CN108818879A - A kind of prefabricated inner partition plate weight hanging structure and its construction technology - Google Patents

A kind of prefabricated inner partition plate weight hanging structure and its construction technology Download PDF

Info

Publication number
CN108818879A
CN108818879A CN201810774492.8A CN201810774492A CN108818879A CN 108818879 A CN108818879 A CN 108818879A CN 201810774492 A CN201810774492 A CN 201810774492A CN 108818879 A CN108818879 A CN 108818879A
Authority
CN
China
Prior art keywords
hole
partition plate
inner partition
lining
prefabricated inner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810774492.8A
Other languages
Chinese (zh)
Other versions
CN108818879B (en
Inventor
李华平
高鹏程
范海平
张琦
张华�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Shi Yu Construction Engineering Co Ltd
Original Assignee
Sichuan Shi Yu Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Shi Yu Construction Engineering Co Ltd filed Critical Sichuan Shi Yu Construction Engineering Co Ltd
Priority to CN201810774492.8A priority Critical patent/CN108818879B/en
Publication of CN108818879A publication Critical patent/CN108818879A/en
Application granted granted Critical
Publication of CN108818879B publication Critical patent/CN108818879B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/14Producing shaped prefabricated articles from the material by simple casting, the material being neither forcibly fed nor positively compacted
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28DWORKING STONE OR STONE-LIKE MATERIALS
    • B28D1/00Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor
    • B28D1/14Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by boring or drilling
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/46Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose specially adapted for making walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Building Environments (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

The invention discloses a kind of prefabricated inner partition plate weight hanging structures, including prefabricated inner partition plate, prefabricated inner partition plate includes the prefabricated Side fascia and lining being connected as one, the through-hole inside connection is offered on lining, the plugging hole core being arranged between Side fascia and lining below through-hole, plugging hole core is equipped with the concrete block of covering through-hole, and the hanged hook across through-hole is inlaid in concrete block;Hanged hook includes connecting rod, and one end that connecting rod protrudes into concrete block is connected with the gag lever post vertical with connecting rod, and one end that connecting rod stretches out through-hole is connected with the hook bar of arcuate structure, and the center of circle for hooking bar is positioned above;The cross-sectional area for hooking bar is gradually reduced from connecting rod one end to the end for hooking bar, improves intensity, stability and safety that hanging structure makes prefabricated inner partition plate have hanging weight.

Description

A kind of prefabricated inner partition plate weight hanging structure and its construction technology
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of prefabricated inner partition plate weight hanging structure and its applies Work technique.
Background technique
Requirement with the fast development and people of building trade to environmental quality is continuously improved, and generates various works therewith Journey construction technology, prefabricated inner partition plate are exactly one of.The appearance of prefabricated inner partition plate gradually replaced locellus point family and Non-load bearing wall form of construction work as made of hollow brick and concrete block masonry, have quality it is light, it is impervious it is good, environmentally protective, Intensity height, good economy performance, sound insulation, fire protecting performance is high, is convenient for the advantages that rapid construction.Although using prefabricated inner partition plate to bring Many advantages, but there is still a need for the domestic installations such as installation heating radiator, hanging cupboard on the prefabricated inner partition plate, due to its peace Dress technique is hollow original because causing installation that can generate crack and using light cellular partition board wall using splicing installation and material internal Be inconvenient to hang weight as the big defect of one, hollow, light wt. partition cannot use expansion bolt or rivet to carry out hanging weight Object is easy to cause wallboard there is a situation where rupturing or generating crack after hanging weight, and wallboard thickness itself is relatively narrow, simple logical The needs of hanging weight can not be met by crossing the progress load-bearing of single layer wallboard, and stability and safety can all have a greatly reduced quality.
Summary of the invention
For the deficiency in the presence of the prior art, the present invention provides a kind of prefabricated inner partition plate weight hanging structure, Intensity, stability and the safety for making prefabricated inner partition plate that there is hanging weight by improving hanging structure;The present invention also mentions For a kind of construction technology of prefabricated inner partition plate weight hanging structure, specify hanging structure in the construction process technique require and Construction process, it is ensured that the hanging structure after construction meets the requirement of hanging weight.
To achieve the above object, present invention employs the following technical solutions:
A kind of prefabricated inner partition plate weight hanging structure, including prefabricated inner partition plate, prefabricated inner partition plate include prefabricated company It is connected in integrated Side fascia and lining, the through-hole inside connection, the Side fascia and lining are offered on the lining Between be arranged with plugging hole core below through-hole, the plugging hole core is equipped with the concrete block of covering through-hole, described mixed The hanged hook across through-hole is inlaid in solidifying soil block;The hanged hook includes connecting rod, and connecting rod protrudes into one end of concrete block It is connected with the gag lever post vertical with connecting rod, one end that connecting rod stretches out through-hole is connected with the hook bar of arcuate structure, and hooks The center of circle of bar is positioned above;The cross-sectional area for hooking bar is gradually reduced from connecting rod one end to the end for hooking bar.
By the cement injection mortar formation concrete block between Side fascia and lining, concrete block is allowed to reinforce Side fascia Bonding strength between lining, and hanged hook is inlayed for hanging weight in concrete block, weight is born in hanged hook After power, the weight for the weight hung directly passes through Side fascia and lining notifies load-bearing, and the gravity of receiving is allowed directly to pass It is delivered on ground, effectively prevents the phenomenon that independent load-bearing of lining easily causes rupture or crack, it is steady to improve whole structure Qualitative and bearing strength;And the structure of hanged hook is also convenient for hanging heating radiator or hanging cupboard, meets in heating The hanging hole reserved on cooling fin or hanging cupboard, moreover it is possible to the stability after guaranteeing hanging.
The present invention also proposes a kind of prefabricated inner partition plate weight hanging structure construction technology, includes the following steps,
A, it positions:Positioning marking is carried out on the lining of prefabricated inner partition plate and determines central point;
B, aperture:By special-purpose machinery using central point as the center of circle holes drilled through on lining, the aperture of through-hole be 50mm~ 70mm;
C, cavity is blocked:Plugging hole core is filled in the prefabricated inner partition plate inner cavity below lead to the hole site, allows plugging hole core It is resisted against between Side fascia and lining and forms sealing;
D, perfusion mortar:It is 1 by weight proportion:Lead to the hole site is carried out filling secret room by 2 cement mortar, and allows cement Mortar face is higher than the top edge of through-hole and difference in height should be greater than 20mm;
E, built-in connection:Before cement mortar initial set, the hanged hook of pre-production is passed through in through-hole insertion cement mortar, And guarantee that hanged hook is in through hole center position;
F, iron net receives face:Filleting band, and the wide through-hole edge out of marginal position of filleting band are bonded in the tapping of lining Spacing distance should be not less than 50mm, wherein the length and width of filleting band be 150mm × 150mm;
G, solid:It is needed solid 28 days after cement mortar filling, cement mortar is allowed sufficiently to solidify.
Compared with the prior art, the present invention has the advantages that:
1, plugging hole core is filled in prefabricated inner partition plate, allows between plugging hole core and Side fascia, lining and seals, from logical It is directly accumulated since plugging hole core after cement injection mortar in hole, cement injection mortar is effectively avoided to need prefabricated internal partition wall The interior wall of plate fills full situation, saves the usage amount of cement mortar;And after passing through cement injection mortar formation concrete block It can reinforce the bonding strength and load bearing stength between Side fascia and lining, be carried out hanged hook tightly by concrete block Gu reinforcing prefabricated so that the gravity after hanged hook load-bearing directly passes through concrete block and prefabricated lining is transmitted on ground The overall stability of inner partition plate guarantees the safety after hanging weight;
2, the gag lever post on hanged hook can guarantee be pulled after connecting rod is embedded into concrete block, avoid connecting Bar is drawn out concrete block, and the hook bar of arcuate structure can will accurately hook bar in blind extension and be inserted into convenient for hanging weight It hangs on weight in prefabricated hanging hole;
3, use length and width for the filleting of 150mm × 150mm specification during cement mortar solid formation concrete block Band is sealed through hole, and the edge of filleting band and the edge spacing distance of through-hole is allowed to be not less than 50mm, guarantees mixed Solidifying soil block avoids cement mortar from leaking out from through-hole during solid.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the structural schematic diagram of hanged hook of the present invention.
In figure, prefabricated inner partition plate 1, lining 102, through-hole 103, plugging hole core 2, concrete block 3, hangs Side fascia 101 Hook 4, gag lever post 402, hooks bar 403 at connecting rod 401.
Specific embodiment
Following further describes the present invention with reference to the drawings.
As shown in FIG. 1 to FIG. 2, a kind of prefabricated inner partition plate weight hanging structure of the present invention, including it is prefabricated it is interior every Wallboard 1, prefabricated inner partition plate 1 include the prefabricated Side fascia 101 being connected as one and lining 102, are opened up on lining 102 There are the through-hole 103 inside connection, the plugging hole core being arranged with below through-hole 103 between Side fascia 101 and lining 102 2, plugging hole core 2 is constituted using foam rods or EPS sheet fragment, when being blocked, addition foamed glue allow entire plugging hole core 2 with Gap between Side fascia 101, lining 102 is sealed, so that plugging hole core 2 has good bearing strength.It is blocking Hole core 2 is equipped with the concrete block 3 of covering through-hole 103, and the ingredient of concrete block 3 is dry cement mortar, wherein cement with The weight proportion of sand is 1:2, can be solid within a short period of time using dry cement mortar, and form concrete block 3 Whole intensity is higher afterwards, the ability with resistance to deformation, rupture.The hanged hook across through-hole 103 is inlaid in concrete block 3 4, when hanged hook 4 is mounted in concrete block 3, in dry cement mortar without completely solid preceding insertion, to guarantee coagulation Hanged hook 4 is fastened as a whole after soil block 3 is solid, so that hanged hook 4, which is inlaid into have after concrete block 3, steadily carries energy Power.
In order to guarantee hanged hook 4 convenient for lifting to common heating radiator, hanging cupboard etc., hanged hook 4 includes connection Bar 401, one end that connecting rod 401 protrudes into concrete block 3 are connected with the gag lever post 402 vertical with connecting rod 401, pass through gag lever post 402 position-limiting action is restricted the movement in concrete block 3 of connecting rod 401, and connecting rod 401 stretches out the one of through-hole 103 End is connected with the hook bar 403 of arcuate structure, and the center of circle for hooking bar 403 is positioned above, hook the cross-sectional area of bar 403 from 401 one end of connecting rod is gradually reduced to the end for hooking bar 403, by hooking the arcuate structure and variable cross-section shape of bar 403, When using hooking bar 403 and carrying out hook weight, being able to carry out blind extension also can guarantee and goes on smoothly hanging.
For the ease of being smoothly filled into through-hole 103 to dry cement mortar, the aperture of through-hole 103 be 50mm~ 70mm allows the perforated area of through-hole 103 to be also able to satisfy subsequent filleting band and is bonded, and guarantees that dry cement mortar will not be let out Dew, the surface after guarantee is solid are flushed with the surface of lining 102;And the plugging device that is sized for of through-hole 103 extends into The laying of row plugging hole core 2.
Embodiment 2:
A kind of prefabricated inner partition plate weight hanging structure construction technology of the present invention, includes the following steps:
A, it positions:Positioning marking is carried out on the lining 102 of prefabricated inner partition plate 1 and determines central point, specific center The determination position of point by the position of the hanging hole on hanging weight according to being determined, when being crossed, using with sharp portion Position nail in hanging hole to crossing on lining 102, so that it is determined that scribing position.
B, aperture:By special-purpose machinery using central point as the center of circle holes drilled through 103 on lining 102, the aperture of through-hole 103 When being drilled, first existed by the drill bit in wall opening apparatus for 50mm~70mm by installing wall opening apparatus on drilling machine Drill centers is carried out centered on determining central point of crossing on lining 102, wall opening apparatus is then allowed to carry out aperture, aperture Aperture can be protruded between 50mm~70mm convenient for subsequent plugging device, be also convenient for subsequent progress cement mortar perfusion.
C, cavity is blocked:Plugging hole core 2 is filled in 1 inner cavity of prefabricated inner partition plate below 103 position of through-hole, allows closure Hole core 2 is resisted against between Side fascia 101 and lining 102 and is formed sealing, and plugging hole core 2 can pass through closure when being filled Equipment protrudes into progress, plugging hole core 2 using EPS sheet fragment or foam rods with foamed glue is sufficiently be bonded forms, during the bonding process The stabilization of plugging hole core 2 can also be bonded by foamed glue, guarantee that filled plugging hole core 2 has bearing strength.
D, perfusion mortar:It is 1 by weight proportion:103 position of through-hole is carried out filling secret room by 2 dry cement mortar, And it allows cement sand pulp to be higher than the top edge of through-hole 103 and difference in height should be greater than 20mm, carried out using dry cement mortar Filling has drying time short, the high advantage of solid rear intensity, and cement sand pulp height is allowed to be higher than 103 top edge of through-hole Greater than 20mm, the lining 102 of the two sides of through-hole 103 can be covered after guaranteeing the solid formation concrete block 3 of cement mortar Lid increases the intensity of through-hole 103, avoids the case where being pulled open after load-bearing.
E, built-in connection:Before cement mortar initial set, the hanged hook 4 of pre-production is passed through into through-hole 103 and is inserted into cement bonded sand In slurry, and guarantee that hanged hook 4 is in 103 center of through-hole, in order to guarantee the bearing strength of hanged hook 4 itself, prefabricated suspension The single hook load capacity of hook 4 is not more than 300N, while also can guarantee the bearing strength of prefabricated inner partition plate 1, dry in cement mortar Gu hanged hook 4 is carried out fastening during to be integrally formed, the dispersion effect of bearing strength is more preferable, in order to guarantee the position of hanged hook 4 Setting will not move down during solid, the lanyard being supported to hanged hook 4 can be arranged on lining 102, solid After can directly remove.
F, iron net receives face:Filleting band, and the wide through-hole out of marginal position of filleting band are bonded in the tapping of lining 102 The spacing distance at 103 edges should be not less than 50mm, and wherein the length and width of filleting band are 150mm × 150mm;By filleting band to through-hole 103 are covered, so that cement mortar be avoided to leak out from through-hole 103, guarantee it is solid in through-hole 103 after formed it is mixed Solidifying soil block 3 is flushed with the surface of lining 102.
G, solid:It is needed solid 28 days after cement mortar filling, cement mortar is allowed sufficiently to solidify.
The prefabricated inner partition plate weight hanging structure of construction technology production in through the invention is overcome completely in prefabricated The hollow structure of partition plate 1 causes that the defect of weight cannot be hung, and promotes have quality light, impervious using prefabricated interior wall partition It is good, environmentally protective, intensity is high, good economy performance, sound insulation, fire protecting performance is high, be convenient for the advantages that rapid construction under the premise of, still have Play the role of carrying out hanging weight indoors, has further pushed the application of prefabricated inner partition plate 1.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of technical solution of the present invention, should all be covered at this In the scope of the claims of invention.

Claims (7)

1. a kind of prefabricated inner partition plate weight hanging structure, including prefabricated inner partition plate, prefabricated inner partition plate include prefabricated connection The Side fascia and lining being integrated, it is characterised in that:The through-hole inside connection, the Side fascia are offered on the lining The plugging hole core being arranged with below through-hole between lining, the plugging hole core are equipped with the concrete of covering through-hole Block is inlaid with the hanged hook across through-hole in the concrete block;
The hanged hook includes connecting rod, and one end that connecting rod protrudes into concrete block is connected with the gag lever post vertical with connecting rod, One end that connecting rod stretches out through-hole is connected with the hook bar of arcuate structure, and the center of circle for hooking bar is positioned above;The hook The cross-sectional area of bar is gradually reduced from connecting rod one end to the end for hooking bar.
2. a kind of prefabricated inner partition plate weight hanging structure according to claim 1, it is characterised in that:The hole of the through-hole Diameter is 50mm~70mm.
3. a kind of prefabricated inner partition plate weight hanging structure according to claim 1 or 2, it is characterised in that:The coagulation The ingredient of soil block is dry cement mortar, and wherein the weight proportion of cement and sand is 1:2.
4. a kind of prefabricated inner partition plate weight hanging structure according to claim 3, it is characterised in that:The plugging hole core Using foam rods or EPS sheet fragment.
5. a kind of prefabricated inner partition plate weight hanging structure construction technology, it is characterised in that:Include the following steps,
A, it positions:Positioning marking is carried out on the lining of prefabricated inner partition plate and determines central point;
B, aperture:By special-purpose machinery, using central point as the center of circle, the holes drilled through on lining, the aperture of through-hole are 50mm~70mm;
C, cavity is blocked:In the prefabricated inner partition plate inner cavity below lead to the hole site fill plugging hole core, allow plugging hole core against Between Side fascia and lining and form sealing;
D, perfusion mortar:It is 1 by weight proportion:Lead to the hole site is carried out filling secret room by 2 dry cement mortar, and allows water Silt particle pulp noodle are higher than the top edge of through-hole and difference in height should be greater than 20mm;
E, built-in connection:Before cement mortar initial set, the hanged hook of pre-production is passed through in through-hole insertion cement mortar, and is protected Card hanged hook is in through hole center position;
F, iron net receives face:It is bonded filleting band in the tapping of lining, and between the wide through-hole edge out of marginal position of filleting band Gauge is from that should be not less than 50mm, and wherein the length and width of filleting band are 150mm × 150mm;
G, solid:It is needed solid 28 days after cement mortar filling, cement mortar is allowed sufficiently to solidify.
6. a kind of prefabricated inner partition plate weight hanging structure construction technology according to claim 5, it is characterised in that:Step Plugging hole core in c using EPS sheet fragment or foam rods with foamed glue is sufficiently be bonded forms, foamed glue, which stablizes plugging hole core, to be glued It connects on Side fascia and lining.
7. a kind of prefabricated inner partition plate weight hanging structure construction technology according to claim 5, it is characterised in that:Step The single hook load capacity of prefabricated hanged hook in e is not more than 300N.
CN201810774492.8A 2018-07-16 2018-07-16 Weight hanging structure of prefabricated inner partition plate and construction process of weight hanging structure Expired - Fee Related CN108818879B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810774492.8A CN108818879B (en) 2018-07-16 2018-07-16 Weight hanging structure of prefabricated inner partition plate and construction process of weight hanging structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810774492.8A CN108818879B (en) 2018-07-16 2018-07-16 Weight hanging structure of prefabricated inner partition plate and construction process of weight hanging structure

Publications (2)

Publication Number Publication Date
CN108818879A true CN108818879A (en) 2018-11-16
CN108818879B CN108818879B (en) 2020-05-19

Family

ID=64137162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810774492.8A Expired - Fee Related CN108818879B (en) 2018-07-16 2018-07-16 Weight hanging structure of prefabricated inner partition plate and construction process of weight hanging structure

Country Status (1)

Country Link
CN (1) CN108818879B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820264A (en) * 2019-10-17 2020-02-21 青岛海尔洗衣机有限公司 Household appliance installation method and wall-mounted household appliance
CN111979720A (en) * 2019-05-22 2020-11-24 青岛海尔洗衣机有限公司 Washing equipment installation structure, installation method and wall-mounted washing equipment
CN113529955A (en) * 2020-07-16 2021-10-22 姚井祥 Installation method of zipper type wall part

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2194384Y (en) * 1993-09-30 1995-04-12 许镇辉 Light wall plate capable of hanging articles
JPH07310728A (en) * 1994-05-18 1995-11-28 Nippon Pitsuto:Kk Embedded hook
CN2637608Y (en) * 2003-08-21 2004-09-01 北京凯润天业科技开发有限公司 Light hollow partition wall plate
CN103452234A (en) * 2013-08-28 2013-12-18 史丹龙涂料(常州)有限公司 Multifunctional household partition wall board
CN204059666U (en) * 2014-01-22 2014-12-31 杜洪宇 Lightweight grouting wall
CN204551864U (en) * 2015-03-11 2015-08-12 中民筑友有限公司 For the combined hollow module of prefabricated units
CN205804714U (en) * 2016-07-15 2016-12-14 青岛博海建设集团有限公司 Novel prefabricated internal partition wall
CN207176988U (en) * 2017-09-25 2018-04-03 中启胶建集团有限公司 It is easy to the combined partition body of handling

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2194384Y (en) * 1993-09-30 1995-04-12 许镇辉 Light wall plate capable of hanging articles
JPH07310728A (en) * 1994-05-18 1995-11-28 Nippon Pitsuto:Kk Embedded hook
CN2637608Y (en) * 2003-08-21 2004-09-01 北京凯润天业科技开发有限公司 Light hollow partition wall plate
CN103452234A (en) * 2013-08-28 2013-12-18 史丹龙涂料(常州)有限公司 Multifunctional household partition wall board
CN204059666U (en) * 2014-01-22 2014-12-31 杜洪宇 Lightweight grouting wall
CN204551864U (en) * 2015-03-11 2015-08-12 中民筑友有限公司 For the combined hollow module of prefabricated units
CN205804714U (en) * 2016-07-15 2016-12-14 青岛博海建设集团有限公司 Novel prefabricated internal partition wall
CN207176988U (en) * 2017-09-25 2018-04-03 中启胶建集团有限公司 It is easy to the combined partition body of handling

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111979720A (en) * 2019-05-22 2020-11-24 青岛海尔洗衣机有限公司 Washing equipment installation structure, installation method and wall-mounted washing equipment
CN111979720B (en) * 2019-05-22 2023-10-20 天津海尔洗涤电器有限公司 Washing equipment mounting structure, mounting method and wall-mounted washing equipment
CN110820264A (en) * 2019-10-17 2020-02-21 青岛海尔洗衣机有限公司 Household appliance installation method and wall-mounted household appliance
CN110820264B (en) * 2019-10-17 2024-03-22 青岛海尔洗衣机有限公司 Household electrical appliance installation method and wall-mounted household electrical appliance
CN113529955A (en) * 2020-07-16 2021-10-22 姚井祥 Installation method of zipper type wall part

Also Published As

Publication number Publication date
CN108818879B (en) 2020-05-19

Similar Documents

Publication Publication Date Title
CN109267677A (en) A kind of GAT external mold plate cast-in-place concrete compound insulation system and its construction technology
CN108818879A (en) A kind of prefabricated inner partition plate weight hanging structure and its construction technology
CN209145035U (en) The node structure blocked when for being in the milk at assembled architecture shear wall installation seam
CN101858114A (en) Construction method for cast-in-place integral light-weight partition wall
CN103061432B (en) The construction method of light energy-saving thermal insulation non-bearing wall body
CN209653173U (en) A kind of cast-in-place foamed concrete wall
CN107386495A (en) A kind of reinforced light steel keel partition of shaped steel and construction method
CN106193499A (en) A kind of combined heat-insulating integral plate anchoring torr hanging hang structure and process
CN106759993A (en) A kind of external heat insulating wall and construction method
CN106284999A (en) Assembled architecture haydite concrete batten of internal partition mounting process
CN205976150U (en) Side fascia installation node
CN105863135A (en) Mounting node for external wall panel
CN110259010A (en) A kind of building exterior wall heat preserving decorative integral system and its installation method
CN109989554A (en) A kind of skyscraper assembled piping shaft and preparation method thereof and installation method
CN206220315U (en) A kind of Side fascia installs node
CN209211707U (en) Cast-in-place concrete exterior wall heat-preserving composite shuttering
CN105971155A (en) Installation joint for outer wallboards
CN206189675U (en) Side fascia installation node
CN109577524A (en) A kind of cast-in-place foamed concrete wall
CN205976146U (en) Side fascia installation node
CN105971152A (en) Installation joint for outer wallboards
CN207512774U (en) Adjacent foundation pits connecting structure of bottom plate
CN207813015U (en) Floor slab preformed hole tool-typed formwork support construction
CN206971461U (en) Insulation and decoration retaining wall
CN109057059A (en) A kind of thermal insulation construction technique of exterior walls of buildings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200519

Termination date: 20210716

CF01 Termination of patent right due to non-payment of annual fee