CN105525753A - Method and structure for simultaneously constructing constructional column and main body structure - Google Patents

Method and structure for simultaneously constructing constructional column and main body structure Download PDF

Info

Publication number
CN105525753A
CN105525753A CN201510302049.7A CN201510302049A CN105525753A CN 105525753 A CN105525753 A CN 105525753A CN 201510302049 A CN201510302049 A CN 201510302049A CN 105525753 A CN105525753 A CN 105525753A
Authority
CN
China
Prior art keywords
constructional column
agent structure
template
fine sand
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510302049.7A
Other languages
Chinese (zh)
Inventor
叶国昌
苏伟
邱宇
张晋蜀
刘辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201510302049.7A priority Critical patent/CN105525753A/en
Publication of CN105525753A publication Critical patent/CN105525753A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a method and a structure for simultaneously constructing a constructional column and a main body structure. The method comprises the following steps of (1) embedding a constructional column lap joint steel bar in a required position in the drawing; (2) binding the lower end of a constructional column steel bar cage with the embedded lap joint steel bar, and binding the upper end of the constructional column steel bar cage with a main body structure steel bar cage; (3) erecting a formwork, and putting a layer of fine sand being 50 to 60mm thick at the bottom inside the constructional column formwork; (4) meanwhile, casting cast concrete of the main body structure and the constructional column; and (5) emptying the fine sand at the bottom of the constructional column before the wall body building, then, filling the bottom of the constructional column by high-grade fine sand concrete, and completing the simultaneous construction of the constructional column and the main body structure. The construction method provided by the invention has the advantages that the secondary construction is not needed; the secondary structure and the main body structure which are difficult in construction are synchronously completed, so that the work intensity of workers is reduced; the work efficiency is improved; and the method and the structure are applicable to places with many engineering constructional columns such as multilayer and frame-shear wall structures.

Description

A kind of method that constructional column and agent structure are constructed simultaneously and structure
Technical field
The present invention relates to method and structure that a kind of constructional column and agent structure construct simultaneously, belong to technical field of building construction.
Background technology
For improving the anti-seismic performance of multistory building masonry structure, code requirement should arrange reinforced concrete post and be connected with collar tie beam by appropriate site in the masonry in house, and the common stability strengthening building, this reinforced concrete post is just called as constructional column usually.Constructional column master if it were not for bearing vertical load, but resists the transverse load such as shearing, antidetonation.Therefore, constructional column has the ability improving wall shear strength and the deformability improving body of wall and house greatly, after constructional column forms obligatory point together with collar tie beam simultaneously, can effectively limit the expansion of wall body slit and be scattered, and ensures that body of wall does not collapse.But generally need reserved horse tooth trough in existing Constructional Col-umn Construction, and adopt template to construct, this form of construction work is high to workman's technical requirements, and efficiency of construction is lower, and body of wall and constructional column can not be constructed simultaneously, affect the duration.In addition, in order to avoid the problems referred to above, constructional column is constructed according to pillar of main frame by some construction corps, when concreting, constructional column is built together with agent structure concrete, think and so both meet construction needs, in turn save artificial, in fact there are major safety risks.Because during design, constructional column does not calculate as support carriers, now constructional column is constructed by frame column, the support system of whole floor just changes, some reinforcing bar is not stressed according to design, is absolute prohibition at the scene, and some even all will order to stop work.
Summary of the invention
The object of the invention is: provide a kind of construction technology is simple, efficiency of construction is high constructional column and the method that agent structure is constructed simultaneously and structure, to overcome the deficiencies in the prior art.
The method that a kind of constructional column of the present invention and agent structure are constructed simultaneously, comprises the following steps:
(1) according to drawing requirement position pre-buried constructional column overlap joint reinforcing bar;
(2) by the lower end of constructional column reinforcing cage together with pre-buried overlap joint reinforced-bar binding, its upper end is together with the colligation of agent structure reinforcing cage;
(3) install template: when installing agent structure template, install constructional column template simultaneously, when installing constructional column template, the thick fine sand of one deck 50 ~ 60mm is placed in the bottom in constructional column template, reinforces after treating formwork erection to template;
(4) when building the concrete of agent structure, the concrete of constructional column is built together with the concrete of agent structure, and vibration compacting;
(5) before masonry panel, the fine sand bottom constructional column is emptied, then fill bottom constructional column with high grade fine sand concrete, can constructional column be completed and agent structure is constructed simultaneously.
In said method, carry out step (3) install template construction time, the bottom of agent structure template is provided with through hole, then the bottom of the upper end of constructional column template and agent structure template is fitted tightly, and constructional column template is docked with this through hole.
Further, when carrying out the concreting of step (4), concrete being built from the through hole bottom agent structure template in constructional column template, and vibrates.
Simultaneously, the invention also discloses the structure that a kind of constructional column and agent structure are constructed simultaneously, this structure comprises agent structure (1) and constructional column (2), lower floor's agent structure (1) is embedded with overlap joint reinforcing bar (4), the lower end of constructional column reinforcing cage (6) and pre-buried overlap joint reinforcing bar (4) bundle fixing, the upper end of constructional column reinforcing cage (6) is together with upper layer main body structure reinforcing bars cage (5) colligation, be provided with gap between the lower end of described constructional column (2) and lower floor's agent structure (1), in gap, be filled with fine sand (4).
Aforesaid fine sand (4) can adopt high grade fine sand concrete to replace.
Further, lower floor's agent structure (1) is provided with boring, overlap joint reinforcing bar (4) is anchored in boring.
The invention has the advantages that: constructional column and agent structure are constructed by the present invention simultaneously, not only construction technology is simple, and convenient and quick construction, cost is lower, and shaping constructional column intensity is good, and perception is good.Therefore, adopting the constructional column of construction method of the present invention, without the need to carrying out secondary construction, the most difficult secondary structure of construction and agent structure synchronously being completed, thus reduce labor strength, improve operating efficiency, be applicable to the place that the engineering construction such as multilayer, frame structure post is more.
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present invention;
Fig. 2 is the structural representation of agent structure template and constructional column template in the present invention.
Description of reference numerals: 1-agent structure, 2-constructional column, 3-fine sand, 4-overlaps reinforcing bar, 5-agent structure reinforcing cage, 6-constructional column reinforcing cage, 7-through hole, 8-agent structure template, 9-constructional column template.
Detailed description of the invention
In order to make the object, technical solutions and advantages of the present invention clearly, below in conjunction with drawings and Examples, the present invention is described in further detail.
Embodiment
See Fig. 1, the structure that a kind of constructional column of the present invention and agent structure are constructed simultaneously, this structure comprises agent structure (1) and constructional column (2), lower floor's agent structure (1) is embedded with overlap joint reinforcing bar (4), the lower end of constructional column reinforcing cage (6) and pre-buried overlap joint reinforcing bar (4) bundle fixing, the upper end of constructional column reinforcing cage (6) is together with upper layer main body structure reinforcing bars cage (5) colligation, be provided with gap between the lower end of described constructional column (2) and lower floor's agent structure (1), in gap, be filled with fine sand (4; Described fine sand (4) can adopt high grade fine sand concrete to replace.Further, lower floor's agent structure (1) is provided with boring, overlap joint reinforcing bar (4) is anchored in boring.
When constructional column and agent structure being constructed, adopt following steps to construct simultaneously:
(1) see Fig. 1, according to drawing requirement position pre-buried constructional column overlap joint reinforcing bar 4, the segment length of stretching out of overlap joint reinforcing bar 4 generally gets 80 ~ 150mm;
(2) bundled in the lower end of constructional column reinforcing cage and pre-buried overlap joint reinforcing bar 4, its upper end is together with the colligation of agent structure reinforcing cage cage;
(3) template is installed: see Fig. 2, when installing agent structure template 5, install constructional column template 6 simultaneously, and a through hole 7 is set in the bottom of agent structure template 5, then the bottom of the upper end of constructional column template 6 and agent structure template 5 is fitted tightly, and constructional column template 6 is docked with this through hole 7, the thick fine sand of one deck 50 ~ 60mm 3 is placed in the bottom then in constructional column template 6, reinforces after treating formwork erection to template;
(4) when building the concrete of agent structure 1, the concrete of constructional column 2 is built together with the concrete of agent structure 1, namely first concrete is built in constructional column template 6 from the through hole 7 bottom agent structure template 5, and vibration compacting, after the concreting of post 2 to be constructed, then build the concrete of agent structure 1;
(5) before masonry panel, the fine sand 3 bottom constructional column 2 is emptied, then fill bottom constructional column 2 with high grade fine sand concrete, constructional column 2 can be completed and construct with agent structure 1 simultaneously.

Claims (6)

1. a constructional column and agent structure method of simultaneously constructing, is characterized in that comprising the following steps:
(1) according to drawing requirement position pre-buried constructional column overlap joint reinforcing bar;
(2) by the lower end of constructional column reinforcing cage together with pre-buried overlap joint reinforced-bar binding, its upper end is together with the colligation of agent structure reinforcing cage cage;
(3) install template: when installing agent structure template, install constructional column template simultaneously, when installing constructional column template, the thick fine sand of one deck 50 ~ 60mm is placed in the bottom in constructional column template, reinforces after treating formwork erection to template;
(4) when building the concrete of agent structure, the concrete of constructional column is built together with the concrete of agent structure, and vibration compacting;
(5) before masonry panel, the fine sand bottom constructional column is emptied, then fill bottom constructional column with high grade fine sand concrete, can constructional column be completed and agent structure is constructed simultaneously.
2. constructional column according to claim 1 and the agent structure method of simultaneously constructing, it is characterized in that: carry out step (3) install template construction time, the bottom of agent structure template is provided with through hole, then the bottom of the upper end of constructional column template and agent structure template is fitted tightly, and constructional column template is docked with this through hole.
3. constructional column according to claim 2 and the agent structure method of simultaneously constructing, is characterized in that: when carrying out the concreting of step (4), being built by concrete, and vibrate from the through hole bottom agent structure template in constructional column template.
4. a constructional column and the agent structure structure of simultaneously constructing, comprise agent structure (1) and constructional column (2), it is characterized in that: in lower floor's agent structure (1), be embedded with overlap joint reinforcing bar (4), the lower end of constructional column reinforcing cage (6) and pre-buried overlap joint reinforcing bar (4) bundle fixing, the upper end of constructional column reinforcing cage (6) is together with upper layer main body structure reinforcing bars cage (5) colligation, be provided with gap between the lower end of described constructional column (2) and lower floor's agent structure (1), in gap, be filled with fine sand (4).
5. constructional column according to claim 4 and the agent structure structure of simultaneously constructing, is characterized in that: described fine sand (4) can adopt high grade fine sand concrete to replace.
6. constructional column according to claim 4 and the agent structure structure of simultaneously constructing, is characterized in that: in lower floor's agent structure (1), be provided with boring, and overlap joint reinforcing bar (4) is anchored in boring.
CN201510302049.7A 2015-06-05 2015-06-05 Method and structure for simultaneously constructing constructional column and main body structure Pending CN105525753A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510302049.7A CN105525753A (en) 2015-06-05 2015-06-05 Method and structure for simultaneously constructing constructional column and main body structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510302049.7A CN105525753A (en) 2015-06-05 2015-06-05 Method and structure for simultaneously constructing constructional column and main body structure

Publications (1)

Publication Number Publication Date
CN105525753A true CN105525753A (en) 2016-04-27

Family

ID=55768248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510302049.7A Pending CN105525753A (en) 2015-06-05 2015-06-05 Method and structure for simultaneously constructing constructional column and main body structure

Country Status (1)

Country Link
CN (1) CN105525753A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088600A (en) * 2016-06-27 2016-11-09 中冶东北建设(沈阳)工程技术有限公司 Primary structure and secondary structure door opening lintel one-shot forming construction method
CN106812315A (en) * 2017-03-13 2017-06-09 中国十七冶集团有限公司 A kind of alien invasion moulding controls construction method
CN107035148A (en) * 2017-06-07 2017-08-11 甘肃第六建设集团股份有限公司 A kind of method that architecture enclosing constructional column is constructed simultaneously with agent structure
CN109680804A (en) * 2017-10-18 2019-04-26 五冶集团上海有限公司 Secondary structure reinforcing bar exempts from pore reinforced construction method
CN111779129A (en) * 2020-08-18 2020-10-16 中国十七冶集团有限公司 Construction method for synchronously pouring high-rise balcony decorative column and shear wall column platform structure
CN113565263A (en) * 2021-07-23 2021-10-29 华北冶建工程建设有限公司 Construction method of constructional column
CN114809769A (en) * 2022-05-18 2022-07-29 龙元建设集团股份有限公司 Method for improving construction speed of masonry structure infilled wall

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1916324A (en) * 2005-08-18 2007-02-21 罗进南 Multifunctional composite hollow building block with no cold bridge, self-heat preserved wall body, and buildings
CN103938864A (en) * 2013-01-21 2014-07-23 高行友 Infilled wall constructional column construction method
CN104295003A (en) * 2014-09-26 2015-01-21 中建七局第二建筑有限公司 Structural column construction method
CN204715764U (en) * 2015-06-05 2015-10-21 中建四局第一建筑工程有限公司 The structure that a kind of constructional column and agent structure are constructed simultaneously

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1916324A (en) * 2005-08-18 2007-02-21 罗进南 Multifunctional composite hollow building block with no cold bridge, self-heat preserved wall body, and buildings
CN103938864A (en) * 2013-01-21 2014-07-23 高行友 Infilled wall constructional column construction method
CN104295003A (en) * 2014-09-26 2015-01-21 中建七局第二建筑有限公司 Structural column construction method
CN204715764U (en) * 2015-06-05 2015-10-21 中建四局第一建筑工程有限公司 The structure that a kind of constructional column and agent structure are constructed simultaneously

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088600A (en) * 2016-06-27 2016-11-09 中冶东北建设(沈阳)工程技术有限公司 Primary structure and secondary structure door opening lintel one-shot forming construction method
CN106812315A (en) * 2017-03-13 2017-06-09 中国十七冶集团有限公司 A kind of alien invasion moulding controls construction method
CN107035148A (en) * 2017-06-07 2017-08-11 甘肃第六建设集团股份有限公司 A kind of method that architecture enclosing constructional column is constructed simultaneously with agent structure
CN107035148B (en) * 2017-06-07 2020-04-17 甘肃第六建设集团股份有限公司 Method for simultaneously constructing building periphery constructional column and main body structure
CN109680804A (en) * 2017-10-18 2019-04-26 五冶集团上海有限公司 Secondary structure reinforcing bar exempts from pore reinforced construction method
CN111779129A (en) * 2020-08-18 2020-10-16 中国十七冶集团有限公司 Construction method for synchronously pouring high-rise balcony decorative column and shear wall column platform structure
CN113565263A (en) * 2021-07-23 2021-10-29 华北冶建工程建设有限公司 Construction method of constructional column
CN114809769A (en) * 2022-05-18 2022-07-29 龙元建设集团股份有限公司 Method for improving construction speed of masonry structure infilled wall

Similar Documents

Publication Publication Date Title
CN105525753A (en) Method and structure for simultaneously constructing constructional column and main body structure
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN108035438A (en) A kind of concrete assembled frame structure system of high-strength high ductility and connection method
CN205421616U (en) Assemble integral shear force wall with steel pipe concrete edge member
CN104295003A (en) Structural column construction method
CN205242706U (en) Cast -in -place constructional column of infilled wall and wall body synchronous construction structure between high -rise outer eaves window
CN106320704A (en) Steel reinforced concrete structure formwork sleeve threaded rod pulling construction method
CN103726589A (en) H-shaped steel and steel pipe framework assembly shear wall with protruding interfaces and bent steel bars and manufacturing method
CN107178209A (en) A kind of constructional column and agent structure integrated construction method
CN107083804B (en) A kind of wall structure column joint bar construction method
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN204715764U (en) The structure that a kind of constructional column and agent structure are constructed simultaneously
CN103938871B (en) A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint
CN203769116U (en) Prefabricated through hole assembly type reinforced concrete shear wall
CN103061508A (en) Triangular slip form device and construction method for the same triangular slip form
CN205976167U (en) Based on cast -in -place floor structures of detachable positioning control spare
CN203022222U (en) Wholly-cast ring beam of brick-concrete building support
CN104929047A (en) V-shaped pier outer support construction method
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN114033111A (en) Assembled cornice inclined roof and installation and construction method thereof
CN108316150B (en) Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
CN206956979U (en) A kind of Linear shear wall with fore-set
CN206769199U (en) After wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN203640061U (en) Node connecting structure of reinforced concrete column of basement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160427