CN106372372A - 一种计及网损变量的频率动态仿真分析方法 - Google Patents

一种计及网损变量的频率动态仿真分析方法 Download PDF

Info

Publication number
CN106372372A
CN106372372A CN201610920555.7A CN201610920555A CN106372372A CN 106372372 A CN106372372 A CN 106372372A CN 201610920555 A CN201610920555 A CN 201610920555A CN 106372372 A CN106372372 A CN 106372372A
Authority
CN
China
Prior art keywords
power
moment
node
frequency
network loss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610920555.7A
Other languages
English (en)
Other versions
CN106372372B (zh
Inventor
李卫东
张蓉蓉
刘娆
巴宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University of Technology
Original Assignee
Dalian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University of Technology filed Critical Dalian University of Technology
Priority to CN201610920555.7A priority Critical patent/CN106372372B/zh
Publication of CN106372372A publication Critical patent/CN106372372A/zh
Application granted granted Critical
Publication of CN106372372B publication Critical patent/CN106372372B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开了一种计及网损变量的频率动态仿真分析方法,包括以下步骤:S1:设t时刻前,n节点电力系统供需平衡,电力系统频率稳定,电力系统参量已知,t时刻,电力系统受到扰动,求解此时电力系统不平衡功率Pacc t,S2:根据发电机组调节特性以及负荷静频特性,建立t+1时刻系统不平衡功率表达式与网损表达式;S3:利用步骤2得到的网损表达式,在常规潮流方程基础上,建立t+1时刻计及网损变量的扩展潮流方程组,利用牛顿拉夫逊算法求解该时刻电力系统频率;S4:判断t+1是否小于总仿真时长,如果“否”,结束;如果“是”,利用步骤3求得电力系统参量,代入S1,进行t+2时刻频率仿真。

Description

一种计及网损变量的频率动态仿真分析方法
技术领域
本发明涉及电力系统频率仿真领域,尤其涉及一种计及网损变量的频率动态仿真分析方法。
背景技术
电力系统频率是电网运行的一项重要参数,保证系统频率稳定也是电网运行的一项重要任务。为更好的保证系统频率稳定,系统的频率仿真具有十分重要的意义。频率仿真目的不同,对仿真也会提出不同要求。若要考虑电网中负荷或发电情况突变对电网频率的影响,仿真则应当保留网络结构。涉及到网络结构运算,那么潮流计算就是一项非常实用的手段。然而在潮流计算过程中,平衡母线是不可或缺的,但平衡母线的存在与系统实际结构是不相符的,平衡母线承担的多余功率在实际系统中也是分摊给相应机组的,这将给频率仿真带来一定的误差。在频率的动态仿真过程中,系统中的节点信息会不断变化,系统网损作为一种系统网络状态的依从变量,在潮流计算之前是未知的。如果还是依靠常规潮流计算方法,在系统动态运行过程中,网损变量将由平衡节点来全部承担,使得计算结果受平衡节点位置影响。随着系统扰动的持续增加,系统中的网损也会非线性增长,而增长的网损造成的功率不平衡量仍由人工选定的平衡节点全部承担,会影响系统潮流计算以及系统频率仿真的精度,不甚合理。
发明内容
针对常规动态潮流在处理网损变量上的不足,本发明引入了网损变量,利用扩展潮流方程方法合理地分配了网损变量,消除了平衡节点承担的多余功率,进而消除了平衡节点的影响,使计算结果符合系统实际物理结构。具体的技术方案是:一种计及网损变量的频率动态仿真分析方法,包括以下步骤:
S1:设t时刻前,n节点电力系统供需平衡,电力系统频率稳定,电力系统参量已知,t时刻,电力系统受到扰动,求解此时电力系统不平衡功率Pacc t,所述电力系统参量包括各节点发电机有功出力、无功出力、有功负荷、无功负荷、节点电压、相角和系统总网损;
S2:根据发电机组调节特性以及负荷静频特性,建立t+1时刻系统不平衡功率表达式与网损表达式;
S3:利用步骤2得到的网损表达式,在常规潮流方程基础上,建立t+1时刻计及网损变量的扩展潮流方程组,利用牛顿拉夫逊算法求解该时刻电力系统频率;
S4:判断t+1是否小于总仿真时长,如果“否”,结束;如果“是”,利用步骤3求得电力系统参量,代入S1,进行t+2时刻频率仿真。
S2中:系统不平衡功率采用如下公式表示:
Pacc t+1=∑PGi t+PGK-i t+1-[(∑PLi t+∑PRi t)+PLK-i t+1+PRi t+1]-(Ploss t+PΔloss t+1)
其中,PGi t为t时刻节点i的机组有功出力,PLi t为t时刻节点i有功负荷,为t时刻网损总量,PRi t为t时刻节点i有功负荷扰动,PGK-i t+1为t到t+1时刻内机组调节变化量,PLK-i t+1为t到t+1时刻内负荷静频特性变化量,PΔloss t+1为t到t+1时刻内网损变化量,PRi t+1为t+1时刻节点i有功负荷扰动量;
系统网损方程采用如下公式表示:
P l o s s t + Σ i = 1 n P G K - i t + 1 - P a c c t + 1 - Σ i = 1 n P L K - i t + 1 - Σ i = 1 n P R i t + 1 + P a c c t - P l o s s t + 1 ( x ) = 0
其中,为t+1时刻网损极坐标表达式,Vi为t+1时刻节点i电压幅值,Gij为节点i与节点j之间电导,θij=θij,θi为节点i电压相角,θj为节点j电压相角,T为系统所有发电机组的惯性时间常数之和,ωΔ t+1为t到t+1时刻内频率变化量,tΔ为仿真步长;
S2:发电机组调节特性包括一次调节特性和二次调节特性,在不同作用时间,对应的机组调节量计算公式也不同,设机组一次调节延迟为T1个单位步长,则有:
P G K - i t + 1 = K G i ω Δ t + 1 - T 1 2 π
其中,KGi为节点i发电机组的单位调节功率;
设机组二次调节以定频率控制(FFC)方式进行调节,则有:
P G K - i t + 1 = K G i ΣK G i P A C E t + 1
其中,PACE t+1为t到t+1时段内的所有机组总调节量,各机组按照其一次调节系数分配调节量,根据不同要求设置机组功率分配向量,用以分配时段内的系统
S3中:利用牛顿拉夫逊算法求解时,扩展潮流方程组的雅可比矩阵采用如下公式表示:
J ′ = H N M J L 0 C D F
式中,[H N;J L]为原常规潮流雅可比矩阵向量,M、C、D、F为扩展向量:
C i = 2 V i Σ j ∈ i V j G i j sinθ i j | t + 1
D i = - 2 V i Σ j ∈ i V j G i j cosθ i j | t + 1
M = T J i t Δ - K L i 2 π
F = T J Σ t Δ - K L Σ 2 π
其中,TJi为系统发电机组i的惯性时间常数,T为系统所有发电机组的惯性时间常数之和,KLi为节点i上负荷的单位调节功率,K为系统所有负荷的单位调节功率之和。
由于采用了上述技术方案,本发明提供的一种计及网损变量的频率动态仿真分析方法,增加了对网损变量的考虑,对平衡节点承担的多余功率进行分配,使得系统仿真结果不受平衡节点位置不同的影响,仿真结果更符合系统实际物理结构,提高了系统仿真精度。
附图说明
为了更清楚地说明本申请实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本申请中记载的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。
图1为本发明的流程图。
具体实施方式
为使本发明的技术方案和优点更加清楚,下面结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚完整的描述:
如图1所示的一种计及网损变量的频率动态仿真分析方法:
S1:设t时刻前,n节点电力系统供需平衡,电力系统频率稳定,电力系统参量已知,t时刻,电力系统受到扰动,求解此时电力系统不平衡功率Pacc t,所述电力系统参量包括各节点发电机有功出力、无功出力、有功负荷、无功负荷、节点电压、相角和系统总网损;
S2:根据发电机组调节特性以及负荷静频特性,建立t+1时刻系统不平衡功率表达式与网损表达式;
S3:利用步骤2得到的网损表达式,在常规潮流方程基础上,建立t+1时刻计及网损变量的扩展潮流方程组,利用牛顿拉夫逊算法求解该时刻电力系统频率;
S4:判断t+1是否小于总仿真时长,如果“否”,结束;如果“是”,利用步骤3求得电力系统参量,代入S1,进行t+2时刻频率仿真。
S1中:系统不平衡功率采用如下公式表示:
Pacc t=ΣPGi t-(ΣPLi t+∑PRi t)-Ploss t
S2中:t+1时刻系统参量关系式表示为
PGi t+1=PGi t+PGK-i t+1
PLi t+1=(PLi t+PRi t)+PLK-i t+1+PRi t+1
Ploss t+1=Ploss t+PΔloss t+1
S2中:系统不平衡功率采用如下公式表示:
Pacc t+1=ΣPGi t+PGK-i t+1-[(ΣPLi t+ΣPRi t)+PLK-i t+1+PRi t+1]-(Ploss t+PΔloss t+1)
其中,PGi t为t时刻节点i的机组有功出力,PLi t为t时刻节点i有功负荷,为t时刻网损总量,PRi t为t时刻节点i有功负荷扰动,PGK-i t+1为t到t+1时刻内机组调节变化量,PLK-i t+1为t到t+1时刻内负荷静频特性变化量,PΔloss t+1为t到t+1时刻内网损变化量,PRi t+1为t+1时刻节点i有功负荷扰动量;
系统网损方程采用如下公式表示:
P l o s s t + Σ i = 1 n P G K - i t + 1 - P a c c t + 1 - Σ i = 1 n P L K - i t + 1 - Σ i = 1 n P R i t + 1 + P a c c t - P l o s s t + 1 ( x ) = 0
其中,为t+1时刻网损极坐标表达式,Vi为t+1时刻节点i电压幅值,Gij为节点i与节点j之间电导,θij=θij,θi为节点i电压相角,θj为节点j电压相角,TJ∑为系统所有发电机组的惯性时间常数之和,ωΔ t+1为t到t+1时刻内频率变化量,tΔ为仿真步长;
S2:发电机组调节特性包括一次调节特性和二次调节特性,在不同作用时间,对应的机组调节量计算公式也不同,设机组一次调节延迟为T1个单位步长,则有:
P G K - i t + 1 = K G i ω Δ t + 1 - T 1 2 π
其中,KGi为节点i发电机组的单位调节功率;
设机组二次调节以定频率控制(FFC)方式进行调节,则有:
P G K - i t + 1 = K G i ΣK G i P A C E t + 1
其中,PACE t+1为t到t+1时段内的所有机组总调节量,各机组按照其一次调节系数分配调节量,根据不同要求设置机组功率分配向量,用以分配时段内的系统调节量。
S2:依据负荷静频特性,负荷在t到t+1时段内的变化量为:
P L K - i t + 1 = K L i ω Δ t + 1 2 π
其中,KLi为负荷的单位调节功率。
S3中:利用牛顿拉夫逊算法求解时,扩展潮流方程组的雅可比矩阵采用如下公式表示:
J ′ = H N M J L 0 C D F
式中,[H N;J L]为原常规潮流雅可比矩阵向量,M、C、D、F为扩展向量:
C i = 2 V i Σ j ∈ i V j G i j sinθ i j | t + 1
D i = - 2 V i Σ j ∈ i V j G i j cosθ i j | t + 1
M = T J i t Δ - K L i 2 π
F = T J Σ t Δ - K L Σ 2 π
其中,TJi为系统发电机组i的惯性时间常数,TJ∑为系统所有发电机组的惯性时间常数之和,KLi为节点i上负荷的单位调节功率,K为系统所有负荷的单位调节功率之和。
实施例:
现以10机39节点系统为例,现系统负荷突减(即系统扰动)300MW。系统负荷突减时刻为0时刻,突减前系统稳定运行情况下网损为42.34MW;系统负荷突减后,考虑网损变量与不考虑网损变量进行对比,结果如下:
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。

Claims (4)

1.一种计及网损变量的频率动态仿真分析方法,其特征在于:包括以下步骤:
S1:设t时刻前,n节点电力系统供需平衡,电力系统频率稳定,电力系统参量已知,t时刻,电力系统受到扰动,求解此时电力系统不平衡功率Pacc t,所述电力系统参量包括各节点发电机有功出力、无功出力、有功负荷、无功负荷、节点电压、相角和系统总网损;
S2:根据发电机组调节特性以及负荷静频特性,建立t+1时刻系统不平衡功率表达式与网损表达式;
S3:利用步骤2得到的网损表达式,在常规潮流方程基础上,建立t+1时刻计及网损变量的扩展潮流方程组,利用牛顿拉夫逊算法求解该时刻电力系统频率;
S4:判断t+1是否小于总仿真时长,如果“否”,结束;如果“是”,利用步骤3求得电力系统参量,代入S1,进行t+2时刻频率仿真。
2.根据权利要求1所述的一种计及网损变量的频率动态仿真分析方法,其特征还在于:S2中:系统不平衡功率采用如下公式表示:
Pacc t+1=ΣPGi t+PGK-i t+1-[(ΣPLi t+ΣPRi t)+PLK-i t+1+PRi t+1]-(Ploss t+PΔloss t+1)
其中,PGi t为t时刻节点i的机组有功出力,PLi t为t时刻节点i有功负荷,为t时刻网损总量,PRi t为t时刻节点i有功负荷扰动,PGK-i t+1为t到t+1时刻内机组调节变化量,PLK-i t+1为t到t+1时刻内负荷静频特性变化量,PΔloss t+1为t到t+1时刻内网损变化量,PRi t+1为t+1时刻节点i有功负荷扰动量;
系统网损方程采用如下公式表示:
其中,为t+1时刻网损极坐标表达式,Vi为t+1时刻节点i电压幅值,Gij为节点i与节点j之间电导,θij=θij,θi为节点i电压相角,θj为节点j电压相角,T为系统所有发电机组的惯性时间常数之和,ωΔ t+1为t到t+1时刻内频率变化量,tΔ为仿真步长。
3.根据权利要求1所述的一种计及网损变量的频率动态仿真分析方法,其特征还在于:S2:发电机组调节特性包括一次调节特性和二次调节特性,在不同作用时间,对应的机组调节量计算公式也不同,设机组一次调节延迟为T1个单位步长,则有:
其中,KGi为节点i发电机组的单位调节功率;
设机组二次调节以定频率控制(FFC)方式进行调节,则有:
其中,PACE t+1为t到t+1时段内的所有机组总调节量,各机组按照其一次调节系数分配调节量,根据不同要求设置机组功率分配向量,用以分配时段内的系统调节量。
4.根据权利要求1所述的一种计及网损变量的频率动态仿真分析方法,其特征还在于:S3中:利用牛顿拉夫逊算法求解时,扩展潮流方程组的雅可比矩阵采用如下公式表示:
式中,[H N;J L]为原常规潮流雅可比矩阵向量,M、C、D、F为扩展向量:
其中,TJi为系统发电机组i的惯性时间常数,TJ∑为系统所有发电机组的惯性时间常数之和,KLi为节点i上负荷的单位调节功率,K为系统所有负荷的单位调节功率之和。
CN201610920555.7A 2016-10-21 2016-10-21 一种计及网损变量的频率动态仿真分析方法 Expired - Fee Related CN106372372B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610920555.7A CN106372372B (zh) 2016-10-21 2016-10-21 一种计及网损变量的频率动态仿真分析方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610920555.7A CN106372372B (zh) 2016-10-21 2016-10-21 一种计及网损变量的频率动态仿真分析方法

Publications (2)

Publication Number Publication Date
CN106372372A true CN106372372A (zh) 2017-02-01
CN106372372B CN106372372B (zh) 2019-10-29

Family

ID=57896265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610920555.7A Expired - Fee Related CN106372372B (zh) 2016-10-21 2016-10-21 一种计及网损变量的频率动态仿真分析方法

Country Status (1)

Country Link
CN (1) CN106372372B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107169245A (zh) * 2017-06-29 2017-09-15 浙江大学 一种电力仿真数据变量对的不稳定性可视分析方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101034809A (zh) * 2007-04-06 2007-09-12 清华大学 基于动态连续潮流的电力系统静态电压稳定的评估方法
CN103904643A (zh) * 2014-03-24 2014-07-02 国家电网公司 一种考虑网损的直流潮流计算方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101034809A (zh) * 2007-04-06 2007-09-12 清华大学 基于动态连续潮流的电力系统静态电压稳定的评估方法
CN103904643A (zh) * 2014-03-24 2014-07-02 国家电网公司 一种考虑网损的直流潮流计算方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
孔德明: "电力系统动态潮流算法与程序开发", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *
孙宏斌 等: "基于动态潮流方程的连续潮流模型与方法", 《中国电机工程学报》 *
杨丽君: "电力系统大停电后恢复算法研究", 《中国博士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107169245A (zh) * 2017-06-29 2017-09-15 浙江大学 一种电力仿真数据变量对的不稳定性可视分析方法
CN107169245B (zh) * 2017-06-29 2019-07-09 浙江大学 一种电力仿真数据变量对的不稳定性可视分析方法

Also Published As

Publication number Publication date
CN106372372B (zh) 2019-10-29

Similar Documents

Publication Publication Date Title
CN104868500B (zh) 一种适用于微电网逆变器并联运行控制方法
CN105514971B (zh) 一种适用于各种运行模式微电网的潮流计算方法
US20060282239A1 (en) Method of setting-up steady state model of VSC-based multi-terminal HVDC transmission system
CN106208102B (zh) 一种基于辅助问题原理的主动配电网分布式无功优化方法
CN107579543A (zh) 一种基于分层控制策略的孤岛微电网分布式协调控制方法
CN105119275B (zh) 一种计及统一潮流控制器的电力系统动态最优潮流的算法
CN101505061B (zh) 一种基于时域仿真的戴维南等值参数跟踪的计算方法
CN103353921B (zh) 一种基于启发式自动网络分区电力系统并行潮流确定方法
CN107171341A (zh) 一种基于分布式计算的输配电网一体化无功优化方法
CN105138739B (zh) 一种计及死区效应的电力系统最低频率快速计算方法
CN105932667B (zh) 一种考虑网损分配的动态潮流仿真方法
CN106208099B (zh) 一种基于二层规划的电力系统无功优化方法及其应用
CN105305439A (zh) 一种考虑输入变量相关性的概率动态潮流计算方法及系统
CN105552915A (zh) 一种考虑静态安全约束的含mmc-hvdc交直流混合电网优化潮流计算方法
CN106786715A (zh) 一种多端vsc‑hvdc系统下垂控制系数确定方法
CN113158573B (zh) 一种基于深度学习的小水电群区域配网最优潮流获取方法
CN104917174A (zh) 一种针对主动配电网的静态电压稳定性判定方法
CN105207204A (zh) 一种计及一次调频不确定性的概率潮流分析方法
CN107359616A (zh) 一种解决大规模电网方式调整后潮流计算不收敛的方法
CN104934973B (zh) 一种考虑温度的电力线路损耗计算方法
CN109066784A (zh) 一种基于分岔理论的微电网稳定性控制方法
CN109638871B (zh) 考虑风电接入的大规模交直流混联系统主网划分方法
CN103401234A (zh) 一种基于发电机节点类型的潮流计算方法
CN106372372A (zh) 一种计及网损变量的频率动态仿真分析方法
CN105281326B (zh) 考虑定子阻尼影响的慢同调分区方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191029

Termination date: 20211021