CN106245594A - Fill armored concrete check dam and the construction method thereof of rubbish - Google Patents

Fill armored concrete check dam and the construction method thereof of rubbish Download PDF

Info

Publication number
CN106245594A
CN106245594A CN201610873107.6A CN201610873107A CN106245594A CN 106245594 A CN106245594 A CN 106245594A CN 201610873107 A CN201610873107 A CN 201610873107A CN 106245594 A CN106245594 A CN 106245594A
Authority
CN
China
Prior art keywords
concrete
rubbish
grid
armored concrete
dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610873107.6A
Other languages
Chinese (zh)
Other versions
CN106245594B (en
Inventor
孟庆川
孟凡与
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610873107.6A priority Critical patent/CN106245594B/en
Publication of CN106245594A publication Critical patent/CN106245594A/en
Application granted granted Critical
Publication of CN106245594B publication Critical patent/CN106245594B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention relates to a kind of armored concrete check dam filling rubbish and construction method thereof.Including armored concrete dam housing, rectangular channel is left in the trapezoidal centre of housing, pre-buried gas gathering network in housing;The rectangular channel of enclosure interior is provided with the clathrum of concreting molding, in the grid in every layer of clathrum, is filled with rubbish, between every layer of clathrum, be provided with the armored concrete demarcation strip pouring molding.Construction method: pouring reinforcement concrete dam housing outside original earth embankment, and pre-buried gas gathering network;First pour ground floor concrete grid in rectangular channel, in grid, fill rubbish, pouring reinforcement concrete demarcation strip on ground floor concrete grid;By this method, until pouring formed top layer concrete grid, in grid, filling rubbish, pour top layer armored concrete.The present invention solves whole concrete dam cost height and landfill magnanimity industry and the problem of house refuse;Sturdy and durable, put things right once and for all;It is applicable to medium and small river, flood control, flood fighting.

Description

Fill armored concrete check dam and the construction method thereof of rubbish
Technical field
The present invention relates to concrete check dam, a kind of armored concrete check dam filling rubbish and the side of building thereof Method.
Background technology
Existing check dam, either earth dam or concrete dam, the problem that all there is function singleness, the most only plays interception Or flooding action, and simple concrete dam cost is the highest.On the other hand, city refuse landfill ground is deficient, ground refuse Stack puzzlement resident living, be increasingly becoming a governance difficult problem.
Summary of the invention
The present invention is directed to the problems referred to above, it is provided that a kind of armored concrete check dam filling rubbish and construction method thereof, one Aspect solves the high problem of concrete dam construction cost of simple function, on the other hand also solves the problem that city refuse landfill ground is deficient Weary problem.
The present invention solves its technical problem and the technical scheme is that
A kind of armored concrete check dam filling rubbish, including armored concrete dam housing, the trapezoidal centre of described housing Leaving rectangular channel, pre-buried gas gathering network in housing, for collecting the biogas that rubbish produces;The rectangular channel of described enclosure interior sets It is equipped with the clathrum of concreting molding, in the grid in every layer of clathrum, is filled with rubbish, arrange between every layer of clathrum There is the armored concrete demarcation strip pouring molding.
The construction method of the described armored concrete check dam filling rubbish, comprises the steps:
(1) in original earth embankment lateral branch template, the middle armored concrete dam housing with rectangular channel, and pre-buried gas collection are poured Pipe network;
(2) pour molding ground floor concrete grid in rectangular channel, fill in grid, fill up rubbish, and tamp rubbish;
(3) on ground floor concrete grid, pour molding armored concrete demarcation strip, on demarcation strip, pour molding Two layer concrete grids;
(4) fill in second layer concrete grid, fill up rubbish, and tamp rubbish;
(5) on second layer concrete grid, pour molding armored concrete demarcation strip, on demarcation strip, pour molding Three layer concrete grids;
(6) fill in third layer concrete grid, fill up rubbish, and tamp rubbish;
(7) on third layer concrete grid, pour molding armored concrete demarcation strip, on demarcation strip, pour molding Four layer concrete grids;
(8) by the above process, after until pouring formed top layer concrete grid, filling in grid, filling up, tamp rubbish, water Build top layer armored concrete, make top layer armored concrete maintain an equal level with dam housing end face and pour and be integrated.
Using the present invention of technique scheme, compared with prior art, it provides the benefit that:
Solve the problem that whole concrete dam cost is high;Solve landfill magnanimity industry and the problem of house refuse;Firm resistance to With, put things right once and for all;It is particularly well-suited to medium and small river, flood control, flood fighting.
Further, armored concrete dam housing end face forms concrete road surface, or overlays asphalt surface.Optionally add The means of transportation such as dress trackside baffle plate, then make check dam dam crest become sightseeing, tour expressway.
Further, armored concrete dam housing end face is provided with biogas lamp, the gas collection that biogas lamp is pre-buried with in housing Pipe network UNICOM.The biogas that rubbish in dam housing produces, can be that biogas lamp provides illumination energy by a gas gathering network part Source, another part can be concentrated and save as combustion gas of living.
Further, armored concrete dam housing reserves suspension column, platform in side near water, or installs breakwater additional.To strengthen Flood control, flood fighting intensity.
Accompanying drawing explanation
Fig. 1 is the section structure schematic diagram of the armored concrete check dam filling rubbish;
Fig. 2 is the perspective view of the armored concrete check dam filling rubbish;
Fig. 3 is gas gathering network schematic diagram;
In figure: 1-armored concrete dam housing;2-concrete grid;3-rubbish;4-armored concrete demarcation strip;5-discharge Net;6-biogas lamp;7-suspension column (platform);8-rectangular channel.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is further illustrated, and purpose is only that and is better understood from the present invention Content, therefore the cited case is not the restriction to present invention.
See Fig. 1, Fig. 2, Fig. 3, a kind of armored concrete check dam filling rubbish, by armored concrete dam housing 1, Concrete grid 2, rubbish 3, armored concrete demarcation strip 4, gas gathering network 5 etc. are constituted, and armored concrete dam housing 1 is in ladder Shape, centre leaves rectangular channel 8, is embedded with the gas gathering network 5 collecting the biogas that rubbish produces in armored concrete dam housing 1, Rectangular channel 8 is provided with multi-layer concrete grid 2, is filled with rubbish 3 in concrete grid 2, sets between every layer concrete grid 2 It is equipped with armored concrete demarcation strip 4.
The construction method of the armored concrete check dam of this filling rubbish is:
(1) outside original earth embankment, install template, pour the middle armored concrete dam housing 1 with rectangular channel 8, and pre-buried Gas gathering network 5;
(2) bottom rectangular channel 8, pour molding ground floor concrete grid 2, fill in ground floor concrete grid 2, fill up Rubbish 3, and tamp rubbish 3;
(3) on ground floor concrete grid 2, pour molding armored concrete demarcation strip 4, separate at this layer of armored concrete Molding second layer concrete grid 2 is poured on plate 4;
(4) fill in second layer concrete grid 2, fill up rubbish 3, and tamp rubbish 4;
(5) on second layer concrete grid 2, pour molding armored concrete demarcation strip 4, separate at this layer of armored concrete Molding third layer concrete grid 2 is poured on plate 4;
(6) fill in third layer concrete grid 2, fill up rubbish 3, and tamp rubbish 3;
(7) on third layer concrete grid 2, pour molding armored concrete demarcation strip 4, separate at this layer of armored concrete Molding the 4th layer concrete grid 2 is poured on plate 4;
(8) by the above process, until pouring formed top layer concrete grid 2, filling in top layer concrete grid 2, fill up, ramming After real rubbish 3, pour top layer armored concrete, make top layer armored concrete maintain an equal level with dam housing end face and pour and be integrated;
(9) end face at armored concrete dam housing 1 lays asphalt surface, installs the means of transportation such as trackside baffle plate additional;
(10) end face at armored concrete dam housing 1 installs the biogas lamp 6 for illumination, and connected set gas pipe network 5, by rubbish 3 biogas produced transport to biogas lamp 6;
(11) suspension column (platform) 7 is reserved in the side near water at armored concrete dam housing 1, it is possible to install breakwater additional.
The armored concrete check dam of above-mentioned filling rubbish is because building year longer and sagging accumulation to a certain extent, permissible End face at armored concrete dam housing 1 overlays thickening pitch layer again.
Original earth embankment inside the armored concrete check dam of above-mentioned filling rubbish, can be used as civil building soil or plantation Greenbelt or as agricultural land sow crops.
Above-described embodiment is only explanation for example to the present invention.Those skilled in the art can be right Described specific embodiment makes various amendment or supplements or use similar mode to substitute, but without departing from this Bright spirit or surmount scope defined in appended claims.

Claims (5)

1. the armored concrete check dam filling rubbish, it is characterised in that: include armored concrete dam housing, described shell Rectangular channel is left in the trapezoidal centre of body, pre-buried gas gathering network in housing, for collecting the biogas that rubbish produces;Described enclosure interior Rectangular channel in be provided with the clathrum of concreting molding, be filled with rubbish, every layer of net in the grid in every layer of clathrum The armored concrete demarcation strip pouring molding it is provided with between compartment.
The armored concrete check dam of filling rubbish the most according to claim 1, it is characterised in that: armored concrete dam Housing end face forms concrete road surface, or overlays asphalt surface.
The armored concrete check dam of filling rubbish the most according to claim 1, it is characterised in that: armored concrete dam Housing end face is provided with the biogas lamp for illumination, the gas gathering network UNICOM that biogas lamp is pre-buried with in housing.
The armored concrete check dam of filling rubbish the most according to claim 1, it is characterised in that: armored concrete dam Housing reserves suspension column, platform in side near water, or installs breakwater additional.
5. as described in any one of claim 1-4, fill a construction method for the armored concrete check dam of rubbish, its feature It is, comprises the steps:
(1) in original earth embankment lateral branch template, the middle armored concrete dam housing with rectangular channel, and pre-buried gas collection are poured Pipe network;
(2) pour molding ground floor concrete grid in rectangular channel, fill in grid, fill up rubbish, and tamp rubbish;
(3) on ground floor concrete grid, pour molding armored concrete demarcation strip, on demarcation strip, pour molding Two layer concrete grids;
(4) fill in second layer concrete grid, fill up rubbish, and tamp rubbish;
(5) on second layer concrete grid, pour molding armored concrete demarcation strip, on demarcation strip, pour molding Three layer concrete grids;
(6) fill in third layer concrete grid, fill up rubbish, and tamp rubbish;
(7) on third layer concrete grid, pour molding armored concrete demarcation strip, on demarcation strip, pour molding Four layer concrete grids;
(8) by the above process, after until pouring formed top layer concrete grid, filling in grid, filling up, tamp rubbish, water Build top layer armored concrete, make top layer armored concrete maintain an equal level with dam housing end face and pour and be integrated.
CN201610873107.6A 2016-10-08 2016-10-08 Fill the armored concrete check dam and its construction method of rubbish Expired - Fee Related CN106245594B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610873107.6A CN106245594B (en) 2016-10-08 2016-10-08 Fill the armored concrete check dam and its construction method of rubbish

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610873107.6A CN106245594B (en) 2016-10-08 2016-10-08 Fill the armored concrete check dam and its construction method of rubbish

Publications (2)

Publication Number Publication Date
CN106245594A true CN106245594A (en) 2016-12-21
CN106245594B CN106245594B (en) 2018-03-09

Family

ID=57612243

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610873107.6A Expired - Fee Related CN106245594B (en) 2016-10-08 2016-10-08 Fill the armored concrete check dam and its construction method of rubbish

Country Status (1)

Country Link
CN (1) CN106245594B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1806950A (en) * 2006-02-16 2006-07-26 中国农业大学 Domestic refuse treatment method
KR20070044829A (en) * 2007-04-10 2007-04-30 한상관 Nature-friendly bank protection engineering method
CN102864782A (en) * 2012-10-22 2013-01-09 安蓉建设总公司 Construction method for fast filling clay core rock-fill dam body
CN105123318A (en) * 2015-09-02 2015-12-09 天津滨海新区津大建筑规划有限责任公司 Ecological network ground weir type channel structure
CN105780741A (en) * 2016-03-16 2016-07-20 河海大学 Flow self-adaptive type water blocking weir with photocatalysis water quality purification function
CN206157669U (en) * 2016-10-08 2017-05-10 孟庆川 Fill reinforced concrete water -stop dam of rubbish

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1806950A (en) * 2006-02-16 2006-07-26 中国农业大学 Domestic refuse treatment method
KR20070044829A (en) * 2007-04-10 2007-04-30 한상관 Nature-friendly bank protection engineering method
CN102864782A (en) * 2012-10-22 2013-01-09 安蓉建设总公司 Construction method for fast filling clay core rock-fill dam body
CN105123318A (en) * 2015-09-02 2015-12-09 天津滨海新区津大建筑规划有限责任公司 Ecological network ground weir type channel structure
CN105780741A (en) * 2016-03-16 2016-07-20 河海大学 Flow self-adaptive type water blocking weir with photocatalysis water quality purification function
CN206157669U (en) * 2016-10-08 2017-05-10 孟庆川 Fill reinforced concrete water -stop dam of rubbish

Also Published As

Publication number Publication date
CN106245594B (en) 2018-03-09

Similar Documents

Publication Publication Date Title
CN105862710B (en) A kind of drain bar and construction method for Tidal Flat Inning Area processing
CN106638918A (en) Construction method for sponge city rainwater collection system
CN104759457B (en) The method for arranging for the dystopy reaction system that chromium-polluted soil is repaired
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN104929224B (en) Pavement system for percolate guide blind pipe
CN102864789B (en) A kind of construction method of retaining wall drainage system
CN203174615U (en) Step type reinforced earth embankment structure
CN107152012A (en) Sluice construction technique
CN104652181B (en) Light supporting structure for existing railway station roadbed on filling roadbed
CN102383408B (en) Greening method for high water level impermeable saline and alkaline lands and greening system
CN102817298B (en) Construction method on frozen soil
CN207228292U (en) One kind omits water system in printing slowly after first catchmenting
CN103243624B (en) Construction method for salty soil district railway roadbed with water content lower than liquid limit
CN204826140U (en) Dirty current drive system of reservoir area rain more than cheuch type landfill dam crest elevation
CN102373675A (en) Fabricated culvert member and construction method thereof
CN204491320U (en) Existing railway station roadbed light supporting structure on filled ground
CN108580503B (en) Large garbage pile slope shaping construction method
CN203716273U (en) Multifunctional ecological draining gutter
CN203960699U (en) Road cutting type protecting immersion road structure
CN202925538U (en) Rammer constructed on frozen soil
CN206157669U (en) Fill reinforced concrete water -stop dam of rubbish
CN107558587A (en) One kind omits water system in printing slowly after first catchmenting
CN106245594A (en) Fill armored concrete check dam and the construction method thereof of rubbish
CN202323906U (en) Assembly type culvert component
CN105019539A (en) System for shunting rainwater and sewage in reservoir area above crest elevation of valley type refuse landfill

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180309

Termination date: 20181008