CN106193514B - Irregular hyperboloid bamboo aluminum composite plate construction method - Google Patents

Irregular hyperboloid bamboo aluminum composite plate construction method Download PDF

Info

Publication number
CN106193514B
CN106193514B CN201610705986.1A CN201610705986A CN106193514B CN 106193514 B CN106193514 B CN 106193514B CN 201610705986 A CN201610705986 A CN 201610705986A CN 106193514 B CN106193514 B CN 106193514B
Authority
CN
China
Prior art keywords
keel
installation
composite plate
aluminum composite
aluminium alloy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610705986.1A
Other languages
Chinese (zh)
Other versions
CN106193514A (en
Inventor
刘永涛
张洪友
刘雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201610705986.1A priority Critical patent/CN106193514B/en
Publication of CN106193514A publication Critical patent/CN106193514A/en
Application granted granted Critical
Publication of CN106193514B publication Critical patent/CN106193514B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/081Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements
    • E04F13/0816Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements the additional fastening elements extending into the back side of the covering elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The step of present invention provides a kind of irregular hyperboloid bamboo aluminum composite plate construction method, belongs to construction engineering technical field, the construction method include:Model is established, in-depth material fabrication plan, surveying setting-out, T-steel keel location and installation, aluminium alloy joist location and installation, fabric installation, the installation of bamboo aluminum composite plate, the closing in of bamboo aluminum composite plate and review adjust.The irregular hyperboloid bamboo aluminum composite plate construction method successfully solves irregular hyperboloid large space inner housing interior trim construction difficult problem.Bamboo aluminum composite plate mounting technique is carried out by skeleton, adjustable connecting piece.Make to install it is more reliable, easy, quick, be easy to overhaul.This method is suitable for the construction of large space, rule or irregular hyperboloid inside mounting decoration panel engineering.Application of this construction method in curved surface project, for reducing cost, energy conservation, green, environmental protection improve construction quality and project progress, have great meaning, there is preferable development prospect.

Description

Irregular hyperboloid bamboo aluminum composite plate construction method
Technical field
The present invention relates to construction engineering technical field, specifically a kind of irregular hyperboloid bamboo aluminum composite plate construction party Method.
Background technique
Living standards of the people further increase in recent years, and under the premise of satisfaction is had enough to eat and wear, cultural life has obtained pole The earth is promoted.As a collection of high starting point such as Grand National Theatre, technical level is high, difficulty of construction is high theater class engineering the whole nation successively Completion.Large space, different curved surface, new material have obtained unprecedented application.How high quality, this kind of engineering of completion of high standard are applied Work task becomes the key of theater building success or failure.
Summary of the invention
Technical assignment of the invention is to solve the deficiencies in the prior art, provides a kind of irregular hyperboloid bamboo aluminum composite plate and applies Work method.
The technical scheme is that realize in the following manner, the irregular hyperboloid bamboo aluminum composite plate construction method, The step of construction method includes:
A, model is established, material fabrication plan is deepened
B, surveying setting-out
C, T-steel keel location and installation
D, aluminium alloy joist location and installation
E, fabric is installed
F, bamboo aluminum composite plate is installed
G, the closing in of bamboo aluminum composite plate and review adjust.
The step of construction method includes:
A, model is established, material fabrication plan is deepened
By BIM system to entire bamboo aluminum composite plate shell, contain decorative keel, spatial modeling is carried out, then according to space Model exports areal model, carries out refinement analysis to areal model, obtains the planar curvature of every keel, specific step is as follows:
Step 1:Inner casing body Model is established by design parameter;
Step 2:CAD areal model is exported by BIM model;
Step 3:Separation is carried out to areal model and obtains keel model;Every section of keel are abnormal-shaped curve;
Step 4:Every keel are deepened, the arc length and radius of keel center line are obtained;
Every section of keel center line takes cy-pres doctrine when being deepened, will original irregular segmental arc similar to circular arc, with Just processing and stretch bending are carried out to every keel;The aluminium alloy joist length of every section of approximate processing controls within 4 meters;
B, surveying setting-out
Finished surface size bullet, which is designed, according to bamboo aluminum composite plate puts ground finished surface control line:
Unwrapping wire takes multiple spot at line principle:The control point on every axis is first positioned, control point takes in axis and structural column The intersection point in sideline is labeled to its determining position in devising and drawing the blueprint after the review of control point and in blueprint, then basis Middle control point devise and draw the blueprint at the distance releasing finished surface control point in the axial direction away from completion millet cake, then will be on adjacent axis Two control points are connected, and the vertical range according to string central point away from finished surface obtains the control point of string center finished surface, by this Control point is connected with the control point of two sides again, obtains the control point of each section of center finished surface, again in a manner described with this Analogize and obtain enough control points, meet cy-pres doctrine, finally each control point is connected and obtains entire ground finished surface control line;
C, T-steel keel location and installation
T-type keel are the vertical construction and bearing keel of hyperboloid structure, are risen to the installation quality of subsequent decorations transom To decisive action;
First original structure H girder steel is checked before T keel installation, the H profile steel beam of raw steel structure is to subsequent T-steel keel Installation play important reference effect, when measurement, will check the space orientation of every H profile steel beam:Along H profile steel beam center line side Every 3m vertical range lays a measuring control point upwards, is calculated as O point;Total station is crossed according to known 3-D walls and floor Netcom to calculate The D coordinates value of each measuring control point is calculated as P point then by measured value and design theory value;It is compared, control point processing opinion Data are provided by Construction of Steel Structure side, to count actual coordinate value at each measurement control point convenient for drawing and subsequent calculating And the deviation of gross data;
The direction vertical with H profile steel beam flange plate is calculated as M axis direction, by M axis the location of in a coordinate system and Trigonometric function calculates deviation of the measuring control point physical location O point compared to design position P point along M axis direction;
T-steel keel take segmented to process, and the every 3m of vertical direction is divided into one section to meet live location requirement;Every section Keel are numbered from the bottom up, are then positioned from lower to upper with former H girder steel by command range;
T keel positioning after first with H profile steel beam reserve steel plate progress spot welding fixes, to the command range to entire T keel into It is fully welded again after row correction, to make welding stress and weld industry to minimum, in welding, selection is reasonably welded suitable The technological measures such as sequence and preheating;Brushing antirust paint after weld seam concealment acceptance is qualified, antirust paint brushing is by first up and then down, first left back Principle application right, from inside outwards, difficult at first and quite easy afterwards, keeps paint film uniform, fine and close, smooth and smooth;
D, aluminium alloy joist location and installation
T keel and reserved steel plate be fully welded and antirust treatment after carry out the installation of aluminium alloy transom;The installation of aluminium alloy transom Preceding elder generation calculates the absolute altitude of every transom center line according to the spatial model of foundation, then by absolute altitude control line bullet in T keel On, first carry out the welding of the zinc-plated steel angle hitch of lower row, after steel angle hitch position check it is errorless after carry out the welding of the zinc-plated steel angle hitch of upper row, Aluminium alloy transom is finally installed;
Anti-corrosion isolated flexible gasket should be added between aluminium alloy transom and zinc-plated corner brace, to prevent different metal contact from generating Bimetallic corrosion;Capturing position when blank size and the crooked radian installation of aluminium alloy transom, all aluminium alloy transoms connect Head is arranged at T-type keel position, and thus effectively avoids transom connectors in space, simplifies working procedure and saves The dosage of aluminum alloy joint profile;
The completion line that aluminium alloy transom is put after the completion of just filling according to ground is adjusted the disengaging of transom, to the greatest extent may be used The error generated by installation can be eliminated;Bolt is fastened after integrated regulation;Aluminium alloy transom installs laggard The installation of the vertical aluminium alloy carinula of row, the fixation keel as subsequent fabric;Because vertical carinula is as the dedicated solid of fabric Determine keel, therefore should be noted when installing centre keel and avoid generating difference of height with transom;
E, fabric is installed
Aluminium alloy joist designs typesetting and Fabric Design width in bamboo aluminum composite plate after the installation is completed, according to bamboo aluminum composite plate Fabric keel clamp is installed, fabric clamp keel radian should be identical as lateral aluminium alloy joist radian, fabric card at transverse slot Son installs fabric after the installation is completed, and fabric installation requirement is tightened, is smooth;
F, bamboo aluminum composite plate is installed
Fabric carries out bamboo aluminum composite plate installation after the installation is completed;Bamboo aluminum composite plate epidermis is natural bamboo skin, should be into before installation Bamboo clappers similar in color is mounted on same panel region and pays attention to the transition of color by row color difference than choosing, is reduced color difference and is imitated to decoration The influence of fruit;Outer wall stone back bolt type dry-hanging method is used for reference in the installation of bamboo aluminum composite plate, and the installation of the every row of bamboo aluminum composite plate is according to setting Meter typesetting starting point starts to install to two sides, carries out from lower to upper, first installs big face, then install corner part, it is ensured that every block of plate Verticality in vertical projection;
G, the closing in of bamboo aluminum composite plate and review adjust
Inspection check will be carried out by often installing one section, avoid deviation accumulation;Guarantee that entirety is bi-curved smooth, transverse joint is wanted Guarantee levelness and width degree;
The smooth of curved surface can be adjusted by L-type aluminium alloy pendant, and transverse joint width degree can be by back of the body bolt pendant Adjusting screw carry out up and down adjustment.
Generated beneficial effect is the present invention compared with prior art:
The irregular hyperboloid bamboo aluminum composite plate construction method successfully solves in irregular hyperboloid large space inner housing Decoration construction problem.
This method makes to seem the Plot Work being difficult to realize and is converted to intuitive spatial modelling by BIM system, and borrows It helps CAD software handle convenient for the simple abstract of practical operation to the vivid data isolated, there is construction quality Effect control, construction speed have obtained significant increase.
This method is using AutoCAD software, BIM software technology, using total station to Irregular Boundary Surface surveying setting-out.
Bamboo aluminum composite plate mounting technique is carried out by skeleton, adjustable connecting piece.Make to install it is more reliable, easy, quick, It is easy to overhaul.
It is cracked installation using fabric and bamboo aluminum composite plate, reaches decorative effect.
This method has carried out a large amount of, complicated point to large space, different curved surface by total station and has calculated, and is decoration panel Installation provides accurate installation positioning.
In this method decoration panel installation use for reference stone curtain wall back bolt type dry-hanging method, make construction safety and construct into Degree has obtained effective guarantee.
The bamboo aluminum composite plate that this method uses is combined using natural bamboo skin with honeycomb aluminum plate, is a kind of novel green Ornament materials can create unique decorative effect, provide good reference for the subsequent use of such material.
This method is suitable for the construction of mounting decoration panel engineering inside large space, rule/irregular hyperboloid.
Application of this construction method in curved surface project, for reducing cost, energy conservation, green, environmental protection improve construction quality And project progress, there is great meaning, there is preferable development prospect.
Detailed description of the invention
Attached drawing 1 is process flow diagram of the invention.
Specific embodiment
Irregular hyperboloid bamboo aluminum composite plate construction method of the invention is described in detail below with reference to the accompanying drawing.
As shown in the picture, the step of irregular hyperboloid bamboo aluminum composite plate construction method of the invention, the construction method, wraps It includes:
A, BIM model is established, material fabrication plan is deepened
By BIM system to entire bamboo aluminum composite plate shell(Containing decorative keel)Spatial modeling is carried out, then according to space Model exports areal model, carries out refinement analysis to areal model, obtains the planar curvature of every keel.Specific step is as follows:
Step 1:Inner casing body Model is established by design parameter;
Step 2:CAD areal model is exported by BIM model;
Step 3:Separation is carried out to areal model and obtains keel model(Every section of keel are abnormal-shaped curve);
Step 4:Every keel are deepened, the arc length and radius of keel center line are obtained;
Every section of keel center line takes cy-pres doctrine when being deepened, will original irregular segmental arc similar to circular arc, So that factory carries out processing and stretch bending to every keel.The aluminium alloy joist length of every section of approximate processing controls within 4m, with Just make error of curvature control in minimum range.It can accurately drawn after the arc length and relevant radii acquisition of every section of keel It is curved, it ensure that the requirement to construction quality.
B, surveying setting-out
Finished surface size bullet, which is designed, according to bamboo aluminum composite plate puts ground finished surface control line:Unwrapping wire takes " multiple spot is at line " former Then:First position the control point on every axis(This Engineering Control point takes the intersection point of axis Yu structural column inner edge, multiple to control point Its position in devising and drawing the blueprint is determined after core and is labeled in blueprint), then basis devises and draw the blueprint middle control point on edge Axis direction releases finished surface control point away from the distance for completing millet cake, then two control points on adjacent axis are connected, according to string Vertical range of the central point away from finished surface obtains the control point of string center finished surface, by the control with two sides again of this control point Point is connected, and obtains the control point of each section of center finished surface again according to the above method, and so on obtain enough control points (Meet approximate requirements), finally each control point is connected and obtains entire ground finished surface control line.
Two control point M, N is first determined, according to M, N two o'clock on Art Design blueprint in the axial direction away from the distance of finished surface Determine A, B two o'clock.It takes the midpoint of AB line to do vertical line, C point is determined away from the distance at finished surface control point according to this midpoint on blueprint, Then it is sequentially connected AC, BC, a, b two o'clock are determined by same procedure.It is sequentially connected with AaCbB and obtains finished surface control line.It is bent The line place of changing greatly can take several points more, to meet required precision.
C, T-steel keel location and installation
T-type keel are the vertical construction and bearing keel of hyperboloid structure, are risen to the installation quality of subsequent decorations transom To decisive action.First original structure H girder steel is checked before T keel installation, " H " girder steel of raw steel structure is to subsequent T-shape The installation of steel joist plays important reference effect, and when measurement will check the space orientation of every " H " girder steel:In " H " girder steel Every 3m vertical range lays a measuring control point on heart line direction(It is calculated as O point), whole station is crossed according to known 3-D walls and floor Netcom Instrument calculates the D coordinates value of each measuring control point, then by measured value and design theory value(It is calculated as P point)It is compared(Control Gross data is provided by Construction of Steel Structure side at point), real at each measurement control point to count convenient for drawing and subsequent calculating The deviation of border coordinate value and gross data(X-direction deviation delta X, Y direction deviation delta Y).It will be vertical with " H " steel beam flange plate Direction be calculated as M axis direction(The circumferential distortion for ignoring H steel beam flange plate, is processed because of aluminium alloy transom to determine curvature, therefore H steel The circumferential distortion of beam flange plate is minimum to the positioning effects of outermost transom.Live transom be installed after to spatial position It is checked, meets construction error requirement), by M axis, location and trigonometric function calculate measuring control point in a coordinate system Physical location O point is compared to design position P point along the deviation of M axis direction(OP•cosα), it is calculated as ± a(Export-oriented be "+" partially, introversive It is partially "-").
By finishing blueprint design, outside " T " keel and the horizontal distance of " H " girder steel outer edge M axis direction is fixed value, meter For A, and assume A value in H girder steel perpendicular to remaining unchanged in the small size migration process of M axis direction.Referring to the deviation at measuring control point(± a), obtain outside T-shape steel joist and the real standard command range of " H " girder steel outer edge M axis direction be A ± a.
T-steel keel take segmented to process, and the every 3m of vertical direction is divided into one section to meet live location requirement.Every section Keel are numbered from the bottom up, are then positioned from lower to upper with former H girder steel by command range.
Steel plate progress spot welding is first reserved after the positioning of T keel with H girder steel to fix, is carried out to the command range to entire T keel It is fully welded again after correction, to make welding stress and weld industry to minimum, should select reasonably to weld in welding suitable The technological measures such as sequence and preheating.Brushing antirust paint after weld seam concealment acceptance is qualified, antirust paint brushing generally should be by first up and then down, first Left back right, from inside outwards, difficult at first and quite easy afterwards principle application, holiday, does not flow pendant, keeps paint film uniform, fine and close, smooth and smooth.
D, aluminium alloy joist location and installation
T keel and reserved steel plate be fully welded and antirust treatment after carry out the installation of aluminium alloy transom.The installation of aluminium alloy transom Preceding elder generation calculates the absolute altitude of every transom center line according to the spatial model that BIM system is established, then by absolute altitude control line bullet On T keel, the welding of the zinc-plated steel angle hitch of lower row is first carried out, carries out the zinc-plated steel angle hitch of upper row after the review of steel angle hitch position is errorless Welding, finally install aluminium alloy transom.
Anti-corrosion isolated flexible gasket should be added between aluminium alloy transom and zinc-plated corner brace, to prevent different metal contact from generating Bimetallic corrosion.The blank size and crooked radian of aluminium alloy transom have passed through BIM software and have been accurately calculated, installation When want capturing position, all aluminium alloy transom connectors are arranged at T-type keel position, and thus effectively avoids transoms to exist Space center tap simplifies working procedure and has saved the dosage of aluminum alloy joint profile.
The completion line that aluminium alloy transom is put after the completion of just filling according to ground is adjusted the disengaging of transom, to the greatest extent may be used The error generated by installation can be eliminated.Bolt is fastened after integrated regulation.Aluminium alloy transom installs laggard The installation of the vertical aluminium alloy carinula of row, the fixation keel as subsequent fabric.Because vertical carinula is as the dedicated solid of fabric Determine keel, therefore should be noted when installing centre keel and avoid generating difference of height with transom.
E, fabric is installed
Aluminium alloy joist designs typesetting and Fabric Design width in bamboo aluminum composite plate after the installation is completed, according to bamboo aluminum composite plate Fabric keel clamp is installed, fabric clamp keel radian should be identical as lateral aluminium alloy joist radian, fabric card at transverse slot Son installs fabric after the installation is completed, and fabric installation requirement is tightened, is smooth.Fabric is by above and below design requirement two at the transverse slot 80mm Long side will be filled in all in prior mounted clamp, and seam stays in lower plywood midline;As long as fabric at the vertical gap 10mm Two short sides are filled in fabric clamp above and below asking.
F, bamboo aluminum composite plate is installed
Fabric carries out bamboo aluminum composite plate installation after the installation is completed.Because bamboo aluminum composite plate epidermis is natural bamboo skin, therefore before installing Color difference should be carried out than choosing, bamboo clappers similar in color is mounted on same panel region and pays attention to the transition of color, reduces color difference to the greatest extent Influence to decorative effect.Outer wall stone back bolt type dry-hanging method is used for reference in the installation of bamboo aluminum composite plate.The peace of the every row of bamboo aluminum composite plate Dress starts to install according to design typesetting starting point to two sides, carries out from lower to upper, first installs big face, then install corner part, really Protect verticality of the every block of plate in vertical projection.
G, the closing in of bamboo aluminum composite plate and review adjust
Inspection check will be carried out by often installing one section, avoid deviation accumulation.Guarantee that entirety is bi-curved smooth, transverse joint is wanted Guarantee levelness and width degree, perps because the reason of the descending tightening of whole curved surface will appear problem small, lower mouth is big suitable for reading, It should control using design perps width as minimum gap suitable for reading, lower mouth can suitably relax, and avoid the dead seam of appearance suitable for reading.It is bent The smooth of face can be adjusted by L-type aluminium alloy pendant, and transverse joint width degree can pass through the adjusting spiral shell on back of the body bolt pendant Silk carries out up and down adjustment.The bamboo composite plate for needing scale, determine radian processing is reserved according to scene as early as possible after the installation is completed in big face Size proposes fabrication plan.
Quality control:
In strict accordance with country and professional standard,《Code for construction quality acceptance of building decoration》(GB50210-2001),, 《Building interior finishing fire prevention construction and acceptance specification》GB50354-2005,《Metal and stone curtain wall engineering legislation》 JGJ133-2001,《Construction fastener type steel pipe scaffold technical specification of security》(JGJ130-2001),《Construction eminence Operation safety technical regulation》(JGJ80-1991),《Code for engineering surveying》(GB50026-2007)Requirement with design drawing into Row construction.A variety of materials have to comply with national standard, professional standard and design requirement.All materials of marching into the arena must have quality certificate and Retrial report, and conscientiously carry out kind, specification, the inspection of geometric dimension and stacking of classifying.
Dominant item:
1, a variety of materials, accessory used in engineering, component and surface treatment etc. should meet design requirement and country is existing The regulation of row product standard and engineering legislation.
Check quantity:Exhaustive test.
The method of inspection:It verifies work certificate book, type inspection report, materials arrival record of acceptance and reviews report.
2, the moulding of bamboo aluminum composite plate wall and facade lattice should meet design requirement.
Check quantity:Exhaustive test.
The method of inspection:Observation checks.
3, the kind, specification, color of panel, gloss and installation direction should meet design requirement.
Check quantity:Exhaustive test.
The method of inspection:Observation;Verify site acceptance record.
4, the metal framework of metope is connect with main structure built-in fitting, connector, fastener must firmly install, and count Amount, specification, position, connection method and preservative treatment should meet design requirement.
Check quantity:Exhaustive test.
Inspection method:Observation;Verify the pull-out test report of record of acceptance of concealed work and construction note, post-install.
The fastening bolt of fastening bolt, crossbeam and column connection that 5 columns are connect with main structure should have anti-loosening arrange It applies;Throat depth, the length of weldering connection should meet design requirement, and commissure should carry out preservative treatment.
Check quantity:Exhaustive test.
Inspection method:Observation;Verify record of acceptance of concealed work and construction note.
6, the connecting node between metope surrounding, corner, inner surface and main structure, various modifications stitch, should meet design It is required that.
Check quantity:Exhaustive test.
Inspection method:Observation;Verify record of acceptance of concealed work and construction note.
7, fabric, which is installed, to tighten, it is smooth to install, and must not have breakage.
Check quantity:Exhaustive test.
The method of inspection:Observation.
General data:
1, bamboo aluminum composite plate surface answers that smooth, clean, color is consistent.
Check quantity:Exhaustive test.
Inspection method:Observation.
2, the press strip of bamboo aluminum composite plate and other materials contact surface answers that straight, clean, interface is tight, firmly installs.
Check quantity:Exhaustive test.
Inspection method:Observation, hand pull inspection.
3, bamboo aluminum composite plate metope tolerance should meet project regulation or national regulations.
Finished product protection measure:
1, the dirt remained on decoration panel, such as impression of the hand, dust, water sundries are wiped clean clearly in time, it is compound that bamboo aluminium is arranged at bottom Plate should carry out protection of blocking after the installation is completed.
2, reasonable construction sequence, a small number of work posts are implemented(Water, electricity, ventilation, equipment installation etc.)Work should do in front, prevent Damage, pollution decoration panel.
3, scaffold is removed and when feeding, forbids to collide decoration panel.
4, decoration panel should remove protective film in time after the installation is completed, remove difficult and damage bamboo clappers table after avoiding overlong time Skin.
Safety measure:
Safety Management Measures:
The safety construction of engineering is included in the unified management of project group, if full-time safety construction supervision and management Member, establishes safety construction accountability, and set up the punishment system of safety construction, carries out safety construction at all levels Responsibility, in place, everyone has responsibility for responsibility.
The occupation progress safety education and technical training for worker and the exchange work post of newly marching into the arena, issue licence rear qualified through examination To being on duty, accomplish to take appointment with certificate.
Safe construction measure:
The screening of steel pipe, the rod piece that all serious corrosions, book wall, severe bends are fissioned should be strictly carried out before 1 scaffold building It should not use, serious corrosion, deformation, crack, the fastener that bolt thread has damaged should not use.All fastener fastening forces of scaffold Square, seat reach 45-55Nm.Brace spreading should not use sleeve couple.Seat is using overlapping mode, two revolution fastener spreadings, No less than O.4m overlap distance regards two part intervals.
2 cutting leftover bits and pieces, clear up at any time, stack as required.
3 enter construction site, it is necessary to which hard hat required at all times buckles well hatband, wearing and proper use of labour protection tool.
It must fasten seat belts when 4 construction personnel's high-rise working.
Safety utilization of electric power measure:
1 steel skeleton must not collide electric wire when making, and carry on construction work at night and be no more than using portable lighter voltage when mobile portable lighter illumination 36 volts.
Should be noted that when 2 carrying profile nearby has clear, overhead line and other interim electrical equipments, prevents material from returning Electric wire is collided when turning or electric shock accidents occurs.
3 electrical equipments must be examined before using through electrician confirms that qualified rear can be used.Electric leakage must be installed in switch-box Protector, socket plug should be intact, and power supply line must not broken skin electric leakage;Operator must wear insulated shoes (rubber overshoes), wear insulation Gloves.
4 non-electromechanical personnel are not allowed to tamper electromechanical equipment.
5 operators at the scene spent material elevator traffic material when, it is necessary to set special messenger commander, it is careful smoothly Position is at the wall column position line;Needing special messenger to keep an eye below material elevator reminds passerby carefully to fall object.
Environmental protection measure:
When carrying on construction work at night, strict control noise operation, to strong noise equipment, sound insulation canopy is added and blocks.
When scene carries out section steel cutting, noise is paid attention to.
Rubbish construct using closed dedicated garbage chute or using container handling, forbids arbitrarily to soar aloft to throw to dissipate to cause fugitive dust.
It aloft carries out that the measure of blocking should be taken when electric welding field, arclight is avoided to leak.
It stacks in the waste materials category set such as profile, is utilized as far as possible, it is unavailable to sell off processing in time.
Construction period, the material in scene should be put well by construction horizontal layout requirement by class bunch, after the completion of each process Surplus material, which is forbidden to huddle, to be left about;Ensure the cleaning of ambient enviroment.
When scaffold building and dismounting, it is necessary to it handles with care, upper and lower, left and right someone transmitting.
Performance analysis:
It is combined using AutoCAD software and BIM software, takes " multiple spot is at line " principle, formulate corresponding construction method, it is real The engineering processing of the main profile of Irregular Boundary Surface is showed, and has been accurately positioned and obtains in the control of unwrapping wire quality, keel and plate Good guarantee.Aluminium alloy extrusions shell system is taken, by being connect by bolt pendant with plate, guarantees installation force structure body It is safety, meets and use function and Security Function Requirements, substitutes traditional gluing construction, it is environmentally protective.Plate takes work Factory's setting, scale processing, locating holes, it is effective to reduce live labor content, i.e. reduction operator's workload, improve work Make efficiency, and save the construction energy, reduces the dust and noise generated when the operations such as cutting, punching.Meet country advocate it is green Color construction concept.Bamboo aluminum composite plate material both can guarantee plate using being combined after the processing of natural bamboo skin micropore with honeycomb aluminum plate Block of material intensity and acoustical demands, and mineral products and bamboo wood resources can be effectively saved, meet " four sections one guarantor " that China advocates and wants It asks, is that one kind can promote new green environment protection material.

Claims (1)

1. irregular hyperboloid bamboo aluminum composite plate construction method, it is characterised in that the step of construction method includes:
A, model is established, material fabrication plan is deepened
By BIM system to entire bamboo aluminum composite plate shell, contain decorative keel, spatial modeling is carried out, then according to spatial model Areal model is exported, refinement analysis is carried out to areal model, obtains the planar curvature of every keel, specific step is as follows:
Step 1:Inner casing body Model is established by design parameter;
Step 2:CAD areal model is exported by BIM model;
Step 3:Separation is carried out to areal model and obtains keel model;Every section of keel are abnormal-shaped curve;
Step 4:Every keel are deepened, the arc length and radius of keel center line are obtained;
Every section of keel center line takes cy-pres doctrine when being deepened, by original irregular segmental arc similar to circular arc, so as to right Every keel carry out processing and stretch bending;The aluminium alloy joist length of every section of approximate processing controls within 4 meters;
B, surveying setting-out
Finished surface size bullet, which is designed, according to bamboo aluminum composite plate puts ground finished surface control line:
Unwrapping wire takes multiple spot at line principle:The control point on every axis is first positioned, control point takes axis and structural column inner edge Intersection point, its position in devising and drawing the blueprint and be labeled in blueprint to being determined after the review of control point, then according to design Control point is releasing finished surface control point away from the distance for completing millet cake in the axial direction in blueprint, then by two controls on adjacent axis System point is connected, and the vertical range according to string central point away from finished surface obtains the control point of string center finished surface, this is controlled Point is connected with the control point of two sides again, obtains the control point of each section of center finished surface again in a manner described, and so on Enough control points are obtained, cy-pres doctrine is met, finally each control point is connected and obtains entire ground finished surface control line;
C, T-type keel location and installation
T-type keel are the vertical construction and bearing keel of hyperboloid structure, are played certainly to the installation quality of subsequent decorations transom It is set for using;
First original structure H girder steel is checked before T-type keel installation, the peace of the H profile steel beam of raw steel structure to subsequent T-type keel Load important reference effect, when measurement will check the space orientation of every H profile steel beam:Along H profile steel beam centerline direction Every 3m vertical range lays a measuring control point, is calculated as O point;According to known 3-D walls and floor Netcom cross total station calculate it is each The D coordinates value of measuring control point is compared then by measured value and design theory value, and gross data is by steel construction at control point Construction party provides, to count actual coordinate value and gross data at each measurement control point convenient for drawing and subsequent calculating Deviation;
The direction vertical with H profile steel beam flange plate is calculated as M axis direction, the location of in a coordinate system and triangle by M axis Function calculates deviation of the measuring control point physical location O point compared to design position P point along M axis direction;
T-type keel take segmented to process, and the every 3m of vertical direction is divided into one section to meet live location requirement;Every section of keel from Under be up numbered, then positioned from lower to upper with former H girder steel by command range;
T-type keel positioning after first with H profile steel beam reserve steel plate progress spot welding fixes, to the command range to entire T-type keel into It is fully welded again after row correction, to make welding stress and weld industry to minimum, in welding, selection is reasonably welded suitable Sequence and pre-heating technique measure;Brushing antirust paint after weld seam concealment acceptance is qualified, antirust paint brushing by it is first up and then down, first left and then right, From inside outwards, principle difficult at first and quite easy afterwards applies, and keeps paint film uniform, fine and close, smooth and smooth;
D, aluminium alloy joist location and installation
T-type keel and reserved steel plate be fully welded and antirust treatment after carry out the installation of aluminium alloy transom;Before the installation of aluminium alloy transom The absolute altitude that every transom center line is first calculated according to the spatial model of foundation, then by absolute altitude control line bullet in T-type keel On, first carry out the welding of the zinc-plated steel angle hitch of lower row, after steel angle hitch position check it is errorless after carry out the welding of the zinc-plated steel angle hitch of upper row, Aluminium alloy transom is finally installed;
Anti-corrosion isolated flexible gasket should be added between aluminium alloy transom and zinc-plated corner brace, to prevent different metal contact from generating double gold Belong to corrosion;Capturing position when blank size and the crooked radian installation of aluminium alloy transom, all aluminium alloy transom connectors are equal Setting is in T-type keel position, and thus effectively avoids transom connectors in space, simplifies working procedure and has saved aluminium The dosage of alloy-junction profile;
The completion line that aluminium alloy transom is put after the completion of just filling according to ground is adjusted the disengaging of transom, disappears as far as possible Except the error generated by installation;Bolt is fastened after integrated regulation;Aluminium alloy transom is erected after the installation is completed Installation to aluminium alloy carinula, the fixation keel as subsequent fabric;Dedicated fixed dragon because of vertical carinula as fabric Bone, therefore should be noted when installing centre keel and avoid generating difference of height with transom;
E, fabric is installed
It is lateral in bamboo aluminum composite plate that aluminium alloy joist designs typesetting and Fabric Design width after the installation is completed, according to bamboo aluminum composite plate Fabric keel clamp is installed, fabric clamp keel radian should be identical as lateral aluminium alloy joist radian, fabric clamp peace at gap Fabric is installed, fabric installation requirement is tightened, is smooth after dress;
F, bamboo aluminum composite plate is installed
Fabric carries out bamboo aluminum composite plate installation after the installation is completed;Bamboo aluminum composite plate epidermis is natural bamboo skin, and color should be carried out before installation Bamboo clappers similar in color is mounted on same panel region and pays attention to the transition of color by difference than choosing, reduces color difference to decorative effect It influences;The installation of bamboo aluminum composite plate uses outer wall stone back bolt type dry-hanging method, and the installation of the every row of bamboo aluminum composite plate is arranged according to design Version starting point starts to install to two sides, carries out from lower to upper, first installs big face, then install corner part, it is ensured that every block of plate is perpendicular Verticality in projection;
G, the closing in of bamboo aluminum composite plate and review adjust
Inspection check will be carried out by often installing one section, avoid deviation accumulation;Guarantee that entirety is bi-curved smooth, transverse joint will guarantee Levelness and width degree;
The smooth of curved surface can be adjusted by L-type aluminium alloy pendant, and transverse joint width degree can be by back of the body bolt pendant Adjusting screw carries out up and down adjustment.
CN201610705986.1A 2016-08-23 2016-08-23 Irregular hyperboloid bamboo aluminum composite plate construction method Active CN106193514B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610705986.1A CN106193514B (en) 2016-08-23 2016-08-23 Irregular hyperboloid bamboo aluminum composite plate construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610705986.1A CN106193514B (en) 2016-08-23 2016-08-23 Irregular hyperboloid bamboo aluminum composite plate construction method

Publications (2)

Publication Number Publication Date
CN106193514A CN106193514A (en) 2016-12-07
CN106193514B true CN106193514B (en) 2018-11-16

Family

ID=57524305

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610705986.1A Active CN106193514B (en) 2016-08-23 2016-08-23 Irregular hyperboloid bamboo aluminum composite plate construction method

Country Status (1)

Country Link
CN (1) CN106193514B (en)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968370B (en) * 2017-02-21 2018-03-23 中建七局建筑装饰工程有限公司 A kind of high speed payout, positioning and the baiting method of ball curtain wall
CN107562980B (en) * 2017-07-14 2020-04-07 青岛理工大学 Geometric information extraction method based on BIM model
CN107724299A (en) * 2017-09-29 2018-02-23 上海宝冶集团有限公司 A kind of manufacture method of hyperboloid anticollision barrier
CN107605076A (en) * 2017-10-18 2018-01-19 重庆建工住宅建设有限公司 A kind of curtain wall construction method
CN108179845A (en) * 2017-11-23 2018-06-19 苏州金螳螂幕墙有限公司 A kind of double curved surface roofing system clod wash glass construction technology
CN108952179A (en) * 2018-07-16 2018-12-07 深圳市中建南方建设集团有限公司 A kind of bumps mirror surface wall of the moulding and construction method of smallpox
CN109113243A (en) * 2018-09-20 2019-01-01 中亿丰建设集团股份有限公司 A kind of hyperbolic steel structure type Pierced Aluminum Plank construction
CN109059889B (en) * 2018-10-26 2020-09-01 佛山市保利来建材实业有限公司 Application method of total station in special-shaped steel structure processing
CN109898776A (en) * 2019-04-17 2019-06-18 深圳海外装饰工程有限公司 A kind of more curved surface aluminium sheet construction methods of assembled
CN110424642A (en) * 2019-07-01 2019-11-08 中国十七冶集团有限公司 A kind of abnormal shape metal Roof bolts the construction method of keel with spigot-and-socket
CN110565856B (en) * 2019-08-20 2021-02-02 金刚幕墙集团有限公司 Quick installation method for double-curved-surface metal plate curtain wall
CN110530344A (en) * 2019-09-18 2019-12-03 中国人民解放军63926部队 Utilize the method for the keel installation that total station and three-dimensional laser scanner assist
CN110821020A (en) * 2019-11-07 2020-02-21 湖北麻一建设有限公司 Construction method of irregular double-curved-surface bamboo-aluminum composite board
CN112431333A (en) * 2020-11-27 2021-03-02 铭创(江苏)幕墙新材料有限公司 Double-curved-surface aluminum plate curtain wall and manufacturing process thereof
CN114509025A (en) * 2022-02-15 2022-05-17 中交四公局第一工程有限公司 Quality detection method and system for aluminum alloy formwork assembly construction process

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100704449B1 (en) * 2006-06-01 2007-05-02 김기태 Construction method of exterior decoration pannel easy construction with perpendicularly establishment of frame
CN101575889B (en) * 2009-03-27 2010-12-08 北京市建筑工程装饰有限公司 Multi-curved surface overhung copper plate curtain wall and construction method thereof
CN101806126A (en) * 2010-05-06 2010-08-18 周进先 Coating-free overall decorative cloth for indoor wall surface
CN103195247B (en) * 2013-04-19 2015-02-25 江苏省华建建设股份有限公司 Saddle-shaped hyperboloidal concrete slab construction method
CN103774853A (en) * 2014-01-08 2014-05-07 永升建设集团有限公司 Installation construction method for curtain wall with hyperbolic metal veneer

Also Published As

Publication number Publication date
CN106193514A (en) 2016-12-07

Similar Documents

Publication Publication Date Title
CN106193514B (en) Irregular hyperboloid bamboo aluminum composite plate construction method
WO2018145510A1 (en) Bim-based construction and decoration method
CN104032925B (en) CSI house wall ground Stilt layer construction method
CN107882220A (en) A kind of construction method of L-shaped biplane hyperbolic aluminum facade
CN106149935A (en) Open cladding hollow ceramic plate curtain wall construction method
CN105421773A (en) Construction method for light steel skeleton special-shaped model suspended ceiling
CN110528891A (en) Large-span Spherical rack integral hoisting method
CN106193590B (en) Concrete-type steel form Construction of Supporting method
CN112523356A (en) Columnar hyperbolic mirror surface supporting system and construction method thereof
CN106703265A (en) Stone and glass mixed curtain wall construction method
CN105825026A (en) Coke oven straight-section flue arch vaulting construction method based on BIM (building information modeling) technology
CN101906858B (en) Seamless installation process for polyline artistic GRC (Glass-fiber Reinforced Composite) board
CN206815640U (en) A kind of suspension type acoustic(al)absorbent ceiling suspension system
CN207419819U (en) A kind of keel hanger rod connecting piece
CN108915136A (en) A kind of construction method of open stone curtain wall
CN110565856B (en) Quick installation method for double-curved-surface metal plate curtain wall
CN113550599B (en) Hyperboloid sawtooth-shaped GRG construction method
CN210152028U (en) Bolt joint method cell cube GRC curtain wall construction
CN107605076A (en) A kind of curtain wall construction method
CN111364767A (en) Construction method of short-slot dry-hanging argil plate
CN115653168A (en) Double-curved-surface honeycomb aluminum plate structure and mounting method thereof
CN113360993B (en) BIM technology-based construction method for large-area complex-modeling suspended ceiling
CN107119931B (en) Theater multistage curve auditorium concrete ladder plate device and its construction method
CN208009789U (en) " rice " font bamboo adorns Steel Structure
CN103912089B (en) A kind of construction method of the lifting furred ceiling of auditorium

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant