CN106223568A - Building stone or porcelain plate steel cable or steel bar ruggedized construction and reinforcement means thereof - Google Patents
Building stone or porcelain plate steel cable or steel bar ruggedized construction and reinforcement means thereof Download PDFInfo
- Publication number
- CN106223568A CN106223568A CN201610834294.7A CN201610834294A CN106223568A CN 106223568 A CN106223568 A CN 106223568A CN 201610834294 A CN201610834294 A CN 201610834294A CN 106223568 A CN106223568 A CN 106223568A
- Authority
- CN
- China
- Prior art keywords
- steel bar
- steel cable
- plate
- steel
- anchor pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0832—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
- E04F13/0833—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable
- E04F13/0851—Hooking means on the back side of the covering elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0296—Repairing or restoring facades
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
Abstract
The present invention discloses a kind of building stone or porcelain plate steel cable or steel bar ruggedized construction and reinforcement means thereof, slot including on stone material or porcelain plate limit, steel cable or steel bar is loaded in groove, enable the decoration panel on metope be connected after planting structure glue will not come off by monolithic, after keelless decoration panel engineering is below made plate be connected by fluting implantation steel cable or steel bar except stone material upper by this technology, junction in the cross crotch of plate uses double end to hook anchor pole or anchor is planted on main body metope and Structure Beam-column, and the decoration panel after reinforcing is more firm.
Description
Technical field
The invention belongs to building field, particularly relate to a kind of building stone or porcelain plate steel cable or steel bar reinforcement technique and execute
Work method.
Background technology
The most easily there is loose or dislocation phenomenon as employing cement wet combining and glue point paste after installing in Decorative Building Stone or porcelain plate,
Must take to add and be affixed to firmly, general fixing means all uses the binding that punches on plate face to fix, and destroys outward appearance and has not also reached
Complete firm, because termination point of anchor rod does not has band slip hook, it is also easy to extract, firm poor effect.
Summary of the invention
It is an object of the invention to provide the strong building stone of a kind of simple fastness of constructing or porcelain plate steel cable or steel bar adds
Fixing structure and reinforcement means thereof, be issued to stone material or porcelain plate plate fixation at the sight not tearing plate and the effect that disfeatures open.
The object of the present invention is achieved like this, described building stone or porcelain plate steel cable or steel bar ruggedized construction, including
Facing plate, it is characterised in that: the avris up and down at every facing plate is sawed skewed slot, puts into steel cable or steel bar in skewed slot,
The steel cable or the steel bar that expose in plate with plate interspace are planted in main body by shank member or anchor pole, described shank member or anchor
Bar, the bullet including rear end hooks and screw rod, and the both sides anterior at screw rod are provided with hook, or are provided with circle in screw rod front portion.
Above-mentioned skewed slot is short groove or groove.
Above-mentioned hook uses the hook of Cornu Caprae seu Ovis type.
Building stone of the present invention or porcelain plate steel cable or the reinforcement means of steel bar ruggedized construction, comprise the steps:
Stone material or the unstable engineering of porcelain plate to the most ready-made building decoration, oblique notches at transverse joint or perps, and at facing plate
Seam punches to main body in cross mouth, clear powder totally after injecting glue in down fold, then put into after steel cable or steel bar filling-in glue again,
After glue be dry, replant shank member or anchor pole make steel cable or steel bar be caught on by the hook in shank member or anchor pole, the most again stem portion and after
The bullet of end hooks to put into notes weather proofing sealant in main body, decoration panel firmly can be held.
Building stone of the present invention or porcelain plate steel cable or the construction method of steel bar ruggedized construction, comprise the steps:
First stone material or porcelain plate to new clothes carry out plate saw skewed slot processing, and then stone material or porcelain plate install on metope, at seam away from uniformly
Cross crotch in hole clear health, the more built-in steel cable of down fold or steel bar, and injecting glue fixes steel cable or steel bar, refills anchor after glue is dry
Rod member or anchor pole make steel cable or steel bar be caught on by the hook in shank member or anchor pole, and the bullet of anchor pole portion and rear end hooks to be put in main body,
After glue is dry, reaches firm, decoration panel firmly can be held, finally note weather proofing sealant.
The hook that each steel cable on adjacent stone material or porcelain plate or steel bar are provided with by the both sides on a shank member or anchor pole
Catching on respectively, it is each that the hook that the both sides in i.e. one shank member or anchor pole are provided with can catch on adjacent stone material or porcelain plate respectively
The steel cable being fixed with or steel bar.
Described building stone or porcelain plate steel cable or steel bar reinforcement means, it is characterised in that the ornamental blocks on metope is not being torn open
Just can strengthening construction under the sight of plate.
Avris up and down at every facing plate saws skewed slot, and in skewed slot, clear dried bean noodles puts into steel cable or steel bar the most afterwards, then
Structure glue is planted in groove, after glue is dry, form plate and plate string will not the danger that comes off of monolithic.At plate and plate
The steel cable exposed in gap or steel bar can be planted in main body by double headed stud or anchor, and described shank member or anchor pole, according to decorations
The original construction method of panel uses anchor or anchor pole targetedly, it is also possible to according to concrete on-the-spot original mounting structure
The defect, the kind that exist are analyzed, and the length specification using one of which anchor pole and anchor is customizable.
Advantage of the present invention is: to keelless decoration panel after being linked into an integrated entity by steel cable or steel bar below except stone material upper
Journey cross crotch away from the junction of four plates use anchor pole or anchor to plant on main body metope and Structure Beam-column, anchor is planted and is made to add
Gu decoration panel after is more firm.
Accompanying drawing explanation
Fig. 1 is a kind of double end anchor pole schematic diagram of the present invention.
Fig. 2 is the another kind of double end anchor pole schematic diagram of the present invention.
Fig. 3 is another shank member schematic diagram of the present invention.
Fig. 4 is equipped with steel cable or steel bar exposed portion and caught on by anchor pole and live schematic diagram with anchor pole circle on facing plate.
Fig. 5 is that glue point is hung and equipped with steel cable or steel bar and fixed by anchor pole and anchor on the facing plate of stone material or porcelain plate
Structural representation.
Fig. 6 is that the facade after facing plate reinforcement by connection arranges schematic diagram.
Fig. 6-1 is the A-A profile of Fig. 6.
Fig. 6-2 is the B-B profile of Fig. 6.
Fig. 7 is the structural representation that skewed slot is short groove of facing plate.
Fig. 8 is the structural representation that skewed slot is groove of facing plate.
Fig. 9 be the steel cable of the stone curtain wall plate of band steel skeleton or steel bar to use steel wire or steel cable to wrap around circle cross bar fixing
Structural representation.
Glue point patch facing board wall unguyed for Figure 10 is perpendicular cuts open figure.
Cement wet combining facing board wall unguyed for Figure 11 is perpendicular cuts open figure.
Glue point hanging of veneer wall after Figure 12 reinforcing erects and cuts open figure.
Cement wet combining facing board wall after Figure 13 reinforcing erects and cuts open figure.
Detailed description of the invention
As shown in drawings, building stone of the present invention or porcelain plate steel cable or steel bar ruggedized construction, including facing plate,
Its construction features is to saw at the avris up and down of every facing plate 3 to have skewed slot, and skewed slot can short groove 6 as described in Figure 7, it is possible to as
Groove 7 described in Fig. 8, in skewed slot, clear powder puts into steel cable or steel bar 1 the most afterwards, then structure glue is planted reaches fixing in groove
Put into the steel cable in groove or steel bar, the steel cable exposed in plate with plate interspace cross crotch or steel bar can by double headed stud or
Anchor catches on plants in main body (such as body of wall), described shank member or anchor pole 2, and the bullet including rear end hooks and screw rod, can use
The structure of Patent No. 200920183353.4 or 201420053536.5, or other existing structure, anterior (anterior at screw rod
Can be front end, or near the screw rod of front end) both sides be provided with ram's horn (2-A, 2-B in as shown in Figure 1, Figure 2), or at steel bar
Bar front portion is provided with circle (2-C as in Fig. 3).
Fig. 9 is fixed for the slabstone on steelframe and saws oblique groove, Fig. 8 opening up and down of facing plate 3;Or oblique short groove Fig. 7 exists
After defending clearly, load steel cable or steel bar in the skewed slot held successfully, then toward injecting glue in groove, after glue is dry, plate seam away from expose
Use steel cable or steel bar 2-E to be bundled on steelframe cross bar on steel cable or steel bar 1, beat weather proofing sealant finally by note, complete to add
Gu program.
The kind of anchor pole can have 2-A(to see Fig. 1), 2-B(see Fig. 2), 2-C(see Fig. 3), the anchor pole front end system of 2-A, 2-B
Becoming Cornu Caprae seu Ovis shape (such as double crotches), both sides Cornu Caprae seu Ovis can catch on the steel cable on plate or steel bar reaches to hold the purpose of plate, after anchor pole
Double bullets that end is shaped with hook to catch on and allow anchor pole be not easy to pull out on the hole wall of main body, also can reach to hold the purpose of plate.As
Shown in Fig. 5, upper and lower two steel cables or steel bar circle can be lived when the ring anchor of 2-C is put into, the bullet of bar portion and front end hooks and can put into
Main body 4(such as body of wall) on, decoration panel firmly can be held, reach the reinforcing purpose of plate.
Reinforce targetedly
First the stone material or porcelain plate loading onto wall carry out structure understand original installation method, specifically exist unstable reason and
Degree is analyzed, and carries out strengthening construction from top to bottom, prevent big emaciated face from falling on original metope after carrying out safeguard protection.Adopt
With the reinforced construction method of this technology, original engineering installed is divided into several structure, should be according to original drawing and construction
Present situation, specify unstable reason exist where, stone material or porcelain plate general structure be divided into steel skeleton stone curtain wall Fig. 9, point hang stone
Panel decorated by material or porcelain plate, and glue point 5 hangs patch and cement wet combining Figure 11, and the defect of stone curtain wall construction easily causes plate and falls
Falling, Vitrolite curtain wall plate thickness deficiency takes the folded patch (referring to Fig. 6-2) of glue to be design defect, and also easily degumming causes plate to fall
Falling, stone material and porcelain plate glue point are hung exterior wall and this technology must be used to reinforce because temperature difference plate flatulence of heat type easily comes off.
Construction procedure
Stone material or the unstable engineering of porcelain plate to the most ready-made building decoration, oblique notches at transverse joint or perps, and at decoration panel
The seam of block 3 punches to main body in cross mouth, injecting glue in clear powder totally rear down fold, puts into filling-in again after steel cable or steel bar
Glue, after glue is dry, the hole interplantation double end shank member from cross crotch or anchor pole 2 make steel cable or steel bar 1 by the both sides sheep on anchor pole again
Angle (crotch) is caught on, and the rear end bullet of anchor pole catches in hole, can pull out out, define globality firm after glue is planted.To new clothes
Stone material or porcelain plate first carry out plate kerf, with metope on glue point rubberizing mud wet combining plate, after clay is dry, at seam away from cross
At seam, boring is after clear health, second injecting glue steel loading rope or steel bar, and in groove, middle injecting structure glue, fixes steel cable or steel bar
Refilling shank member or the anchor pole of double end slip hook after glue is dry, finally note weather proofing sealant, anchor pole portion catches on steel cable or steel bar in front end
The bullet of rear end hooks to be put in main body (such as body of wall), decoration panel firmly can be held.
The stone curtain-wall hanging part of steel frame construction uses the plate of monocline easily to be inhaled by wind and flies, and shown in Fig. 9, fixing means is at plate
After the bottom and upper segment fluting of block 3 buries steel cable or steel bar underground, then being bundled on steelframe cross bar by steel wire 2-E, this can be plate
Hold, reach to be firmly fixed.
The facing plate that can come off generation before Jia Guing, carries out structure inspection according to original design drawing, to not having drawing
Project carries out taking site inspection practical structures apart, if Fig. 6-2 is porcelain plate point hanging hang structure, installs panel thick not employing patch small pieces and reaches
To plate thickness, so causing plate to come off after sticker position departs from, it is necessary to reinforce in front big sheet 1, every plate is led to
Cross steel cable or steel bar is slotted after burying underground, after glue is dry, be fixed in main body away from middle implantation double headed stud at cross crotch, reach jail
Gu.
Claims (6)
1. building stone or porcelain plate steel cable or a steel bar ruggedized construction, including facing plate, it is characterised in that: at every facing
The saw of avris up and down of plate has skewed slot, puts into steel cable or steel bar in skewed slot, the steel cable exposed in plate with plate interspace or
Steel bar is planted in main body by shank member or anchor pole, described shank member or anchor pole, and the bullet including rear end hooks and screw rod, at screw rod
Anterior both sides are provided with hook, or are provided with circle in screw rod front portion.
Building stone the most according to claim 1 or porcelain plate steel cable or steel bar ruggedized construction, it is characterised in that: skewed slot is short
Groove or groove.
Building stone the most according to claim 1 and 2 or porcelain plate steel cable or steel bar ruggedized construction, it is characterised in that: hook is adopted
Hook by Cornu Caprae seu Ovis type.
4. building stone described in claim 1 or 2 or 3 or porcelain plate steel cable or the reinforcement means of steel bar ruggedized construction, including such as
Lower step: stone material or the unstable engineering of porcelain plate to the most ready-made building decoration, oblique notches at transverse joint or perps, and at facing
The seam of plate punches to main body in cross mouth, clear powder totally after injecting glue in down fold, then put into after steel cable or steel bar again
Filling-in glue, replants shank member after glue is dry or anchor pole makes steel cable or steel bar be caught on by the hook in shank member or anchor pole, the most again
The bullet of bar portion and rear end hooks to put into notes weather proofing sealant in main body, decoration panel firmly can be held.
5. building stone described in claim 1 or 2 or 3 or porcelain plate steel cable or the construction method of steel bar ruggedized construction, including such as
Lower step: first stone material or porcelain plate to new clothes carry out plate saw skewed slot processing, and then stone material or porcelain plate install on metope, at seam
Hole in uniform cross crotch clear health, the more built-in steel cable of down fold or steel bar, and injecting glue fixes steel cable or steel bar, after glue is dry
Refilling shank member or anchor pole makes steel cable or steel bar be caught on by the hook in shank member or anchor pole, the bullet of anchor pole portion and rear end hooks puts into master
On body, after glue is dry, reaches firm, decoration panel firmly can be held, finally note weather proofing sealant.
6. according to the method described in claim 4 or 5, it is characterised in that: each steel cable on adjacent stone material or porcelain plate or
The hook that steel bar is provided with by the both sides on a shank member or anchor pole catches on respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610834294.7A CN106223568B (en) | 2016-09-20 | 2016-09-20 | Building stone or porcelain plate steel rope or steel bar reinforcing structure and reinforcing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610834294.7A CN106223568B (en) | 2016-09-20 | 2016-09-20 | Building stone or porcelain plate steel rope or steel bar reinforcing structure and reinforcing method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106223568A true CN106223568A (en) | 2016-12-14 |
CN106223568B CN106223568B (en) | 2023-09-22 |
Family
ID=58075724
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610834294.7A Active CN106223568B (en) | 2016-09-20 | 2016-09-20 | Building stone or porcelain plate steel rope or steel bar reinforcing structure and reinforcing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106223568B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106906977A (en) * | 2017-04-21 | 2017-06-30 | 中建海峡建设发展有限公司 | The mounting process and metope of abnormal curved surface GRG surfaces overlying art pottery ceramics |
CN109779093A (en) * | 2017-11-11 | 2019-05-21 | 天津二建水电安装工程有限公司 | A kind of light partition wall and its construction method |
CN110778043A (en) * | 2019-11-11 | 2020-02-11 | 海盐宝仕龙塑业股份有限公司 | Fast-assembling type PVC wallboard |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19547845A1 (en) * | 1995-12-21 | 1997-06-26 | Loba Bautenschutz Gmbh & Co Kg | Bonding heat insulation panels to walls in composite heat insulating facade systems |
JPH1088735A (en) * | 1996-09-11 | 1998-04-07 | Kajima Corp | Curtain wall |
JP2001032499A (en) * | 1999-07-19 | 2001-02-06 | Abc Trading Co Ltd | Facing panel installing structure and facing panel |
CN2585909Y (en) * | 2002-04-27 | 2003-11-12 | 上海斯米克建筑陶瓷股份有限公司 | Anchor arm |
CN201241453Y (en) * | 2008-06-18 | 2009-05-20 | 周述文 | Stone or ceramic tile wire cable or bar steel prestress pulling and hanging glue implant paste installation apparatus |
CN201411869Y (en) * | 2009-06-05 | 2010-02-24 | 周述文 | Combined T-type steel bar mounting device for architectural decoration component |
CN102061793A (en) * | 2010-11-15 | 2011-05-18 | 周述文 | Device and method for mounting wire rope of architectural veneer |
CN102561640A (en) * | 2010-12-28 | 2012-07-11 | 福建溪石股份有限公司 | Fixing device capable of replacing stone panel and application thereof |
CN206174381U (en) * | 2016-09-20 | 2017-05-17 | 周述文 | Building stone or porcelain plate steel cable or billet reinforced structure |
-
2016
- 2016-09-20 CN CN201610834294.7A patent/CN106223568B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19547845A1 (en) * | 1995-12-21 | 1997-06-26 | Loba Bautenschutz Gmbh & Co Kg | Bonding heat insulation panels to walls in composite heat insulating facade systems |
JPH1088735A (en) * | 1996-09-11 | 1998-04-07 | Kajima Corp | Curtain wall |
JP2001032499A (en) * | 1999-07-19 | 2001-02-06 | Abc Trading Co Ltd | Facing panel installing structure and facing panel |
CN2585909Y (en) * | 2002-04-27 | 2003-11-12 | 上海斯米克建筑陶瓷股份有限公司 | Anchor arm |
CN201241453Y (en) * | 2008-06-18 | 2009-05-20 | 周述文 | Stone or ceramic tile wire cable or bar steel prestress pulling and hanging glue implant paste installation apparatus |
CN201411869Y (en) * | 2009-06-05 | 2010-02-24 | 周述文 | Combined T-type steel bar mounting device for architectural decoration component |
CN102061793A (en) * | 2010-11-15 | 2011-05-18 | 周述文 | Device and method for mounting wire rope of architectural veneer |
CN102561640A (en) * | 2010-12-28 | 2012-07-11 | 福建溪石股份有限公司 | Fixing device capable of replacing stone panel and application thereof |
CN206174381U (en) * | 2016-09-20 | 2017-05-17 | 周述文 | Building stone or porcelain plate steel cable or billet reinforced structure |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106906977A (en) * | 2017-04-21 | 2017-06-30 | 中建海峡建设发展有限公司 | The mounting process and metope of abnormal curved surface GRG surfaces overlying art pottery ceramics |
CN109779093A (en) * | 2017-11-11 | 2019-05-21 | 天津二建水电安装工程有限公司 | A kind of light partition wall and its construction method |
CN109779093B (en) * | 2017-11-11 | 2020-08-11 | 天津建工城市建设发展有限公司 | Light partition wall and construction method thereof |
CN110778043A (en) * | 2019-11-11 | 2020-02-11 | 海盐宝仕龙塑业股份有限公司 | Fast-assembling type PVC wallboard |
Also Published As
Publication number | Publication date |
---|---|
CN106223568B (en) | 2023-09-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106223568A (en) | Building stone or porcelain plate steel cable or steel bar ruggedized construction and reinforcement means thereof | |
CN103556819B (en) | A kind of construction method of reserved constructional column hole on beam slab | |
CN102561642B (en) | Mounting device with elastic hook and construction method for hanging and combining building stone or ceramic tiles with mastic | |
KR101286278B1 (en) | Korean traditional roof structure | |
CN104674997B (en) | A kind of supporting construction and its construction method on timber buildings roof modelled after an antique | |
CN106193389A (en) | One is exempted to tear building template assembly open | |
CN206174381U (en) | Building stone or porcelain plate steel cable or billet reinforced structure | |
CN205444235U (en) | Prefabricated retaining wall with prop up and keep off rib | |
KR101551196B1 (en) | Method for gong-po installation thereby and structure for gong-po installation of korean-style house | |
CN108818879A (en) | A kind of prefabricated inner partition plate weight hanging structure and its construction technology | |
CN206495369U (en) | A kind of assembly type light steel wall | |
CN105201100B (en) | The cladding node of assembled architecture outer wall and the precast facade with the node | |
CN112112299A (en) | Building fireproof heat-preservation net rack plate mounting structure and construction method thereof | |
CN104047607A (en) | Construction method for lifting out shield tunneling machine under condition of envelop enclosure | |
CN106088514B (en) | A kind of stone material dry suspending slabstone fixed structure with high anti-seismic function | |
CN104831929B (en) | Decorated construction method of the interior wall plaque without scaffold | |
JP2008156946A (en) | Decorative chain mounting implement for down pipe | |
KR101566891B1 (en) | Method for building construction of Korean-style house | |
CN207079606U (en) | The anchor structure of the prefabricated concrete gridiron of highway slope protection | |
CN207469520U (en) | The structure that a kind of steel structure keel is combined with concrete prefabricated hanging plate | |
CN206815543U (en) | A kind of assembling frame bean column node | |
KR101052939B1 (en) | Device installation method and installation method for decoration of soil compaction wall | |
CN105155847B (en) | The construction method of imitative cave architectural surface | |
CN205577157U (en) | Window flower structure for building wall | |
CN204001277U (en) | For the combined wall masonry stationary device that cornices |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |