CN103556819B - A kind of construction method of reserved constructional column hole on beam slab - Google Patents
A kind of construction method of reserved constructional column hole on beam slab Download PDFInfo
- Publication number
- CN103556819B CN103556819B CN201310593262.9A CN201310593262A CN103556819B CN 103556819 B CN103556819 B CN 103556819B CN 201310593262 A CN201310593262 A CN 201310593262A CN 103556819 B CN103556819 B CN 103556819B
- Authority
- CN
- China
- Prior art keywords
- hole
- slab
- steel plate
- plate base
- sleeve pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 37
- 239000004567 concrete Substances 0.000 claims abstract description 30
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 29
- 239000010959 steel Substances 0.000 claims abstract description 29
- 229920000915 polyvinyl chloride Polymers 0.000 claims abstract description 28
- 239000002002 slurry Substances 0.000 claims abstract description 9
- 238000009415 formwork Methods 0.000 claims abstract description 4
- 230000003014 reinforcing Effects 0.000 claims description 8
- 239000002184 metal Substances 0.000 claims description 3
- 239000000463 material Substances 0.000 abstract description 2
- 239000011148 porous material Substances 0.000 abstract description 2
- 238000005266 casting Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 11
- 239000003795 chemical substances by application Substances 0.000 description 4
- 239000000084 colloidal system Substances 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 239000000428 dust Substances 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000007689 inspection Methods 0.000 description 2
- 239000011241 protective layer Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000007711 solidification Methods 0.000 description 2
- 210000003205 Muscles Anatomy 0.000 description 1
- 210000000282 Nails Anatomy 0.000 description 1
- 210000002435 Tendons Anatomy 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000010926 purge Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Abstract
For the deficiency of existing constructional column pore reinforced construction method, the invention provides a kind of construction method of reserved constructional column hole on beam slab: with the beam-slab template framework of construction formwork splicing in order to beam slab of casting; In beam-slab template framework, need the position that constructional column is set to put domatic steel plate base; Four root hole hole backstays are welded with on the end face of domatic steel plate base is vertical; Release agent is coated on the surface of domatic steel plate base and hole backstay; Be socketed a PVC sleeve pipe outward at each hole backstay, concrete slurry is filled up the cavity of beam-slab template framework, concrete slurry solidifies out into concrete beam plate; Beam-slab template framework, PVC sleeve pipe, domatic steel plate base and hole backstay are removed.The advantage that the present invention exists has: the operation of the inventive method is simple, workable, difficulty of construction is little, and can not cause damage to the intensity of beam slab, thus shortens construction period, save people's material resources cost and ensure that the architecture quality of building.
Description
Technical field
The invention belongs to technical field of building construction, relate to the construction of constructional column reinforcing bar in construction work secondary structure.Be specifically related to a kind of construction method of reserved constructional column hole on beam slab.
Background technology
For improving the anti-seismic performance of multistory building masonry structure, need appropriate site in the masonry in house to arrange reinforced concrete post and be connected with collar tie beam, the common stability strengthening building, this reinforced concrete post is just called as constructional column usually.And the way of traditional constructional column reinforcing bar is generally after beam slab concrete placings completes; adopt the mode bar planting of boring; its construction process is generally: preparation of construction, fixed point location, boring, removing floating dust, inject colloid, anchor into reinforcing bar, reinforcing bar corrects, solidification protection, self-inspection and the transfer project acceptance inspection, there is the shortcomings such as complex procedures, poor operability, difficulty of construction are large in it.
There are two outstanding drawbacks in above-mentioned construction method: one is that whole operation expense of taking a lot of work is expected, delays the cycle of construction; Two is in construction, need boring, and the inequality that high-frequency vibration can cause beam slab internal stress distribute and easily in beam slab opening area generation fine cracks, beam and slab structure being caused damage.
Summary of the invention
In order to solve the deficiency of existing constructional column pore reinforced construction method, the invention provides a kind of construction method of reserved constructional column hole on beam slab.Concrete technical scheme of the present invention is as follows:
A construction method for reserved constructional column hole on beam slab, carry out as follows:
Step one: with the beam-slab template framework 3 of construction formwork splicing in order to build beam slab; In beam-slab template framework 3, need the position that constructional column is set to put domatic steel plate base 11; The consistent size of described domatic steel plate base 11 bed-plate dimension and constructional column, domatic steel plate base 11 end face is less than the size of its bottom surface, is up-small and down-big, that surrounding becomes domatic metal sheet roof covering;
Step 2: the hole backstay 12 being welded with more than four or four on the end face of domatic steel plate base 11 is vertical; Described hole backstay 12 is reinforcing bar with ribbing; The length of hole backstay 12 is greater than the degree of depth of beam-slab template framework 3;
Step 3: coat release agent on the surface of domatic steel plate base 11 and hole backstay 12;
Step 4: at each hole backstay 12 outer socket PVC sleeve pipe 2, the outer wall of PVC sleeve pipe 2 all smears one deck release agent;
Step 5: cavity concrete slurry being filled up beam-slab template framework 3, and leave standstill; Until concrete slurry solidifies out into concrete beam plate 4;
Step 6: beam-slab template framework 3 is removed from concrete beam plate 4 surface; PVC sleeve pipe 2 is taken out place above concrete beam plate 4; Domatic steel plate base 11 is removed from the bottom of concrete beam plate 4 together with hole backstay 12.
Preferred scheme is, after PVC sleeve pipe 2 is socketed in hole backstay 12, is bent downwards the upper end of PVC sleeve pipe 2, namely makes PVC sleeve pipe 2 in inverted J-shaped.
Preferred scheme is, the vertical interval between the top port of PVC sleeve pipe 2 and hole backstay 12 top is not less than 3cm.
Preferred scheme is, the thickness of domatic steel plate base 11 is not less than 1cm.
The advantage that the present invention exists has:
The operation of the inventive method is simple, workable, difficulty of construction is little, and can not cause damage to the intensity of beam slab, thus shortens construction period, save people's material resources cost and ensure that the architecture quality of building.What time following concrete outstanding embodiment is:
1) the main muscle of structure is destroyed for avoiding when this method avoids traditional construction, and the process that structure protective layer is chiseled---this process is difficult to operation because structural beam slab tendon protective layer thickness thinner (being generally 1.5 ~ 2cm) and the disturbance of building in concrete process make the variable thickness of reinforcement cover);
2) this method avoids the boring procedure in traditional construction---and in fact, at the scene in practice of construction process, be difficult to implement the regulation of the regulation (hole depth is at least 10cm) of the basic anchorage length of bar planting according in " concrete structure reinforcement design specifications GB50367-2006 " to the bore operation of beam slab;
3) this method avoids the scale removal process of dust and water in traditional construction mesopore---need in traditional handicraft process to clean out dust and water in hole with hairbrush and blower fan;
4) this method avoids injecting glue process---this process need check colloid quality, and needs the air purge in got out hole in work progress, namely avoids air to be enclosed in duct by colloid, and this operation can not be disturbed before colloid solidification in addition; Difficulty of construction is very large.
Accompanying drawing explanation
Fig. 1 is the Construction State schematic diagram after implementing the inventive method step one to step 3.
Fig. 2 is the Construction State schematic diagram after implementing the inventive method step 4.
Fig. 3 is the Construction State schematic diagram after implementing the inventive method step 5.
Fig. 4 is the schematic diagram of the construction product (finished product) after implementing the inventive method step 6.
Reference numeral: domatic steel plate base 11, hole backstay 12, PVC sleeve pipe 2, beam-slab template framework 3, concrete beam plate 4, preformed hole 5.
Detailed description of the invention
Now further describe design feature of the present invention by reference to the accompanying drawings.
A construction method for reserved constructional column hole on beam slab, carry out as follows:
Step one (see Fig. 1): with the beam-slab template framework 3 of construction formwork splicing in order to build beam slab; In beam-slab template framework 3, need the position that constructional column is set to put domatic steel plate base 11; The consistent size of described domatic steel plate base 11 bed-plate dimension and constructional column, domatic steel plate base 11 end face is less than the size of its bottom surface, is up-small and down-big, that surrounding becomes domatic metal sheet roof covering;
Step 2 (see Fig. 1): the hole backstay 12 being welded with more than four or four on the end face of domatic steel plate base 11 is vertical; Described hole backstay 12 is reinforcing bar with ribbing; The length of hole backstay 12 is greater than the degree of depth of beam-slab template framework 3;
Step 3 (see Fig. 1): coat release agent on the surface of domatic steel plate base 11 and hole backstay 12;
Step 4 (see Fig. 2): at each hole backstay 12 outer socket PVC sleeve pipe 2, the outer wall of PVC sleeve pipe 2 all smears one deck release agent;
Step 5 (see Fig. 3): cavity concrete slurry being filled up beam-slab template framework 3, and leave standstill; Until concrete slurry solidifies out into concrete beam plate 4;
Step 6 (see Fig. 4): beam-slab template framework 3 is removed from concrete beam plate 4 surface; PVC sleeve pipe 2 is taken out place above concrete beam plate 4; Domatic steel plate base 11 is removed from the bottom of concrete beam plate 4 together with hole backstay 12, namely completes the making of the concrete beam plate 4 offering preformed hole 5.
See Fig. 2, preferred scheme is, after PVC sleeve pipe 2 is socketed in hole backstay 12, is bent downwards the upper end of PVC sleeve pipe 2, namely makes PVC sleeve pipe 2 in inverted J-shaped.This structure can prevent in concrete placings process, and concrete slurry enters PVC sleeve pipe 2 and pollutes hole backstay 12, causes PVC sleeve pipe 2 and hole backstay 12 to condense into Unified Global, the problem that cannot dismantle.
Preferred scheme is, the vertical interval between the top port of PVC sleeve pipe 2 and hole backstay 12 top is not less than 3cm.
Preferred scheme is, the thickness of domatic steel plate base 11 is not less than 1cm.With nail, domatic steel plate base 11 is fixed on the end face of beam-slab template framework 3 groove, prevent when concreting slip, the placement location of domatic steel plate base 11 offsets; Domatic steel plate base 11 is made as domatic, contributes to the later stage conveniently to prize, be beneficial to the demoulding.
Further preferred version is: hole backstay 12 adopts diameter to be the reinforcing bar of 10 or 12mm.
Further preferred version is: PVC sleeve pipe 2 is made up of the water power PVC spool of Φ 16mm conventional in building operations.
Claims (4)
1. on beam slab, reserve a construction method for constructional column hole, it is characterized in that, carry out as follows:
Step one: with the beam-slab template framework (3) of construction formwork splicing in order to build beam slab; In beam-slab template framework (3), need the position that constructional column is set to put domatic steel plate base (11); The consistent size of described domatic steel plate base (11) bed-plate dimension and constructional column, domatic steel plate base (11) end face is less than the size of its bottom surface, is up-small and down-big, that surrounding becomes domatic metal sheet roof covering;
Step 2: the hole backstay (12) being welded with more than four or four on the end face of domatic steel plate base (11) is vertical; Described hole backstay (12) is reinforcing bar with ribbing; The length of hole backstay (12) is greater than the degree of depth of beam-slab template framework (3);
Step 3: coat release agent on the surface of domatic steel plate base (11) and hole backstay (12);
Step 4: be socketed a PVC sleeve pipe (2) outward each hole backstay (12), the outer wall of PVC sleeve pipe (2) all smears one deck release agent;
Step 5: cavity concrete slurry being filled up beam-slab template framework (3), and leave standstill; Until concrete slurry solidifies out into concrete beam plate (4);
Step 6: beam-slab template framework (3) is removed from concrete beam plate (4) surface; PVC sleeve pipe (2) is taken out place from concrete beam plate (4) top; Domatic steel plate base (11) is removed from the bottom of concrete beam plate (4) together with hole backstay (12).
2. the construction method of a kind of reserved constructional column hole on beam slab as claimed in claim 1, it is characterized in that, after PVC sleeve pipe (2) is socketed in hole backstay (12), the upper end of PVC sleeve pipe (2) is bent downwards, namely makes PVC sleeve pipe (2) in inverted J-shaped.
3. the construction method of a kind of reserved constructional column hole on beam slab as claimed in claim 1, it is characterized in that, the vertical interval between the top port of PVC sleeve pipe (2) and hole backstay (12) top is not less than 3cm.
4. the construction method of a kind of reserved constructional column hole on beam slab as claimed in claim 1, it is characterized in that, the thickness of domatic steel plate base (11) is not less than 1cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310593262.9A CN103556819B (en) | 2013-11-23 | 2013-11-23 | A kind of construction method of reserved constructional column hole on beam slab |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310593262.9A CN103556819B (en) | 2013-11-23 | 2013-11-23 | A kind of construction method of reserved constructional column hole on beam slab |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103556819A CN103556819A (en) | 2014-02-05 |
CN103556819B true CN103556819B (en) | 2015-12-09 |
Family
ID=50011155
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310593262.9A Active CN103556819B (en) | 2013-11-23 | 2013-11-23 | A kind of construction method of reserved constructional column hole on beam slab |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103556819B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104831924B (en) * | 2015-05-29 | 2017-03-22 | 中建五局第三建设有限公司 | Construction method for PVC piping of incoming and outgoing lines of distribution box at beam bottom |
CN105155669B (en) * | 2015-09-15 | 2017-12-12 | 成都市第四建筑工程公司 | Concealed beam floor framing rod structure construction method |
CN107542157A (en) * | 2016-06-28 | 2018-01-05 | 五冶集团上海有限公司 | A kind of rapid shaping construction method of underground catch pit |
CN106968334A (en) * | 2017-04-25 | 2017-07-21 | 天津市建工工程总承包有限公司 | A kind of construction method of cast-in-place concrete framework secondary structure constructional column |
CN108842732A (en) * | 2018-08-09 | 2018-11-20 | 何胜东 | It is a kind of municipal administration water conservancy dykes and dams check well construction auxiliary sleeve tool and its method |
CN114086696A (en) * | 2021-12-01 | 2022-02-25 | 中冶南方城市建设工程技术有限公司 | Construction method of overlapped constructional column |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1101883A1 (en) * | 1999-11-17 | 2001-05-23 | Construmat Ag | Device for the execution of a reinforcement connection between a concrete construction element and a connected construction element |
CN201460211U (en) * | 2009-07-27 | 2010-05-12 | 中国第二冶金建设有限责任公司 | Water-heating preformed hole mould |
CN201574583U (en) * | 2009-12-30 | 2010-09-08 | 山东万鑫建设有限公司 | Simple pipe hole preformed mould |
CN201620602U (en) * | 2010-03-18 | 2010-11-03 | 江苏弘盛建设工程集团有限公司 | Preburied sleeve |
CN102121315A (en) * | 2011-01-07 | 2011-07-13 | 中建五局第三建设有限公司 | Hole reserving construction method for tightly-fixed steel sleeve |
-
2013
- 2013-11-23 CN CN201310593262.9A patent/CN103556819B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1101883A1 (en) * | 1999-11-17 | 2001-05-23 | Construmat Ag | Device for the execution of a reinforcement connection between a concrete construction element and a connected construction element |
CN201460211U (en) * | 2009-07-27 | 2010-05-12 | 中国第二冶金建设有限责任公司 | Water-heating preformed hole mould |
CN201574583U (en) * | 2009-12-30 | 2010-09-08 | 山东万鑫建设有限公司 | Simple pipe hole preformed mould |
CN201620602U (en) * | 2010-03-18 | 2010-11-03 | 江苏弘盛建设工程集团有限公司 | Preburied sleeve |
CN102121315A (en) * | 2011-01-07 | 2011-07-13 | 中建五局第三建设有限公司 | Hole reserving construction method for tightly-fixed steel sleeve |
Also Published As
Publication number | Publication date |
---|---|
CN103556819A (en) | 2014-02-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103556819B (en) | A kind of construction method of reserved constructional column hole on beam slab | |
CN105220874B (en) | The construction method of basement superelevation exterior wall self-supporting single side formwork system | |
CN104652830B (en) | The construction method that a kind of Prefabricated construction panel and prefabricated panel are built | |
CN204983662U (en) | To drawing screw rod and steel pipe framed bent combination unilateral formwork device | |
CN108755972B (en) | Foot pad for prefabricated part and using method thereof | |
US8650830B2 (en) | Method of basement construction | |
CN103469806A (en) | Construction method for replacing brick forming die with prefabricated concrete foundation bearing platform side die | |
CN203383508U (en) | One-sided formwork body structure backing onto brick concrete retaining wall | |
CN206616862U (en) | Formwork root bracing means | |
CN109577639A (en) | Exterior wall protects mould integrated board and aluminum alloy mould plate combined system construction method | |
CN106894587A (en) | Precast stair connection method | |
CN203429641U (en) | Single-side supporting formwork reinforcing structure system for building construction | |
CN105525753A (en) | Method and structure for simultaneously constructing constructional column and main body structure | |
CN104727552A (en) | Construction method for reserving water feed pipe grooves in prefabricated shear wall | |
CN105275097A (en) | A post-cast strip water-stop steel plate and demolition-free template net installing method | |
EA039205B1 (en) | System for wall to wall connection for precast shear walls and method thereof | |
CN106284653A (en) | The construction method that a kind of balcony construct capital interspaces in advance | |
CN107083804B (en) | A kind of wall structure column joint bar construction method | |
CN104947719A (en) | Basement roof post-cast strip hanging support formwork structure and post-cast strip construction method thereof | |
CN204959798U (en) | Basement superelevation outer wall self -supporting unilateral component die body system | |
CN202509764U (en) | Template bracing structure for constructional column | |
CN102352690B (en) | Construction method of anti-floating locating system of cast-in-place concrete hollow floorslab steel tube | |
CN106836463A (en) | The constructing device and construction method of cushion cap and ground girder construction | |
CN104763158B (en) | Tenon joint type light-weight aggregate chained block construction method | |
CN106351376A (en) | Construction method of garage roof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province Patentee after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau Address before: 230011 science and Technology Department of No.6 company of China Construction Fourth Bureau, Dongfang Building, Changjiang East Street, Yaohai District, Hefei City, Anhui Province Patentee before: CHINA CONSTRUCTION 4TH ENGINEERING BUREAU, 6TH Co.,Ltd. |