CN106463940A - Auxiliary device for power distribution facility live-line working, and power distribution facility live-line working method using same - Google Patents
Auxiliary device for power distribution facility live-line working, and power distribution facility live-line working method using same Download PDFInfo
- Publication number
- CN106463940A CN106463940A CN201580030707.XA CN201580030707A CN106463940A CN 106463940 A CN106463940 A CN 106463940A CN 201580030707 A CN201580030707 A CN 201580030707A CN 106463940 A CN106463940 A CN 106463940A
- Authority
- CN
- China
- Prior art keywords
- cross arm
- wires
- wooden cross
- mentioned
- insulator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/24—Cross arms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01B—CABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
- H01B17/00—Insulators or insulating bodies characterised by their form
- H01B17/14—Supporting insulators
- H01B17/16—Fastening of insulators to support, to conductor, or to adjoining insulator
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/02—Devices for adjusting or maintaining mechanical tension, e.g. take-up device
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/05—Suspension arrangements or devices for electric cables or lines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/20—Spatial arrangements or dispositions of lines or cables on poles, posts or towers
- H02G7/205—Installation of electric cables, extending along a pole
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Electric Cable Installation (AREA)
Abstract
A power distribution facility live-line working method is disclosed. The power distribution facility live-line working method of the present invention comprises the steps of: mounting an temporary arm part on an electric pole; transferring an electric wire connected to the electric pole to an electric wire support part mounted on the temporary arm part; by moving the temporary arm part or the electric wire support part upward, separating the electric wire from an existing LP insulator pre-installed on a regular pole; replacing the existing LP insulator with a new LP insulator; moving the temporary arm part or the electric wire support part downward toward the new LP insulator; and transferring the electric wire connected to the electric wire support part to the new LP insulator.
Description
Technical field
The present invention is controller switching equipment livewire work servicing unit and utilizes it to carry out controller switching equipment livewire work method
Related content, is for changing the controller switching equipment livewire work servicing unit installing LP insulator on utility poles and utilization
It carries out the related content of controller switching equipment livewire work method.
Background technology
Cross-arm typically can be installed in the top of electric pole, and cross-arm is by horizontal iron cross arm and 3 insulation being arranged on iron cross arm
Son composition.3 phase electric wires are connected respectively to 3 insulators by binding agent.
When safeguarding mounted electric pole, cross-arm, insulator, replace old insulator with new insulator, replace with new cross-arm
Old cross-arm, is replaced with regard to electric pole by new electric pole, or the prolongation angle increase of electric wire that causes of the change in location of electric pole etc. is former
Cause, has and PIN cross-arm is replaced with the operations such as interior cross-arm.Also have because the extended position change etc. of electric wire newly sets newly setting of electric pole etc.
The operation of controller switching equipment.
These work are to move up and down the electric wire of electriferous state, therefore have certain security risk.So, in order to
Reduce security risk, preferably carry out livewire work, just developing various device and technology.
Related online technique Korean published Patent announce No. 2006-0082713 (2006.7.19. is open,
Denomination of invention:Possess 2 dimensions and the distribution line operation multi-axis robot of the comprehensive driving method of 3-dimensional) illustrate.
Content of the invention
Problem to be solved
The purpose of the present invention is, provides controller switching equipment livewire work servicing unit and to utilize it to carry out controller switching equipment charged
The method of operation, makes staff can easily install and be applied to controller switching equipment livewire work, and staff utilizes electric power
While the local remote auto away from electric wire moves electric wire, carry out changing the charged work of controller switching equipment of LP insulator safely
Industry.
The method of solution problem
The controller switching equipment livewire work servicing unit of the present invention:Include interim wooden cross arm, by above-mentioned interim wooden cross arm
Fix interim wooden cross arm fixed part on utility poles, the 1st lifting moving portion that above-mentioned interim wooden cross arm is moved up and down, installation
At above-mentioned interim wooden cross arm, and support the wire rack of the electric wire being connected on said wires bar, by upper and lower for said wires support
2nd lifting moving portion of movement.
Above-mentioned 1st lifting moving portion preferably include be arranged on above-mentioned interim wooden cross arm fixed part electric pole installation portion,
It is arranged on said wires bar installation portion, after the power accepting the 1st driver, move up and down the 1st driving of above-mentioned interim wooden cross arm
Portion.
Above-mentioned 2nd lifting moving portion preferably includes interim wooden cross arm installation portion, the peace being arranged on above-mentioned interim wooden cross arm
It is contained in above-mentioned interim wooden cross arm installation portion, after the power accepting the 2nd driver, move up and down the 2nd driving of said wires support
Portion.
The controller switching equipment livewire work method of the present invention includes interim wooden cross arm is installed to the stage of electric pole, will connect
Electric wire on said wires bar moves to the stage of the wire rack being arranged on above-mentioned interim wooden cross arm, by above-mentioned interim wood
Cross-arm or said wires support move up, and make said wires away from the rank of the old LP insulator being arranged on common cross-arm
Section, with the stage of the old LP insulator of new LP replacing insulator, by above-mentioned interim wooden cross arm or said wires support to above-mentioned new LP
Stage that insulator direction moves down, move the said wires being connected to said wires support to the rank of new LP insulator
Section.
It is that the 1st lifting moving portion accepts the 1st driver by the Perfected process that above-mentioned interim wooden cross arm moves up or down
Power after, move up and down above-mentioned interim wooden cross arm.
It is that the 2nd lifting moving portion accepts the 2nd driver by the best approach that said wires support moves up or down
After power, move up and down said wires support.
Invention effect
Controller switching equipment livewire work servicing unit according to the present invention, utilizes the electricity of the 1st driver or the 2nd driver
Power, automatically adjusts the height of interim wooden cross arm, the height of each wire rack, the electric wire height being fixed on wire rack, can be light
Pine carries out the replacing operation of LP insulator.
According to the present invention, the 1st driver or the 2nd driver can use electric drill, the electricity being generally used for changing controller switching equipment
The electric tools such as dynamic screwdriver, staff can be easily real without specially preparing mobile electric device needed for wire rack
Existing.
It according to the present invention, is possible not only to multistage and adjusts interim wooden cross arm and the overall height of wire rack, by only upper and lower
The sub-extension that in mobile wire rack, electric wire fixing segments is formed, gets final product 3 sections of regulation electric wire fixing segments or electric wire height.
According to the present invention, can regulate electric wire fixing segments or electric wire height by automatic or manual, regulation length is up to vertical extension
The length in portion, the length of main extension, the length sum of sub-extension, regulate interim wooden cross arm and wire rack by multistage
Highly, close to after target fulcrum, by the sub-extension of fine setting, electric wire fixing segments is placed in more accurately object height.
According to the present invention, staff, according to operating environment or convenience, optionally adjusts interim wooden cross arm
Highly, wire rack whole height, the height of sub-extension, can stablize, easily enter to be about to electric wire and be temporarily placed within electric wire
Operation on support, guarantee the operation that LP insulator requisite space will be changed.
According to the present invention, utilizing the 1st driver or the 2nd driver, staff can be long-range with electric wire remote position
Electric wire is moved to the top of old LP insulator, can more easily control guarantee to change the livewire work space needed for LP insulator, can
Reduce staff and line contacts when changing LP insulator and cause the danger of security incident.
According to the present invention, check, keep in repair, when changing the different LP insulator of multiple height, utilize the 2nd lifting moving portion,
According to the height of LP insulator, individually lift wire rack, can easily carry out operation, use live-wire work tool and utensil to be stranded
When difficult, it is also possible to adjust up and down and use position, make operation be more prone to.
According to the present invention, in the state of multiple wire racks are arranged on interim wooden cross arm, move up interim wooden cross arm, can
Avoid the trouble that wire rack one by one moves up, all of wire rack can be moved up with identical displacement simultaneously.
Brief description
Fig. 1 is the perspective sketch map of the controller switching equipment livewire work servicing unit of one embodiment of the invention.
Fig. 2 is the perspective sketch map in the interim wooden cross arm fixed part of one embodiment of the invention and the 1st lifting moving portion.
Fig. 3 is the lateral concept map of the 1st lifting moving portion internal structure of one embodiment of the invention.
Fig. 4 is that the concept map that the 1st drive division of one embodiment of the invention runs is described.
Fig. 5 is the perspective sketch map in the wire rack of one embodiment of the invention and the 1st lifting moving portion.
Fig. 6 is that the concept map that the 1st lifting moving portion of one embodiment of the invention runs is described.
Fig. 7 is for illustrating the concept map inserting electric wire process in electric wire fixing segments of one embodiment of the invention.
Fig. 8 is the flow chart of the controller switching equipment livewire work method that one embodiment of the invention is described.
Fig. 9 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates interim wooden cross arm is fixed on electricity
The concept map of line bar process.
Figure 10 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates wire rack to electric wire side
To the concept map of the process of moving up.
Figure 11 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates to move electric wire to electric wire and props up
The concept map of frame process.
Figure 12 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates to move up wire rack,
Make electric wire away from the concept map of old LP insulator process.
Figure 13 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates with new LP replacing insulator old
The concept map of LP insulator process.
Figure 14 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates wire rack exhausted to new LP
Edge direction moves down the concept map of process.
Figure 15 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates electric wire to new LP insulator
The concept map of moving process.
Figure 16 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates interim wooden cross arm from electric wire
The concept map of bar unloading process.
Figure 17 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates to be fixed on interim wooden cross arm
The concept map of electric pole process.
Figure 18 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates wire rack to electric wire side
To the concept map of the process of moving up.
Figure 19 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates to move electric wire to electric wire and props up
The concept map of frame process.
Figure 20 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates to move up wire rack,
Make electric wire away from the concept map of old LP insulator process.
Figure 21 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates with new LP replacing insulator old
The concept map of LP insulator process.
Figure 22 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates wire rack exhausted to new LP
Edge direction moves down the concept map of process.
Figure 23 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates electric wire to new LP insulator
The concept map of moving process.
Figure 24 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates interim wooden cross arm from electric wire
The concept map of bar unloading process.
Detailed description of the invention
The particular content carrying out an invention
Hereinafter, with reference to the drawing in annex, the controller switching equipment livewire work servicing unit of the present invention is described and utilizes it
Carry out the embodiment of controller switching equipment livewire work method.During this, clearly demonstrate for convenience, the thickness of the line in drawing or
The sizes of assembly etc. may compare exaggeration.
Term described later is the term considering function in the present invention and defining, according to user, operating personnel purpose or
Convention may be different.Therefore, these terms should be defined based on this detail entire content.
First, the controller switching equipment livewire work servicing unit 500 of the present invention is described.
Fig. 1 is the perspective sketch map of the controller switching equipment livewire work servicing unit of one embodiment of the invention.
With reference to Fig. 1, the controller switching equipment livewire work servicing unit 500 of the present invention is horizontal by interim wooden cross arm the 510th, interim wood
Load fixed part the 520th, the 1st lifting moving portion the 530th, wire rack the 540th, the 2nd lifting moving portion 550 forms.
Interim wooden cross arm 510 is fixed on electric pole 10, with wire rack 540 and the electricity being connected on wire rack 540
Line 30 forms and supports the framework bearing a heavy burden.The 511st, the interim wooden cross arm 510 of one embodiment of the invention is vertically prolonged by horizontal extension portion
Long portion the 513rd, support 515 forms.
Horizontal extension portion 511 forms for horizontal direction prolongation.Therefore, vertical extensions 513 is fixed on electric pole 10
Under state, horizontal extension portion 511 is arranged side by side with the iron cross arm being arranged on electric pole 10.In the horizontal extension portion 511 of level
One or more wire rack 540 is installed.
Vertical extensions 513 is connected to the bottom in horizontal extension portion 511.Vertical extensions 513 along electric pole 10 with vertically
Direction extends, and is fixed on electric pole 10 by interim wooden cross arm 520.
Support 515 is rod shape, tilts to be installed between horizontal extension portion 511 and vertical extensions 513, and connects level
Extension 511 and vertical extensions 513.The top of support 515 connects with the chaining part 516 being arranged on horizontal extension portion 511 end
Connecing so that it is rotatable, the bottom of support 515 is connected with vertical extensions 513.By above-mentioned attachment structure, support 515 with
On the basis of the connecting portion of vertical extensions 513, support level extension 511.
The method that chaining part 516 is installed to horizontal extension portion 511:Chaining part 516 is inserted level frame connecting portion 521
After end, the bolt fittings such as lifting bolt are run through the side of chaining part 516, by tight to chaining part 516 and horizontal extension portion 511
It is close to be connected together.
Fig. 2 is the perspective sketch map in the interim wooden cross arm fixed part of one embodiment of the invention and the 1st lifting moving portion;Fig. 3
Lateral concept map for the 1st lifting moving portion internal structure of one embodiment of the invention;Fig. 4 is for illustrating the present invention one enforcement
The concept map that 1st drive division of example runs.
Interim wooden cross arm the 510 or the 1st lifting moving portion 530 is fixed on electric pole 10 by interim wooden cross arm fixed part 520.Ginseng
Examining Fig. 2, the interim wooden cross arm fixed part 520 of one embodiment of the invention is connected by interim wooden cross arm connecting portion 521 and electric pole
Portion 523 forms.
Interim wooden cross arm connecting portion 521 is the part being connected with interim wooden cross arm the 510 or the 1st lifting moving portion 530.Temporarily
Wooden cross arm connecting portion 521 has the 1st connecting portion 531a's that can load and unload in interim wooden cross arm the 510 or the 1st lifting moving portion 530
2nd connecting portion 522 structure.
In one embodiment of the invention, the 1st connecting portion 531a can longitudinally extend (up and down), and bottom is in the opening wider than top
Shape, the outward appearance that the 2nd connecting portion 522 is the outer connecting portion prominent to the 1st side, lifting moving portion 530, the width of end can pass through
The bottom of the 1st connecting portion 531a, but top cannot be passed through.
The 2nd connecting portion 522 is inserted in the bottom of the 1st connecting portion 531a, releases and lift the lifting of interim wooden cross arm the 510 or the 1st
The external force of moving part 530, because of the weight in interim wooden cross arm the 510 or the 1st lifting moving portion 530, the 1st connecting portion 531a is to moving down
Dynamic, make the 2nd connecting portion 522 be positioned at the top of the 1st connecting portion 531a.Now, the end of the 2nd connecting portion 522 hangs over the 1st connecting portion
The top of 531a.By above-mentioned assembling, interim wooden cross arm the 510 or the 1st lifting moving portion 530 can be contained in interim wooden cross arm and connect
On portion 521.
Electric pole connecting portion 523 is secured to the part of electric pole 10.Electric pole connecting portion 523 is connected with interim wooden cross arm
Portion 521 connects, and has the clip structure being loaded and unloaded on electric pole 10.
General clip is the accessory that the 1st accessory is connected to the 2nd accessory, can encase the 2nd accessoryShape or
" C " shape, or banding, its end has the connector such as bolt or nut.Although the electric pole of one embodiment of the invention connects
Portion 523 is clip structure, but if interim wooden cross arm 510 can be fixed to electric pole 10, not limit structure and outward appearance.
In the state of 1st lifting moving portion 530 is to be fixed on interim wooden cross arm fixed part 520, by interim wooden cross arm 510
Lower movement.With reference to Fig. 2~Fig. 4, the 1st lifting moving portion 530 of one embodiment of the invention is by electric pole installation portion 531 and the 1st
Drive division 533 forms.
In the state of electric pole installation portion 531 is to be arranged on interim wooden cross arm fixed part 520, formation can support and include hanging down
Straight extension 513 is at the framework of interior interim wooden cross arm 510 and electric wire 30 weight.Electric pole installation portion 531 side has can faced
When wooden cross arm fixed part 520 on handling the 1st connecting portion 531a.Have and the 1st connecting portion 531a on interim wooden cross arm fixed part 520
The 2nd connecting portion 522 being spirally connected.By being spirally connected of the 1st connecting portion 531a and the 2nd connecting portion 522, can be by the 1st lifting moving
Portion 530 is installed on interim wooden cross arm fixed part 520.By releasing being spirally connected of the 1st connecting portion 531a and the 2nd connecting portion 522,
1st lifting moving portion 530 can be separated with interim wooden cross arm fixed part 520.
Offside at electric pole installation portion 531 installs vertical extensions 513 so that it is can move up and down.Install and vertically prolong
During long portion 513, run through electric pole installation portion 531 up and down so that it is coordinate the motion of the 1st drive division 533, move up and down.
For preventing the friction with electric pole installation portion 531 from hindering the movement of vertical extensions 513, the electricity being connected with vertical extensions 513
Line bar installation portion 531 is mounted with multiple roller 532 in the way of being arranged above and below.Vertical extensions 513 upwards/lower mobile when, rolling
Son 532 keeps the state contacting with vertical extensions 513, coordinates the movement of vertical extensions 513, to side or reverse rotation.
1st drive division 533 is arranged on electric pole installation portion 531, after accepting the power of the 1st driver 41, and will interim wood
Cross-arm 510 moves up and down.1st driver 41 can be suitable for electric drill, the electric screw driver etc. commonly using when changing controller switching equipment
The driving means such as electric tool or motor.1st drive division 533 of one embodiment of the invention is by the 1st driving section the 534th, the 1st beam barrel
537th, the 1st transmission band 538 forms.
1st driving section 534 is rotated driving by the 1st driver 41.In one embodiment of the invention, the 1st driving section 534
It is made up of the 1st worm screw the 535 and the 1st worm gear 536.
The end of the 1st worm screw 535 has the 1st power receiving portion 535a being connected with the 1st driver 41, accepts the 1st driver
41 rotary powers transmitting.1st worm gear 536 engages with the 1st worm screw 535, is separately mounted on the 1st beam barrel 537 and power transmission shaft, with
1st worm screw 535 linkage rotates.Using electric tool as the 1st driver 41 use when, the 1st worm screw 535 by with the 1st swash
The rotation linkage encouraging device 41 rotates, and the 1st worm gear 536 is then rotated in deceleration by linking with the rotation of the 1st worm screw 535,
Increase revolving force simultaneously.
As described above, according to the turbine structure possessing the 1st worm screw the 535 and the 1st worm gear 536, power can only be from the 1st worm screw
535 transmit to the 1st worm gear 536, it is impossible to transmit from the 1st worm gear 536 to the 1st worm screw 535.That is, rotation is imposed to the 1st worm gear 536
Power, it is impossible to making the 1st worm screw 535 rotate, the 1st worm gear 536 also will not rotate.
1st worm gear 536 is connected with interim wooden cross arm 510 by the 1st beam barrel the 537 and the 1st transmission band 538, according to above-mentioned
Worm gear arrangement, can prevent because the weight such as interim wooden cross arm 510 and electric wire 30 make interim wooden cross arm 510 move down.
The 1st transmission band 538 is rolled or untied to 1st beam barrel 537 by the 1st driving section 534 to side or reverse rotation.1st
Beam barrel 537 is the cylindrical structural that can batch the 1st transmission band 538, is connected on power transmission shaft with the 1st worm gear 536.
1st transmission band 538 will be rolled to the 1st beam barrel 537, and end is connected to interim wooden cross arm 510.1st transmission band 538 can
To be the general transmission band of flat rectangle or linear section, it is possible to use the linear accessory such as cable, cable wire.1st transmission band 538 end
End is carried out with interim wooden cross arm 510 by the connector that hook, joint (fitting), buckle, spiro connecting piece etc. can connect and separate
Connect.
The state that 1st driver 41 connects with its end and the 1st power receiving portion 535a is rotated to side, rotary power
Being transferred to the 1st beam barrel 537 by the 1st driving section 534, the 1st beam barrel 537 rotates to side will while rolling the 1st transmission band 538
The interim wooden cross arm 510 being connected with the 1st transmission band 538 end is pulled upwardly.If making the 1st driver 41 reversely rotate, the 1st axle
Cylinder 537 also reversely rotates, and while untiing the 1st transmission band 538, interim wooden cross arm 510 declines.
Can add bottom interim wooden cross arm 510 and limit the safety position limiter 539 that interim wooden cross arm 510 moves down.This
Inventing in an embodiment, safety position limiter 539 is the banded structure with certain length, its end and interim wooden cross arm 510
Connect.Safety position limiter 539, with as the 1st transmission band 538, can be connected by hook, joint (fitting), buckle, spiro connecting piece etc.
The connector connecing and separating is attached with interim wooden cross arm 510.
With reference to Fig. 1~Fig. 4, the controller switching equipment livewire work of one embodiment of the invention is with in servicing unit 500, temporarily wooden
Cross-arm 510 is attached with interim wooden cross arm fixed part 520 by the 1st lifting moving portion 530.That is, interim wooden cross arm fixed part
520 are fixed to electric pole 10 by the 1st lifting moving portion 530 and interim wooden cross arm fixed part 520.
But, the controller switching equipment livewire work of the present invention is with in servicing unit 500, if the 1st lifting moving portion 530 can only
Lift interim wooden cross arm 510, it is not necessary to be arranged between interim wooden cross arm 510 and interim wooden cross arm fixed part 520.That is, face
When wooden cross arm 510 do not pass through the 1st lifting moving portion 530, but be directly installed to electric pole by interim wooden cross arm fixed part 520
On 10;1st lifting moving portion 530 is not between interim wooden cross arm 510 and interim wooden cross arm fixed part 520, and is mounted to electricity
Other positions of line bar 10, control the lifting of interim wooden cross arm 510.
Fig. 5 is the perspective sketch map in the wire rack of one embodiment of the invention and the 1st lifting moving portion;Fig. 6 is for illustrating this
The concept map that 2nd lifting moving portion of one embodiment of invention runs;Fig. 7 is for illustrating the solid to electric wire of one embodiment of the invention
Determine portion inserts the concept map of electric wire process.
Wire rack 540 supports, with the state being arranged on interim wooden cross arm 510, the electric wire 30 being connected on electric pole 10.Ginseng
Examining Fig. 5, the wire rack 540 of one embodiment of the invention is made up of extension 541 and electric wire fixing segments 545.
Extension 541 is the structure that can extend up and down, is arranged on horizontal extension portion 511, by the 2nd lifting moving portion 550
Move up and down.The extension 541 of one embodiment of the invention is by main extension the 542nd, sub-extension the 543rd, fixed part 544 groups
Become.
Main extension 542 is connected with lifting moving portion 550, after accepting the power of the 2nd driver 42, is moved by the 2nd lifting
Dynamic portion 550 moves up and down.Sub-extension 543 includes isolation material, is arranged on the main extension of cylindrical shape in the way to insert
Bottom within 542 so that it is can move to the top of main extension 542.
Fixed part 544 and extension 541 are fixed on the sub-extension 543 moving up on main extension 542.Fixing
Portion 544 can use rotary fixing device, run through sub-extension 543 and main extension 542 run through device.
When fixed part 544 uses rotary fixing device, by son being prolonged fixed part 544 by way of side rotates
Long portion 543 is fixed on main extension 542, can be by reversely rotating the connection releasing sub-extension 543 and main extension 542.As
Fruit has fixed part 544, moves sub-extension 543 to object height, by with fixed part 544 stator extension 543
Process manually regulate the length of extension 541.
Without fixed part 544, the connecting portion at sub-extension 543 and main extension 542 arranges screw bolt and nut, logical
Cross the mode that sub-extension 543 is rotated to side, sub-extension 543 is fixed on main extension 542 so that it is move down on cannot
Dynamic;Reversely rotate sub-extension 543 and can release the connection of sub-extension 543 and main extension 542.
Electric wire fixing segments 545 be install electricity lines 30 part, be arranged on the top of sub-extension 543.Electric wire fixing segments 545 will
Electric wire 30 is tightly attached on wire rack 540.With reference to Fig. 7, the electric wire fixing segments 545 of one embodiment of the invention is by support
546 and sticking department 548 form.
Support 546 is attached with extension 541, and possess can the opening 546a that passes through of supply lines 30.Sticking department 548 with
Support 546 is attached, and switchs opening 546a.In one embodiment of the invention, opening 546a is at support 546 top, sticking department
548 one end being arranged on support 546, rotatable.
When rotating sticking department 548 to side, sticking department 548 closes opening 546a while hanging over support 546.(reference
When Fig. 5) reversely rotating sticking department 548, sticking department 548, away from the other end of support 546, opens opening 546a simultaneously.(reference
While Fig. 7) as described above, switch opening 546a by operation sticking department 546, electric wire 30 is inserted electric wire fixing segments 545 and enters
Row is fixing, or removes electric wire 30 from electric wire fixing segments 545.
It is mounted with lower roller 547 on support 546, it can be made to rotate in assigned position, sticking department 548 is mounted with
Top roller 549, can make it rotate in assigned position.Electric wire 30 is inserted what support 546 inside sticking department 548 locked
Under state, the outside of electric wire 30 contacts with lower roller 547 and top roller 549.That is, electric wire 30 is inserting electric wire fixing segments
In the state of 545, electric wire 30 and electric wire fixing segments 545 carry out Structure deformation.
Therefore, during changing controller switching equipment, when there is relative displacement between electric wire fixing segments 545 and electric wire 30, can
Prevent electric wire 30 from being injured by electric wire fixing segments 545, can stably keep the connection status of electric wire fixing segments 545 and electric wire 30, simultaneously
Can ensure that electric wire fixing segments 545 or the smooth of electric wire 30 move.
2nd lifting moving portion 550 moves up and down wire rack 540.2nd lifting moving portion 550 can individually lift each electric wire
Support 540.Therefore, the quantity in the 2nd lifting moving portion 550 is determined by the quantity of wire rack 540.With reference to Fig. 6, the present invention the 2nd
2nd lifting moving portion 550 of embodiment is made up of interim wooden cross arm installation portion the 551 and the 1st drive division 553.
Interim wooden cross arm installation portion 551 is arranged on horizontal extension portion 511.There is folder on interim wooden cross arm installation portion 551
Minor structure, is connected in horizontal extension portion 511, and can load and unload.Shelf structure about interim wooden cross arm installation portion 551 refers to
Electric pole connecting portion 523 related description, is not repeated herein.
Have on the interim wooden cross arm installation portion 551 of one embodiment of the invention and guide leading of moving up and down of wire rack 540
Rail 552.In order to make wire rack 540 to insert the state lifting within guide rail 552, guide rail 552 has the hollow extending up and down
Guide-track groove 552a.
If can be fixed in horizontal extension portion 511 by lifting moving portion 550, interim wooden cross arm installation portion 551 comprises to fit
It for the clip structure on interim wooden cross arm fixed part 520 or the structure different from interim wooden cross arm fixed part 520, is not limited to spy
Fixed structure and shape.
2nd drive division 553 is arranged on interim wooden cross arm installation portion 551, after accepting the power of the 2nd driver 42, by electricity
Line bracket 540 moves up and down.2nd driver 42 is identical with the 1st driver 41, it is possible to use change during controller switching equipment operation general
The driving means such as electric tool or motor such as the electric screw driver using.2nd drive division 553 of the present invention the 2nd embodiment is by the 2nd
Driving section the 554th, the 2nd beam barrel the 557th, the 1st transmission band 558 forms.
2nd driving section 554 is rotated driving by the 2nd driver 42.In one embodiment of the invention, the 2nd driving section 554
Being made up of the 2nd worm screw the 555 and the 2nd worm gear 556, the 2nd worm screw 555 end has the 2nd power receiving portion being connected with the 2nd driver 42
555a.
The 2nd driving section the 554th, the 2nd beam barrel on 2nd drive division 553 the 557th, the 2nd the 1st biography with the 558 and the 1st drive division 533
The structure of dynamic portion the 534th, the 1st beam barrel the 537th, the 1st transmission band 538 is identical, omits related description herein.
It according to the worm gear arrangement of the 2nd worm screw the 555 and the 2nd worm gear 556 composition, is possible to prevent because the weight of electric wire 30 grade causes
Wire rack 540 moves down.In the state of the end of the 2nd driver 42 and the 2nd power receiving portion 555a connect, by by the
2 drivers 42, to side or reverse rotation, pull up or move down wire rack 540.
Controller switching equipment livewire work servicing unit 500 according to the present invention, utilizes above-mentioned 1st driver the 41 or the 2nd to swash
Encourage the power of device 42, can adjust the height of interim wooden cross arm 510, the height of wire rack 540, frame on wire rack 540
The height of electric wire 30.
Illustrate further:Utilize the 1st driver 41, carry out the 1st movement, make interim wooden cross arm 510 face with being arranged on
When wooden cross arm 510 on wire rack 540 closer to or away from electric wire 30;Utilize the 2nd driver 42, carry out the 2nd movement,
Make wire rack 540 closer to or away from electric wire 30.By adjusting the height of sub-extension 543, fine setting is connected to sub-prolongation
The height of the electric wire fixing segments 545 in portion 543, or the total length of scalable adjustment wire rack 540.
According to the present invention, the 1st driver the 41 or the 2nd driver 42 can use the electricity being generally used for changing controller switching equipment
The electric tools such as brill, electric screw driver, staff is without specially preparing mobile electric device needed for wire rack 540
Easily realize.
According to the present invention, utilize the electric power of the 1st driver the 41 or the 2nd driver 42, supporting electric wire 30 can be moved up and down
The wire rack 540 of weight, it is not necessary to utilize pulley etc. to move up and down electric wire 30 by tractive force, makes livewire work become lighter
Pine.
According to the present invention, utilize the 1st driver the 41 and the 1st lifting moving portion the 530th, the 2nd driver the 42 and the 2nd lifting moving
Portion 550, moves wire rack 540 or electric wire 30 with certain speed, is accurately put into object height.
Below, introduction is utilized the controller switching equipment livewire work servicing unit 500 of the present invention of said structure, use new LP
(Line Post) insulator 25 changes the controller switching equipment band of the present invention of the old LP insulator 22 being arranged on common cross-arm 20
Electricity operational method.
Common cross-arm 20 is different from the extended arm that multiple insulator is all installed to electric pole 10 side, it be insulator with
It centered on electric pole 10, is evenly distributed on the cross-arm of the both sides newly setting electric pole.The insulator of common cross-arm 20 is with electric pole 10
Centered on be distributed in both sides, the clearance space between it can meet staff and carry out livewire work.
Fig. 8 is the flow chart of the controller switching equipment livewire work method that one embodiment of the invention is described.
With reference to Fig. 8, the controller switching equipment livewire work method of the embodiment of the present invention includes and is arranged on interim wooden cross arm 510
The stage S1 of electric wire 10, by interim wooden cross arm 510 or the wire rack 540 that is arranged on interim wooden cross arm 510 to electric pole
Stage S2 that 10 electric wire 30 directions connecting move up, electric wire 30 is moved to the stage S3 of wire rack 540, will interim wood
Cross-arm 510 or wire rack 540 move up again, by remotely mounted for the electric wire 30 old LP insulator 22 on common cross-arm 20
Stage S4, changed by new LP insulator 25 old LP insulator 22 stage S5, by interim wooden cross arm 510 or wire rack 540 to
Stage S6 that new LP insulator 25 direction moves down, move the electric wire 30 being connected to wire rack 540 to new LP insulator
The stage S7 and the stage S8 that interim wooden cross arm 510 is removed from electric pole 10 of 25.
Fig. 9 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates interim wooden cross arm is fixed on electricity
The concept map of line bar process;Figure 10 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates wire rack
Move up the concept map of process to electric wire direction;Figure 11 is in the controller switching equipment livewire work method of the present invention the 1st embodiment,
Illustrate to move electric wire to the concept map of wire rack process.
Figure 12 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates to move up wire rack,
Make electric wire away from the concept map of old LP insulator process;Figure 13 is the controller switching equipment livewire work method of the present invention the 1st embodiment
In, the concept map by new LP replacing insulator old LP insulator process is described;Figure 14 is the controller switching equipment of the present invention the 1st embodiment
In livewire work method, illustrate to move down wire rack to new LP insulator direction the concept map of process.
Figure 15 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, illustrates electric wire to new LP insulator
The concept map of moving process;Figure 16 is in the controller switching equipment livewire work method of the present invention the 1st embodiment, and illustrating will interim wood horizontal stroke
Load is from the concept map of electric pole unloading process.
With reference to Fig. 9~Figure 16, the controller switching equipment livewire work method of the present invention the 1st embodiment is to utilize controller switching equipment charged
Operation servicing unit 500 changes the method for Geju City LP insulator 22 with a new LP insulator 25.
With reference to Fig. 9, it is achieved interim wooden cross arm 510 is fixed on the method for the stage S1 of electric pole 10:By interim wooden cross arm
Fixed part 520 is fixed on electric pole 10, and the 1st lifting moving portion 530 is fixed on interim wooden cross arm fixed part 520, connects the 1st
2nd lifting moving portion 550 and wire rack 540 are fixed on interim wooden cross arm by lifting moving portion 530 and interim wooden cross arm 510
On 510 so that it is position is corresponding with mounted LP insulator 22.
Order when connecting interim wooden cross arm 510 and the 1st lifting moving portion 530 is first to be arranged on vertical extensions 513
1st lifting moving portion 530, connects behind horizontal extension portion 511 on vertical extensions 513 top, in horizontal extension portion 511 and vertical
Mounting bracket 515 between extension 513.
The order of mounting bracket 515 between horizontal extension portion 511 and vertical extensions 513:Chaining part 516 is arranged on water
After on flat extension, the top of support 515 is arranged on chaining part 516 so that it is can rotate, the bottom peace of support 515
On the securing members such as the lifting bolt being contained in vertical extensions 513 bottom so that it is can be loaded and unloaded.
The order being fixed on the 2nd lifting moving portion 550 and wire rack 540 on interim wooden cross arm 510:First by the 2nd liter
Fall moving part 550 is fixed on interim wooden cross arm 510, then is connected to wire rack 540 in the 2nd lifting moving portion 550.Also may be used
After being first connected to wire rack 540 in the 2nd lifting moving portion 550, the 2nd lifting moving portion 550 is being fixed on temporarily
On wooden cross arm 510.
Also the method for the stage S1 being fixed on interim wooden cross arm 510 on electric pole 10 can be realized:Will be equipped with the 2nd lifting to move
The interim wooden cross arm 510 of dynamic portion 550 and wire rack 540 is connected to the 1st lifting moving portion 530 or interim wooden cross arm fixed part
520.
With reference to Figure 10, it is achieved by interim wooden cross arm 510 or wire rack 540 to the side of the stage S2 that electric wire 30 moves up
Method:Sub-extension 543 is moved up by the mode that staff is manually operated to electric wire 30 direction.
Also can realize interim wooden cross arm 510 or wire rack 540 to the method for the stage S2 that electric wire 30 moves up:Root
According to the convenience of operating condition or staff, by the 1st driver the 41 and the 1st lifting moving portion 530, only by interim wooden cross arm
510 move up;Or the 2nd driver the 42 and the 2nd lifting moving portion 550 of passing through, only will be arranged on interim wooden cross arm 510
Wire rack 540 moves up.
Also can realize interim wooden cross arm 510 or wire rack 540 to the method for the stage S2 that electric wire 30 moves up:Root
According to the convenience of operating condition or staff, the 1st driver the 41 and the 1st lifting moving portion 530 can be passed through, only will interim wood horizontal stroke
Load 510 moves up, and passes through the 2nd driver the 42 and the 2nd lifting moving portion 550, only will be arranged on interim wooden cross arm 510
Wire rack 540 move up.
Also can realize interim wooden cross arm 510 or wire rack 540 to the method for the stage S2 that electric wire 30 moves up:Root
According to the convenience of operating condition or staff, the 1st driver the 41 and the 1st lifting moving portion 530 can be passed through, by interim wooden cross arm
510 move up and are manually operated with staff, move up sub-extension 543 to electric wire 30 direction.
Also can realize interim wooden cross arm 510 or wire rack 540 to the method for the stage S2 that electric wire 30 moves up:Root
According to the convenience of operating condition or staff, the 2nd driver the 42 and the 2nd lifting moving portion 550 can be passed through, will be arranged on interim
The wire rack 540 of wooden cross arm 510 moves up and is manually operated with staff, by sub-extension 543 to electric wire 30 side
To movement.
Also can realize interim wooden cross arm 510 or wire rack 540 to the method for the stage S2 that electric wire 30 moves up:Root
According to the convenience of operating condition or staff, the 1st driver the 41 and the 1st lifting moving portion 530 can be passed through, by interim wooden cross arm
510 move up, and by the 2nd driver the 42 and the 2nd lifting moving portion 550, prop up the electric wire being arranged on interim wooden cross arm 510
Frame 540 moves up, and staff is manually operated, and moves sub-extension 543 to electric wire 30 direction.
In the explanation of the present invention, wire rack 540 is moved up or down, includes by mobile main extension 542,
Mobile wire rack 540 including main extension 542 and sub-extension 543 is overall, or only moves on wire rack 540
The embodiment of the sub-extension in portion 543, the part of the electric wire fixing segments 545 being connected with electric wire 30 in wire rack 540, i.e. include
Adjust the process of wire rack 540 upper height up or down.
That is, in the explanation of the present invention, mobile wire rack 540 includes by 42 grade of the 2nd lifting moving portion of the 2nd driver
550 move the embodiment of wire rack 540 entirety, mover extension 543 in wire rack 540 embodiment, comprehensive move
Dynamic wire rack 540 and the embodiment of mover extension 543 process.
Therefore, even if not specified mobile wire rack 540 is overall and mover extension 543, the explanation of the present invention
In mention mobile wire rack 540 refer to above three embodiment one of them.
In the state of opening the opening 546a on support 546 top, enter to be about to interim wooden cross arm 510 or wire rack 540 to
During the stage S2 that electric wire 30 direction moves up, complete by wire rack 540 after the stage S2 that electric wire 30 direction moves up,
It is internal that electric wire 30 enters support 546 by opening 546a.
With reference to Figure 11, it is achieved the method that electric wire 30 is moved the stage S3 to wire rack 540:Electric wire 30 is connected to electricity
After line bracket 540, release the connection of electric wire 30 and old LP insulator 22.
With reference to Figure 12, it is achieved by the side of the stage S4 of remotely mounted for the electric wire 30 old LP insulator 22 on common cross-arm 20
Method:Locking electric wire 30 is through support 546 sticking department 548 within opening 546a entrance, i.e. block opening 546a with sticking department 548.
Release electric wire 30 and the method for old LP insulator 22 connection:Cut off and connect electric wire 30 and old LP insulator 22
Binder, or the operation releasing Binder such as Binder is removed from electric wire.
Although not illustrating in the drawing of the present invention, for protecting electric wire 30 grade controller switching equipment, typically outside electric wire 30
Parcel hot line set, insulator cover isoelectric line set.Before releasing the connection of electric wire 30 and old LP insulator 22, then move up electric wire and prop up
Frame 540, can generate the space releasing needed for Binder between electric wire 30 and old LP insulator 22.
After electric wire 30 is connected to wire rack 540, before releasing the connection between electric wire 30 and old LP insulator 22, then
Move up wire rack 540, will not be adjacent between electric wire 30 and old LP insulator 22, between electric wire 30 and old LP insulator 22
Space will be produced, make electric wire set will not encounter old LP insulator 22.Therefore, the convenience according to staff, can be by electric wire
30 move along electric wire set, smoothly complete controller switching equipment and change operation.
Now, before releasing the connection between electric wire 30 and old LP insulator 22, then the side of wire rack 540 is moved up
Method is, by the 2nd driver the 42 and the 2nd lifting moving portion 550, moves up wire rack 540.Certainly, it is possible to swashed by the 1st
Encourage device the 41 and the 1st lifting moving portion 530 to move interim wooden cross arm 510 and realize.
Interim wooden cross arm 510 or wire rack 540 are moved up, makes electric wire 30 away from the stage S4 of old LP insulator 22
It is to ensure that the process of the operation requisite space changing old LP insulator 22 with new LP insulator 25.
With reference to Figure 12, it is achieved interim wooden cross arm 510 or wire rack 540 are moved up, makes electric wire 30 exhausted away from old LP
The method of the stage S4 of edge 22:Move up interim wooden cross arm 510 by the 1st driver the 41 and the 1st lifting moving portion 530,
And move up wire rack 540 by the 2nd driver the 42 and the 2nd lifting moving portion 550.
Also can realize moving up interim wooden cross arm 510 or wire rack 540, make electric wire 30 away from old LP insulator 22
The method of stage S4:According to the convenience of operating condition and staff, can be only by by the 1st driver the 41 and the 1st lifting
Moving part 530 moves interim wooden cross arm 510, or moves wire rack by the 2nd driver the 42 and the 2nd lifting moving portion 550
540, or by staff is manually operated, sub-extension 543 is moved up to electric wire 30 direction.
Also can realize moving up interim wooden cross arm 510 or wire rack 540, make electric wire 30 away from old LP insulator 22
The method of stage S4:According to the convenience of operating condition or staff, the 1st driver the 41 and the 1st lifting moving can be passed through
Interim wooden cross arm 510 is moved up and is manually operated with staff, by sub-extension 543 to electric wire 30 direction by portion 530
Move up.
Also can realize moving up interim wooden cross arm 510 or wire rack 540, make electric wire 30 away from old LP insulator 22
The method of stage S4:According to the convenience of operating condition or staff, by the 2nd driver the 42 and the 2nd lifting moving portion
550, the wire rack 540 being arranged on interim wooden cross arm 510 is moved up, and staff is manually operated, by son
Extension 543 moves up to electric wire 30 direction.
Also can realize moving up interim wooden cross arm 510 or wire rack 540, make electric wire 30 away from old LP insulator 22
The method of stage S4:According to the convenience of operating condition or staff, by the 1st driver the 41 and the 1st lifting moving portion
530, interim wooden cross arm 510 is moved up, and passes through the 2nd driver the 42 and the 2nd lifting moving portion 550, will be arranged on and face
When wooden cross arm 510 on wire rack 540 move up, and staff is manually operated, by sub-extension 543 to electricity
Line 30 direction is moved.
With reference to Figure 13, it is achieved change the method for the stage S5 of old LP insulator 22 with new LP insulator 25:Utilize by inciting somebody to action
Interim wooden cross arm 510 or wire rack 540 move up, and make the sky that electric wire 30 guarantees away from the stage S4 of old LP insulator 22
Between, after pulling down the old LP insulator 22 on iron cross arm 21, new LP insulator 25 is installed.
With reference to Figure 14, it is achieved move down interim wooden cross arm 510 or wire rack 540 to new LP insulator 25 direction
The method of stage S6:Move down interim wooden cross arm 510 by the 1st driver the 41 and the 1st lifting moving portion 530, and pass through
2nd driver the 42 and the 2nd lifting moving portion 550 moves down wire rack 540.
Also the stage that interim wooden cross arm 510 or wire rack 540 are moved down can be realized to new LP insulator 25 direction
The method of S6:According to the convenience of operating condition and staff, can be only by by the 1st driver the 41 and the 1st lifting moving portion
530 move interim wooden cross arm 510, or move wire rack 540 by the 2nd driver the 42 and the 2nd lifting moving portion 550, or logical
Cross that staff is manually operated to be moved down sub-extension 543 to electric wire 30 direction.
Also the stage that interim wooden cross arm 510 or wire rack 540 are moved down can be realized to new LP insulator 25 direction
The method of S6:According to the convenience of operating condition or staff, by the 1st driver the 41 and the 1st lifting moving portion 530, will
Interim wooden cross arm 510 moves down, and staff is manually operated, and sub-extension 543 is downward to electric wire 30 direction
Mobile.
Also the stage that interim wooden cross arm 510 or wire rack 540 are moved down can be realized to new LP insulator 25 direction
The method of S6:According to the convenience of operating condition or staff, by the 2nd driver the 42 and the 2nd lifting moving portion 550, will
The wire rack 540 being arranged on interim wooden cross arm 510 moves down, and staff is manually operated, by sub-extension
543 move down to electric wire 30 direction.
Also the stage that interim wooden cross arm 510 or wire rack 540 are moved down can be realized to new LP insulator 25 direction
The method of S6:According to the convenience of operating condition or staff, by the 1st driver the 41 and the 1st lifting moving portion 530, will
Interim wooden cross arm 510 moves down, and passes through the 2nd driver the 42 and the 2nd lifting moving portion 550, will be arranged on interim wood horizontal
Wire rack 540 in load 510 moves down, and staff is manually operated, by sub-extension 543 to electric wire 30 side
To moving down.
With reference to Figure 15, it is achieved the electric wire 30 being connected to wire rack 540 is moved the stage S7's to new LP insulator 25
Method:After electric wire 30 is adjacent to and is fixed to new LP insulator 25, release the connection of electric wire 30 and wire rack 540.By electricity
Line 30 is fixed to new LP insulator 25 and refers to, with connectors such as rubber cable, adhesive tape, buckles, electric wire 30 is fixed to new LP and insulate
Son 25.
The method of the connection of releasing electric wire 30 and wire rack 540 is that spin locking portion 548 opens opening 546a, passes through
Electric wire 30 is pulled out outside support 546 by opening 546a.
With reference to Figure 16, it is achieved by the method for the stage S8 that interim wooden cross arm 510 removes from electric pole 10:By the 2nd liter
After fall moving part 550 and wire rack 540 remove from interim wooden cross arm 510, by interim wooden cross arm 510 from interim wooden cross arm
Fixed part the 520 or the 1st removes in lifting moving portion 530, tears the 1st lifting moving portion 530 open from interim wooden cross arm fixed part 520
Get off, more interim wooden cross arm fixed part 520 is removed from electric pole 10.
Also the method for the stage S8 that interim wooden cross arm 510 is removed from electric pole 10 can be realized:Will be equipped with the 2nd lifting
The interim wooden cross arm 510 of moving part 550 and wire rack 540 removes from electric pole 10.
Carrying out the flow process as shown in Fig. 9~Figure 16 successively, an available new LP insulator 25 changes Geju City LP insulation
Son 22.Stage S2 through moving up interim wooden cross arm 510 or wire rack 540 to electric wire 30 direction for several times extremely will connect
Move to the stage S7 of new LP insulator 25 to the electric wire 30 of wire rack 540, many Geju City LP insulator 22 can be changed successively.
Figure 17 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates to be fixed on interim wooden cross arm
The concept map of electric pole process;Figure 18 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates to prop up electric wire
Frame moves up the concept map of process to electric wire direction;Figure 19 is the controller switching equipment livewire work method of the present invention the 2nd embodiment
In, illustrate to move electric wire to the concept map of wire rack process.
Figure 20 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates to move up wire rack,
Make electric wire away from the concept map of old LP insulator process;Figure 21 is the controller switching equipment livewire work method of the present invention the 2nd embodiment
In, the concept map by new LP replacing insulator old LP insulator process is described;Figure 22 is the controller switching equipment of the present invention the 2nd embodiment
In livewire work method, illustrate to move down wire rack to new LP insulator direction the concept map of process.
Figure 23 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, illustrates electric wire to new LP insulator
The concept map of moving process;Figure 24 is in the controller switching equipment livewire work method of the present invention the 2nd embodiment, and illustrating will interim wood horizontal stroke
Load is from the concept map of electric pole unloading process.
With reference to Figure 17~Figure 24, the controller switching equipment livewire work method of the present invention the 2nd embodiment is to utilize controller switching equipment band
The method of many Geju City LP insulator 22 changed by electricity operation servicing unit 500 with multiple new LP insulators 25.
According to the controller switching equipment livewire work method of the present invention the 2nd embodiment, by the process of a Figure 17~Figure 24, can
Change many Geju City LP insulator 22 with disposable.
According to the controller switching equipment livewire work method of the present invention the 2nd embodiment, interim wooden cross arm 510 is fixed to electric pole
In the stage S1 of 10, lifting moving portion 550 and wire rack 540 are installed to and the corresponding position of LP insulator 22, each Geju City;
The rank that the wire rack 540 being arranged on interim wooden cross arm 510 is moved up to electric wire 30 direction being connected to electric pole 10
In section S2, multiple wire racks 540 are moved up simultaneously.
Electric wire 30 is moved to the stage S3 of wire rack 540, simultaneously mobile for multiple electric wires 30 extremely multiple electric wires are propped up
Frame 540, the stage afterwards is applied simultaneously to each Geju City LP insulator the 22nd, new LP insulator the 25th, electric wire 30, through once installing
The stage S2 moving up to electric wire 30 direction being connected to electric pole 10 at the wire rack 540 of interim wooden cross arm 510 extremely will
The electric wire 30 being connected to wire rack 540 moves to the stage S7 of new LP insulator 25, can by many Geju City LP insulator 22 once
Property is replaced by new LP insulator 25.
Controller switching equipment livewire work method according to the invention described above, utilizes the 1st driver the 41 or the 2nd driver 42 electronic
Power, automatically adjusts the height of interim wooden cross arm 510, the height of wire rack 540, the electric wire moving to wire rack 540 direction
The height of 30, easily realizes the replacing operation of LP insulator.
It according to the present invention, is possible not only to multistage and adjusts the height of interim wooden cross arm 510 and wire rack 540 entirety, also may be used
By move up and down live wire fixed part 545 in wire rack 540 sub-extension 543,3 sections regulate electric wire fixing segments 545 or
The height of electric wire 30.
According to the present invention, staff is according to operating condition or convenience, the selective height adjusting interim wooden cross arm 510
Degree, the height of wire rack 540 entirety, the height of sub-extension 543, can easily carry out changing the operation of LP insulator.
According to the present invention, utilizing the 1st driver the 41 or the 2nd driver 42, staff can be in the place away from electric wire 30
Electric wire 30 is moved to old LP insulator 22, can easily guarantee the space needed for the livewire work of replacing LP insulator,
When can avoid changing LP insulator, the security incident that the direct trolley wire of staff 30 is brought is dangerous simultaneously.
According to the present invention, in the state of multiple wire racks 540 have been installed to interim wooden cross arm 510, move up interim
Wooden cross arm 510, the trouble that wire rack 540 can be avoided to move one by one, the displacement making multiple wire rack 540 move up is equal
Identical.
The present invention is the explanation being carried out by the embodiment in drawing, but this only illustrates, if possessing this
The people of technical field relevant knowledge, it should be understood that from the present invention other enforcements of can develop various deformation and ad eundem
Example.Therefore, the technical protection scope of the present invention should be following patent claim.
Claims (12)
1. a controller switching equipment livewire work servicing unit, it is characterised in that include:
Interim wooden cross arm;
Interim wooden cross arm fixed part, above-mentioned interim wooden cross arm is fixed on utility poles by it;
1st lifting moving portion, it is used for moving up and down above-mentioned interim wooden cross arm;
Wire rack, it is arranged on above-mentioned interim wooden cross arm, for supporting the electric wire being connected on said wires bar;
2nd lifting moving portion, it is used for moving up and down said wires support.
2. controller switching equipment livewire work servicing unit according to claim 1, it is characterised in that
Above-mentioned 1st lifting moving portion includes:
It is arranged on the electric pole installation portion on above-mentioned interim wooden cross arm fixed part;And
It is arranged on said wires bar installation portion, move up and down the 1st of above-mentioned interim wooden cross arm after the power accepting the 1st driver and drive
Dynamic portion.
3. controller switching equipment livewire work servicing unit according to claim 1, it is characterised in that
Above-mentioned 2nd lifting moving portion includes:
The interim wooden cross arm installation portion being arranged on above-mentioned interim wooden cross arm;And
It is arranged on above-mentioned interim wooden cross arm installation portion, after the power accepting the 2nd driver, move up and down the 2nd of said wires support
Drive division.
4. a controller switching equipment livewire work method, it is characterised in that include:
Interim wooden cross arm is installed to the stage of electric pole;
Move the said wires being connected to said wires bar to the stage of the wire rack being arranged on above-mentioned interim wooden cross arm;
Above-mentioned interim wooden cross arm or said wires support are moved up, makes said wires away from being arranged on common cross-arm
The stage of old LP insulator;
Remove the above-mentioned old LP insulator being arranged on common cross-arm, above-mentioned common cross-arm is installed the rank of new LP insulator
Section;
The stage that above-mentioned interim wooden cross arm or said wires support are moved down to above-mentioned new LP insulator direction;And
Move the said wires being connected to said wires support to the stage of new LP insulator.
5. controller switching equipment livewire work method according to claim 4, it is characterised in that
Above-mentioned interim wooden cross arm is moved up or down and is realized by operation the 1st lifting moving portion, wherein, the 1st lifting
Moving part moves up and down above-mentioned interim wooden cross arm after the power accepting the 1st driver.
6. controller switching equipment livewire work method according to claim 4, it is characterised in that
Moving up or down said wires support and being realized by operation the 2nd lifting moving portion, wherein, the 2nd lifting moves
Dynamic portion moves up and down said wires support after the power accepting the 2nd driver.
7. a controller switching equipment livewire work method,
With regard to use include interim wooden cross arm, by fixing for above-mentioned interim wooden cross arm interim wooden cross arm fixed part on utility poles,
Support is arranged on interim wooden cross arm, and is connected to multiple wire racks of electric wire on said wires bar, above-mentioned electricity of independent lifting
The controller switching equipment livewire work method of the controller switching equipment livewire work servicing unit in multiple 2nd lifting moving portions of line bracket,
Including above-mentioned interim wooden cross arm is installed to the stage of said wires bar;
Move the said wires being connected to said wires bar to the rank of the said wires support being arranged on above-mentioned interim wooden cross arm
Section,
Said wires is moved to the stage of above-mentioned wire rack,
Including above-mentioned 2nd lifting moving portion accepts after the power of the 2nd driver, frame have the said wires of said wires prop up
Frame moves up, and props up said wires and is placed on above-mentioned old LP insulator, it is to avoid the electric wire of parcel said wires is enclosed within shifting
When dynamic, the stage of old LP insulator encountered by said wires set;
Release the Binder connecting said wires and above-mentioned old LP insulator, shape between said wires and above-mentioned old LP insulator
Become space, the stage that said wires set is moved to above-mentioned wire rack direction along said wires.
8. controller switching equipment livewire work method according to claim 7, it is characterised in that
Include after said wires is moved to said wires support, above-mentioned interim wooden cross arm or said wires support are upwards moved
Dynamic, by said wires away from stage of above-mentioned old LP insulator.
9. controller switching equipment livewire work method according to claim 8, it is characterised in that
Include before above-mentioned interim wooden cross arm is removed from said wires bar, by by above-mentioned interim wooden cross arm or above-mentioned
Wire rack moves down, the stage moving down said wires to new LP insulator direction;
The said wires being connected to said wires support is moved to the stage of above-mentioned new LP insulator.
10. controller switching equipment livewire work method according to claim 9, it is characterised in that
Include by said wires before above-mentioned new LP insulator direction moves down, said wires is exhausted away from above-mentioned old LP
In the state of edge, remove above-mentioned old LP insulator, and the stage of new LP insulator is installed.
The 11. controller switching equipment livewire work methods according to any claim in claim 7 to 10, it is characterised in that
Accepted the power of above-mentioned 2nd driver by above-mentioned 2nd lifting moving portion after, move up and down said wires support, by upper
State wire rack to move up or down.
12. controller switching equipment livewire work methods according to claim 7, it is characterised in that
Above-mentioned controller switching equipment livewire work servicing unit further comprises the 1st lifting moving moving up and down above-mentioned interim wooden cross arm
Portion.
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20140006513 | 2014-01-20 | ||
KR10-2014-0069772 | 2014-06-09 | ||
KR1020140069772A KR101473822B1 (en) | 2014-01-20 | 2014-06-09 | Method for hot line work of power distribution equipment |
PCT/KR2015/005796 WO2015190813A1 (en) | 2014-06-09 | 2015-06-09 | Auxiliary device for power distribution facility live-line working, and power distribution facility live-line working method using same |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106463940A true CN106463940A (en) | 2017-02-22 |
CN106463940B CN106463940B (en) | 2018-09-11 |
Family
ID=52679199
Family Applications (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201580030649.0A Active CN106463939B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the controller switching equipment livewire work method for utilizing this device |
CN201580030710.1A Active CN106463941B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
CN201580030707.XA Active CN106463940B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the method for carrying out controller switching equipment livewire work using it |
CN201580030633.XA Active CN106463938B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
Family Applications Before (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201580030649.0A Active CN106463939B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work auxiliary device and the controller switching equipment livewire work method for utilizing this device |
CN201580030710.1A Active CN106463941B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201580030633.XA Active CN106463938B (en) | 2014-01-20 | 2015-06-09 | Controller switching equipment livewire work method |
Country Status (2)
Country | Link |
---|---|
KR (12) | KR101473823B1 (en) |
CN (4) | CN106463939B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107086488A (en) * | 2017-04-28 | 2017-08-22 | 国网山东省电力公司青岛供电公司 | A kind of charged for replacement overhead transmission line straight line pole cross-arm, insulator arrangement |
Families Citing this family (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101631916B1 (en) * | 2015-09-14 | 2016-06-20 | 탑이앤지 주식회사 | Method for changing power distribution line in hot line |
KR101616484B1 (en) * | 2015-09-21 | 2016-04-28 | (주)우신전기기술사사무소 | Method for changing power distribution line in hot line |
CN106545213A (en) * | 2015-09-23 | 2017-03-29 | 国网辽宁省电力有限公司本溪供电公司 | A kind of adjustable bearing pole girdle ring |
CN107288406A (en) * | 2016-03-30 | 2017-10-24 | 国网辽宁省电力有限公司本溪供电公司 | A kind of adjustable bearing pole girdle ring |
CN105762702B (en) * | 2016-04-01 | 2017-08-04 | 中国南方电网有限责任公司超高压输电公司南宁局 | The method of replacing ± 800kV DC power transmission line L insulator strings |
KR101757195B1 (en) * | 2016-10-11 | 2017-07-11 | 주식회사 성진 | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work |
CN107437712A (en) * | 2016-12-30 | 2017-12-05 | 广州程科电子科技有限公司 | A kind of durable electric insulation post |
KR101864309B1 (en) | 2017-01-19 | 2018-06-05 | 삼성기술감리 주식회사 | Apparatus for changing power distribution line in hot line |
KR101889080B1 (en) | 2017-02-20 | 2018-08-16 | 주식회사진흥기업 | live jumper wire wirelessly disconnect and connect method |
CN107039919A (en) * | 2017-05-05 | 2017-08-11 | 国网江苏省电力公司常州供电公司 | A kind of wire-binding device |
CN107504343A (en) * | 2017-08-11 | 2017-12-22 | 国网浙江台州市黄岩区供电公司 | Stand transformer base leveling device |
US11185840B2 (en) | 2017-10-12 | 2021-11-30 | Kureha Corporation | Continuous polymerization apparatus and continuous production method for polymer |
JP7089791B2 (en) * | 2017-12-18 | 2022-06-23 | 株式会社永木精機 | Insulator separation method and direction change tool, pillar lifting device, insulator support tool and utility pole fixer used in this method. |
CN108321753A (en) * | 2017-12-28 | 2018-07-24 | 青岛九州汇德新能源有限公司 | A kind of solar energy system power supply support device |
CN108155601A (en) * | 2018-01-08 | 2018-06-12 | 国网辽宁省电力有限公司鞍山供电公司 | A kind of method that on-load straight line pole changes tension-resistant rod |
CN108258617A (en) * | 2018-01-16 | 2018-07-06 | 国网新疆电力公司塔城供电公司 | A kind of more changing device that formula overhanging golden tool is twisted for transmission line of electricity aerial condutor |
CN108683122B (en) * | 2018-06-08 | 2020-07-28 | 国网山东省电力公司青岛供电公司 | Auxiliary device and method for sharing straight line rod of corridor in live migration |
KR101955155B1 (en) * | 2018-07-11 | 2019-03-06 | 대원전기 주식회사 | Uninterruptible power method and Indirect live lifting device for Electronic pole for power line |
KR102112471B1 (en) * | 2018-11-30 | 2020-05-19 | 한국전력공사 | Method for hot line work |
KR102321043B1 (en) | 2018-12-12 | 2021-11-03 | 주식회사 중앙백신연구소 | A promoter being expressed in Kluyveromyces marxianus strain and the gene expression system using thereof |
KR102273339B1 (en) * | 2019-06-10 | 2021-07-06 | 한국전력공사 | Wire support device supporting switchgear lead wire or jumper wire |
KR102650799B1 (en) * | 2019-12-18 | 2024-03-26 | 한국전력공사 | Auxiliary apparatus for hot line work of power distribution equipment and method for hot line work of power distribution equipment using thereof |
CN111456520B (en) * | 2020-03-22 | 2021-04-02 | 徐宏坤 | Distribution line building device and installation method |
KR102173375B1 (en) * | 2020-03-30 | 2020-11-03 | 김정호 | Uninterruptible power method and lndirect live lifting device for Electronic polefor power line |
KR102173378B1 (en) * | 2020-06-10 | 2020-11-03 | 김정호 | electric power line device for Uninterruptible power method |
KR102173377B1 (en) * | 2020-06-10 | 2020-11-03 | 김정호 | Uninterruptible power method of utilization electric power line device |
CN111987639A (en) * | 2020-08-04 | 2020-11-24 | 中国电建集团河南工程有限公司 | Construction method for replacing tension porcelain insulator |
CN111910982A (en) * | 2020-08-05 | 2020-11-10 | 国网黑龙江省电力有限公司伊春供电公司 | Transmission line ground clearance promotes cross arm |
KR102240478B1 (en) * | 2020-09-22 | 2021-04-16 | 대원전기 주식회사 | Insulator clip for indirect live wire and LP insulator replacement indirect live wire method using the same |
KR102236410B1 (en) * | 2020-10-14 | 2021-04-05 | 이종학 | Wire installing method |
CN112366603B (en) * | 2020-11-18 | 2022-05-24 | 广东电网有限责任公司 | Electric power supporting equipment |
CN112551258B (en) * | 2020-11-18 | 2023-01-24 | 广东电网有限责任公司 | Cable support device and electric power support equipment |
KR20220085571A (en) | 2020-12-15 | 2022-06-22 | 한국전력공사 | Fixing device for distribution facility and fixing method using the same |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050103700A (en) * | 2004-04-27 | 2005-11-01 | 양희성 | A |
CN102510029A (en) * | 2011-11-22 | 2012-06-20 | 上海市电力公司 | Ground potential electrified bar cutter device changing method |
KR101218710B1 (en) * | 2011-01-31 | 2013-01-09 | 서광전기통신공사(주) | The cable fixing bar provisionally installation equipment for work power distribution line |
KR101243860B1 (en) * | 2012-04-27 | 2013-03-20 | 임용호 | The changing device of lp insualtor for power distribution line |
KR101254577B1 (en) * | 2012-11-21 | 2013-04-15 | 서광전기통신공사(주) | The cable fixing bar provisionally installation equipment for work power distribution line |
CN103510739A (en) * | 2013-10-24 | 2014-01-15 | 国网湖南省电力公司带电作业中心 | Multifunctional combinatorial insulation cross arm |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4188477B2 (en) * | 1999-02-04 | 2008-11-26 | 株式会社中電工 | How to remove an imaginary ground wire |
KR100934083B1 (en) * | 2007-11-05 | 2009-12-24 | 양희성 | Jumper Wire Fixture |
JP5306031B2 (en) * | 2009-04-13 | 2013-10-02 | 中国電力株式会社 | Indirect hot tool support |
FI125939B (en) * | 2010-12-30 | 2016-04-15 | Meclimb Oy | Method and apparatus for transporting tools to a workplace along an elongated piece and use of the apparatus |
KR101106236B1 (en) * | 2011-06-28 | 2012-01-19 | 주식회사 지이플러스 | Apparatus and method for live wire using trane truck |
KR101344289B1 (en) * | 2012-04-27 | 2013-12-23 | 임용호 | The pole fittings changing method use lifting apparatus |
KR101275111B1 (en) | 2013-02-13 | 2013-06-17 | 임용호 | Replacement method for power distribution equipment of direct live wire for double insulation |
-
2014
- 2014-06-09 KR KR1020140069775A patent/KR101473823B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069766A patent/KR20150087781A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069763A patent/KR101473821B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069772A patent/KR101473822B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069769A patent/KR20150087784A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069758A patent/KR20150087779A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069771A patent/KR101592964B1/en active IP Right Grant
- 2014-06-09 KR KR1020140069759A patent/KR20150087780A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069768A patent/KR20150087783A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069767A patent/KR20150087782A/en not_active Application Discontinuation
- 2014-06-09 KR KR1020140069770A patent/KR20150087785A/en not_active Application Discontinuation
- 2014-06-09 KR KR20140069760A patent/KR101473820B1/en active IP Right Grant
-
2015
- 2015-06-09 CN CN201580030649.0A patent/CN106463939B/en active Active
- 2015-06-09 CN CN201580030710.1A patent/CN106463941B/en active Active
- 2015-06-09 CN CN201580030707.XA patent/CN106463940B/en active Active
- 2015-06-09 CN CN201580030633.XA patent/CN106463938B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050103700A (en) * | 2004-04-27 | 2005-11-01 | 양희성 | A |
KR101218710B1 (en) * | 2011-01-31 | 2013-01-09 | 서광전기통신공사(주) | The cable fixing bar provisionally installation equipment for work power distribution line |
CN102510029A (en) * | 2011-11-22 | 2012-06-20 | 上海市电力公司 | Ground potential electrified bar cutter device changing method |
KR101243860B1 (en) * | 2012-04-27 | 2013-03-20 | 임용호 | The changing device of lp insualtor for power distribution line |
KR101254577B1 (en) * | 2012-11-21 | 2013-04-15 | 서광전기통신공사(주) | The cable fixing bar provisionally installation equipment for work power distribution line |
CN103510739A (en) * | 2013-10-24 | 2014-01-15 | 国网湖南省电力公司带电作业中心 | Multifunctional combinatorial insulation cross arm |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107086488A (en) * | 2017-04-28 | 2017-08-22 | 国网山东省电力公司青岛供电公司 | A kind of charged for replacement overhead transmission line straight line pole cross-arm, insulator arrangement |
Also Published As
Publication number | Publication date |
---|---|
KR101473822B1 (en) | 2014-12-18 |
CN106463939A (en) | 2017-02-22 |
CN106463938B (en) | 2018-09-07 |
KR20150087784A (en) | 2015-07-30 |
KR101473823B1 (en) | 2014-12-18 |
KR20150087780A (en) | 2015-07-30 |
CN106463939B (en) | 2018-09-11 |
CN106463938A (en) | 2017-02-22 |
KR20150087781A (en) | 2015-07-30 |
CN106463940B (en) | 2018-09-11 |
KR20150087785A (en) | 2015-07-30 |
KR20150087779A (en) | 2015-07-30 |
KR20150087782A (en) | 2015-07-30 |
KR101473821B1 (en) | 2014-12-18 |
CN106463941A (en) | 2017-02-22 |
KR101592964B1 (en) | 2016-02-25 |
CN106463941B (en) | 2018-09-07 |
KR101473820B1 (en) | 2014-12-18 |
KR20150087786A (en) | 2015-07-30 |
KR20150087783A (en) | 2015-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106463940A (en) | Auxiliary device for power distribution facility live-line working, and power distribution facility live-line working method using same | |
US11146047B2 (en) | Cable pulling apparatus for cable tray | |
CN110729674B (en) | Self-traction type wire coating robot wire-feeding and wire-hanging method and coating robot | |
KR101757195B1 (en) | Stationary Auxiliary Arm Apparatus and Method Using In Uninterruptible Power Distribution Work | |
CN108599007A (en) | A kind of apparatus and method of high-tension line unmanned plane installation pulley insulating cord | |
US10000368B2 (en) | Hoist system for retrofitting small scissor lift to access enclosed areas in building structure | |
CN106744539A (en) | Automatic rod rising device and electric power maintenance vehicle | |
US20160365177A1 (en) | Method and System for Assembling and Installing a Wire Bundle Assembly Group | |
CN109416024A (en) | Rotor blade repair apparatus | |
CN107370079A (en) | It is a kind of to connect and hook the livewire work method of clip lead | |
CN109955925A (en) | A kind of climbing level robot | |
CN108462117A (en) | A kind of skyscraper cable-laying gear and its application method | |
CN107486704A (en) | A kind of GIL conductors Intelligent assembly tool | |
DE112019000030T5 (en) | CENTRAL CONTROL SYSTEM FOR AUTOMATICALLY LOCATING AND DISTRIBUTING SEATS OF A FLOATING TRANSPORTATION DEVICE | |
EP1589627B1 (en) | Device vor lifting and fastening busbars | |
CN208585237U (en) | A kind of railway passenger station platform automatic safety protective system | |
CN109066453B (en) | Special tool for repairing overhead lightning conductor of power transmission line | |
CN209748055U (en) | insulating rope sideslip prevention device for feeding | |
CN209728291U (en) | A kind of optical cable aerial construction of high stability | |
CN107293998B (en) | Power transmission line live working robot winding and unwinding device | |
CN106241590A (en) | A kind of oil drilling tools automatic clamping and placing equipment | |
EP3654476A2 (en) | Pre-fabricated concrete component and charging system | |
CN205389188U (en) | Photovoltaic module angle governing system with portable angle adjusting device | |
CN105986755A (en) | Integrated climbing device | |
CN105071307B (en) | A kind of device of auxiliary connection and the method that wiring is carried out using the device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |