Building stone or porcelain plate steel cable or steel bar ruggedized construction
Technical field
The utility model belongs to building field, more particularly to a kind of building stone or porcelain plate steel cable or steel bar reinforcement technique.
Background technology
All easily there is loose or dislocation phenomenon after installing as pasted using cement wet combining and glue point in Decorative Building Stone or porcelain plate,
Reinforcing must be taken to firmly, general fixing means is all fixed using the binding that punched in plate face, is destroyed outward appearance and has not been reached also
It is complete firm, because termination point of anchor rod does not have band slip hook, it is also easy to extract, firm effect on driving birds is not good.
The content of the invention
The purpose of this utility model is to provide a kind of simple fastness strong building stone or porcelain plate steel cable or steel of constructing
Bar ruggedized construction, is not tearing plate open and the scene of the effect that disfeatures is issued to stone material or porcelain plate plate fixation.
The purpose of this utility model is achieved in that described building stone or porcelain plate steel cable or steel bar ruggedized construction,
Including facing plate, it is characterised in that:There is skewed slot in the saw of avris up and down of every facing plate, steel cable or steel are put into skewed slot
Bar, the steel cable exposed in plate and plate interspace or steel bar are planted in main body by shank member or anchor pole, described shank member
Or anchor pole, including the bullet of rear end hooks and screw rod, is provided with hook in the anterior both sides of screw rod, or be provided with circle in screw rod front portion.
Above-mentioned skewed slot is short groove or groove.
Above-mentioned hook uses the hook of goat's horn type.
The reinforcement means of building stone described in the utility model or porcelain plate steel cable or steel bar ruggedized construction, including following step
Suddenly:To the unstable engineering of stone material or porcelain plate of ready-made building decoration, oblique notched in transverse joint or perps, and in facing plate
Seam punched to main body in cross mouthful, injecting glue in down fold, then puts into filling-in again after steel cable or steel bar after clear powder is clean
Glue, after glue is dry replanting shank member or anchor pole makes steel cable or steel bar be caught on by the hook in shank member or anchor pole, finally stem portion again
Hook to put into the bullet of rear end and note weather proofing sealant in main body, decoration panel can be firmly held.
The construction method of building stone described in the utility model or porcelain plate steel cable or steel bar ruggedized construction, including following step
Suddenly:Stone material or porcelain plate to new clothes carry out plate saw skewed slot processing first, and then stone material or porcelain plate are attached on metope, in seam away from equal
Drill clear health in even cross crotch, then the built-in steel cable of down fold or steel bar, and injecting glue fixes steel cable or steel bar, is refilled after glue is dry
Shank member or anchor pole make steel cable or steel bar be caught on by the hook in shank member or anchor pole, and the bullet of anchor pole portion and rear end is hooked puts into main body
On, reached firmly after glue is dry, decoration panel can be firmly held, finally note weather proofing sealant.
The hook that each steel cable or steel bar on adjacent stone material or porcelain plate are provided with by the both sides on a shank member or anchor pole
Catch on respectively, i.e. the hook that both sides in a shank member or anchor pole are provided with can catch on each on adjacent stone material or porcelain plate respectively
The steel cable or steel bar being fixed with.
Described building stone or porcelain plate steel cable or steel bar reinforcement means, it is characterised in that the ornamental blocks on metope are not being torn open
Unloading just can strengthening construction under the scene of plate.
Skewed slot is sawed in the avris up and down of every facing plate, clear dried bean noodles threading steel cable or the steel bar afterwards only in skewed slot, then
Structure glue is planted into groove, form plate after glue is dry and plate string will not the danger that comes off of monolithic.In plate and plate
The steel cable or steel bar exposed in gap can be planted in main body by double headed stud or anchor, described shank member or anchor pole, according to decorations
The original construction method of panel carries out targetedly using anchor or anchor pole, it is also possible to according to specific live original mounting structure
The defect of presence, species are analyzed, and the length specification using one of which anchor pole and anchor is customizable.
The utility model advantage is:Except stone material it is upper following linked into an integrated entity by steel cable or steel bar after to keelless decorations
Panel journey in cross crotch, using anchor pole or anchor planted on main body metope and Structure Beam-column by four junctions of plate in, and anchor is planted
Make the decoration panel after reinforcing more firm.
Brief description of the drawings
Fig. 1 is a kind of double end anchor pole schematic diagram of the present utility model.
Fig. 2 is another double end anchor pole schematic diagram of the present utility model.
Fig. 3 is another shank member schematic diagram of the present utility model.
Fig. 4 is to be caught on and anchor pole circle firmly schematic diagram equipped with steel cable or steel bar exposed portion on facing plate and by anchor pole.
Fig. 5 is that glue point is hung equipped with steel cable or steel bar on the facing plate of stone material or porcelain plate and fixed by anchor pole and anchor
Structural representation.
Fig. 6 is the facade arrangement schematic diagram after facing plate reinforcement by connection.
Fig. 6-1 is the A-A profiles of Fig. 6.
Fig. 6-2 is the B-B profiles of Fig. 6.
Fig. 7 for facing plate skewed slot be short groove structural representation.
Fig. 8 is the structural representation of groove for the skewed slot of facing plate.
Fig. 9 is that the steel cable or steel bar of the stone curtain wall plate with steel skeleton wrap around circle cross bar fixation using steel wire or steel cable
Structural representation.
Figure 10 unguyed glue point patch facing board wall is perpendicular to cut open figure.
Figure 11 unguyed cement wet combining facing board wall is perpendicular to cut open figure.
Glue point hanging of veneer wall after Figure 12 reinforcings is erected and cuts open figure.
Cement wet combining facing board wall after Figure 13 reinforcings is erected and cuts open figure.
Specific embodiment
As shown in drawings, building stone described in the utility model or porcelain plate steel cable or steel bar ruggedized construction, including facing
Plate, its design feature is to saw to have skewed slot in the every avris up and down of facing plate 3, the short groove 6 that skewed slot can be as described in Figure 7,
Also groove 7 that can be as described in Figure 8, clear powder totally puts into steel cable or steel bar 1 afterwards in skewed slot, then structure glue is planted is reached into groove
To the fixed steel cable or steel bar put into groove, the steel cable or steel bar exposed in plate and plate interspace cross crotch can be by double ends
Crab-bolt or anchor catch on plants in main body(Such as wall)On, described shank member or anchor pole 2, including the bullet of rear end are hooked and screw rod, can
With using the structure of Patent No. 200920183353.4 or 201420053536.5, or other existing structures, before screw rod
Portion(Front portion can be front end, or near the screw rod of front end)Both sides be provided with ram's horn(2-A, 2-B in as shown in Figure 1, Figure 2), or
Person is provided with circle in steel bar bar front portion(Such as the 2-C in Fig. 3).
Fig. 9 is fixed for the slabstone on steelframe open the oblique groove of saw, Fig. 8 up and down in facing plate 3;Or tiltedly short groove Fig. 7 exists
Load steel cable or steel bar after clear defending in the skewed slot held successfully, then toward injecting glue in groove, after glue is dry, expose in plate seam
It is bundled on steelframe cross bar using steel cable or steel bar 2-E on steel cable or steel bar 1, weather proofing sealant is beaten finally by note, completes to add
Gu program.
The species of anchor pole can have 2-A(See Fig. 1)、2-B(See Fig. 2)、2-C(See Fig. 3), the anchor pole front end system of 2-A, 2-B
Into goat's horn shape(Such as double crotches), the steel cable or steel bar that both sides goat's horn can be caught on plate reach the purpose for holding plate, after anchor pole
Double bullets for being formed with of end hook to catch on and allowed on the hole wall of main body anchor pole and be not easy to pull out, and can also reach the purpose of pulling plate.Such as
Shown in Fig. 5, the ring anchor of 2-C can live upper and lower two steel cables or steel bar circle when putting into, and the bullet of bar portion and front end is hooked and can put into
Main body 4(Such as wall)On, decoration panel can be firmly held, reach the reinforcing purpose of plate.
Targetedly reinforce
Structure is carried out in the stone material or porcelain plate for having loaded onto wall and understand original installation method, specifically there is unstable original first
Cause and degree are analyzed, and strengthening construction is carried out from top to bottom after carrying out safeguard protection on original metope, prevent big emaciated face
Fall.Reinforced construction method using this technology is divided into several structures to original engineering for installing, should be according to original drawing
And construction status, specify unstable reason and there is where, stone material or porcelain plate general structure be divided into steel skeleton stone curtain wall Fig. 9,
Point hangs stone material or porcelain plate decoration panel, and glue point 5 hangs patch and cement wet combining Figure 11, and the defect of stone curtain wall construction is easily caused
Plate drops, and Vitrolite curtain wall plate thickness deficiency takes the folded patch of glue(Refer to Fig. 6-2)It is design defect, also easy degumming causes plate
Block is dropped, and stone material and porcelain plate glue point are hung exterior wall and must be reinforced using this technology because temperature difference plate heat expansion easily comes off.
Construction procedure
To the unstable engineering of stone material or porcelain plate of ready-made building decoration, oblique notched in transverse joint or perps, and in decorations
The seam of panel block 3 punches in cross mouthful to main body, and injecting glue in down fold, mends again after putting into steel cable or steel bar after clear powder is clean
Flat glue, steel cable or steel bar 1 are made by the both sides on anchor pole after glue is dry from hole interplantation double end shank member or anchor pole 2 in cross crotch again
Goat's horn(Crotch)Catch on, the rear end bullet of anchor pole is caught in hole, can not pulled out out after glue plant, form globality firm.To new
The stone material or porcelain plate of dress carry out plate kerf first, with metope on glue point rubberizing mud wet combining plate, after clay is dry, in seam away from ten
Drilling is after clear health at word seam, second injecting glue steel loading rope or steel bar, and middle injecting structure glue, fixes steel cable or steel in groove
Bar refills the shank member or anchor pole of double end slip hook after glue is dry, finally notes weather proofing sealant, and anchor pole portion catches on steel cable or steel in front end
The bullet of bar rear end is hooked puts into main body(Such as wall)On, decoration panel can be firmly held.
The stone curtain-wall hanging part of steel frame construction is easily inhaled by wind using the plate of monocline and is flown, and shown in Fig. 9, fixing means is in plate
After the embedded steel cable of bottom and upper segment fluting or steel bar of block 3, then it is bundled on steelframe cross bar by steel wire 2-E, this can be plate
Hold, reach and be firmly fixed.
The facing plate that can be come off to generation before reinforcing, carries out structure inspection, to no drawing according to former design drawing
Project carries out taking site inspection practical structures apart, and such as Fig. 6-2 is porcelain plate point hanging hang structure, installs panel not enough thickness and is reached using patch small pieces
To plate thickness, so causing plate to come off after sticker position departs from, it is necessary to reinforce 1 in preceding big sheet, every plate is led to
Cross steel cable or steel bar is slotted after burying, after glue is dry, be fixed in main body away from middle implantation double headed stud in cross crotch, reach jail
Gu.