm by the 2nd driver 42 and the 2nd lifting moving portion 550
510 wire rack 540 moves up;And staff is moved sub- extension 543 to 30 direction of electric wire by manual operation
It is dynamic.
Also the method that can realize the stage S5 being placed in electric wire 30 on 23 predetermined mounting height of PIN cross-arms:According to operation
The convenience of condition or staff, can by the 1st driver 41 and the 1st lifting moving portion 530, by interim wooden cross arm 510 to
Upper movement, and by the 2nd driver 42 and the 2nd lifting moving portion 550, by the electric wire branch on interim wooden cross arm 510
Frame 540 moves up and staff is by manual operation, and sub- extension 543 is moved to 30 direction of electric wire.
Electric wire 30 is placed in the stage S5 on 23 predetermined mounting height of PIN cross-arms, it is assumed that the predetermined installation of PIN cross-arms 23
It is highly constant, the distance of electric wire 30 is moved up according to a pair of adjacent degree of sag for having set electric wire 30 between electric pole 10, that is,
Interim wooden cross arm 510 is fixed on and the height of interim wooden cross arm 510 is installed in the new stage S2 set on electric pole 13 is varied from.
Staff predicts there is an error when 30 degree of sag of electric wire, or interim wooden cross arm 510 and main extension 542 is maximum to moving up
Dynamic sum of the distance less than electric wire 30 move up apart from when, sub- extension 543 can be used.For example, staff predicts electric wire
30 sagging 1m, when the maximum of interim wooden cross arm 510 and main extension 542 being moved up sum of the distance being set as 1m, even if electric
Sagging 30 reality of line is 1.5m, and staff can be smoothly completed by the way that sub- extension 543 is moved up 0.5m again by electric wire 30
The stage S5 being placed on the predetermined mounting height of PIN cross-arms.
With reference to figure 14, the method for realization stage S6 of installation PIN cross-arms 23 on newly setting electric pole 13:Electric wire 30 is placed in
Stage S5 on 23 predetermined mounting height of PIN cross-arms, using reserved working space, installation includes PIN iron cross arms 24 and more
The PIN cross-arms of a LP insulators 25.
The stage S6 that PIN cross-arms 23 are installed on newly setting electric pole 13, after first installing PIN iron cross arms 24, by multiple LP
Insulator 25 is installed on PIN iron cross arms 24, or the PIN iron cross arms equipped with multiple LP insulators 25 are installed to and newly set electric wire
Bar 13.
With reference to figure 15, the stage for moving down interim wooden cross arm 510 or wire rack 540 to PIN cross-arms direction is realized
The method of S7:Staff will be interim using the 1st driver 41 and the 1st lifting moving portion 530 in the place far from electric wire 30
Wooden cross arm 510 is automatic and remotely moves down.
Also it can realize the stage S7's for moving down interim wooden cross arm 510 or wire rack 540 to 23 direction of PIN cross-arms
Method:According to operating condition or the convenience of staff, only by the 2nd driver 43 and the 2nd lifting moving portion 550 to moving up
Dynamic interim wooden cross arm 510 or staff are moved sub- extension 543 to 30 direction of electric wire by manual operation.
Also it can realize the stage S7's for moving down interim wooden cross arm 510 or wire rack 540 to 23 direction of PIN cross-arms
Method:According to operating condition or the convenience of staff, by the 1st driver 41 and the 1st lifting moving portion 530, will only face
When wooden cross arm 510 move down, and by the 2nd driver 42 and the 2nd lifting moving portion 550, it is horizontal will to be only mounted on interim wood
Wire rack 540 in load 510 moves up.
Also it can realize the stage S7's for moving down interim wooden cross arm 510 or wire rack 540 to 23 direction of PIN cross-arms
Method:It will be interim by the 1st driver 41 and the 1st lifting moving portion 530 according to operating condition or the convenience of staff
Wooden cross arm 510 moves down and staff is by manual operation, and sub- extension 543 is moved down to 30 direction of electric wire.
Also it can realize the stage S7's for moving down interim wooden cross arm 510 or wire rack 540 to 23 direction of PIN cross-arms
Method:It will be installed by the 2nd driver 42 and the 2nd lifting moving portion 550 according to operating condition or the convenience of staff
The wire rack 540 of interim wooden cross arm 510 move down and staff by manual operation, by sub- extension 543 to
30 direction of electric wire moves down.
Also it can realize the stage S7's for moving down interim wooden cross arm 510 or wire rack 540 to 23 direction of PIN cross-arms
Method:It will be interim by the 1st driver 41 and the 1st lifting moving portion 530 according to operating condition or the convenience of staff
Wooden cross arm 510 moves down, and by the 2nd driver 42 and the 2nd lifting moving portion 550, will be mounted on interim wooden cross arm 510
On wire rack 540 move down and staff by manual operation, by sub- extension 543 to 30 direction of electric wire to
Lower movement.
With reference to figure 16, the side for the stage S8 for moving the electric wire 30 being connect with wire rack 540 to PIN cross-arms 23 is realized
Method:After the multiple electric wires 30 being connect with multiple wire racks 540 are adjacent to and are fixed on multiple LP insulators 25, electricity is released
Line 30 and wire rack 540 connect.Refer to fixed to LP insulators 25 by electric wire 30, with connections such as rubber cable, adhesive tape, buckles
Electric wire 30 is fixed to LP insulators 25 by part.
The method for releasing the connection of electric wire 30 and wire rack 540 is that spin locking portion 548 opens opening 546a, passes through
Opening 546a pulls out electric wire 30 to outside holder 546.
With reference to figure 17, realize interim wooden cross arm 510 from the method for newly setting the stage S9 removed on electric pole 13:By
After 2 lifting moving portions 550 and wire rack 540 are removed from interim wooden cross arm 510, by interim wooden cross arm 510 from interim wood
It is removed in cross-arm fixed part 520 or the 1st lifting moving portion 530, by the 1st lifting moving portion 530 from interim wooden cross arm fixed part
520 remove, then interim wooden cross arm fixed part 520 is removed from new set on electric pole 13.
Also it can realize interim wooden cross arm 510 from the method for newly setting the stage S9 removed on electric pole 13:The 2nd will be equipped with
The interim wooden cross arm 510 of lifting moving portion 550 and wire rack 540 is removed from new set on electric pole 13.
According to the method for controller switching equipment livewire work as described above of the invention, the flow as shown in Fig. 9~Figure 17 can
Using controller switching equipment livewire work easily electric pole is newly set with auxiliary device 500.
About multiple LP insulators 25, each stage shown in unified applicable Figure 10~Figure 16, by once will be interim
What the stage S3 that wooden cross arm 510 or wire rack 540 are moved up to 30 direction of electric wire extremely moved electric wire 30 to PIN cross-arms 23
The process of stage S8 can install PIN cross-arms 23 in new set on electric pole 13.
About each LP insulators 25, by separately from by interim wooden cross arm 510 or wire rack 540 to 30 direction of electric wire
The process of the stage S3 moved up to the stage S8 for moving from electric wire 30 to PIN cross-arms 23, that is, being applicable in by multiplicating will
The stage S3 that interim wooden cross arm 510 or wire rack 540 are moved up to 30 direction of electric wire extremely moves electric wire 30 to PIN cross-arms 23
Dynamic stage S8 installs multiple LP insulators 25 successively.
According to the present invention interim wooden cross arm 510 is automatically adjusted using the 1st driver 41 or 42 electric power of the 2nd driver
Highly, the height of wire rack 540, the height of the electric wire 30 moved to 540 direction of wire rack, easily realize and newly set electric pole
Operation.
According to the present invention, the height of 540 entirety of interim wooden cross arm 510 and wire rack can be not only adjusted with multistage, may be used also
543,3 sections of the sub- extension by moving up and down live wire fixed part 545 in wire rack 540 adjust electric wire fixing segments 545 or
The height of electric wire 30.
According to the present invention, staff selectively adjusts the height of interim wooden cross arm 510 according to operating condition or convenience
The whole height of degree, wire rack 540, the height of sub- extension 543, you can easily carry out newly setting electric pole operation.
According to the present invention, using the 1st driver 41 or the 2nd driver 42, staff can be in the place far from electric wire 30
Electric wire 30 is moved on PIN cross-arms 23, can easily ensure PIN cross-arms 23 being installed to needed for new set on electric pole 13
Livewire work space, at the same can be to avoid installation PIN cross-arms 23 when, staff is in direct contact caused by electric wire 30 dangerous.
According to the present invention, multiple wire racks 540 have been installed in the state of interim wooden cross arm 510, are moved up interim
Wooden cross arm 510, the trouble that can be one by one moved to avoid wire rack 540 keep the displacement that multiple wire racks 540 move up equal
It is identical.
The present invention is the explanation carried out by embodiment in drawing, but this only illustrates, if it is having this
The people of technical field relevant knowledge, it should can understand other implementations of can develop from the present invention various deformation and ad eundem
Example.Therefore, technical protection scope of the invention should be following patent claim.
Claims (3)
1. a kind of controller switching equipment livewire work method,
About using including interim wooden cross arm, be fixed on above-mentioned interim wooden cross arm newly setting the interim wooden cross arm on electric pole and fixing
Portion, is mounted on above-mentioned interim wooden cross arm, the electric wire of supporting electric wire at the 1st lifting moving portion for moving up and down above-mentioned interim wooden cross arm
The controller switching equipment livewire work of holder, the 2nd lifting moving portion for individually lifting each said wires holder newly sets electricity with auxiliary device
The controller switching equipment livewire work method of line bar,
Newly set the stage of electric pole between electric pole on said wires circuit including having set;
Above-mentioned interim wooden cross arm is fixed on the above-mentioned new stage for setting electric pole;
Said wires are connected to the stage of the wire rack on above-mentioned interim wooden cross arm;
Move up above-mentioned interim wooden cross arm and said wires holder, by said wires be placed in the predetermined mounting height of PIN cross-arms it
On stage;
Above-mentioned PIN cross-arms are installed to the above-mentioned new stage for setting electric pole;
The stage that said wires holder is moved down to above-mentioned PIN cross-arms direction;
And the said wires for being connected to said wires holder are moved to the stage of above-mentioned PIN cross-arms;
It is that above-mentioned 1st lifting moving portion receives to come from the 1st driver by the method that above-mentioned interim wooden cross arm moves up or down
Power after, move up and down above-mentioned interim wooden cross arm;It is by the method that said wires holder moves up or down, the above-mentioned 2nd
After lifting moving portion receives the power from the 2nd driver, said wires holder is moved up and down;
Above-mentioned interim wooden cross arm and said wires holder are moved up, said wires are placed in the predetermined mounting height of PIN cross-arms
On stage, including by above-mentioned 1st driver and above-mentioned 1st lifting moving portion, move up above-mentioned interim wooden cross arm
Process and by above-mentioned 2nd driver and above-mentioned 2nd lifting moving portion, promotes the process of wire rack to realize.
2. controller switching equipment livewire work method according to claim 1, which is characterized in that
Said wires are fixed to the stage of said wires holder,
Include that in the state that said wires insertion has the internal stent of said wires holder, above-mentioned holder is closed with sticking department
The process of opening;
Said wires are moved to the stage of above-mentioned PIN cross-arms,
Include that electric wire is pulled out by process to above-mentioned bracket outer by above-mentioned opening.
3. controller switching equipment livewire work method according to claim 1, which is characterized in that
Above-mentioned PIN cross-arms are horizontally arranged common cross-arms.
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20140006513 | 2014-01-20 | ||
KR1020140069775A KR101473823B1 (en) | 2014-01-20 | 2014-06-09 | Method for hot line work of power distribution equipment |
KR10-2014-0069775 | 2014-06-09 | ||
PCT/KR2015/005797 WO2015190814A1 (en) | 2014-06-09 | 2015-06-09 | Power distribution facility live-line working method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106463938A CN106463938A (en) | 2017-02-22 |
CN106463938B true CN106463938B (en) | 2018-09-07 |
Family
ID=52679199
Family Applications (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201580030633.XA Active CN106463938B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
CN201580030707.XA Active CN106463940B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the method for carrying out controller switching equipment livewire work using it |
CN201580030649.0A Active CN106463939B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the controller switching equipment livewire work method for utilizing this device |
CN201580030710.1A Active CN106463941B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
Family Applications After (3)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201580030707.XA Active CN106463940B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the method for carrying out controller switching equipment livewire work using it |
CN201580030649.0A Active CN106463939B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the controller switching equipment livewire work method for utilizing this device |
CN201580030710.1A Active CN106463941B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
Country Status (2)
Country | Link |
---|---|
KR (12) | KR101473822B1 (en) |
CN (4) | CN106463938B (en) |
Families Citing this family (34)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101631916B1 (en) | 2015-09-14 | 2016-06-20 | 탑이앤지 주식회사 | Method for changing power distribution line in hot line |
KR101616484B1 (en) | 2015-09-21 | 2016-04-28 | (주)우신전기기술사사무소 | Method for changing power distribution line in hot line |
CN106545213A (en) * | 2015-09-23 | 2017-03-29 | 国网辽宁省电力有限公司本溪供电公司 | A kind of adjustable bearing pole girdle ring |
CN107288406A (en) * | 2016-03-30 | 2017-10-24 | 国网辽宁省电力有限公司本溪供电公司 | A kind of adjustable bearing pole girdle ring |
CN105762702B (en) * | 2016-04-01 | 2017-08-04 | 中国南方电网有限责任公司超高压输电公司南宁局 | The method of replacing ± 800kV DC power transmission line L insulator strings |
KR101757195B1 (en) * | 2016-10-11 | 2017-07-11 | 주식회사 성진 | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work |
CN107437712A (en) * | 2016-12-30 | 2017-12-05 | 广州程科电子科技有限公司 | A kind of durable electric insulation post |
KR101864309B1 (en) | 2017-01-19 | 2018-06-05 | 삼성기술감리 주식회사 | Apparatus for changing power distribution line in hot line |
KR101889080B1 (en) | 2017-02-20 | 2018-08-16 | 주식회사진흥기업 | live jumper wire wirelessly disconnect and connect method |
CN107086488A (en) * | 2017-04-28 | 2017-08-22 | 国网山东省电力公司青岛供电公司 | A kind of charged for replacement overhead transmission line straight line pole cross-arm, insulator arrangement |
CN107039919A (en) * | 2017-05-05 | 2017-08-11 | 国网江苏省电力公司常州供电公司 | A kind of wire-binding device |
CN107504343A (en) * | 2017-08-11 | 2017-12-22 | 国网浙江台州市黄岩区供电公司 | Stand transformer base leveling device |
CN110088171B (en) | 2017-10-12 | 2022-03-04 | 株式会社吴羽 | Continuous polymerization apparatus and method for continuously producing polymer |
JP7089791B2 (en) * | 2017-12-18 | 2022-06-23 | 株式会社永木精機 | Insulator separation method and direction change tool, pillar lifting device, insulator support tool and utility pole fixer used in this method. |
CN108321753A (en) * | 2017-12-28 | 2018-07-24 | 青岛九州汇德新能源有限公司 | A kind of solar energy system power supply support device |
CN108155601A (en) * | 2018-01-08 | 2018-06-12 | 国网辽宁省电力有限公司鞍山供电公司 | A kind of method that on-load straight line pole changes tension-resistant rod |
CN108258617A (en) * | 2018-01-16 | 2018-07-06 | 国网新疆电力公司塔城供电公司 | A kind of more changing device that formula overhanging golden tool is twisted for transmission line of electricity aerial condutor |
CN108683122B (en) * | 2018-06-08 | 2020-07-28 | 国网山东省电力公司青岛供电公司 | Auxiliary device and method for sharing straight line rod of corridor in live migration |
KR101955155B1 (en) * | 2018-07-11 | 2019-03-06 | 대원전기 주식회사 | Uninterruptible power method and Indirect live lifting device for Electronic pole for power line |
KR102112471B1 (en) * | 2018-11-30 | 2020-05-19 | 한국전력공사 | Method for hot line work |
KR102321043B1 (en) | 2018-12-12 | 2021-11-03 | 주식회사 중앙백신연구소 | A promoter being expressed in Kluyveromyces marxianus strain and the gene expression system using thereof |
KR102273339B1 (en) * | 2019-06-10 | 2021-07-06 | 한국전력공사 | Wire support device supporting switchgear lead wire or jumper wire |
KR102650799B1 (en) * | 2019-12-18 | 2024-03-26 | 한국전력공사 | Auxiliary apparatus for hot line work of power distribution equipment and method for hot line work of power distribution equipment using thereof |
CN111456520B (en) * | 2020-03-22 | 2021-04-02 | 徐宏坤 | Distribution line building device and installation method |
KR102173375B1 (en) * | 2020-03-30 | 2020-11-03 | 김정호 | Uninterruptible power method and lndirect live lifting device for Electronic polefor power line |
KR102173377B1 (en) * | 2020-06-10 | 2020-11-03 | 김정호 | Uninterruptible power method of utilization electric power line device |
KR102173378B1 (en) * | 2020-06-10 | 2020-11-03 | 김정호 | electric power line device for Uninterruptible power method |
CN111987639A (en) * | 2020-08-04 | 2020-11-24 | 中国电建集团河南工程有限公司 | Construction method for replacing tension porcelain insulator |
CN111910982A (en) * | 2020-08-05 | 2020-11-10 | 国网黑龙江省电力有限公司伊春供电公司 | Transmission line ground clearance promotes cross arm |
KR102240478B1 (en) * | 2020-09-22 | 2021-04-16 | 대원전기 주식회사 | Insulator clip for indirect live wire and LP insulator replacement indirect live wire method using the same |
KR102236410B1 (en) * | 2020-10-14 | 2021-04-05 | 이종학 | Wire installing method |
CN112551258B (en) * | 2020-11-18 | 2023-01-24 | 广东电网有限责任公司 | Cable support device and electric power support equipment |
CN112366603B (en) * | 2020-11-18 | 2022-05-24 | 广东电网有限责任公司 | Electric power supporting equipment |
KR20220085571A (en) | 2020-12-15 | 2022-06-22 | 한국전력공사 | Fixing device for distribution facility and fixing method using the same |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102510029A (en) * | 2011-11-22 | 2012-06-20 | 上海市电力公司 | Ground potential electrified bar cutter device changing method |
CN103510739A (en) * | 2013-10-24 | 2014-01-15 | 国网湖南省电力公司带电作业中心 | Multifunctional combinatorial insulation cross arm |
Family Cites Families (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4188477B2 (en) * | 1999-02-04 | 2008-11-26 | 株式会社中電工 | How to remove an imaginary ground wire |
KR20050103700A (en) * | 2004-04-27 | 2005-11-01 | 양희성 | A |
KR100934083B1 (en) * | 2007-11-05 | 2009-12-24 | 양희성 | Jumper Wire Fixture |
JP5306031B2 (en) * | 2009-04-13 | 2013-10-02 | 中国電力株式会社 | Indirect hot tool support |
FI125939B (en) * | 2010-12-30 | 2016-04-15 | Meclimb Oy | Method and apparatus for transporting tools to a workplace along an elongated piece and use of the apparatus |
KR101218710B1 (en) * | 2011-01-31 | 2013-01-09 | 서광전기통신공사(주) | The cable fixing bar provisionally installation equipment for work power distribution line |
KR101106236B1 (en) * | 2011-06-28 | 2012-01-19 | 주식회사 지이플러스 | Apparatus and method for live wire using trane truck |
KR101344289B1 (en) * | 2012-04-27 | 2013-12-23 | 임용호 | The pole fittings changing method use lifting apparatus |
KR101243860B1 (en) * | 2012-04-27 | 2013-03-20 | 임용호 | The changing device of lp insualtor for power distribution line |
KR101254577B1 (en) * | 2012-11-21 | 2013-04-15 | 서광전기통신공사(주) | The cable fixing bar provisionally installation equipment for work power distribution line |
KR101275111B1 (en) * | 2013-02-13 | 2013-06-17 | 임용호 | Replacement method for power distribution equipment of direct live wire for double insulation |
-
2014
- 2014-06-09 KR KR1020140069772A patent/KR101473822B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069770A patent/KR20150087785A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069767A patent/KR20150087782A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069769A patent/KR20150087784A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069759A patent/KR20150087780A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069768A patent/KR20150087783A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069775A patent/KR101473823B1/en active IP Right Grant
- 2014-06-09 KR KR20140069760A patent/KR101473820B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069758A patent/KR20150087779A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069771A patent/KR101592964B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069766A patent/KR20150087781A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069763A patent/KR101473821B1/en active IP Right Grant
-
2015
- 2015-06-09 CN CN201580030633.XA patent/CN106463938B/en active Active
- 2015-06-09 CN CN201580030707.XA patent/CN106463940B/en active Active
- 2015-06-09 CN CN201580030649.0A patent/CN106463939B/en active Active
- 2015-06-09 CN CN201580030710.1A patent/CN106463941B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102510029A (en) * | 2011-11-22 | 2012-06-20 | 上海市电力公司 | Ground potential electrified bar cutter device changing method |
CN103510739A (en) * | 2013-10-24 | 2014-01-15 | 国网湖南省电力公司带电作业中心 | Multifunctional combinatorial insulation cross arm |
Also Published As
Publication number | Publication date |
---|---|
KR20150087783A (en) | 2015-07-30 |
CN106463941A (en) | 2017-02-22 |
KR101473822B1 (en) | 2014-12-18 |
CN106463940B (en) | 2018-09-11 |
KR101473821B1 (en) | 2014-12-18 |
KR101473823B1 (en) | 2014-12-18 |
KR20150087785A (en) | 2015-07-30 |
KR20150087786A (en) | 2015-07-30 |
CN106463939A (en) | 2017-02-22 |
CN106463940A (en) | 2017-02-22 |
CN106463941B (en) | 2018-09-07 |
CN106463938A (en) | 2017-02-22 |
KR20150087782A (en) | 2015-07-30 |
KR101592964B1 (en) | 2016-02-25 |
KR101473820B1 (en) | 2014-12-18 |
KR20150087784A (en) | 2015-07-30 |
CN106463939B (en) | 2018-09-11 |
KR20150087779A (en) | 2015-07-30 |
KR20150087780A (en) | 2015-07-30 |
KR20150087781A (en) | 2015-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106463938B (en) | Controller switching equipment livewire work method | |
CN106827603B (en) | A kind of wheel production steel ring automatic grabbing device | |
CN108599007A (en) | A kind of apparatus and method of high-tension line unmanned plane installation pulley insulating cord | |
CN107370079A (en) | It is a kind of to connect and hook the livewire work method of clip lead | |
CN111115523A (en) | Special logistics support vehicle for electric power operation and maintenance | |
CN105401873A (en) | Insulating elevator | |
CN109702707A (en) | A kind of distribution network live line work robot | |
CN108462117A (en) | A kind of skyscraper cable-laying gear and its application method | |
CN108150786A (en) | A kind of environment supervision instrument stent | |
CN206669659U (en) | A kind of multi-angle LED installs equipment | |
CN108996400B (en) | Battery box hoisting accessory | |
CN106144974A (en) | A kind of bucket lowering or hoisting gear | |
CN209748055U (en) | insulating rope sideslip prevention device for feeding | |
CN108178062A (en) | A kind of natural gas line installation gripping arranging apparatus | |
US20170260745A1 (en) | Hanging Three Dimensional Grid System For Lighting, Data, and Power | |
CN109066453B (en) | Special tool for repairing overhead lightning conductor of power transmission line | |
CN207719617U (en) | A kind of power distribution cabinet with movable support | |
CN201040702Y (en) | Lifting device for TV set | |
CN105071307B (en) | A kind of device of auxiliary connection and the method that wiring is carried out using the device | |
CN207006069U (en) | A kind of infrared illumination system structure of liftable and the anglec of rotation | |
CN217296995U (en) | Cigarette rack lifting device | |
CN206979135U (en) | Self-balancing wall covering rack | |
CN218650222U (en) | Flue-cured tobacco goes up heatable brick bed device | |
CN205442450U (en) | Long -range controlled tower crane device | |
CN205384909U (en) | Electric power cable recovery unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |