CN106337562A - Method for building walls by stacking of hollow bricks and grouting - Google Patents

Method for building walls by stacking of hollow bricks and grouting Download PDF

Info

Publication number
CN106337562A
CN106337562A CN201610232422.0A CN201610232422A CN106337562A CN 106337562 A CN106337562 A CN 106337562A CN 201610232422 A CN201610232422 A CN 201610232422A CN 106337562 A CN106337562 A CN 106337562A
Authority
CN
China
Prior art keywords
wall
walls
hollow brick
hollow
slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610232422.0A
Other languages
Chinese (zh)
Inventor
杨建汉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610232422.0A priority Critical patent/CN106337562A/en
Publication of CN106337562A publication Critical patent/CN106337562A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention provides a method for building walls by stacking of hollow bricks and grouting. The method comprises the following steps: uniformly mixing and stirring cement, mixed crude sand and clear water according to a national standard ratio to obtain slurries formed by taking the capability of naturally flowing as the standard for later use; stacking the hollow bricks according to the needs of the walls into the walls as high as 3 to 5 layers; injecting the mixed slurries into hollow core holes of the hollow bricks from the upper parts of the walls which are stacked as high as 3 to 5 layers until the mixed slurries are fully injected; after carrying out grouting, checking leakage conditions of wall surfaces on two sides of the hollow brick walls and whether displacement of the brick bodies is generated or not, if yes, beating by a wooden hammer to reset, and injecting the slurries once every 3 to 5 layers of the hollow bricks until the walls are finished. By adopting the method to build the walls, the labor and time are saved, and the speed is high; especially, the expenditure on manually building the walls block by block and the sand screening cost can be fully saved, and the walls can be form an integrated structure to get firmer. The crude sand containing stone of which the diameter is equal to or smaller than 6cm is directly used in the materials, so that the sand screening cost is further saved.

Description

Built a wall body method using Hollow brick pile slip casting
Technical field
The present invention relates to a kind of building trade wall building method, specifically a kind of built a wall body method using Hollow brick pile slip casting.
Background technology
In building trade, when building a wall in construction house, it is all by artificial, brick block-by-block of plastering to be assembled and is integrally formed wall, this traditional block-by-block method built a wall of plastering is always the difficult problem of building trade, mainly artificial put into big, costly, cement materials are big, speed is slow, and high labor intensive, simultaneously as it is inter-adhesive that body of wall assembles constituted body of wall, also there is certain impact in intensity.
Content of the invention
It is an object of the invention to provide one kind is built a wall body method using Hollow brick pile slip casting, Hollow brick can be made full use of and constitute body of wall by injecting slurry, speed is fast, saving of work and time, save money, quality is good.
The present invention includes cement, mixed crude and clear water mixing and stirring, and the technical scheme being adopted is:
As follows using Hollow brick pile slip casting body method of building a wall:
Step 1, by cement, mixed crude and clear water press national standard proportioning mixing and stirring stand-by, by the slurry of the formation that can be defined by natural flow;
Step 2, Hollow brick is needed pile to become body of wall by body of wall reach 3~5 floor heights;
Step 3, become above the body of wall of 3~5 floor heights from the hollow hole of Hollow brick implantation step 1 mixed slurry to full slurry in pile;
After the completion of step 4, injection slurry, check whether the seepage situation of Hollow brick body of wall both sides metope and brick body shift, beat reset if any displacement wooden mallet, every 3~5 layers of Hollow brick inject a slurry, until body of wall completes.
In technique scheme: the mixed crude in step 1 refers to the mixing sand raw material obtaining in river.
Stone diameter≤6cm in described mixed crude.
The present invention has following advantageous effect: by technique scheme, due to building by the way of cement slurry is reinjected using Hollow brick pile as body of wall, the body of wall being constituted can self-assembling formation overall, intensity is high, plaster the mode assembling due to eliminating block-by-block, directly pile injection speed is fast, directly decrease personnel's operating expenses, solve the trouble that traditional block-by-block assembles body of wall, favourable minimizing building cost and raising built speed, employ the roughing sand direct feeding containing diameter≤6cm stone, more save sieve sand expense.
Specific embodiment
Embodiment 1
As follows using Hollow brick pile slip casting body method of building a wall:
Step 1, by cement, mixed crude and clear water press national standard proportioning mixing and stirring stand-by, by the slurry of the formation that can be defined by natural flow;
Step 2, Hollow brick is needed pile to become body of wall by body of wall reach 3 floor heights;
Step 3, become above the body of wall of 3 floor heights from the hollow hole of Hollow brick implantation step 1 mixed slurry to full slurry in pile;
After the completion of step 4, injection slurry, check whether the seepage situation of Hollow brick body of wall both sides metope and brick body shift, beat reset if any displacement wooden mallet, every 3 layers of Hollow brick inject a slurry, until body of wall completes.
Mixed crude in step 1 refers to the mixing sand raw material obtaining in river.
Stone diameter≤6cm in described mixed crude.
Embodiment 2
As follows using Hollow brick pile slip casting body method of building a wall:
Step 1, by cement, mixed crude and clear water press national standard proportioning mixing and stirring stand-by, by the slurry of the formation that can be defined by natural flow;
Step 2, Hollow brick is needed pile to become body of wall by body of wall reach 4 floor heights;
Step 3, become above the body of wall of 4 floor heights from the hollow hole of Hollow brick implantation step 1 mixed slurry to full slurry in pile;
After the completion of step 4, injection slurry, check whether the seepage situation of Hollow brick body of wall both sides metope and brick body shift, beat reset if any displacement wooden mallet, every 4 layers of Hollow brick inject a slurry, until body of wall completes.
Mixed crude in step 1 refers to the mixing sand raw material obtaining in river.
Stone diameter≤6cm in described mixed crude.
Embodiment 3
As follows using Hollow brick pile slip casting body method of building a wall:
Step 1, by cement, mixed crude and clear water press national standard proportioning mixing and stirring stand-by, by the slurry of the formation that can be defined by natural flow;
Step 2, Hollow brick is needed pile to become body of wall by body of wall reach 5 floor heights;
Step 3, become above the body of wall of 5 floor heights from the hollow hole of Hollow brick implantation step 1 mixed slurry to full slurry in pile;
After the completion of step 4, injection slurry, check whether the seepage situation of Hollow brick body of wall both sides metope and brick body shift, beat reset if any displacement wooden mallet, every 5 layers of Hollow brick inject a slurry, until body of wall completes.
Mixed crude in step 1 refers to the mixing sand raw material obtaining in river.
Stone diameter≤6cm in described mixed crude.
When being embodied as this technology, described Hollow brick can be selected for another utility model of the applicant with regard to arranging the patent of the Hollow brick of glazed layer, the Hollow brick that this patent document is stated is cement cavity brick, and carry carrying handle, more favorably improve pile speed, described slurry can also refer to the c20 of " masonry mortar mixing ratio design discipline " jgj98-20007 defined, during enforcement, it will increase 3-5% with water proportioning, is allowed to be formed the grout of flowable osmotic.
Water consumption is defined to 8% in the present invention, be with national standard be with reference to obtain numerical value, when being embodied as should by compound stirring after can natural flow be defined.

Claims (3)

1. one kind is built a wall body method using Hollow brick pile slip casting, including by cement, mixed crude and clear water mixing and stirring it is characterised in that:
As follows using Hollow brick pile slip casting body method of building a wall:
Step 1, by cement, mixed crude and clear water press national standard proportioning mixing and stirring stand-by, by the slurry of the formation that can be defined by natural flow;
Step 2, Hollow brick is needed pile to become body of wall by body of wall reach 3~5 floor heights;
Step 3, become above the body of wall of 3~5 floor heights from the hollow hole of Hollow brick implantation step 1 mixed slurry to full slurry in pile;
After the completion of step 4, injection slurry, check whether the seepage situation of Hollow brick body of wall both sides metope and brick body shift, beat reset if any displacement wooden mallet, every 3~5 layers of Hollow brick inject a slurry, until body of wall completes.
2. according to claim 1 using Hollow brick pile slip casting build a wall body method it is characterised in that: the mixed crude in step 1 refer in river obtain mixing sand raw material.
3. according to claim 1 and 2 using Hollow brick pile slip casting build a wall body method it is characterised in that: the stone diameter≤6cm in described mixed crude.
CN201610232422.0A 2016-04-14 2016-04-14 Method for building walls by stacking of hollow bricks and grouting Pending CN106337562A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610232422.0A CN106337562A (en) 2016-04-14 2016-04-14 Method for building walls by stacking of hollow bricks and grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610232422.0A CN106337562A (en) 2016-04-14 2016-04-14 Method for building walls by stacking of hollow bricks and grouting

Publications (1)

Publication Number Publication Date
CN106337562A true CN106337562A (en) 2017-01-18

Family

ID=57826111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610232422.0A Pending CN106337562A (en) 2016-04-14 2016-04-14 Method for building walls by stacking of hollow bricks and grouting

Country Status (1)

Country Link
CN (1) CN106337562A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2224619A1 (en) * 1973-04-09 1974-10-31 Desjoyaux Jean Hollow building blocks used as permanent formwork - can be reinforced and concrete poured into vert. cavities
GB2349159B (en) * 1999-04-23 2002-01-16 Univ Napier Bricks
CN2627092Y (en) * 2003-07-24 2004-07-21 北京亿力通达科技发展有限责任公司 Lightweight concrete thermal insulation hollow building-block
CA2254003C (en) * 1997-12-12 2006-07-18 Bradley S. Dressler Holder for adjustable positioning of reinforcing rods
CN1858373A (en) * 2005-05-25 2006-11-08 北京市燕兴隆新型墙体材料有限公司 Large hole light aggregate hollow block filling wall and construction method
CN104499611A (en) * 2014-12-13 2015-04-08 株洲博尔曼科技发展有限公司 Novel plastering rapid construction wall after grouting and construction method thereof
CN105113699A (en) * 2015-07-03 2015-12-02 甘伟 High-strength concrete block used as outer wall of grouted composite wall as well as grouted composite wall and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2224619A1 (en) * 1973-04-09 1974-10-31 Desjoyaux Jean Hollow building blocks used as permanent formwork - can be reinforced and concrete poured into vert. cavities
CA2254003C (en) * 1997-12-12 2006-07-18 Bradley S. Dressler Holder for adjustable positioning of reinforcing rods
GB2349159B (en) * 1999-04-23 2002-01-16 Univ Napier Bricks
CN2627092Y (en) * 2003-07-24 2004-07-21 北京亿力通达科技发展有限责任公司 Lightweight concrete thermal insulation hollow building-block
CN1858373A (en) * 2005-05-25 2006-11-08 北京市燕兴隆新型墙体材料有限公司 Large hole light aggregate hollow block filling wall and construction method
CN104499611A (en) * 2014-12-13 2015-04-08 株洲博尔曼科技发展有限公司 Novel plastering rapid construction wall after grouting and construction method thereof
CN105113699A (en) * 2015-07-03 2015-12-02 甘伟 High-strength concrete block used as outer wall of grouted composite wall as well as grouted composite wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN101581093B (en) Composite high performance soil cement mortar pile construction method
CN103216024A (en) Self-heat-preservation mortar-free block masonry shear wall system and construction method thereof
CN103898831A (en) Ultrahigh-performance-concrete prefabricated assembled-type arch rib and manufacturing and mounting method thereof
CN102433958A (en) Prefabricated wall board construction member
CN201495651U (en) Composite wall construction tie node of antique bricks and insulation blocks
CN108560949A (en) Adobe wall alien invasion ruggedized construction and adobe wall alien invasion reinforcement means
CN108049521A (en) A kind of assembled wall structure of the assembled light raw-soil and bionical soil RPC materials
CN203961099U (en) A kind of high strength hollow constructional column template brick and the constructional column of building thereof
KR100900155B1 (en) Manufacturing method of double-sided natural stone block
CN106545008A (en) A kind of cast-in-situ bored pile pile making method
CN208023830U (en) One kind exempting from plastering and exempts from common brick ribbed panel
CN203129402U (en) Self-insulating building block
CN106337562A (en) Method for building walls by stacking of hollow bricks and grouting
CN207959202U (en) A kind of CFG bracing means
CN102535847B (en) Method for constructing gypsum self-insulation outer wall block masonry
CN109057066A (en) A kind of flexible connection anti-seismic structure and construction method
CN107246106A (en) A kind of surface cuts shaping haydite concrete prefabricated panel
CN203296209U (en) Self-insulation mortarless block masonry shear wall system
CN209244008U (en) A kind of water-tight exterior wall structure
CN103321184A (en) Cured plane-interlocking stereo-stacking engineering block and production method thereof
CN2584693Y (en) Building wall
CN206784653U (en) It is a kind of to there is what there was a tenon at the fourth of the twelve Earthly Branches to exempt from decorative brick
CN203373872U (en) Cast-in-place concrete self-warm-keeping wall with dismounting-free outer formworks
CN208329480U (en) Overlap installing type ground decoration tile
CN206873727U (en) A kind of accomodation ground backfills structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170118

RJ01 Rejection of invention patent application after publication