KR101757195B1 - Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work - Google Patents
Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work Download PDFInfo
- Publication number
- KR101757195B1 KR101757195B1 KR1020160131108A KR20160131108A KR101757195B1 KR 101757195 B1 KR101757195 B1 KR 101757195B1 KR 1020160131108 A KR1020160131108 A KR 1020160131108A KR 20160131108 A KR20160131108 A KR 20160131108A KR 101757195 B1 KR101757195 B1 KR 101757195B1
- Authority
- KR
- South Korea
- Prior art keywords
- wire
- insulator
- electric
- moving mechanism
- jumper
- Prior art date
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
- H02G1/04—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/05—Suspension arrangements or devices for electric cables or lines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/20—Spatial arrangements or dispositions of lines or cables on poles, posts or towers
Landscapes
- Electric Cable Installation (AREA)
Abstract
본 발명은 무정전 배전공사에 이용하는 고정식 가완목 장치 및 공법에 관한 것으로, 더욱 상세하게는 배전선로의 기존 핀장주 또는 내장주에서 완철 아래에 절연체로 제작된 고정식 가완목으로 장주를 구성하고, 전선이동기구 또는 현수애자연결구를 이용하여 선로를 완철 상에서 고정식 가완목의 암 상으로 이동시키고, 희망하는 전기설비 작업을 무정전으로 시행하는 고정식 가완목 장치 및 공법에 관한 것이다.The present invention relates to a fixed type fastener and method for use in uninterruptible power distribution, and more particularly, to a fixed type fastener made of an insulator under a pin rail or an internal lead of a distribution line, The present invention relates to a stationary type fastening apparatus and method for moving a railway track from a railway track to a stationary railway track using an apparatus or suspension connector, and to perform the desired electric equipment operation in an uninterrupted manner.
Description
본 발명은 무정전 배전공사에 이용하는 고정식 가완목 장치 및 공법에 관한 것으로, 더욱 상세하게는 배전선로의 기존 핀장주 또는 내장주에서 완철 아래에 절연체로 제작된 고정식 가완목으로 장주를 구성하고, 전선이동기구 또는 현수애자연결구를 이용하여 선로를 완철 상에서 고정식 가완목의 암 상으로 이동시키고, 희망하는 전기설비 작업을 무정전으로 시행하는 고정식 가완목 장치 및 공법에 관한 것이다.The present invention relates to a fixed type fastener and method for use in uninterruptible power distribution, and more particularly, to a fixed type fastener made of an insulator under a pin rail or an internal lead of a distribution line, The present invention relates to a stationary type fastening apparatus and method for moving a railway track from a railway track to a stationary railway track using an apparatus or suspension connector, and to perform the desired electric equipment operation in an uninterrupted manner.
배전선로에서 전기설비를 관리하기 위하여 다양한 작업들이 시행된다. Various tasks are carried out to manage electrical facilities in distribution lines.
완철 및 전주 공사, LP애자교체, 장주의 변경, 1상 또는 2상 선로의 3상화 등의 여러 가지 작업들이 시행되는데, 우리나라의 전기사업자인 한전은 고품질의 전기를 공급하고자 정전을 수반하지 않으며, 전기설비를 관리하고자 무정전 공법을 도입하여 시행중에 있다.Various works such as Wanchul and Jeonju construction, LP insulator replacement, Changju change, and 3 phase of 1 phase or 2 phase line are implemented. KEPCO, an electric company in Korea, does not carry out power outage to supply high quality electricity, The uninterruptible power supply method is being implemented to manage the electric facilities.
종래 배전선로에서 무정전으로 전기설비를 관리하는 공법 중 직접 활선공법이 이용되고 있는데, 상기 직접 활선공법은 절연체로 제작된 여러 개의 봉으로 임시장주를 구성하고 완철 상에 설치된 전기선로를 임시장주의 절연봉 상으로 이동시키고 희망하는 전기설비 작업을 시행한다.Conventionally, a direct live method has been used as a method of managing electric equipment from uninterrupted power lines to uninterruptible power lines. The direct live method is a method in which a plurality of rods made of an insulator are used to form a temporary lane, Move to the salary and perform the desired electrical equipment work.
상기 임시장주는 역삼각형으로 구성되며, 핀장주에서 임시장주의 수평 절연봉 상에 고정된 와이어홀더에 전선을 삽입하여 탈락을 방지하고 LP애자 상부의 전선 바인드를 풀고 로프와 도르레를 이용하여 임시장주 전체를 위로 이동하여 선로를 완철 상에서 분리한 후, 전기설비 작업을 시행한 다음 임시장주 전체를 아래로 이동하여 전선이 완철 상의 LP애자 상부에 위치하도록 한 후 전선을 LP애자와 바인드하여 결속하고 임시장주를 철거하여 공사를 종료한다. The market leader is composed of inverted triangles. The wire is inserted into the wire holder fixed on the horizontal insulation barrel of the market in the pin rail, so that it is prevented from dropping. The wire binding on the upper part of the LP insulator is loosened, After moving the whole up to remove the track from the rail, perform the electric equipment work, and then move the entire temporary rail down to place the electric wire on the upper part of the LP insulator on the bare iron, bind the wire with the LP insulator, The construction will be terminated by removing Zhangzhou.
상기한 직접 활선공법은 기구의 구성과 조작이 복잡하여 작업에 많은 시간이 소요되고, 핀장주에서 전기선로를 완철 상에서 수평 절연봉 상으로 분리 또는 수평 절연봉 상에서 신설한 완철 상으로 복귀시키기 위하여 임시장주 전체를 상하로 이동시켜야 하므로 전기선로가 각도를 이루는 등 불평형 장력이 걸리는 개소의 경우, 임시장주를 상하로 이동시키는 과정에서 임시장주가 쉽게 회전하므로 안정성이 떨어지고 불평형 장력으로 인하여 임시장주의 상하 이동에 어려움이 있다. The above-mentioned direct live-line method requires a long time for the operation because of the complicated structure and operation of the apparatus. In order to return the wire to the horizontal rail by separating the wire from the rail, In the case of the unbalanced tension, such as the angle of the electric wire, the entire market should be moved up and down. In the process of moving the temporary market in the up and down direction, the market is easily rotated and the stability is deteriorated. There is a difficulty in.
상기한 공법을 일부 개선한 한국등록특허 10-1344289호인 '승강구동장치를 이용한 배전활선 장주 교체공법'과, 한국등록특허 10-1254577호인 '배전선로 활선작업용 자주식 가완목 시설장비'와, 한국등록특허 10-1275111호인 '이중절연 공간확보를 위한 직접활선 배전설비 교체공법'과, 한국등록특허 10-1473820호인 '배전설비 활선작업 방법'과, 한국공개특허 10-2015-0087786호인 '배전설비 활선작업 방법'이 있으며, 이 공법 또한 장치를 구성하는 절연봉의 길이가 길어서 해당 전주에 설치된 전기설비가 복잡할 경우 장치 설치에 어려움이 있을 수 있고, 장치의 상하 이동시 불평형 하중 특히 각도주에서 발생하는 높은 횡하중을 수직 절연봉이 감당해야 하므로 수직 절연봉의 표면에 손상를 주게 되고, 장치의 하향 이동이 장치 및 전기설비의 자체 무게로 이루어지므로 높은 횡장력이 발생하는 경우 기구의 하향이동이 어려울 수 있고, 내장주에서 전주가 상하로 위치에 따라 굵기를 달리하는 원추형의 구조로 수평 절연봉과 현수애자의 연결거리가 변하여 연결에 어려움이 있고, 전원 및 부하측 현수애자를 완철 상에서 절연봉 상으로 이동시킬 때 전선에서 발생하는 높은 장력을 일시에 수평 절연봉에 인가하지 못하여 전원 및 부하측을 몇 차례 오가며 조금씩 나누어 인가해야 하는 불편함 등의 문제점이 여전히 상존하고 있다.Korean Patent No. 10-1344289 ', which is a partial improvement of the above-mentioned method, and' Korean Patent Registration No. 10-1254577 'Self-propelled barbed equipment for live-line work' Patent No. 10-1275111 discloses a method for replacing direct live distribution equipment for securing a double insulation space, a method of operating a distribution facility using live equipment, Korean Registered Patent No. 10-1473820, and Korean Utility Model Registration No. 10-2015-0087786, This method also has a problem that it is difficult to install the equipment if the electric equipment installed in the electric pole is long because of the long length of the insulating bar that constitutes the device and the unbalanced load during the vertical movement of the device, Since the vertical cutting bar must be subjected to high lateral loads, the surface of the vertical cutting bar is damaged, and the downward movement of the device is made by the own weight of the device and the electric equipment In case of high lateral tension, it may be difficult to move the mechanism downward, and conical structure in which the horizontal and vertical positions of the pole are different according to the position of the pole. , The problem of inconvenience that the high tension generated from the electric wire can not be applied to the horizontal insulation bar at the time of moving the power source and the load side insulator to the insulation bar on the brass rail, It still exists.
또한, 절연봉를 전주에 고정하여 임시장주를 구성하는 구조의 장치로 한국특허등록 10-0558607호인 '단상 및 3상 배전선로용 무정전 선로공법 및 그 전선이선기구'가 개시된 바 있다.In addition, Korean Unexamined Patent Application No. 10-0558607 entitled " Uninterruptible power line method for single-phase and three-phase power distribution line and its wire line device " has been disclosed as a structure device constituting a temporary power line by fixing an insulating rod to a pole.
상기 공법은 기존 장주가 핀장주인 경우, LP애자로부터 전선을 분리하여 상향으로 이동하는 것이 어렵고, 내장주인 경우, 전주가 상하로 위치에 따라 굵기를 달리하는 원추형의 구조로 수평 절연봉과 현수애자의 연결거리가 변하여 연결에 어려움이 있고, 수평 절연봉과 기존의 완철이 상하로 겹치어 현수애자의 이동연결이 어렵고, 완철의 상부로 경유하는 점퍼선의 이동에 어려움이 있는 등의 단점이 있다.The above method is difficult to move upwards by separating the wires from the LP insulator when the existing long pole is the main pole, and when the pole is built-in, the pole has a conical structure having different thicknesses depending on the positions. There is a disadvantage that it is difficult to connect due to the change of the connection distance, and it is difficult to move the suspension of the suspending jig by overlapping the horizontal exfoliation bar and the existing wavy bar vertically and it is difficult to move the jumper line passing through the upper part of the barrel.
따라서 본 발명은 상기와 같은 종래 기술의 문제점을 감안하여 제안된 것으로서, 무정전 배전공사에 이용하는 임시장주를 고정식으로 간단하게 구성하여 적용 개소를 확대하고, 핀장주에서 선로가 각도를 이루어 발생하는 횡하중 또는 전기설비의 무게로 인한 수직 하중에도 무리 없이 전선이동기구를 이용하여 안전하고 용이하게 전선을 상하로 이동시키고, 높은 전선의 장력이 발생하는 내장주에서 현수애자연결구 양단 연결볼트의 조정으로 전원 및 부하측 현수애자의 연결거리를 조절하여 선로의 장력을 완화시켜 현수애자를 이동하여 연결하는 작업이 용이하고, 전원 및 부하측의 현수애자를 현수애자연결구의 양단과 직접 연결하여 선로의 장력이 평형을 이루도록 하여 임시장주의 수평 절연봉에 부담을 경감하는 무정전 배전공사에 이용하는 장치 및 공법을 제공하는 데 그 목적이 있다.SUMMARY OF THE INVENTION Accordingly, the present invention has been made keeping in mind the above problems occurring in the prior arts, and it is an object of the present invention to provide an apparatus and a method for preventing unintentional power distribution, It can safely and easily move the wire up and down by using the wire moving mechanism without any difficulty even under the vertical load due to the weight of the electric equipment and adjust the connection bolts at both ends of the hanging insulator end connection in the built- By adjusting the connection distance of the suspending insulator, it is easy to move and connect the suspending insulator by loosening the tension of the line, and by connecting the suspending insulator of the power source and the load side directly to both ends of the suspending insulator connection, It is used for uninterruptible power distribution to reduce the burden on the horizontal rail To provide a value, and there is a method that purpose.
본 발명이 해결하고자 하는 과제를 달성하기 위하여, 본 발명인 무정전 배전공사에 이용하는 고정식 가완목 장치는,In order to accomplish the object of the present invention, there is provided a fixed type fastener for use in uninterruptible power distribution,
전주(10)의 외부 둘레면에 결합되고, 양측으로 암(200)과 결합하도록 구성되는 암밴드(100);An armband (100) coupled to the outer circumferential surface of the electric pole (10) and configured to mate with the arm (200) on both sides;
원형의 절연봉으로 구성되되, 상기 암(200)의 둘레면에 수직으로 결합되고, 승강부(710)의 상부에 전선을 수용하고 상하로 이동 가능하도록 구성되는 전선이동기구(500);A wire moving mechanism (500) composed of a circular cutting bar, vertically coupled to the circumferential surface of the arm (200), configured to receive a wire at an upper portion of the elevating part (710) and move up and down;
고정기구(920)를 구성하여 상기 암(200)의 일 측면에 결합되고, 양단에 회전시켜서 연결거리를 조절하며 일측에 결합용 고리를 지닌 연결볼트를 구성하여 전원 및 부하측 현수애자를 직접 연결하는 현수애자연결구(900)를 포함하여 구성한다.The
또한, 본 발명인 무정전 배전공사에 이용하는 고정식 가완목 공법은,Further, in the fixed type welding method used in the uninterruptible power distribution work of the present invention,
전주(10)의 둘레면에 암밴드(100)를 결합하고, 암밴드(100)의 양측에 암(200)을 결합하기 위한 고정식가완목장주설치단계(S100)와;A step S100 of installing a fixed type ranch ranch for coupling an
선로의 유형에 따라 상기 암(200) 상에 전선이동기구(500) 또는 현수애자연결구(900)를 결합하되, 상기 전선이동기구(500)를 하단에 구비된 크람프를 이용하여 전선의 위치에 맞추어 암(200)의 일 면에 고정하거나, 고정기구를 이용하여 상기 현수애자연결구(900)를 현수애자의 위치에 맞추어 암(200) 상에 결합하고 전원 및 부하측 현수애자의 연결거리를 감안하여 현수애자연결구 양단의 연결볼트를 조작하거나, 고정기구 대용으로 전선이동기구를 이용하여 현수애자연결구를 지지하도록 설치 구성하는 선로이동용기구설치단계(S200)와;The electric
상기 전선이동기구(500)를 이용하여 전선을 상향으로 또는 상기 현수애자연결구의 양단으로 현수애자를 이동시키되, 전선이동기구의 상부에 형성된 승강부(710)에 전선을 수용하여 탈락을 방지하고, 전선과 LP애자를 결속하는 바인드를 풀고 전선이동기구 승강부의 구동축(714)을 활선작업차의 유압렌치로 구동시켜서 승강부를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 상향으로 이동시키거나, 2대의 활선용 장선기를 전원 및 부하측 완철(40)에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 완철로부터 현수애자를 분리하여 현수애자연결구 양단 연결볼트(910)의 고리에 연결한 후, 장선기를 차례로 장력 해제하고 철거하여 전원 및 부하측의 현수애자를 현수애자연결구(900)가 직접 연결하도록 하고, 완철의 상부로 경유하는 점퍼선의 위치에 맞추어 전선이동기구(500)를 암(200)의 일 면에 고정하고, 점퍼선을 LP애자에서 분리하여 전선이동기구(500)로 지지함으로써, 기존 선로를 완철 상에서 분리하여 가완목의 암 상으로 이동시키는 선로이동단계(S300)와; The
상기 선로이동단계(S300)를 통해 고정식 가완목의 암 상으로 선로를 이동시킨 후, 원하는 전기설비 작업을 시행하는 설비작업단계(S400)와;A facility operation step (S400) for moving the line to the arm of the fixed type door through the line moving step (S300) and then performing a desired electric equipment operation;
상기 선로이동단계(S300) 및 설비작업단계(S400)에서 이용한 기구를 설치의 역순으로 환원하여 철거하고, 선로 구성에 불필요한 전주 및 전선 설비를 철거하는 이용기구및불용설비철거단계(S500);를 포함함으로써, 본 발명의 과제를 해결하게 된다.A utilization mechanism and an insoluble facility dismantling step (S500) for reducing and dismounting the mechanisms used in the line moving step (S300) and the equipment working step (S400) in the order of installation and dismantling the electric pole and wire facilities unnecessary for the line configuration; Thereby solving the problems of the present invention.
이상의 구성 및 작용을 지니는 본 발명에 따른 무정전 배전공사에 이용하는 고정식 가완목 장치 및 공법을 통해, 배전선로에서 무정전으로 전기설비 작업을 시행하기 위하여 임시로 구성하는 장주를 고정식으로 간단하게 구성하고, 전선이동기구로 전선을 용이하게 상하로 이동시키고, 2대의 활선용 장선기를 사용하여 전원 및 부하측의 완철과 연결된 현수애자를 현수애자연결구 양단으로 이동시키면 현수애자연결구가 장력이 큰 쪽으로 이동하여 선로의 장력이 평형을 이루도록 함으로써, 장치의 적용 개소를 확대시킬 수 있고, 작업시간을 단축시킬 수 있으며, 안정적으로 전기설비 작업을 수행할 수 있는 효과를 제공하게 된다.The fixed type fastener and the method for uninterruptible power distribution according to the present invention having the above-described constitution and function can constitute a temporary fixed type simple structure for performing the electric equipment work in uninterrupted power distribution line, Moving the wire easily up and down with the moving mechanism and moving the suspending insulator connected to the power supply and the load side iron wire to both ends of the suspending insulator connection by using the two live wire inserters moves the tension insulator to the larger tension side, It is possible to enlarge the application point of the apparatus, shorten the working time, and provide the effect of stably performing the electric equipment work.
도 1은 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 전체 구성도이다.
도 2는 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 암밴드 구성도이다.
도 3은 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 전선이동기구 구성도이며, 도 3a는 승강부의 상세 구조도이며, 도 3b는 봉결합부 내지 암결합부 간의 결합 구조도이다.
도 4는 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 현수애자연결구 구성도이다.
도 5는 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 보조암 구성도이다.
도 6은 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법의 공정도이다.FIG. 1 is an overall block diagram of a fixed type fastener used in a fixed type fast clip method used in uninterruptible power distribution according to an embodiment of the present invention.
FIG. 2 is a view illustrating an armband of a stationary type fastener used in a fixed type fast clip method used in uninterruptible power distribution according to an embodiment of the present invention.
FIG. 3 is a structural view of a wire moving mechanism of a fixed type wire cutting device used in a fixed type wire cutting method for use in an uninterruptible power distribution according to an embodiment of the present invention, FIG. 3a is a detailed structural diagram of a lift portion, Arm coupling portion.
FIG. 4 is a view showing the construction of a hanging insulator connector of a fixed type fastener used in a fixed type fast clip method used in an uninterruptible power distribution according to an embodiment of the present invention.
FIG. 5 is a view illustrating the auxiliary arm of the stationary type fastener used in the fixed type fast clip method used in the uninterruptible power distribution according to the embodiment of the present invention.
FIG. 6 is a process diagram of a fixed type fast cutting method used in uninterruptible power distribution according to an embodiment of the present invention.
이하, 본 발명에 의한 무정전 배전공사에 이용하는 고정식 가완목 장치 및 공법에 대하여 구체적으로 설명하도록 하겠다.Hereinafter, a fixed type fastening device and a method for use in the uninterruptible power distribution according to the present invention will be described in detail.
도 1은 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 전체 구성도이다.FIG. 1 is an overall block diagram of a fixed type fastener used in a fixed type fast clip method used in uninterruptible power distribution according to an embodiment of the present invention.
도 1에 도시한 바와 같이, 본 발명의 고정식 가완목 장치는,As shown in Fig. 1, in the fixed type warping apparatus of the present invention,
전주(10)의 외부 둘레면에 결합하고, 양측으로 암(200)과 결합하도록 구성되는 암밴드(100), An
일측이 상기 암밴드(100)의 일측과 결합하고, 타측이 연장암 및 암타이와 결합할 수 있되, 임시로 구성하는 장주에서 완철의 역할을 수행하는 암(200), An
일측이 상기 암(200)의 타측과 결합하되, 임시로 구성하는 장주에서 암(200)의 길이를 연장하는 역할을 수행할 수 있도록 구성되는 연장암(400), An
양단에 고정장치(255)를 구비하여 완철(40)의 측면 하부에 고정되고, 둘레면에 전선이동기구(500) 혹은 전선이동기구타이(540)와 결합하되, 상기 암(200)의 역할을 수행하는 보조암(250),A
상기 암밴드(100)의 하부 전주(10)의 외부 둘레면에 결합하고, 양측이 암타이(300)의 일측과 결합하도록 구성되는 암타이밴드(310), An
상기 암타이 밴드(310)의 일측과 상기 암(200)의 타측에 대각으로 결합하며, 선로가 수직으로 각도를 이루어 발생되는 높은 수직 하중이 걸리는 개소에서 암(200)을 보강하는 암타이(300),An
원형의 절연봉(510) 하단에 크람프(505)를 구비하여 상기 암(200)의 둘레면에 수직으로 고정되고, 상부에 랙기어(600)를 구비하여 승강부(710)와 결합하고, 승강부(710)의 상부에 전선을 수용하는 홈(711)과 탈락을 방지하는 덮개(712)와 고정장치를 구비하며, 승강부(710)의 내부에 상기 랙기어(600)와 기어 결합하는 헤리컬기어(713)와 상기 헤리컬기어(713)와 기어 결합하는 웜기어(715)와 상기 웜기어(715)와 결합하는 구동축(714)을 구비하되, 상기 승강부의 상부 홈(711)에 전선을 삽입하고 덮개(712)를 고정하여 탈락을 방지하고, 활선작업차의 유압렌치로 상기 구동축(714)을 구동하면 웜기어(715)와 헤리컬기어(713)가 동작하여 전선을 수용한 승강부(710)가 랙기어(600)의 기어 면을 따라 상하로 이동하는 전선이동기구(500), A
선로가 수평으로 각도를 이루어 횡하중이 발생하는 개소에서, 상기 전선이동기구(500)의 일면과 상기 암(200)의 일면에 대각으로 결합함으로써, 전선이동기구를 보강하도록 하는 전선이동기구타이(540),A wire moving mechanism tie 540 for reinforcing the wire moving mechanism by engaging one side of the
고정기구(920)를 구성하여 상기 암(200)의 일 측면에 결합되고, 양단에 회전시켜서 연결거리를 조절하며, 일측에 결합용 고리를 지닌 연결볼트(910)를 구성하여 전원 및 부하측 현수애자와 직접 연결하는 현수애자연결구(900)를 포함하여 구성되는 것을 특징으로 한다.And a connecting
도 2는 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 암밴드 구성도이다.FIG. 2 is a view illustrating an armband of a stationary type fastener used in a fixed type fast clip method used in uninterruptible power distribution according to an embodiment of the present invention.
도 2에 도시한 암밴드(100)는 본 출원인이 출원한 대한민국 특허출원번호 '10-2016-0037339호'에 구체적으로 개시하였으며, 본 발명에서는 고정식 가완목 장치 및 공법에 활용되는 구성수단을 간략하게 설명하도록 한다.The
상기 암밴드는 전주(10)의 외부 둘레면에 결합하고, 양측으로 암(200)과 결합하도록 구성되는 것을 특징으로 한다.The armband is configured to be coupled to the outer peripheral surface of the electric pole (10) and to be coupled to the arm (200) on both sides.
도 2에 도시한 바와 같이, 양측에 암을 연결하기 위한 연결홈을 구성하게 된다.As shown in Fig. 2, the connecting grooves for connecting the arms are formed on both sides.
도 3은 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 전선이동기구 구성도이며, 도 3a는 승강부의 상세 구조도이며, 도 3b는 봉결합부 내지 암결합부 간의 결합 구조도이다.FIG. 3 is a structural view of a wire moving mechanism of a fixed type wire cutting device used in a fixed type wire cutting method for use in an uninterruptible power distribution according to an embodiment of the present invention, FIG. 3a is a detailed structural diagram of a lift portion, Arm coupling portion.
도 3 내지 도 3b에 도시한 전선이동기구는 본 출원인이 출원한 대한민국 특허출원번호 '10-2016-0037334'에 구체적으로 개시하였으며, 본 발명에서는 고정식 가완목 공법에 활용되는 구성수단을 간략하게 설명하도록 한다.3 to 3B has been specifically disclosed in Korean Patent Application No. 10-2016-0037334 filed by the applicant of the present invention, and the present invention has a brief description .
도 3과 도 3a를 참조하여 상기 전선이동기구의 승강부(710)를 구체적으로 설명하자면, 상기 승강부(710)는 상부에 전선과 결합되는 전선결합홈(711), 상기 전선결합홈(711)의 상부에 위치하되, 전선이 전선결합홈(711)에 결합될 시 이탈되지 않도록 전선결합홈(711)을 덮고 고정할 수 있는 덮개(712)와 고정장치, 절연봉(510) 상부의 랙기어(600)와 맞물리는 헤리컬기어(713), 상기 헤리컬기어(713)와 맞물려 형성되는 웜기어(715), 상기 웜기어(715)와 결합하는 구동축(714), 상기 승강부(710)가 상기 랙기어(600)의 측면에 결합되어 이탈하지 않도록 구속하는 결합판(716)을 포함하여 구성되는 것을 특징으로 한다.3 and 3A, the
따라서, 상기 승강부(710)는 상부의 전선결합홈(711)에 전선을 수용하고, 활선작업차의 유압렌치로 상기 구동축(714)을 구동하면 웜기어(715)와 헤리컬기어(713)가 동작하고, 헤리컬기어(713)가 랙기어(600)와 맞물려 랙기어(600)의 측면을 따라 상하로 이동하게 되는 것이다. Therefore, when the
도 3과 도 3b를 참조하여 크람프(505)를 구체적으로 설명하자면, 전선이동기구(500)는 암(200)의 둘레면에 수직으로 조임 결합할 수 있도록 구성되는 암결합부(530)와,Referring to FIGS. 3 and 3B, the
절연봉(510)의 하단과 상기 암결합부(530)의 일측이 결합될 수 있도록 구성되는 봉결합부(520)를 포함하여 구성되는 것을 특징으로 한다.And a
상기한 암결합부(530)와 봉결합부(520)를 크람프(505)라 정의하도록 하겠다.The
한편, 상기 봉결합부(520)는 일면과 마주보는 면의 상측이 기어 형태의 기어면(522)으로 구성되고, 측면이 반원의 홈을 형성하여 구성되는 하우징(521), The rod-engaging
상기 하우징(521)의 일면과 마주보는 면을 관통하여 절연봉(510) 하단의 원형홀과 결합하되, 절연봉(510)이 굴절할 때, 회전축으로 기능하기 위한 제1결합부(523), A first engaging
상기 절연봉(510)의 하단의 타원형 홀을 관통하여 상기 하우징(521)의 상측에 구성되는 기어면(522)과 결합되도록 구성되고 상기 절연봉(510)의 굴절 각도를 조정하는 제2결합부(524), And a second coupling unit configured to be coupled to a
일측이 상기 제1결합부(523)와 결합되고, 타측이 상기 제2결합부(524)와 결합하여 제2결합부(524)가 상기 봉결합부(520)의 기어면(522)을 이탈하지 않도록 구성되는 탄성부(526)를 포함하여 구성하게 된다.The other end of the second
따라서, 상기 크람프(505)는 절연봉(510)을 암(200)의 일면에 결합시키고, 절연봉(510)이 상기 제1결합부(523)를 축으로 굴절하고, 상기 제2결합부(524)가 상기 하우징(521)의 기어면(522)에 결합하여 절연봉(510)의 굴절 각도를 조절할 수 있게 하는 것이다.Therefore, the
도 4는 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 현수애자연결구 구성도이다.FIG. 4 is a view showing the construction of a hanging insulator connector of a fixed type fastener used in a fixed type fast clip method used in an uninterruptible power distribution according to an embodiment of the present invention.
도 4에 도시한 현수애자연결구는 본 출원인이 출원한 대한민국 특허출원번호 '10-2016-0037353'에 구체적으로 개시하였으며, 본 발명에서는 고정식 가완목 장치 및 공법에 활용되는 구성수단을 간략하게 설명하도록 한다.4 is specifically disclosed in Korean Patent Application No. 10-2016-0037353 filed by the applicant of the present application. In the present invention, in order to briefly explain the constituent means used in the fixed type fastener and the method, do.
상기 현수애자연결구(900)는 고정기구(920)를 구성하여 상기 암(200)의 일 측면에 결합되고, 양단에 회전시켜서 연결거리를 조절하며 일측에 결합용 고리를 지닌 연결볼트(910)를 구성하되, 고정기구(920)와 현수애자연결구(900)의 결합은 현수애자연결구(900)가 전원 및 부하측 현수애자와 결합시, 선로 장력의 크기에 따라 이동할 수 있도록 유격이 있게 결합하는 것이다.The
따라서, 현수애자연결구 양단의 연결볼트(910)를 돌려서 전원 및 부하측 현수애자의 연결거리를 조절함으로써, 선로 장력의 크기를 조절하고, 양단과 전원 및 부하측 현수애자와 직접 연결하여 장력의 크기에 따라 현수애자연결구(900)가 선로와 함께 이동함으로써, 선로의 장력이 평형을 이루어 전선의 높은 장력이 암에 가해지지 않도록 하는 기능을 제공하게 되는 것이다.Therefore, by adjusting the connection distance between the power source and the load-side suspending insulator by turning the connecting
도 5는 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법에 이용되는 고정식 가완목 장치의 보조암 구성도이다.FIG. 5 is a view illustrating the auxiliary arm of the stationary type fastener used in the fixed type fast clip method used in the uninterruptible power distribution according to the embodiment of the present invention.
도 5에 도시한 바와 같이, 상기 보조암(250)은 양단에 고정장치(255)를 구비하고 있으며, 고정장치를 이용하여 도 1에 도시한 바와 같이, 완철(40)의 측면 하부에 고정되고, 둘레 면에 전선이동기구(500) 혹은 전선이동기구타이(540)와 결합하여 LP애자 교체 작업 등에서 개별로 전선을 이동시킬 때 편리하게 이용하는 것으로 상기 암(200)의 역할을 수행하는 것을 특징으로 한다.As shown in FIG. 5, the
도 6은 본 발명의 실시예에 따른 무정전 배전공사에 이용하는 고정식 가완목 공법의 공정도이다.FIG. 6 is a process diagram of a fixed type fast cutting method used in uninterruptible power distribution according to an embodiment of the present invention.
도 1 내지 도 5를 통해, 본 발명의 고정식 가완목 공법을 수행하기 위한 구성수단들에 대하여 설명하였다.1 to 5, the constituent means for carrying out the fixed type complete method of the present invention has been described.
다음은 도 6을 참조하여 본 발명인 고정식 가완목 공법에 대하여 구체적으로 설명하도록 하겠다. The following will specifically describe the fixed type laminating method of the present invention with reference to Fig.
즉, 본 발명인 고정식 가완목 공법은 크게, 고정식가완목장주설치단계(S100)와; 선로이동용기구설치단계(S200)와; 선로이동단계(S300)와; 설비작업단계(S400)와; 이용기구및불용설비철거단계(S500);를 포함하여 이루어지게 된다.That is, the fixed type cutting method of the present invention is roughly composed of a step S100 of installing a fixed type ranching ranch; Installing a line moving mechanism (S200); A line moving step S300; Equipment operation step (S400); A utilization mechanism and an insoluble facility dismantling step (S500).
상기 고정식가완목장주설치단계(S100)는 전주(10)의 둘레면에 암밴드(100)를 결합하고, 암밴드(100)의 양측에 암(200)을 결합하는 과정이다.In the step S100, the
그리고, 해당 현장의 여건과 작업내용에 따라 암밴드(100) 하부 전주(10)의 둘레면에 상기 암타이밴드(310)를 결합하고 암(200)의 일측 및 암타이밴드(310)의 일측과 대각으로 결합하여 암(200)을 보강하는 암타이(300)를 결합할 수 있다.The
또한, 암(200)의 일측과 상기 연장암(400)의 일측을 결합하여 암(200)의 길이를 연장하도록 구성할 수 있으며, 전주와 전주 사이에 할입 전주를 새로 설치하는 경우에는 사전에 전주를 건주하고, 신설한 전주 상에 암밴드를 이용하여 암(200)을 설치하게 된다.The length of the
한편, LP애자를 교체하는 경우에는 암의 대용으로 보조암(250)을 완철의 측면 하부에 고정하게 된다.On the other hand, when replacing the LP insulator, the
이후, 상기 선로이동용기구설치단계(S200)는 선로의 유형에 따라 상기 암(200) 상에 전선이동기구(500) 또는 현수애자연결구(900)를 결합하게 된다.In the step S200 of installing the line moving mechanism, the
이때, 상기 전선이동기구(500)를 하단에 구비된 크람프(505)를 이용하여 전선의 위치에 맞추어 암(200)의 일 면에 고정하거나, 현수애자연결구(900)의 고정기구(920)를 이용하여 상기 현수애자연결구(900)를 현수애자의 위치에 맞추어 암(200) 상에 결합하고 전원 및 부하측 현수애자의 연결거리를 감안하여 현수애자연결구 양단의 연결볼트(910)를 조작하거나, 고정기구(920) 대용으로 전선이동기구(500)를 이용하여 현수애자연결구(900)를 지지하도록 설치 구성하게 된다.At this time, the
즉, 핀장주의 경우에는 전선이동기구를 이용하게 되며, 내장주의 경우에는 현수애자연결구 혹은 전선이동기구를 이용하게 되는 것이다.That is, in the case of the pin shaft, the wire moving mechanism is used, while in the case of the built-in connector, the suspension connector or wire moving mechanism is used.
이후, 선로이동단계(S300)는 상기 전선이동기구(500)를 이용하여 전선을 상향으로 또는 상기 현수애자연결구의 양단으로 현수애자를 이동시키게 된다.Thereafter, in the line moving step S300, the
이때, 전선이동기구에 형성된 승강부(710)의 상부에 구비된 홈(711)에 전선을 수용하여 탈락을 방지하고, 전선과 LP애자를 결속하는 바인드를 풀고 승강부(710)의 구동축(714)을 활선작업차의 유압렌치로 구동시켜서 승강부(710)를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 상향으로 이동시키게 된다.At this time, the electric wire is received in the
또는 2대의 활선용 장선기를 전원 및 부하측 완철(40)에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 완철로부터 현수애자를 분리하여 현수애자연결구 양단 연결볼트(910)의 고리에 연결한 후, 장선기를 차례로 장력 해제하고 철거하여 전원 및 부하측의 현수애자를 현수애자연결구(900)가 직접 연결하도록 하며, 완철의 상부로 경유하는 점퍼선의 위치에 맞추어 전선이동기구(500)를 암(200)의 일 면에 고정하고, 점퍼선을 LP애자에서 분리하여 전선이동기구(500)로 지지함으로써, 기존 선로를 완철 상에서 분리하여 가완목의 암 상으로 이동시키게 된다.Or the two live wire brackets are connected to the power and load
즉, 핀장주의 경우에는 전선이동기구로 전선을 상향 이동시키고, 내장주의 경우에는 현수애자를 현수애자연결구의 양단으로 이동시키게 된다. That is, in the case of the pin shaft, the electric wire is moved upward by the wire moving mechanism, and in the case of the built-in case, the suspender insulator is moved to both ends of the suspension connector.
이후, 상기 설비작업단계(S400)는 상기 선로이동단계를 통해 고정식 가완목의 암 상으로 선로를 이동시킨 후, 원하는 전기설비 작업을 시행하게 되는 과정이다.Hereinafter, the facility operation step (S400) is a process in which a desired electric equipment operation is performed after the line is moved to the arm of the fixed type door via the line moving step.
상기 원하는 전기설비 작업으로는 완철 교체, LP애자교체, 장주변경, 선로 3상화, 전주교체, 할입전주 신설, 개폐기 설치 등이 있으며, 희망하는 전기설비 작업에 따라 작업 과정은 달라질 수가 있다.Examples of the desired electrical equipment work include replacing a full iron wire, replacing a LP insulator, changing a long wire, changing a wire, upgrading a pole, installing a new pole, and installing a switch.
이에 대하여 하기에서 좀 더 구체적으로 설명하도록 하겠다.This will be described in more detail below.
이후, 상기 이용기구및불용설비철거단계(S500)는 상기 선로이동단계(S300) 및 설비작업단계(S400)에서 이용한 기구, 예를 들어, 전선이동기구, 보조암, 암, 암밴드, 암타이, 암타이밴드, 전선이동기구타이, 현수애자연결구, 연장암 등을 의미한다.The utilization mechanism and the insoluble facility dismantling step S500 may be performed by using the mechanism used in the line moving step S300 and the facility operation step S400, for example, a wire moving mechanism, an auxiliary arm, An arm tie band, a wire moving mechanism tie, a suspension connector, and an extension arm.
이때, 이용한 기구를 설치의 역순으로 환원하여 철거하고, 선로 구성에 불필요한 전주 및 전선 등의 설비를 철거하는 과정이다.At this time, the mechanism used is reduced and removed in the reverse order of the installation, and equipment such as poles and wires unnecessary for line configuration is removed.
다음은 원하는 전기설비 작업에 따라 수행되는 공법을 구체적으로 설명하도록 하겠다.The following is a detailed description of the work to be carried out according to the desired electrical equipment work.
상기한 설비작업단계(S400)에서, 원하는 전기설비 작업이 완철 교체인 경우에는 완철및애자교체단계(S410)와, 선로복귀단계(S411)를 포함하여 이루어지게 된다.In a case where the desired electric equipment operation is a full iron replacement in the above-mentioned facility operation step (S400), it includes a full iron and an insulator replacement step (S410) and a line returning step (S411).
구체적으로, 기존 완철 및 애자를 철거하고 새로운 완철 및 애자를 설치(S410)한 후, 기존 완철이 핀장주를 구성하는 경우, 전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선를 LP애자와 바인드로 결속하게 된다.Specifically, when the existing wire rod and the insulator are removed and a new wire rod and insulator are installed (S410), when the existing wire rod constitutes the pin rail, the driving
또는, 기존 완철이 내장주를 구성하는 경우, 2대의 활선용 장선기를 이용하여 새로 설치한 전원 및 부하측 완철에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 현수애자연결구(900) 양단으로부터 현수애자를 분리하여 전원 및 부하측 완철과 쇄클을 이용하여 연결한 후, 장선기를 철거하고, 완철의 상부로 경유하는 점퍼선을 전선이동기구(500)에서 분리하여 LP애자와 바인드로 결속하여 지지(S411)하는 과정을 수행하게 된다.Alternatively, when the existing bare iron constitutes the built-in bare wire, it is connected to the newly installed power source and the load side bare iron by using the two live wire brackets, and the power and the load side wire are pulled to release the tension applied to the hanging bracket, The jumper wires are disconnected from the both ends and connected to the power source and the load side brass rods by the shackles. Then, the jumper wires are removed and the jumper wires passing through the upper side of the brass rods are separated from the
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
한편, 상기한 설비작업단계(S400)에서, 전기설비 작업이 LP애자 교체인 경우에는 LP애자교체단계(S420)와, 선로복귀단계(S421)를 거치게 된다.Meanwhile, in the above-mentioned facility operation step (S400), if the electrical equipment operation is LP insulator replacement, the LP insulator replacement step (S420) and the line returning step (S421) are performed.
구체적으로, 기존 LP애자를 철거하고 새로운 LP애자를 설치(S420)한 후, 전선이동기구 승강부(710)의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선를 LP애자와 바인드로 결속하여 지지(S421)하는 과정을 수행하게 된다.Specifically, after the existing LP insulator is removed and a new LP insulator is installed (S420), the driving
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
한편, 상기한 설비작업단계(S400)에서, 전기설비 작업이 장주 변경인 경우에는 완철교체단계(S430)와, 현수애자설치단계(S431)와, 전선하향이동단계(S432)와, 내장전선설치단계(S433)를 거치게 된다.If the electrical equipment operation is a long-term change in the facility operation step (S400), the full-bar replacement step S430, the hanging insulator installation step S431, the wire downward movement step S432, Step S433 is performed.
구체적으로, 기존 완철과 LP애자를 철거하고 겹 완철를 설치(S430)한 후, 새로 설치한 전원 및 부하측 완철에 쇄클을 이용하여 현수애자를 연결(S431)하게 된다.Specifically, after the existing bare iron and LP bare iron are removed and the double bare iron is installed (S430), the suspension is connected to the newly installed power source and the load side bare iron using the shackle (S431).
이후, 전선이동기구 승강부(710)의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동(S432)시킨 후, 2대의 활선용 장선기를 새로 설치한 전원 및 부하측 완철에 연결하여 전원 및 부하측의 전선을 당기고, 바이패스 점퍼케이블을 이용하여 전선이동기구 승강부(710) 상의 전선과 병렬회로를 구성하고, 현수애자의 연결거리를 감안하여 전원 및 부하측 전선을 절단하고 피복을 벗겨서 데드앤드크람프로 현수애자와 전선을 연결한 후 장선기를 철거하고, 전원 및 부하측 전선을 점퍼선으로 연결하여 바이패스 점퍼와 병렬회로를 구성하게 된다.Thereafter, the driving
그리고, 완철의 상부로 경유하는 점퍼선은 LP애자를 설치하고, 바인드로 결속하여 지지하고, 바이패스 점퍼를 분리(S433)하는 과정을 거치게 된다.Then, the jumper wire passing through the upper portion of the solid iron is subjected to a process of installing a LP insulator, binding and supporting the same, and separating the bypass jumper (S433).
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
한편, 상기한 설비작업단계(S400)에서, 전기설비 작업이 1상 또는 2상 선로의 3 상화인 경우에는 완철및애자교체단계(S440)와, 상신설단계(S441)와, 선로복귀단계(S442)를 거치게 된다.If the electric equipment operation is a three-phase operation of the one-phase or two-phase line in the facility operation step (S400), the step of replacing the coarse iron and the insulator (S440), the step of establishing a superstructure (S441) S442).
구체적으로, 기존 완철과 애자를 철거하고 새로운 완철과 애자를 설치(S440)한 후, 증가하는 1상 또는 2 상의 선로를 신설한 완철 상에 설치하되, 전선을 LP애자의 상부에 바인드로 결속하거나, 현수애자와 연결(S441)하여 증가하는 상을 설치하게 된다.Specifically, after removing the existing wire rods and insulators and installing new wire rods and insulators (S440), an increasing one-phase or two-phase wire is installed on the new wire rods, and the wire is bound to the upper portion of the LP insulator (S441), and an increasing phase is established.
이후, 전선이동기구 승강부(710)의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선를 LP애자와 바인드로 결속하거나,Thereafter, the driving
또는, 2대의 활선용 장선기를 새로 설치한 전원 및 부하측 완철에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 현수애자연결구(900) 양단으로부터 현수애자를 분리하여 전원 및 부하측 완철과 쇄클을 이용하여 연결한 후, 장선기를 철거하고, 완철의 상부로 경유하는 점퍼선을 전선이동기구(500)에서 분리하여 LP애자와 바인드로 결속하여 지지(S442)하는 과정을 거치게 된다.Alternatively, the two live wires are connected to the newly installed power source and the load side iron wire, and the electric power and the wires on the load side are pulled to release the tension applied to the suspending insulator, and the suspender insulator is separated from both ends of the suspending
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
한편, 상기한 설비작업단계(S400)에서, 전기설비 작업이 전주 교체인 경우에는 전주설치단계(S450)와, 완철/애자철거및설치단계(S451)와, 선로신설및이동단계(S452)를 거치게 된다.If the electrical equipment operation is the electric pole change, the electric pole installation step S450, the complete wire / insulator removal and installation step S451, the line installation and movement step S452, .
구체적으로, 전기 선로를 감안하여 기존 전주 인근에 새로운 전주를 신설(S450)한 후, 기존 전주 상에 설치된 완철과 애자를 철거하고 신설한 전주 상에 완철과 애자를 설치(S451)하게 된다.Specifically, in consideration of the electric line, a new electric pole is installed near the existing electric pole (S450), and the electric pole and the insulator installed in the existing electric pole are removed, and the electric pole and the insulator are installed (S451).
그리고, 기존 전주가 핀장주인 경우, 전선이동기구 승강부(710)의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선을 신설한 전주의 완철 상에 설치된 LP애자와 바인드로 결속하여 지지하거나,When the existing electric pole is a pin fence body, the driving
또는, 기존 전주가 내장주인 경우, 신설한 전주에서 길어지는 경간측 구간에 선로를 신설하고, 2대의 활선용 장선기를 신설 전주의 전원 및 부하측 완철에 연결하여 신설한 전주를 기준으로 양측의 전선을 당기고, 신설 전주에서 전선을 내장으로 설치할 것을 감안하여 기존 전선과 상기 신설한 구간의 전선을 바이패스 점퍼로 연결하여 병렬회로를 구성하고, 현수애자와 연결할 거리 및 점퍼선의 길이를 감안하여 기존 전선을 절단하고 피복을 벗겨서 데드앤드크람프로 현수애자와 연결한 후 장선기를 철거하고, 점퍼선을 신설한 선로와 연결하여 바이패스 점퍼와 병렬회로를 구성하고, 완철의 상부로 경유하는 점퍼선을 LP애자와 바인드로 결속하여 지지하고, 바이패스 점퍼를 분리(S452)하는 과정을 거치게 된다.Or, if the existing electric pole is the built-in electric pole, a new railway line is to be established between the span of the newly installed electric pole and the two live wire rods are connected to the power pole of the new pole and the load side pole of the new pole. Considering the installation of the electric wire in the new electric pole, it is necessary to construct a parallel circuit by connecting the existing electric wire and the electric wire of the newly created section with the bypass jumper, and consider the distance to be connected to the suspender insulator and the length of the jumper wire, Cut off the jacket and connect it to the Dead and Krampro Suspension Insulator, demolish the jumper, connect the jumper wire to the newly installed line, construct a parallel circuit with the bypass jumper, and connect the jumper wire to the LP And the bypass jumpers are separated from each other (S452).
즉, 핀장주일 경우에는 신설 전주 상으로 전선를 이동하여 설치하는 것이며, 내장주인 경우에는 신설 경간이 기설 경간 대비 길어지는 경간은 전선을 신설하고 짧아지는 경간은 기존 전선을 이용하여 내장으로 전선을 설치하는 것이다.In the case of a built-in main span, the span where the new span is longer than the existing span is installed with the electric wire, and the span which is shortened is installed with the built-in electric wire using the existing electric wire. will be.
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
한편, 상기한 설비작업단계(S400)에서, 전기설비 작업이 할입 전주 신설인 경우에는 완철및애자설치단계(S460)와, 전선하향이동및설치단계(S461)를 거치게 된다.Meanwhile, in the above-described facility operation step (S400), if the electrical equipment operation is to install an introductory electric pole, it is subjected to a full iron and insulator installation step (S460) and a wire downward movement and installation step (S461).
구체적으로, 사전에 신설한 전주 상에 완철과 애자를 설치(S460)한 후, 전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구에 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선을 신설한 할입 전주의 완철 상에 설치된 LP애자와 바인드로 결속하여 지지하거나,More specifically, after the wire and the insulator are installed on the pre-installed electric pole (S460), the
또는, 할입 전주가 내장주인 경우, 2대의 활선용 장선기를 할입 전주의 전원 및 부하측 완철에 연결하여 양측의 전선을 당기고, 바이패스 점퍼를 전원 및 부하측 전선과 연결하여 병렬회로를 구성하고, 현수애자와 연결할 거리를 감안하여 전선을 절단하고 피복을 벗겨서 데드앤드크람프로 현수애자와 연결한 후 장선기를 철거하고, 전원 및 부하측 전선을 점퍼선으로 연결하여 바이패스 점퍼와 병렬회로를 구성하고, 완철의 상부로 경유하는 점퍼선을 LP애자와 바인드로 결속하여 지지하고, 바이패스 점퍼를 분리(S461)하는 과정을 거치게 된다.Alternatively, in the case where the introductory electric pole is the built-in electric pole, two parallel electric wire lines are connected to the power source and the load side electric wire of the rechargeable electric pole to pull the electric wires from both sides and the bypass jumper is connected to the power source and the load side electric wire to constitute a parallel circuit, , Cut off the wire, peel off the cover and connect it to the dead and krampro suspender, remove the jumper, connect the power supply and the load side wire to the jumper wire to construct the bypass jumper and the parallel circuit, The jumper wire passing through the upper portion is bound and supported by the LP insulator and the binders, and the bypass jumper is separated (S461).
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
한편, 상기한 설비작업단계(S400)에서, 내장전선설치단계(S433) 이후에 개폐기를 추가하여 설치하고자 하는 경우에는 개폐기설치단계(S433a)와, 개폐기리드선연결단계(S433b)를 거치게 된다.Meanwhile, if it is desired to additionally install an additional switch after the built-in wire installation step (S433) in the facility operation step (S400), the switch installation step S433a and the switch connection lead connection step S433b are performed.
구체적으로, 전원 및 부하측 전선을 점퍼선으로 연결하고, 바이패스 점퍼를 분리하는 대신 내장 완철단 아래의 전주 상에 개폐기를 설치(S433a)하고, 이후 전원 및 부하측 전선과 개폐기의 1차 및 2차 리드선을 연결하고 개폐기를 투입하여 바이패스 점퍼와 병렬회로를 구성하고 바이패스 점퍼를 분리(S433b)하는 과정을 거치게 된다.Specifically, instead of disconnecting the bypass jumper by connecting the power source and the load side wire with a jumper wire, an opening and closing device is installed on the electric pole under the built-in tread (S433a), and then the primary side and the secondary side The lead wire is connected and the switch is turned on to form a parallel circuit with the bypass jumper and the bypass jumper is separated (S433b).
여기서, 할입 전주를 신설에 이어 개폐기를 설치하는 경우, 상기 전선하향이동및설치단계(S461)에서 전원 및 부하측 전선을 점퍼선으로 연결하고 바이패스 점퍼를 분리하는 대신 상기 개폐기설치단계(S433a)와, 개폐기리드선연결단계(S433b)를 수행하여 설치할 수도 있다.Here, in the case where the breaker is installed after the break-in electric pole is newly installed, in the downward movement and installation step S461, the power source and the load side wire are connected by the jumper wire and the bypass jumper is removed, , And an opening and closing lead connecting step (S433b).
이후, 이용기구및불용설비철거단계(S500)를 수행하여 작업을 완료하게 된다.Thereafter, the use mechanism and the insoluble facility dismantling step (S500) are performed to complete the work.
본 발명에서는 무정전 배전공사를 위한 현장조사, 안전회의, 시작보고, 충전부방호 등 사전 준비단계와 방호장비 철거, 완료보고 등 사후 마무리단계는 일반적인 단계이므로 구체적인 설명은 생략하였으며, 본 발명의 공법은 작업자가 활선작업차의 바켓에 탑승하여 시행하게 된다.In the present invention, the post-finishing step such as the preliminary preparation step such as field surveys, safety meetings, start-up reports, and charging parts protection for uninterruptible power distribution works, demolition of protective equipment, and completion report are general steps, Will be carried on the bucket of the live car.
그리고, 본 공법의 공정은 해당 공사의 내용에 따라 일부 진행 순서를 변경하여 적용할 수도 있다.In addition, the process of this method may be applied by changing the order of some processes according to the contents of the corresponding construction.
본 공법은 임시로 장주를 구성하는 가완목을 고정식으로 간단하게 전주 상에 고정하고, 선로에서 발생하는 횡장력에도 무리없이 전선이동기구를 이용하여 안전하고 용이하게 전선을 이동시킬 수 있고, 전선의 가선에 따른 높은 장력이 발생하는 내장개소에서 현수애자연결구의 연결거리 조절로 선로의 장력을 완화하여 현수애자를 이동시키는 작업이 용이하다.This method can securely and easily move the wire by using the wire moving mechanism without any difficulty to the horizontal tension generated in the line, It is easy to move the suspension by loosening the tension of the line by adjusting the connection distance of the hanging insulator connection at the internal point where high tension is generated according to the line.
또한, 전원 및 부하측의 현수애자를 현수애자연결구의 양단으로 직접 연결함으로써, 선로의 장력이 암에 가해지지 않도록 기능한다.In addition, by connecting the suspending insulator of the power source and the load side directly to both ends of the suspending insulator connection, the tension of the line is prevented from being applied to the arm.
따라서, 본 고정식 가완목 장치 및 공법은 장치의 적용개소를 확대시킬 수 있고 작업시간을 단축시킬 수 있으며 안정적으로 전기설비 작업을 시행할 수 있도록 하는 효과를 제공하게 된다.Therefore, the present fixed type fastening apparatus and method can expand the application point of the apparatus, shorten the working time, and provide the effect of stably performing the electric equipment operation.
상기 서술한 내용 중 도면에 표시되지 않은 내용은 상기 서술된 내용을 바탕으로 당업자가 충분히 이해할 수 있는 내용으로 이하 도면에 표시되지 않아도 본 발명의 권리에 포함되어야 한다.The contents not described in the drawings should be understood by those skilled in the art based on the above description and should be included in the right of the present invention without being shown in the drawings.
이상에서와 같은 내용의 본 발명이 속하는 기술 분야의 당업자는 본 발명의 기술적 사상이나 필수적 특징을 변경하지 않고서 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시 예들은 모든 면에서 예시된 것이며 한정적인 것이 아닌 것으로 이해해야만 한다.It will be appreciated by those skilled in the art that the present invention may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. It is to be understood, therefore, that the embodiments described above are to be considered in all respects as illustrative and not restrictive.
본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구 범위의 의미 및 그리고 그 등가 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.It is intended that the present invention covers the modifications and variations of this invention provided they come within the scope of the appended claims and their equivalents. .
10 : 전주
100 : 암밴드
200 : 암
500 : 전선이동기구
600 : 랙기어
710 : 승강부
900 : 현수애자연결구10: Electric pole
100: Armband
200: Cancer
500: wire moving mechanism
600: Rack gear
710:
900: Suspension connector
Claims (9)
전주(10)의 둘레면에 암밴드(100)를 결합하고, 암밴드(100)의 양측에 암(200)을 결합하기 위한 고정식가완목장주설치단계(S100)와;
선로의 유형에 따라 상기 암(200) 상에
원형의 절연봉(510) 하단에 크람프(505)를 구비하여 상기 암(200)의 둘레면에 수직으로 고정되고, 상부에 랙기어(600)를 구비하여 승강부(710)와 결합하고, 승강부(710)의 상부에 전선을 수용하는 홈(711)과 탈락을 방지하는 덮개(712)와 고정장치를 구비하며, 승강부(710)의 내부에 상기 랙기어(600)와 기어 결합하는 헤리컬기어(713)와 상기 헤리컬기어(713)와 기어 결합하는 웜기어(715)와 상기 웜기어(715)와 결합하는 구동축(714)을 구비하되, 상기 승강부의 상부 홈(711)에 전선을 삽입하고 덮개(712)를 고정하여 탈락을 방지하고, 활선작업차의 유압렌치로 상기 구동축(714)을 구동하면 웜기어(715)와 헤리컬기어(713)가 동작하여 전선을 수용한 승강부(710)가 랙기어(600)의 기어 면을 따라 상하로 이동하는 전선이동기구(500) 또는
고정기구(920)를 구성하여 상기 암(200)의 일 측면에 결합되고, 양단에 회전시켜서 연결거리를 조절하며, 일측에 결합용 고리를 지닌 연결볼트(910)를 구성하여 전원 및 부하측 현수애자와 직접 연결하는 현수애자연결구(900)를 결합하되,
상기 전선이동기구(500)를 하단에 구비된 크람프를 이용하여 전선의 위치에 맞추어 암(200)의 일 면에 고정하거나, 고정기구를 이용하여 상기 현수애자연결구(900)를 현수애자의 위치에 맞추어 암(200) 상에 결합하고 전원 및 부하측 현수애자의 연결거리를 감안하여 현수애자연결구 양단의 연결볼트를 조작하거나, 고정기구 대용으로 전선이동기구(500)를 이용하여 현수애자연결구(900)를 지지하도록 설치 구성하는 선로이동용기구설치단계(S200)와;
상기 전선이동기구(500)를 이용하여 전선을 상향으로 또는 상기 현수애자연결구의 양단으로 현수애자를 이동시키되, 전선이동기구의 상부에 형성된 승강부(710)에 전선을 수용하여 탈락을 방지하고, 전선과 LP애자를 결속하는 바인드를 풀고 전선이동기구 승강부의 구동축(714)을 활선작업차의 유압렌치로 구동시켜서 승강부를 전선이동기구의 상부에 결합된 랙기어(600)의 측면을 따라 상향으로 이동시키거나, 2대의 활선용 장선기를 전원 및 부하측 완철(40)에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 완철로부터 현수애자를 분리하여 현수애자연결구 양단 연결볼트(910)의 고리에 연결한 후, 장선기를 차례로 장력 해제하고 철거하여 전원 및 부하측의 현수애자를 현수애자연결구(900)가 직접 연결하도록 하고, 완철의 상부로 경유하는 점퍼선의 위치에 맞추어 전선이동기구(500)를 암(200)의 일 면에 고정하고, 점퍼선을 LP애자에서 분리하여 전선이동기구(500)로 지지함으로써, 기존 선로를 완철 상에서 분리하여 가완목의 암 상으로 이동시키는 선로이동단계(S300)와;
상기 선로이동단계(S300)를 통해 고정식 가완목의 암 상으로 선로를 이동시킨 후, 원하는 전기설비 작업을 시행하는 설비작업단계(S400)와;
상기 선로이동단계(S300) 및 설비작업단계(S400)에서 이용한 기구를 설치의 역순으로 환원하여 철거하고, 선로 구성에 불필요한 전주 및 전선 설비를 철거하는 이용기구및불용설비철거단계(S500);를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.
In the fixed type seamless method used for uninterruptible power distribution,
A step S100 of installing a fixed type ranch ranch for coupling an armband 100 to the circumference of the electric pole 10 and coupling the arm 200 to both sides of the armband 100;
Depending on the type of line,
A crumb 505 is provided at the lower end of the circular cutting bar 510 and is fixed to the circumferential surface of the arm 200. The rack gear 600 is coupled to the elevating portion 710, A groove 711 for accommodating electric wires at the upper part of the elevating part 710 and a lid 712 for preventing falling off and a fixing device are provided in the elevating part 710, A worm gear 715 to be engaged with the helical gear 713 and a drive shaft 714 to be coupled to the worm gear 715. The worm gear 715 is connected to the upper groove 711 of the lift part When the drive shaft 714 is driven by the hydraulic wrench of the live operation tool, the worm gear 715 and the helical gear 713 are operated to move the lifting portion 710 are moved up and down along the gear surface of the rack gear 600,
And a connecting bolt 910 having a coupling ring on one side thereof is formed to constitute a fixing mechanism 920. The connecting bolt 910 is coupled to one side of the arm 200, And a suspension connector 900 directly connected to the suspension connector 900,
The wire moving mechanism 500 may be fixed to one surface of the arm 200 by using a crumb provided at the lower end of the wire to match the position of the electric wire or the suspension connector 900 may be fixed to a position The connection bolts on both ends of the suspension connector are operated in consideration of the connection distance between the power source and the load-side suspending insulator, or the suspension connector 900 (S200);
The wire moving mechanism 500 is used to move the suspender insulator upward or to both ends of the hanging insulator connection opening so as to receive the wire in the elevating portion 710 formed at the upper portion of the wire moving mechanism, And the drive shaft 714 of the electric wire moving mechanism elevating portion is driven by the hydraulic wrench of the live wire working vehicle so that the elevating portion is moved upward along the side surface of the rack gear 600 coupled to the upper portion of the electric wire moving mechanism Or the tension applied to the suspension insulator is released by pulling the electric wires of the power source and the load side, and the suspension insulator is separated from the coarse iron to connect the two ends of the suspension insulator connection bolt 910 ), The tensioners are successively released from the tension and dismantled in order to connect the suspending insulators of the power source and the load side directly to the suspension insulator connection port 900, The wire moving mechanism 500 is fixed to one surface of the arm 200 in accordance with the position of the jumper wire passing through the upper portion and the jumper wire is separated from the LP insulator and supported by the wire moving mechanism 500, A line moving step (S300) of separating and moving the arm to the arm of the fastener;
A facility operation step (S400) for moving the line to the arm of the fixed type door through the line moving step (S300) and then performing a desired electric equipment operation;
A utilization mechanism and an insoluble facility dismantling step (S500) for reducing and dismounting the mechanisms used in the line moving step (S300) and the equipment working step (S400) in the order of installation and dismantling the electric pole and wire facilities unnecessary for the line configuration; Wherein the unloading and unloading operation is performed by the unloading operation.
상기 설비작업단계(S400)에서,
전기설비 작업이 완철 교체인 경우,
기존 완철 및 애자를 철거하고 새로운 완철 및 애자를 설치하는 완철및애자교체단계(S410)와,
기존 완철이 핀장주를 구성하는 경우, 전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선를 LP애자와 바인드로 결속하거나,
또는, 기존 완철이 내장주를 구성하는 경우, 2대의 활선용 장선기를 새로 설치한 전원 및 부하측 완철에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 현수애자연결구(900) 양단으로부터 현수애자를 분리하여 전원 및 부하측 완철과 쇄클을 이용하여 연결한 후, 장선기를 철거하고, 완철의 상부로 경유하는 점퍼선을 전선이동기구(500)에서 분리하여 LP애자와 바인드로 결속하여 지지하는 선로복귀단계(S411)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.
The method according to claim 1,
In the facility operation step (S400)
If the electrical equipment operation is a full replacement,
(Step S410) of removing the existing full iron and the insulator and installing a new full iron and the insulator,
The driving shaft 714 of the wire moving mechanism elevating portion is driven to move the elevating portion 710 which receives the electric wire to the upper portion along the side surface of the rack gear 600 coupled to the upper portion of the wire moving mechanism Moves the wires downward, binds the wires with the LP insulator and binds them,
Alternatively, in the case where the existing solid wire constitutes the built-in wire, the two live wire wires are connected to the newly installed power source and the load side barb, and the electric power and the wire on the load side are pulled to release the tension applied to the suspension insulator, And the jumper wire passing through the upper part of the solid iron wire is separated from the wire moving mechanism 500 and bound to the LP insulator and bound to be supported (S411), wherein the line restoring step (S411) includes a line returning step (S411).
상기 설비작업단계(S400)에서,
전기설비 작업이 LP애자 교체인 경우,
기존 LP애자를 철거하고 새로운 LP애자를 설치하는 LP애자교체단계(S420)와,
전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선를 LP애자와 바인드로 결속하여 지지하는 선로복귀단계(S421)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.The method according to claim 1,
In the facility operation step (S400)
If the electrical equipment operation is a LP insulator replacement,
Replacing the LP insulator (S420) for removing the existing LP insulator and installing a new LP insulator,
The driving shaft 714 of the electric wire moving mechanism elevating portion is driven to move the elevating portion 710 accommodating the electric wire in the upper portion downward along the side surface of the rack gear 600 coupled to the upper portion of the electric wire moving mechanism, (S421) for restraining and supporting the cable to the uninterrupted power distribution work.
상기 설비작업단계(S400)에서,
전기설비 작업이 장주 변경인 경우,
기존 완철과 LP애자를 철거하고 겹 완철를 설치하는 완철교체단계(S430)와,
새로 설치한 전원 및 부하측 완철에 쇄클을 이용하여 현수애자를 연결하는 현수애자설치단계(S431)와,
전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키는 전선하향이동단계(S432)와,
2대의 활선용 장선기를 새로 설치한 전원 및 부하측 완철에 연결하여 전원 및 부하측의 전선을 당기고, 바이패스 점퍼를 이용하여 전선이동기구 승강부(710) 상의 전선과 병렬회로를 구성하고, 현수애자의 연결거리를 감안하여 전원 및 부하측 전선을 절단하고 피복을 벗겨서 데드앤드크람프로 현수애자와 전선을 연결한 후 장선기를 철거하고, 전원 및 부하측 전선을 점퍼선으로 연결하여 바이패스 점퍼와 병렬회로를 구성하고, 완철의 상부로 경유하는 점퍼선은 LP애자를 설치하고, 바인드로 결속하여 지지하고, 바이패스 점퍼를 분리하는 내장전선설치단계(S433)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.
The method according to claim 1,
In the facility operation step (S400)
If the electrical equipment operation is a long-term change,
(S430) of replacing the existing bare iron and the LP insulator and installing the double bare iron,
A suspender insulator installation step (S431) for connecting the suspending insulator to the newly installed power source and the load side brass using a shackle,
A wire downward moving step S432 for moving the elevating portion 710, which receives the wire at the upper portion by driving the drive shaft 714 of the wire moving mechanism elevating portion, downward along the side surface of the rack gear 600 coupled to the upper portion of the wire moving mechanism, )Wow,
The two live wire harnesses are connected to the newly installed power source and the load side brass wire to pull the electric wires of the power source and the load side and to constitute a parallel circuit with electric wires on the wire moving mechanism elevator 710 by using the bypass jumper, Considering the connection distance, cut off the power supply and load side wires, peel off the cover, connect the dead and crumpler suspender insulator and wire, demolish the equipment, connect the power supply and load side wires to the jumper wire and configure the bypass jumper and the parallel circuit. And a built-in electric wire installation step (S433) of installing a jumper wire passing through the upper part of the solid iron bar to install and retain the LP insulator, bind the same, and separate the bypass jumper Fixed - type unloading method.
상기 설비작업단계(S400)에서,
전기설비 작업이 1상 또는 2상 선로의 3 상화인 경우,
기존 완철과 애자를 철거하고 새로운 완철과 애자를 설치하는 완철및애자교체단계(S440)와,
증가하는 1 또는 2 상의 선로를 신설한 완철 상에 설치하되, 전선을 LP애자의 상부에 바인드로 결속하거나, 현수애자와 연결하는 상신설단계(S441)와,
전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선를 LP애자와 바인드로 결속하거나,
또는, 2대의 활선용 장선기를 새로 설치한 전원 및 부하측 완철에 연결하고 전원 및 부하측의 전선을 당겨서 현수애자에 걸리는 장력을 해제하고 현수애자연결구(900) 양단으로부터 현수애자를 분리하여 전원 및 부하측 완철과 쇄클을 이용하여 연결한 후, 장선기를 철거하고, 완철의 상부로 경유하는 점퍼선을 전선이동기구(500)에서 분리하여 LP애자와 바인드로 결속하여 지지하는 선로복귀단계(S442)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.
The method according to claim 1,
In the facility operation step (S400)
If the electrical equipment operation is a three-phase conversion of one-phase or two-phase line,
(Step S440) of removing the existing wrought iron and the insulator and installing new wrought iron and insulators,
(S441) in which a wire is connected to an upper portion of the LP insulator by a binding or connected to a suspending insulator,
The driving shaft 714 of the electric wire moving mechanism elevating portion is driven to move the elevating portion 710 accommodating the electric wire in the upper portion downward along the side surface of the rack gear 600 coupled to the upper portion of the electric wire moving mechanism, Respectively,
Alternatively, the two live wires are connected to the newly installed power source and the load side iron wire, and the electric power and the wires on the load side are pulled to release the tension applied to the suspending insulator, and the suspender insulator is separated from both ends of the suspending insulator connection hole 900, And a line returning step (S442) of separating the jumper wire passing through the upper part of the wire rods from the wire moving mechanism (500) and binding and binding the LP insulator and the bind wire Wherein the unloading operation is performed in the uninterruptible power distribution system.
상기 설비작업단계(S400)에서,
전기설비 작업이 전주 교체인 경우,
전기 선로를 감안하여 기존 전주 인근에 새로운 전주를 신설하는 전주설치단계(S450)와,
기존 전주 상에 설치된 완철과 애자를 철거하고 신설한 전주 상에 완철과 애자를 설치하는 완철/애자철거및설치단계(S451)와,
기존 전주가 핀장주인 경우, 전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선을 신설한 전주의 완철 상에 설치된 LP애자와 바인드로 결속하여 지지하거나,
또는, 기존 전주가 내장주인 경우, 신설한 전주에서 길어지는 경간측 구간에 선로를 신설하고, 2대의 활선용 장선기를 신설 전주의 전원 및 부하측 완철에 연결하여 신설한 전주를 기준으로 양측의 전선을 당기고, 신설 전주에서 전선을 내장으로 설치할 것을 감안하여 기존 전선과 상기 신설한 구간의 전선을 바이패스 점퍼로 연결하여 병렬회로를 구성하고, 현수애자와 연결할 거리 및 점퍼선의 길이를 감안하여 기존 전선을 절단하고, 피복을 벗겨서 데드앤드크람프로 현수애자와 연결한 후, 장선기를 철거하고, 점퍼선을 신설한 선로와 연결하여 바이패스 점퍼와 병렬회로를 구성하고, 완철의 상부로 경유하는 점퍼선을 LP애자와 바인드로 결속하여 지지하고, 바이패스 점퍼를 분리하는 선로신설및이동단계(S452)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.
The method according to claim 1,
In the facility operation step (S400)
If the electrical equipment work is a pole change,
(S450) in which a new electric pole is installed near the existing electric pole in consideration of the electric line,
(S451), which is used to remove the brass and insulators installed on the existing electric pole and install the brass and insulators on the newly installed electric pole,
The driving shaft 714 of the wire moving mechanism elevating portion is driven to move the elevating portion 710 accommodating the electric wire to the upper portion along the side of the rack gear 600 coupled to the upper portion of the wire moving mechanism And the wires are connected and held together by the LP insulator and the bind which are installed on the bare iron of the electric pole newly installed,
Or, if the existing electric pole is the built-in electric pole, a new railway line is to be established between the span of the newly installed electric pole and the two live wire rods are connected to the power pole of the new pole and the load side pole of the new pole. Considering the installation of the electric wire in the new electric pole, it is necessary to construct a parallel circuit by connecting the existing electric wire and the electric wire of the newly created section with the bypass jumper, and consider the distance to be connected to the suspender insulator and the length of the jumper wire, Cut off the cover and connect it to the Dead and Krampro Suspension Insulator. Then remove the connector and connect the jumper wire to the newly installed line to form a parallel circuit with the bypass jumper. (S452) of binding and supporting the LP insulator and the bind and separating the bypass jumper. This is a fixed type fastening method used for uninterrupted power distribution works.
상기 설비작업단계(S400)에서,
전기설비 작업이 할입 전주 신설인 경우,
사전에 신설한 전주 상에 완철과 애자를 설치하는 완철및애자설치단계(S460)와,
전선이동기구 승강부의 구동축(714)을 구동시켜서 상부에 전선을 수용한 승강부(710)를 전선이동기구 상부에 결합된 랙기어(600)의 측면을 따라 하향으로 이동시키고, 전선을 신설한 할입 전주의 완철 상에 설치된 LP애자와 바인드로 결속하여 지지하거나,
또는, 할입 전주가 내장주인 경우, 2대의 활선용 장선기를 전원 및 부하측 완철에 연결하여 양측의 전선을 당기고, 바이패스 점퍼를 할입 전주의 전원 및 부하측 전선과 연결하여 병렬회로를 구성하고, 현수애자와 연결할 거리를 감안하여 전선을 절단하고 피복을 벗겨서 데드앤드크람프로 현수애자와 연결한 후 장선기를 철거하고, 전원 및 부하측 전선을 점퍼선으로 연결하여 바이패스 점퍼와 병렬회로를 구성하고, 완철의 상부로 경유하는 점퍼선을 LP애자와 바인드로 결속하여 지지하고, 바이패스 점퍼를 분리하는 전선하향이동및설치단계(S461)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.The method according to claim 1,
In the facility operation step (S400)
If the electrical equipment work is newly established,
(S460) in which a wire and an insulator are installed in a preform newly installed in advance,
The driving shaft 714 of the wire moving mechanism elevating portion is driven to move the elevating portion 710 accommodating the electric wire in the upper portion downward along the side surface of the rack gear 600 coupled to the upper portion of the wire moving mechanism, It is supported by binding with LP insulator and bind which are installed on the pole of the pole,
Alternatively, in the case where the induction pole is the built-in coil, the two live wire coils are connected to the power source and the load coils to pull the coils on both sides, and the bypass jumper is connected to the power coils and the load coils of the coils, , Cut off the wire, peel off the cover and connect it to the dead and krampro suspender, remove the jumper, connect the power supply and the load side wire to the jumper wire to construct the bypass jumper and the parallel circuit, (S461) of binding and jumpering the jumper wire passing through the upper portion to the LP insulator and binding and separating the bypass jumper (S461).
상기 설비작업단계(S400)의 내장전선설치단계(S433)에서,
전기설비 작업이 장주 변경에 이어 개폐기 설치인 경우,
전원 및 부하측 전선을 점퍼선으로 연결하고, 바이패스 점퍼를 분리하는 대신 내장 완철단 아래의 전주 상에 개폐기를 설치하는 개폐기설치단계(S433a)와,
전원 및 부하측 전선과 개폐기의 1차 및 2차 리드선을 연결하고, 개폐기를 투입하여 바이패스 점퍼와 병렬회로를 구성하고, 바이패스 점퍼를 분리하는 개폐기리드선연결단계(S433b)를 포함하여 이루어지는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 공법.
5. The method of claim 4,
In the built-in wire installation step (S433) of the facility operation step (S400)
In the case where the electrical equipment operation is followed by a change of state,
(S433a) for connecting the power source and the load-side wire with a jumper wire and installing an opening / closing device on a pole below the built-
(S433b) connecting the primary and secondary lead wires of the power source and the load side wire to the switch, constituting a parallel circuit with the bypass jumper by putting the switch, and disconnecting the bypass jumper This is a fixed method for uninterrupted power distribution.
전주(10)의 외부 둘레면에 결합되고, 양측으로 암(200)과 결합하도록 구성되는 암밴드(100);
원형의 절연봉(510) 하단에 크람프(505)를 구비하여 상기 암(200)의 둘레면에 수직으로 고정되고, 상부에 랙기어(600)를 구비하여 승강부(710)와 결합하고, 승강부(710)의 상부에 전선을 수용하는 홈(711)과 탈락을 방지하는 덮개(712)와 고정장치를 구비하며, 승강부(710)의 내부에 상기 랙기어(600)와 기어 결합하는 헤리컬기어(713)와 상기 헤리컬기어(713)와 기어 결합하는 웜기어(715)와 상기 웜기어(715)와 결합하는 구동축(714)을 구비하되, 상기 승강부의 상부 홈(711)에 전선을 삽입하고 덮개(712)를 고정하여 탈락을 방지하고, 활선작업차의 유압렌치로 상기 구동축(714)을 구동하면 웜기어(715)와 헤리컬기어(713)가 동작하여 전선을 수용한 승강부(710)가 랙기어(600)의 기어 면을 따라 상하로 이동하는 전선이동기구(500);
고정기구(920)를 구성하여 상기 암(200)의 일 측면에 결합되고, 양단에 회전시켜서 연결거리를 조절하며 일측에 결합용 고리를 지닌 연결볼트를 구성하여 전원 및 부하측 현수애자를 직접 연결하는 현수애자연결구(900);를 포함하여 구성하는 것을 특징으로 하는 무정전 배전공사에 이용하는 고정식 가완목 장치.
A fixed type fastener for use in uninterruptible power distribution,
An armband (100) coupled to the outer circumferential surface of the electric pole (10) and configured to mate with the arm (200) on both sides;
A crumb 505 is provided at the lower end of the circular cutting bar 510 and is fixed to the circumferential surface of the arm 200. The rack gear 600 is coupled to the elevating portion 710, A groove 711 for accommodating electric wires at the upper part of the elevating part 710 and a lid 712 for preventing falling off and a fixing device are provided in the elevating part 710, A worm gear 715 to be engaged with the helical gear 713 and a drive shaft 714 to be coupled to the worm gear 715. The worm gear 715 is connected to the upper groove 711 of the lift part When the drive shaft 714 is driven by the hydraulic wrench of the live operation tool, the worm gear 715 and the helical gear 713 are operated to move the lifting portion 710) is moved up and down along the gear surface of the rack gear (600);
The fixing mechanism 920 is constituted so as to be connected to one side of the arm 200 and to be rotated at both ends to adjust the connection distance and to have a connecting bolt having a coupling ring on one side to directly connect the power source and the load- And a hanging insulator connection port (900). The stationary type fastening apparatus used in the uninterruptible power distribution work.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020160131108A KR101757195B1 (en) | 2016-10-11 | 2016-10-11 | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work |
PCT/KR2016/013377 WO2018070593A1 (en) | 2016-10-11 | 2016-11-21 | Fixed type temporary arm apparatus and method used for non-blackout power distribution work |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020160131108A KR101757195B1 (en) | 2016-10-11 | 2016-10-11 | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101757195B1 true KR101757195B1 (en) | 2017-07-11 |
Family
ID=59354555
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020160131108A KR101757195B1 (en) | 2016-10-11 | 2016-10-11 | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work |
Country Status (2)
Country | Link |
---|---|
KR (1) | KR101757195B1 (en) |
WO (1) | WO2018070593A1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108598747A (en) * | 2018-03-30 | 2018-09-28 | 广东电网有限责任公司佛山供电局 | A kind of 10kV overhead transmission lines shunt line apparatus temporarily |
CN110752549A (en) * | 2019-12-04 | 2020-02-04 | 云南电网有限责任公司带电作业分公司 | Operation method for breaking or connecting 10kV strain rod drainage wire of insulating short rod |
CN113315027A (en) * | 2021-05-31 | 2021-08-27 | 青海送变电工程有限公司 | Auxiliary device is changed to overhead ground wire gold utensil |
KR20210143033A (en) * | 2020-05-19 | 2021-11-26 | 한국전력공사 | Apparatus for fixing power cable |
KR20220153319A (en) * | 2021-05-11 | 2022-11-18 | 한국전력공사 | Portable electric pole |
KR20230149080A (en) * | 2022-04-19 | 2023-10-26 | 주식회사 이에스시스템 | Bypass Method Among The Truce Lines For Temporary System Configuration Between Transmission Lines |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110676786A (en) * | 2019-10-12 | 2020-01-10 | 国网湖北省电力有限公司随州供电公司 | Herringbone frame fixing device for electric power |
CN110739639B (en) * | 2019-11-25 | 2024-06-04 | 国网新疆电力有限公司乌鲁木齐供电公司 | Emergency disconnection processing device |
CN111404066B (en) * | 2020-04-23 | 2022-01-21 | 中国长江电力股份有限公司 | GIS body equipment technical transformation construction method |
CN111622576A (en) * | 2020-05-14 | 2020-09-04 | 张加叶 | High-strength metal electric power tower structure and erection method |
CN114725833B (en) * | 2022-05-09 | 2024-04-02 | 国网安徽省电力有限公司马鞍山供电公司 | Ring piece mounting platform, mounting device, mounting method and electric quantity control method |
CN115275871B (en) * | 2022-06-13 | 2023-07-07 | 国网山东省电力公司济南供电公司 | Tensioning device for high-altitude power construction cable |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101579183B1 (en) | 2015-02-16 | 2015-12-24 | 주식회사 현신 | Apparatus for exchanging distribution line applied to the processing of distribution line replacement |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20130024565A (en) * | 2011-08-31 | 2013-03-08 | 한국전력공사 | Wire changing device inside of electric pole |
KR101344289B1 (en) * | 2012-04-27 | 2013-12-23 | 임용호 | The pole fittings changing method use lifting apparatus |
KR20150087785A (en) * | 2014-01-20 | 2015-07-30 | 서광전기통신공사(주) | Method for hot line work of power distribution equipment |
KR101616484B1 (en) * | 2015-09-21 | 2016-04-28 | (주)우신전기기술사사무소 | Method for changing power distribution line in hot line |
-
2016
- 2016-10-11 KR KR1020160131108A patent/KR101757195B1/en active IP Right Grant
- 2016-11-21 WO PCT/KR2016/013377 patent/WO2018070593A1/en active Application Filing
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101579183B1 (en) | 2015-02-16 | 2015-12-24 | 주식회사 현신 | Apparatus for exchanging distribution line applied to the processing of distribution line replacement |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108598747A (en) * | 2018-03-30 | 2018-09-28 | 广东电网有限责任公司佛山供电局 | A kind of 10kV overhead transmission lines shunt line apparatus temporarily |
CN110752549A (en) * | 2019-12-04 | 2020-02-04 | 云南电网有限责任公司带电作业分公司 | Operation method for breaking or connecting 10kV strain rod drainage wire of insulating short rod |
KR102355161B1 (en) * | 2020-05-19 | 2022-01-25 | 한국전력공사 | Apparatus for fixing power cable |
KR102355167B1 (en) * | 2020-05-19 | 2022-02-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210148982A (en) * | 2020-05-19 | 2021-12-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210148981A (en) * | 2020-05-19 | 2021-12-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210148979A (en) * | 2020-05-19 | 2021-12-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210148978A (en) * | 2020-05-19 | 2021-12-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210148980A (en) * | 2020-05-19 | 2021-12-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210148983A (en) * | 2020-05-19 | 2021-12-08 | 한국전력공사 | Apparatus for fixing power cable |
KR102355164B1 (en) * | 2020-05-19 | 2022-02-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20210143033A (en) * | 2020-05-19 | 2021-11-26 | 한국전력공사 | Apparatus for fixing power cable |
KR102355168B1 (en) * | 2020-05-19 | 2022-02-08 | 한국전력공사 | Apparatus for fixing power cable |
KR102355169B1 (en) * | 2020-05-19 | 2022-02-08 | 한국전력공사 | Apparatus for fixing power cable |
KR102355166B1 (en) * | 2020-05-19 | 2022-02-08 | 한국전력공사 | Apparatus for fixing power cable |
KR102355165B1 (en) * | 2020-05-19 | 2022-02-08 | 한국전력공사 | Apparatus for fixing power cable |
KR20220153319A (en) * | 2021-05-11 | 2022-11-18 | 한국전력공사 | Portable electric pole |
KR102587413B1 (en) * | 2021-05-11 | 2023-10-12 | 한국전력공사 | Portable electric pole |
CN113315027A (en) * | 2021-05-31 | 2021-08-27 | 青海送变电工程有限公司 | Auxiliary device is changed to overhead ground wire gold utensil |
KR20230149080A (en) * | 2022-04-19 | 2023-10-26 | 주식회사 이에스시스템 | Bypass Method Among The Truce Lines For Temporary System Configuration Between Transmission Lines |
KR102641663B1 (en) | 2022-04-19 | 2024-02-28 | 주식회사 이에스시스템 | Bypass Method Among The Truce Lines For Temporary System Configuration Between Transmission Lines |
Also Published As
Publication number | Publication date |
---|---|
WO2018070593A1 (en) | 2018-04-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101757195B1 (en) | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work | |
KR101955155B1 (en) | Uninterruptible power method and Indirect live lifting device for Electronic pole for power line | |
KR101777080B1 (en) | Uninterrupted power distribution method in which wires are separated in de-energized power lines state by using insulated live wire grip and bypass jumper cables | |
KR20150087780A (en) | Method for hot line work of power distribution equipment | |
KR101906769B1 (en) | Device for replacing an lp insulator supporting power line | |
KR20130026849A (en) | Cable support apparatus and method for separating power cable using the same | |
MXPA03011498A (en) | Wire-changing device inside of electric pole and non-power-failure power distribution method. | |
KR20130121398A (en) | The pole fittings changing method use lifting apparatus | |
KR101616484B1 (en) | Method for changing power distribution line in hot line | |
KR101593000B1 (en) | Crossarm lifting apparatus for live line work and live line job method | |
WO2018097357A1 (en) | Movable auxiliary arm apparatus for use in uninterruptible power distribution works and method using same | |
KR100857774B1 (en) | Pole clamp applied in uninterrupted replacement method of utility pole for distribution line | |
KR101043557B1 (en) | Crossarm holder applied in uninterupted method for replacement of utility pole without temporary move of wire and crossarm | |
CN102623927B (en) | Charged for replacement 220kV circuit multiloop double bundle conductor insulator tool and method | |
JP5056659B2 (en) | Utility pole rebuilding tool and utility pole rebuilding method | |
KR101475264B1 (en) | Power transmission cable insulation support | |
CN209844414U (en) | Single-string tension insulator overhaul platform | |
KR100355492B1 (en) | wire-changing device inside of electric pole and non-power-failure power distribution method | |
US20160300655A1 (en) | Site Replacement Of Internal Saturable Reactors Of A Rectifier Power Transformer | |
KR101043559B1 (en) | Uninterupted method for replacement of utility pole without temporary move of wire using isolating pole and crosscarm holder | |
KR102173375B1 (en) | Uninterruptible power method and lndirect live lifting device for Electronic polefor power line | |
US9997896B2 (en) | By-pass systems for overhead power lines | |
KR200252786Y1 (en) | wire-changing device inside of electric pole | |
CN211226071U (en) | Hoisting device for on-load tap-changer of angle-type converter transformer | |
KR20100036065A (en) | Exchanging method of distribution line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GRNT | Written decision to grant |